CALCULATION NOTE OF FORMWORK FOR SLAB 0.50 M. THK.

OF POWER INTAKE
CALCULATION NOTE FOR TEMPORARY SLAB FORM FOR POWER INTAKE

B. Slab at EL. 525.94 and EL.533.44 (500 mm. Thickness)


1. Materials shall be used as list below.
1. Plywood 20 mm. thk
2. Square Tube 100x100x2.3 mm.
3. Manufactured Scaffolding

2. Calculation
2.1 Maximum Pressure on Slab Form Will Be Appied form Pouring Concrete

P = 1.00*0.50*2.40 (500 mm. Thk. Slab)


2
= 1,200 Kg/m .
+20 % of Impact Load
2
= 1,440 Kg/m .
2
Say = 1,500 Kg/m .

2.2. Determine Spacing of The Underneath of Plywood


2.2.1 Control Deflection of Frame by Bending Moment

Fb = 6M Plywood, Fb = 135 Ksc


bd2 b = 100 cm.
d = 2 cm.
From E = 115,500 Ksc.
M = Wa 2
10
2
M = 1,500*1 *a Kg-cm.
100 10

135 = 6*(1,500*1.00) * a2
100*22 *100 10

a = 6,000

= 77 cm.

2.2.2 Control Deflection of Frame by Deflection Equation

a = 3 128 * EI E = 115,500 Ksc.


360 W I = 1 * bd3
12
= 1 * (100)*(2)3
12
4
= 66.67 cm
W = 1.00 * Ps
100
= 15.00 Kg/ cm.
3
a = 128 * (115,500)*(66.67)
360 15.00

= 57 cm. (Clear Span)

Use 50 cm. ( Cl to Cl of Frame)


3. Check Upper Frame (Underneath Plywood form)
Used 100x100x 2.3 mm. @ 50 cm. for frames , Ix = 140 cm4 , Sx = 28.0 cm3
Structure Steel Grade A-36 Fy = 2,500 ksc.

3.1 Control Deflection of Frame by Bending Moment

M = W L2
10
2
= 1,500*(0.50) * L
1
100 10

From Fb = M
S
Section Property of 100x100x2.30 mm.

bf = 100 < 544


2tf 2*(2*2.30) Fy ,Fy = 2,500 Ksc.

10.870 < 10.88 (Compact Section)


Fb = 0.66 Fy
= 0.66*2,500
= 1,650 Ksc.
Sx = 28 cm3
M = 1,650*28
= 46 200
46,200 kg-cm 2

1 = 2 L2 = 46,200*10*100
1,500*0.50
L = 248 Cm.

3.2 Control Deflection of Frame by Deflection Equation

L = 1 * WL 4
360 128 EI

L = 3 128 * EI E = 2.0*106 Ksc.


4
360 W Ix = 140.00 cm
W = 1,500*0.50
100
= 7.50 Kg/cm.
3
L = 128 * (2.0*106)*(140.0)
360 7.5

= 237 Cm.

Use beam for frame support as spacing not more than 237 cm.
Use 121.9 cm. (Equalize the width of manufactured scaffolding)

4. Check Beam to Support Frame that Fixed with Plywood


Used 100x100x 2.3 mm.for beam, Ix = 140 cm4 , Sx = 28.0 cm3
4.1. Control Deflection of Frame by Bending Moment
Bending moment of beam 1 each

M = W L2
10
= 1,500*1.219 *1.2192
10
272 Kg-m

S = M
Fb
= 272*100
1,650
3 3
= 16.47 cm < 28.00 cm

4.2 Control Deflection of Frame by Deflection equation


Deflection = 1 * WL 4 E = 2.0*106 Ksc.
128 EI L = 122 cm
W = 1,500*1.219
100
= 18.29 Kg/cm.
4
Ix = 140.00 Cm

= 1 * (18.29)*(121.9)4
128 (2.0 106))*140
(2 0*10 140.00
00

= 0.113 Cm.
Allowable = L
360
= 121.9
360
= 0.339 > 0.189 Ok.
4.3 Check Shear Stress

V = 5 WL
8
= 5 *(1,600)*1.219*1.219
8
= 1,393 Kg.

v = V
bwd
= 1,393
(2*0.23)*10
= 302.845 Ksc < 0.4 Fy = 0.40*2,500 =1,000 Ksc Ok.

5. Load to Axial of Scffolding Column

Total Load = 1.219*1.219 *2.4*0.50


1.78 Ton / column

Allowable (Load) = 5/2


(Technical Data) 2.50 Ton / column
> 1.78 Ok.
6. Check Load on Supports to Concrete
1,780 Kg.

Square Tube 100*100*2.3mm.

350

Shim Plate 4 mm (min.) Thk.

300
DB 28

6.1 Check for Square Tube


Web Crippling Check
Maximum Shear Force Act 'R = 1,780 Kg.

R = 1,780 Kg. < 282 tw2 ( 1+3 (N/d)(tw / tf)1.5) (Fywtf/tw)1/2

1,780 Kg. < 282 *(0.23*2)2 * ( 1+3 (10/10)(0.23*2 / 0.23)1.5) (2,500*0.23/(2*0.23))1/2

1,780 < 20,011 Ok.

6.2 Check for Shim Plate (4 mm. Thk.)


Web Crippling Check
Maximum Shear Force Act 'R = 1,780 Kg.

R = 1,780 Kg. < 282 tw2 ( 1+3 (N/d)(tw / tf)1.5) (Fywtf/tw)1/2

1,780 Kg. < 282 *(0.4*2)2 * ( 1+3 (15/50)(0.40*2 / 0.40)1.5) (2,500*0.40/(2*0.40))1/2

1,780 < 22,624 Ok.

6.3 Check for DB 25 Anchor


Shear Force Check
Say Maximum Shear Force Act to Rebar R = 1,780 Kg.

v = 1,780 Kg.

V = 1780/(pi()*(2.50/2)^2)
362.62 Ksc < 0.40*(4,000) =1,600 Ok
DRAWINGS
MANUFACTURED SCAFFOLDING INFORMATION