FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
DISCREPANCIES : Civil Works
1. GENERAL DETAILS
1 CPN-03 Civil CPN-03_Civil CP N-01
Drawings 28- Works Vol_1- _01_ALT03_2
Aug-2020 4_ALIGNMENT 0201014
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
2. VIADUCT GENERAL DETAILS / STANDARD DRAWINGS (VIA00)
27 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-VIA00-ST-0062 20.1Add.Notes 7 Refer to Drainage Dreawwing Uten
Drawings 28- Works Vol_2- 03_03_ST_VIA 20.2 Web Thickness 300 to 300 (500)
28 Aug-2020 4_BR_VIA 00 -[TYP. CP Uten
29 N01- MCRP-DWG-VIA00-ST-0063 20.1Add.Notes 7 Refer to Drainage Dreaw Uten
30 03]_20201014 MCRP-DWG-VIA00-ST-0203 20.1Revised.Notes 5 A Temporary prestress system Uten
shall povide a minimum compressive stress of 0.21
mPa and average stress of 0.28 mPa across the joint
until the epoxy has cured.
31 MCRP-DWG-VIA00-ST-0301 Pilecap for pier type P1:20.1 Add. Type 13 R9, Type Uten
25 R9
32 MCRP-DWG-VIA00-ST-0303 Pilecap for for pier type: Delete Table 3, Table 5, Uten
Revised Table 4
33 MCRP-DWG-VIA00-ST-0321 20.1 Specify bar size ; P01 N20 Uten
1/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
20.2 Change bar size from P01 N16 to P01 N20
20.3 Add. Table 3 – Pile rienforcement for Type P23
20.4 Revised Notes 1 Concrete exposure
classification: B2 to : Moderate
20.5 Table 1 Pile rienforcement for Type P1:Add.
Type 23 R9
20.6 Table 2 Pile rienforcement for Type P2 : Add.
Type 19 r9
34 MCRP-DWG-VIA00-ST-0322 20.1 Specify bar size ; P01 N20 Uten
20.2 Table 1 Pile rienforcement for Type P1:Add.
Type 11 R9
20.6 Table 2 Pile rienforcement for Type P1 : Add.
Type 13 r9
35 MCRP-DWG-VIA00-ST-0323 (New drawing No.) 1500 Dia. Pile details P3 Piers Uten
36 MCRP-DWG-VIA00-ST-0324 (New drawing No.) 1500 Dia. Pile details P5 Piers Uten
37 MCRP-DWG-VIA00-ST-0341 20.2 Revised Notes 1 Concrete exposure Uten
classification: B2 to : Moderate
20.3 Add. Table 2 and Specify rienforcement detail
20.4 Add. Pilecap type A and A1
20.5 Add. Pilecap type 5B
38 MCRP-DWG-VIA00-ST-0342 20.1 Table 1 6 Pile Pilecap rienforcement Uten
Delete 9 Pile Pilecap detail
39 MCRP-DWG-VIA00-ST-0343 Change 12 Pile Pilecap detail to9 Pile Pilecap detail Uten
20.1 Table 2 9 Pile Pilecap rienforcement
40 MCRP-DWG-VIA00-ST-0344 Change 3&8 Pile Pilecap detail to12 Pile Pilecap detail Uten
41 MCRP-DWG-VIA00-ST-0345 (New drawing No.) 3 Pile Pile cap detail Uten
42 MCRP-DWG-VIA00-ST-0400 20.1 Add. Pier type 7 &12 Uten
20.2 Add. Pier type 23
20.3 Add. Pier type 13
20.4 Add. Pier type 5E
43 MCRP-DWG-VIA00-ST-0400 Table 1-Pier type P1 Dimensions Uten
20.1 Add. Type 13 r9, Type 23 r9, Type 25 r9
44 MCRP-DWG-VIA00-ST-0421 20.1-20.4 Add. Table 1: Pier dimensions and details Uten
45 MCRP-DWG-VIA00-ST-0422 20.1 Change From Bearing arangment Type 12& 13 Uten
to Bearing arangment Type1-8
46 MCRP-DWG-VIA00-ST-0423 20.1 Change by deleted Bearing arangment Type Uten
12,15&17
Revised Table 1- Pier type3 Bearing arangment
dimension.
47 MCRP-DWG-VIA00-ST-0424 (New drawing No.) Pier type 23 concrete details Uten
48 MCRP-DWG-VIA00-ST-0447 20.1 Change Bearing arrangement for portal pier- Uten
Type 1-6 and Add. Bearing setout dimension-P5D
49 MCRP-DWG-VIA00-ST-0448 Change from Bearing arangment for portal pier-Type Uten
9,10,16. Table 1 Bearing arangment type 1
2/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
dimensions. Table 2 Bearing arangment type 2
dimensions. Table 3 Bearing arangment type 3
dimensions Table 11 Bearing arangment type 3
dimension: to Table 1 Bearing setout dimension-P5D
50 MCRP-DWG-VIA00-ST-0449 Cancelled Uten
51 MCRP-DWG-VIA00-ST-0460 (New drawing No.) Pier type P13 Concrete details Uten
52 MCRP-DWG-VIA00-ST-0471 20.1Revsed table 1: Bearing setout dimension-P5D Uten
20.2 Add. More detail
53 MCRP-DWG-VIA00-ST-0472 (New drawing No.) Pier type P5E Concrete details Uten
54 MCRP-DWG-VIA00-ST-0472 Table 1 Pier type 6 dimension 20.1 Add. Pile cap Uten
dimension
55 MCRP-DWG-VIA00-ST-0502 20.1 Add. More detail for inspection platform Uten
56 MCRP-DWG-VIA00-ST-0503 (New drawing No.) Inspection platform details sheet Uten
2
57 MCRP-DWG-VIA00-ST-0504 (New drawing No.) Inspection platform details sheet Uten
3
58 MCRP-DWG-VIA00-ST-0505 (New drawing No.) Inspection platform details sheet Uten
4
59 MCRP-DWG-VIA00-ST-0505 (New drawing No.) Inspection platform details sheet Uten
5
60 MCRP-DWG-VIA00-ST-0510 (New drawing No.) Pier type P12 concrete details Uten
sheet 1
61 MCRP-DWG-VIA00-ST-0601 20.1 Change lap splicing to coupler and specify more Uten
detail of reinforcement.
62 MCRP-DWG-VIA00-ST-0603 Table 1: Vertical reinforcement-bar sizes Uten
20.1Add. P1-type 11 R9
20.2 Add. P1-type 13, P1-type 13r9
63 MCRP-DWG-VIA00-ST-0621 Specify more detail of reinforcement. Uten
64 MCRP-DWG-VIA00-ST-0622 Improved reinforcement details for pier type 3 Uten
65 MCRP-DWG-VIA00-ST-0623 Improved reinforcement details for specific P3- type Uten
2
66 MCRP-DWG-VIA00-ST-0624 Improved reinforcement details for specific P3- type Uten
3
67 MCRP-DWG-VIA00-ST-0625 (New drawing No.) Pier type P3 reinforcement Uten
details sheet 5
68 MCRP-DWG-VIA00-ST-0626 (New drawing No.) Pier type P3 reinforcement Uten
details sheet 6
69 MCRP-DWG-VIA00-ST-0627 (New drawing No.) Pier type P3 reinforcement Uten
details sheet 7
70 MCRP-DWG-VIA00-ST-0628 (New drawing No.) Pier type P3 reinforcement Uten
details sheet 8
71 MCRP-DWG-VIA00-ST-0646 Specify more reinforcement details of pier type P5D Uten
72 MCRP-DWG-VIA00-ST-0647 (New drawing No.) Pier type P5D reinforcement Uten
details sheet 3
73 MCRP-DWG-VIA00-ST-0648 (New drawing No.) Pier type P5D reinforcement Uten
3/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
details sheet 4
74 MCRP-DWG-VIA00-ST-0649 (New drawing No.) Pier type P5D reinforcement Uten
details sheet 5
75 MCRP-DWG-VIA00-ST-0660 (New drawing No.) Pier type P13 reinforcement Uten
details sheet 1
76 MCRP-DWG-VIA00-ST-0660 (New drawing No.) Pier type P13 reinforcement Uten
details sheet 1
77 MCRP-DWG-VIA00-ST-0661 (New drawing No.) Pier type P13 reinforcement Uten
details sheet 2
78 MCRP-DWG-VIA00-ST-0662 (New drawing No.) Pier type P13 reinforcement Uten
details sheet 3
79 MCRP-DWG-VIA00-ST-0663 (New drawing No.) Pier type P13 reinforcement Uten
details sheet 4
80 MCRP-DWG-VIA00-ST-0671 Specify more detail of reinforcement Uten
81 MCRP-DWG-VIA00-ST-0680 (New drawing No.) Pier type P12 reinforcement Uten
details sheet 1
82 MCRP-DWG-VIA00-ST-0681 (New drawing No.) Pier type P12 reinforcement Uten
details sheet 2
83 MCRP-DWG-VIA00-ST-0690 (New drawing No.) Pier type P23 reinforcement Uten
details sheet 1
84 MCRP-DWG-VIA00-ST-0691 (New drawing No.) Pier type P23 reinforcement Uten
details sheet 2
85 MCRP-DWG-VIA00-ST-0692 (New drawing No.) Pier type P23 reinforcement Uten
details sheet 3
86 MCRP-DWG-VIA00-ST-0781 Specify more detail of bearing type 1 Uten
87 MCRP-DWG-VIA00-ST-0802 Precast segmental construction typical details: Uten
Revised shear key spacing
88 MCRP-DWG-VIA00-ST-0804 Precast segmental construction typical details: Uten
Cancelled typical shear key details-type B
89 MCRP-DWG-VIA00-ST-0821 Precast segmental construction 10.3 wide box: Uten
Revised segment layout.
90 MCRP-DWG-VIA00-ST-0901 Precast segmental construction type A1 segment Uten
concrete: Revised web thickness.
3. GENERAL ARRANGEMENT DRAWINGS (VIA03)
91 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-VIA03-ST-0001 Drawing Deleted of Abutment Detail sheet 1,2 BK
Drawings 28- Works Vol_2- 03_02_ST_VIA referred to MCRP-DWG-VIA03-ST-0161 and 0162. Pls
Aug-2020 4_BR_VIA 03_20201014 confirm P-1142 in detail and change.
92 MCRP-DWG-VIA03-ST-0012 Pls clarify of disappear detail of viaducts BK
93 MCRP-DWG-VIA03-ST-0018 to Pls clarify of disappear detail of river training for BK
0021 construction
94 MCRP-DWG-VIA03-ST-0027 Note for change pier type P-966 to 969 and piling BK
depth.All rights reserves to Variation Cost.
95 MCRP-DWG-VIA03-ST-0028 Note for change pier type P-975 to 978 and piling BK
depth.All rights reserves to Variation Cost.
4/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
96 MCRP-DWG-VIA03-ST-0029 Note for change pier type P-981 to 985 and piling BK
depth.All rights reserves to Variation Cost.
97 MCRP-DWG-VIA03-ST-0030 Note for change pier type P-989 to 990 and piling BK
depth.All rights reserves to Variation Cost.
98 MCRP-DWG-VIA03-ST-0033 Note for change pier type P-1020 to 1021 and piling BK
depth.All rights reserves to Variation Cost.
99 MCRP-DWG-VIA03-ST-0034 Note for change pier type P-1020 to 1021 and piling BK
depth.All rights reserves to Variation Cost.
100 MCRP-DWG-VIA03-ST-0041 Note for change pier type P-1092 to 1093 and piling BK
depth.All rights reserves to Variation Cost.
101 MCRP-DWG-VIA03-ST-0042 Note for change pier type P-1101 to 1107 and piling BK
depth.All rights reserves to Variation Cost.
102 MCRP-DWG-VIA03-ST-0043 Note for change pier type P-1109 to 1118 and piling BK
depth.All rights reserves to Variation Cost.
103 MCRP-DWG-VIA03-ST-0044 Note for change pier type P-1120 to 1121 and piling BK
depth.All rights reserves to Variation Cost.
104 MCRP-DWG-VIA03-ST-0045 Note for change pier type P-1130 to 1131 and piling BK
depth.All rights reserves to Variation Cost.
105 MCRP-DWG-VIA03-ST-0046 Note for additional stair at P-1142 and pls clarify for BK
detail of interface work CP-N03 and Cp-N04.
All rights reserves to Variation Cost.
106 MCRP-DWG-VIA03-ST-0083 Note for change number of pile foundation from 2 BK
and increase change to 3. All rights reserves to
Variation Cost.
107 MCRP-DWG-VIA03-ST-0093 Note for change number of pile foundation from 3 BK
and decrease change to 2. All rights reserves to
Variation Cost.
108 MCRP-DWG-VIA03-ST-0095 Note for change number of pile foundation from 2 BK
and increase change to 3. All rights reserves to
Variation Cost.
109 MCRP-DWG-VIA03-ST-0101 to Note addition of Column Pilecap Reinforcement BK
0111 Type. Change for information of Pier Schedule. All
rights reserves to Variation Cost.
110 MCRP-DWG-VIA03-ST-0150 Note for change pier type P-974 and P-977. BK
All rights reserves to Variation Cost.
111 MCRP-DWG-VIA03-ST-0151 Note for change pier type P-988. BK
All rights reserves to Variation Cost.
112 MCRP-DWG-VIA03-ST-0153 Note for change pier type P-1120. BK
All rights reserves to Variation Cost.
113 MCRP-DWG-VIA03-ST-0161 to Drawing Deleted of Abutment Detail sheet 1,2 Pls BK
0162 confirm P-1142 in detail and change.
114 MCRP-DWG-VIA03-ST-0216 Note for additional provide information bore hole BK
NBH-474 to 479 totally 6 nos. All rights reserves to
Variation Cost.
5/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
4. BC01 / BALANCED CANTILEVER BRIDGE (50m+70m+50m SPAN)
6/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
03]_20201014
149
150
151
6. BC03 / BALANCED CANTILEVER BRIDGE (70m+90m+70m SPAN)
152 CPN-03 Civil CPN-03_Civil CP N-
Drawings 28- Works Vol_2- 03_06_ST_BC
Aug-2020 4_BR_VIA 03 -[TYP. CP
N01-
03]_20201014
153
154
155
156
157
158
159
160
161
162
163
164
165
166
7. CIS40 (2-CELL CAST-IN-SITU BOX GIRDERS - VERTICAL WEB)
167 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-CIS40-ST-0001 (New drawing No.) Natee
Drawings 28- Works Vol_2- 03_07_ST_CIS MCRP-DWG-CIS40-ST-0090 drainages details
Aug-2020 4_BR_VIA 40 -[TYP. CP MCRP-DWG-CIS40-ST-0100 camber details
168 N01- MCRP-DWG-CIS40-ST-0032 change bar bending shape No. B52 N12 Natee
169 03]_20201014 MCRP-DWG-CIS40-ST-0041 change standard of tendon from pr EN 10138 to Natee
ASTM A416/416M
170 MCRP-DWG-CIS40-ST-0042 change SECTION 2, dead end to stressing end Natee
171 MCRP-DWG-CIS40-ST-0043 change TYPICAL TENDON LAYOUT, dead end to Natee
stressing end
172 MCRP-DWG-CIS40-ST-0080 change ELEVATION of bearing from MIN.30@eadges Natee
to 66.5
8. CIS50 (3-CELL CAST-IN-SITU BOX GIRDERS - VERTICAL WEB)
173 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-CIS50-ST-0001 (New drawing No.) Natee
Drawings 28- Works Vol_2- 03_08_ST_CIS MCRP-DWG-CIS50-ST-0090 drainages details
Aug-2020 4_BR_VIA 50 -[TYP. CP MCRP-DWG-CIS50-ST-0100 camber details
N01-
174 03]_20201014 MCRP-DWG-CIS50-ST-0032 change bar bending shape No. B52 N12 Natee
175 MCRP-DWG-CIS50-ST-0041 change standard of tendon from pr EN 10138 to Natee
7/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
ASTM A416/416M
176 MCRP-DWG-CIS50-ST-0043 change TYPICAL TENDON LAYOUT, dead end to Natee
stressing end
177 MCRP-DWG-CIS50-ST-0080 change ELEVATION of bearing from MIN.30@eadges Natee
to 66.5
9. CIS60 - 55-56m SINGLE CELL CAST IN SITU BOX GIRDERS
178 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-CIS60-ST-0001 (New drawing No.) Natee
Drawings 28- Works Vol_2- 03_09_ST_CIS MCRP-DWG-CIS60-ST-0090 drainages details
Aug-2020 4_BR_VIA 60 -[TYP. CP MCRP-DWG-CIS60-ST-0100 camber details
N01-
03]_20201014
179 MCRP-DWG-CIS60-ST-0031 change dimension & number of rebar Natee
180 MCRP-DWG-CIS60-ST-0033 change dimension & number of rebar Natee
181 MCRP-DWG-CIS60-ST-0034 change shape, dimension & number of rebar Natee
182 MCRP-DWG-CIS60-ST-0041 change standard of tendon from pr EN 10138 to Natee
ASTM A416/416M
183 MCRP-DWG-CIS60-ST-0042 change TYPICAL TENDON LAYOUT, dead end to Natee
stressing end
10. CIS70 MAINTENANCE RAMPS (SINGLE CELL CAST-IN-SITU BOX GIRDERS - VERTICAL WEB)
184 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-CIS70-ST-0001 (New drawing No.) Natee
Drawings 28- Works Vol_2- 03_10_ST_CIS MCRP-DWG-CIS70-ST-0100 maintenance ramp
Aug-2020 4_BR_VIA 70 -[TYP. CP bridges (CIS70) abutment concrete details sheet 1
N01- MCRP-DWG-CIS70-ST-0130 maintenance ramp
03]_20201014 bridges (CIS70) drainage details
MCRP-DWG-CIS70-ST-0140 maintenance ramp
bridges (CIS70) camber details
185 MCRP-DWG-CIS70-ST-0002 change slope of approach ramp structure from 3% to Natee
3.5%
change number of piles MT01-ABUT & MT01-1 from
4 piles to 6 piles
186 MCRP-DWG-CIS70-ST-0003 change number of piles MT01-2, MT01-3 & MT01-4 Natee
from 4 piles to 6 piles
187 MCRP-DWG-CIS70-ST-0004 change length of maintenance ramp bridge from Natee
47502 to 31744
188 MCRP-DWG-CIS70-ST-0005 change number of piles MT03-1&MT03-2 from 24 Natee
piles to 21 piles
remodel substation (SS19)
189 MCRP-DWG-CIS70-ST-0033 change dimension & number of rebar Natee
190 MCRP-DWG-CIS70-ST-0034 change shape, dimension & number of rebar Natee
191 MCRP-DWG-CIS70-ST-0041 change standard of tendon from pr EN 10138 to Natee
ASTM A416/416M
192 MCRP-DWG-CIS70-ST-0080 add new table 5 bearing schedule Natee
change ELEVATION of bearing from MIN.30@eadges
to 66.5
193 MCRP-DWG-CIS60-ST-0113 change dimension of rebar Natee
8/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
11. MAINTENANCE ROAD
194 CPN-03 Civil CPN-03_Civil CP N-
Drawings 28- Works Vol_3- 03_01_RD_VI
Aug-2020 4_ROADS A03_2020101
4
195
196
197
12. EXISTING ROAD REALIGNMENT AND WIDENING
198 CPN-03 Civil CPN-03_Civil CP N-
Drawings 28- Works Vol_3- 03_02_RD_VI
Aug-2020 4_ROADS A03_2020101
4
199
200
201
202
203
13. ANGELES STATION ROAD NETWORK
204 CPN-03 Civil CPN-03_Civil CP N-
Drawings 28- Works Vol_3- 03_03_CW_A
Aug-2020 4_ROADS NG_20201014
205
206
207
208
209
210
14. CLARK STATION ROAD NETWORK
211 CPN-03 Civil CPN-03_Civil CP N-
Drawings 28- Works Vol_3- 03_04_CW_CL
Aug-2020 4_ROADS A_20201014
212
213
214
215
216
217
218
219
15. DRAINAGE MAIN ALIGNMENT VIA00
220 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-VIA00-DR-0001 (New drawing No.) Natee
Drawings 28- Works Vol_4- 03_00_DR_VI MCRP-DWG-VIA00-DR-0304 drainages details
Aug-2020 4_DRAINAGE A00-[TYP. CP manhole connection type 1C, type2A and type 2B
9/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
N01- MCRP-DWG-VIA00-DR-
04]_20201014 0305,0351,0421,0422,0451,0452,0461,0463,0501,05
02
cancel drawing no. 0410,0411
221 MCRP-DWG-VIA00-DR-0305 change dimension and spacing rebar of manhole Natee
222 MCRP-DWG-VIA00-DR-0406 add a new geotextile fabric Natee
16. DRAINAGE MAIN ALIGNMENT VIA03
223 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-VIA03-DR-0001 (New drawing No.) Natee
Drawings 28- Works Vol_4- 03_01_DR_VI MCRP-DWG-VIA03-DR-3011,3012,3013
Aug-2020 4_DRAINAGE A03_2020101
4
224 MCRP-DWG-VIA03-DR-0005 add a new schedule of drainage crossing Natee
225 MCRP-DWG-VIA03-DR-0105 change dimension of at-grade drainage elements Natee
226 MCRP-DWG-VIA03-DR-0106 change dimension of at-grade drainage elements Natee
227 MCRP-DWG-VIA03-DR-0107 change dimension of at-grade drainage elements Natee
228 MCRP-DWG-VIA03-DR-0108 change dimension of at-grade drainage elements Natee
229 MCRP-DWG-VIA03-DR-0109 change dimension of at-grade drainage elements Natee
230 MCRP-DWG-VIA03-DR-0110 change dimension of at-grade drainage elements Natee
231 MCRP-DWG-VIA03-DR-0111 change dimension of at-grade drainage elements Natee
232 MCRP-DWG-VIA03-DR-0112 change dimension of at-grade drainage elements Natee
233 MCRP-DWG-VIA03-DR-0113 change dimension of at-grade drainage elements Natee
234 MCRP-DWG-VIA03-DR-0114 change dimension of at-grade drainage elements Natee
235 MCRP-DWG-VIA03-DR-0115 change dimension of at-grade drainage elements Natee
236 MCRP-DWG-VIA03-DR-0116 change dimension of at-grade drainage elements Natee
237 MCRP-DWG-VIA03-DR-0117 change dimension of at-grade drainage elements Natee
238 MCRP-DWG-VIA03-DR-0118 change dimension of at-grade drainage elements Natee
239 MCRP-DWG-VIA03-DR-0119 change dimension of at-grade drainage elements Natee
240 MCRP-DWG-VIA03-DR-0120 change dimension of at-grade drainage elements Natee
241 MCRP-DWG-VIA03-DR-0121 change dimension of at-grade drainage elements Natee
242 MCRP-DWG-VIA03-DR-0122 change dimension of at-grade drainage elements Natee
243 MCRP-DWG-VIA03-DR-0123 change dimension of at-grade drainage elements Natee
244 MCRP-DWG-VIA03-DR-0124 change dimension of at-grade drainage elements Natee
245 MCRP-DWG-VIA03-DR-0125 change dimension of at-grade drainage elements Natee
246 MCRP-DWG-VIA03-DR-0126 change dimension of at-grade drainage elements Natee
247 MCRP-DWG-VIA03-DR-0127 change dimension of at-grade drainage elements Natee
248 MCRP-DWG-VIA03-DR-0128 change dimension of at-grade drainage elements Natee
249 MCRP-DWG-VIA03-DR-0129 change dimension of at-grade drainage elements Natee
250 MCRP-DWG-VIA03-DR-0130 change dimension of at-grade drainage elements Natee
251 MCRP-DWG-VIA03-DR-0131 change dimension of at-grade drainage elements Natee
252 MCRP-DWG-VIA03-DR-0132 change dimension of at-grade drainage elements Natee
253 MCRP-DWG-VIA03-DR-0133 change dimension of at-grade drainage elements Natee
254 MCRP-DWG-VIA03-DR-0134 change dimension of at-grade drainage elements Natee
255 MCRP-DWG-VIA03-DR-0135 change dimension of at-grade drainage elements Natee
256 MCRP-DWG-VIA03-DR-0136 change dimension of at-grade drainage elements Natee
10/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
257 MCRP-DWG-VIA03-DR-0137 change dimension of at-grade drainage elements Natee
258 MCRP-DWG-VIA03-DR-0138 change dimension of at-grade drainage elements Natee
259 MCRP-DWG-VIA03-DR-0139 change dimension of at-grade drainage elements Natee
260 MCRP-DWG-VIA03-DR-0140 change dimension of at-grade drainage elements Natee
17. DRAINAGE MAIN ALIGNMENT VIA03 (SAPANG BALEN)
261 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-VIA03-RIV-4001 (New drawing No.) Natee
Drawings 28- Works Vol_4- 03_02_RIV_VI MCRP-DWG-VIA03-RIV-4006 SAPANG BALEN RIVER
Aug-2020 4_DRAINAGE A03_2020101 TYPICAL CROSSECTION DETAIL 2
4
262 MCRP-DWG-VIA03-RIV-4001 at details of concrete slope protection, add a new Natee
line of 12 mm@0.15m OC.BM.
18. ANGELES STATION ROAD NETWORK
263 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-ANG-DR-2001 cancel drawing no. 2012,2013,2014 Natee
Drawings 28- Works Vol_4- 03_03_DR_AN add new drawing no.
Aug-2020 4_DRAINAGE G_20201014 2021,2031,2041,2042,2043,2044,2051
264 MCRP-DWG-ANG-DR-2004- change dimension of at-grade drainage elements and Natee
2005 add new that elements
19. CLARK STATION ROAD NETWORK
265 CPN-03 Civil CPN-03_Civil CP N- MCRP-DWG-CLA-DR-2001 cancel drawing no. 2012,2013,2014 Natee
Drawings 28- Works Vol_4- 03_04_DR_CL add new drawing no.
Aug-2020 4_DRAINAGE A_20201014 2021,2031,2041,2042,2043,2044,2051
266 MCRP-DWG-CLA-DR-2004 change structure type and dimension of at-grade Natee
drainage elements
DISCREPANCIES : Architecture Works
1. GENERAL STATION
267 CPN-03 Arch CPN-03_Arch PDF CP N-
Drawings 28- 1-4_ARCH 03_00_AR_ST
Aug-2020 A_20201014
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
2. ANGELES STATION
11/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
283 CPN-03 Arch CPN-03_Arch PDF CP N-
Drawings 28- 1-4_ARCH 03_01_AR_AN
Aug-2020 G_20201014
284
285
286
287
288
289
290
291
292
293
3. CLARK STATION
294 CPN-03 Arch CPN-03_Arch PDF CP N-
Drawings 28- 1-4_ARCH 03_02_AR_CL
Aug-2020 A_20201014
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
4. SUBSTATION
313 CPN-03 Arch CPN-03_Arch PDF CP N-
Drawings 28- 1-4_ARCH 03_03_AR_PS
Aug-2020 S_20201014
314
315
316
317
318
12/12
CONTRACT FINALIZATION CLARIFICATIONS RESPONSE LOG ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED
FOR TEXT DOCUMENTS [HELD IN ELECTRONIC FOLDERS] NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT (NSCR-EX)
Batch 2 - [Date DD-MM-YYYY] PACKAGE: CP N-03
Remar Clarification
Reference Question Enquirer Date
Query k Request
No. Primary Folder Sub-folder No. Sub-folder
Drawing No.
No. / File No. /File Name
319
320
321
322
323
324
325
5. BATTERY POST
326 CPN-03 Arch CPN-03_Arch PDF CP N-
Drawings 28- 1-4_ARCH 03_04_AR_BP
Aug-2020 _20201014
327
328
329
330
331
332
333
334
335