You are on page 1of 4

12mm THICK CEMENT PLASTERING C

MATERIAL REQUIREMENT ANALYSIS FOR 10M3 VOLUME


12mm thick plaster (1:3)= 100 m2
Thickness 0.012 m
Qty of mortar required= 1.200 m3
After adding additional mortar for, joints, uneven surface

Qty of mortar required= 2.000 m3

>Cement
Quantity of Cement = 0.50 m3
Nos of Cement Bag= 14 bag

>Sand
Quantity of sand = 1.50 m3

RATE ANAL
ITEM NAME : 12mm THICK CEMENT PLASTERING IN C
(B) Material Cost Analysis
SR.NO MATERIAL QUANTITY

1 SAND 1.50 m3
2 CEMENT 14.29 bag
3 SUNDRIES -
4
5
6
7
8
9

(A) Labour Cost Analysis


SR.NO LABOUR NUMBERS

1 MISTRI 0.25
2 MASON 10
3 MALE COOLIE 10.00
4 FEMALE COOLIE 10
5 BHISTI 2
6 SUNDRIES -
(B) Equipment Cost Analysis
SR.NO Equipment Name

1
2 -
3 -
TOTAL COST

NOTES
- Material, Labour,and Equipment price is change as per location and time
- Material and equiment requirement is as per your uses.
- This is most common Rate Analysis Sheet which is majorly used
construction.
EMENT PLASTERING COST ANALYSIS

UME

ortar for, joints, uneven surface, dry wet conversion. etc

0.50 m3

RATE ANALYSIS SHEET


HICK CEMENT PLASTERING IN CEMENT MORTAR (1;3), QUANTITY (100 SQURE METER)

RATE PER AMOUNT


RS/- RS/-
800 CUBIC METER 1200
320 bag 4571.42857142857
- - 50

TOTAL COST RS/- 5821.42857142857

RATE PER AMOUNT


RS/- RS/-
400 day 100
300 day 3000
200 day 2000
180 day 1800
200 day 400
- - 50
Total Cost 7350

(A) MATERIAL COST 5821.429


HIRE CHARGES (B) LABOUR COST 7350
RS/- Ps. (C)EQUIPMENT COST 0
0 0
0 0 TOTAL COST OF LABOUR & EQUIPMENT
0 0 1 A+B+C 13171.43
TOTAL COST 0 2 1.5% WATER CHARGE 197.5714
3 10% CONTRACTOR'S PROFIT 1317.143
TOTAL COST RS/- 14686.14
s per location and time FOR 100 SQUARE METER RS/- 14686.14
r uses. FOR 1 SQUARE METER RS/- 146.8614
s majorly used

You might also like