ID Item Duration Start Finish May '15 Jun '15 Jul '15 Aug '15 Sep '15 Oct '15 Nov '15 Dec '15 Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16
19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
1 1 Lime Kiln Erection 392 days May 7, 2015 June 1, 2016
3 2.1 Kiln Shell #1 (521.100), including refractory 265 days May 7, 2015 January 26, 2016
4 2.1.1 General Preparation including Compaction 23 days May 7, 2015 May 29, 2015
5 2.1.2 Pre-Cast Transport ( 48 Pcs ) & Arrange Pre-Cast to position 5 days May 30, 2015 June 4, 2015
6 2.1.3 Temporary Support Fabrication 7 days May 30, 2015 June 6, 2015
7 2.1.4 Kiln Shell & live rings Transport to Assembly Area qty = 16 Pcs 14 days June 6, 2015 June 20, 2015
8 2.1.5 Pre-assembly Fit-up & Welding of kiln shell on ground Qty= 3 Joint 41 days June 6, 2015 July 17, 2015
9 2.1.5.1 Fit-up Kiln shell (no.3 to no.4) qty= 1 Joint 7 days June 16, 2015 June 22, 2015
10 2.1.5.2 Fit-up Kiln shell (no.6 to no.7) qty= 1 Joint 6 days June 23, 2015 June 28, 2015
11 2.1.5.3 Fit-up Kiln shell (no.9 to no.10) qty= 1 Joint 6 days June 6, 2015 June 12, 2015
12 2.1.5.4 Welding of kiln shell (no.3 to no.4)qty= 1 Joint 6 days June 23, 2015 June 28, 2015
13 2.1.5.5 Welding of kiln shell (no.6 to no.7) qty= 1 Joint 6 days June 30, 2015 July 5, 2015
14 2.1.5.6 Welding of kiln shell (no.9 to no.10) qty= 1 Joint 12 days July 6, 2015 July 17, 2015
15 2.1.6 Install Anchor bolt on Piers (from fire end) 62 days June 18, 2015 August 18, 2015
20 2.1.7 Erect and align base plate on Piers (from fire end) 56 days June 30, 2015 August 24, 2015
23 2.1.7.3 Pier III 3 days July 19, 2015 July 22, 2015
25 2.1.8 Pouring around anchor bolt & base plate on Piers (from fire end) 46 days July 4, 2015 August 19, 2015
28 2.1.8.3 Pier III 6 days July 16, 2015 July 21, 2015
30 2.1.9 Erect and align bearings and support roller 34 days August 14, 2015 September 16, 2015
31 2.1.10 Grouting of base plate 11 days September 17, 2015 September 27, 2015
32 2.1.11 Erect temporary supports for the kilnshell erection 8 days October 1, 2015 October 8, 2015
33 2.1.12 Erect liverings on kilnshell on ground qty = 4 Pcs 28 days September 11, 2015 October 8, 2015
34 2.1.12.1 Erect liverings #I 7 days September 11, 2015 September 17, 2015
35 2.1.12.2 Erect liverings #II 7 days September 18, 2015 September 24, 2015
36 2.1.12.3 Erect liverings #III 7 days September 25, 2015 October 1, 2015
38 2.1.13 Erect trust roller 2 days October 13, 2015 October 14, 2015
39 2.1.14 Lifting of kilnshells 8 days October 15, 2015 October 22, 2015
40 2.1.15 Adjustment of trust roller 12 days October 16, 2015 October 27, 2015
41 2.1.16 Erect kiln gear and drive station temporary aligned 22 days October 28, 2015 November 18, 2015
42 2.1.17 Barring motor and temporary power available for rotation of kiln 1 day November 19, 2015 November 19, 2015
43 2.1.18 Aligment of kilnshell and liverings 15 days November 18, 2015 December 2, 2015
44 2.1.19 Welding of kilnshell and removal of stiffening cross and brackets 36 days December 3, 2015 January 7, 2016
46 2.1.21 UT checking of welds and general control of shell alignment 6 days December 18, 2015 December 23, 2015
47 2.1.22 Welding guiderings for liverings 10 days December 21, 2015 December 30, 2015
48 2.1.23 Final erection and alignment of kiln drive including gearguad 8 days December 28, 2015 January 4, 2016
49 2.1.24 inlet and outlet sectors 2 days December 3, 2015 December 4, 2015
50 2.1.25 Refractory lining kiln 43 days December 15, 2015 January 26, 2016
51 2.2 Precipitator #1 (521.610) 147 days September 30, 2015 February 23, 2016
52 2.2.1 Preassembly of ESP casing, stairtower platforms etc. 42 days September 30, 2015 November 10, 2015
53 2.2.2 Erect support structure 9 days November 3, 2015 November 11, 2015
54 2.2.3 Erect casing and bottom hopper 40 days November 12, 2015 December 21, 2015
55 2.2.4 Erect inlet and outlet hood 7 days December 22, 2015 December 28, 2015
56 2.2.5 Erect collecting and electrode system 25 days December 29, 2015 January 22, 2016
57 2.2.6 Erect rapping system 15 days January 23, 2016 February 7, 2016
58 2.2.7 Erect roof structure complete with railling 31 days January 21, 2016 February 20, 2016
59 2.2.8 Erect stairtower and platforms 40 days December 16, 2015 January 24, 2016
60 2.2.9 Erect dragchain (521.615) and airsluice (521.620) and chute 16 days December 17, 2015 January 1, 2016
61 2.2.10 Dustsilo (521.645) preassembly 22 days October 9, 2015 October 30, 2015
62 2.2.11 Dustsilo erection including discharge spout (521.655) and gates 15 days November 3, 2015 November 17, 2015
63 2.2.12 Erect airsluices (521.630) dragchain (521.635) to dustsilo 15 days December 10, 2015 December 24, 2015
64 2.2.13 Insulation ESP 40 days January 15, 2016 February 23, 2016
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Progress
Project : Lime Kiln Mechanical Erection Schedule Rev.01
Date : May 17,2015 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Slippage
Milestone External Tasks Inactive Milestone Duration-only Start-only Baseline Manual Progress
67 2.2.16 Connecting ducts from top cyclone to stack 25 days November 25, 2015 December 19, 2015
68 2.2.17 Recirculation duct 25 days December 17, 2015 January 10, 2016
69 2.2.18 Insulation of ducts 36 days January 18, 2016 February 22, 2016
70 2.3 Kiln Feed System/flash/Limestone intake #1 127 days October 12, 2015 February 15, 2016
71 2.3.1 Limestone silo & hopper preassembly 22 days October 12, 2015 November 2, 2015
72 2.3.2 Limestone silo (521.026) erection 4 days November 3, 2015 November 7, 2015
73 2.3.3 Limestone hopper (521.002), extraction feeder (521.005) 4 days November 4, 2015 November 7, 2015
74 2.3.4 Bucket Elevator (521.020) with top platform 22 days November 8, 2015 November 30, 2015
75 2.3.5 Extraction screw conveyors 2 off (521.035) 15 days November 28, 2015 December 13, 2015
76 2.3.6 Chutes, rodgates (521.030) slidegates (521.032) 20 days December 18, 2015 January 6, 2016
78 2.3.8 Smockchamber (521.060) 5 days November 23, 2015 November 28, 2015
79 2.3.9 Flash,riser pipe and cyclone (521.060) 22 days November 26, 2015 December 17, 2015
80 2.3.10 Downpipe and Sluice Valve (521.060) 15 days December 18, 2015 January 1, 2016
82 2.3.12 Refractory smoke chamber and flash preheater 36 days December 20, 2015 January 25, 2016
83 2.3.13 Insulation flash and cyclone and downpipe and michelanous equipment 41 days January 3, 2016 February 13, 2016
84 2.3.14 Lime mud feedscrew (521.050) slidegate (521.050) 8 days December 17, 2015 December 24, 2015
85 2.3.15 Water injection system (521.070) 8 days December 27, 2015 January 4, 2016
86 2.3.16 Kiln Inlet seal 15 days January 31, 2016 February 15, 2016
87 2.4 Lime cooler (521.210) Hydraulic roller breaker (521.250) #1 122 days October 14, 2015 February 12, 2016
88 2.4.1 Checking of foundations, setting out lines, general preparations etc 15 days October 14, 2015 October 28, 2015
89 2.4.2 Grouting of alignment plates and anchor bolts for CB Cooler 6 days October 29, 2015 November 3, 2015
90 2.4.3 Erection of bottom frame structure and location of hydraulic pipe system 15 days November 1, 2015 November 16, 2015
91 2.4.4 Erection and alignment of grate level 22 days November 16, 2015 December 8, 2015
92 2.4.5 Preassembly of kilnhood and cooler casing,cyclones and duct 31 days December 8, 2015 January 8, 2016
94 2.4.7 Erection of kiln hood 8 days January 3, 2016 January 11, 2016
95 2.4.8 Kiln outlet seal, sealing air fan (521.100) 16 days January 11, 2016 January 27, 2016
96 2.4.9 Erection of cyclone (521.300) duct and dampers 36 days December 20, 2015 January 25, 2016
97 2.4.10 Hydraulic system including oilflushing 22 days January 5, 2016 January 26, 2016
99 2.4.12 Dedusting fan (521.320) 15 days November 29, 2015 December 14, 2015
100 2.4.13 Cooling Fans (521.240/241/242/243) and duct and dampers 84 days November 1, 2015 January 24, 2016
101 2.4.14 Walkways and platforms 23 days January 3, 2016 January 26, 2016
102 2.4.15 Refractory lining cooler and kilnhood 41 days January 3, 2016 February 13, 2016
103 2.4.16 Insulation of cyclone, Fans and Duct 36 days October 14, 2015 November 18, 2015
104 2.5 Lime Transport and makeup lime intake #1 111 days November 1, 2015 February 20, 2016
105 2.5.1 Lime silos to be in place 1 day November 1, 2015 November 2, 2015
106 2.5.2 Bucket elevator (521.435) including top platform 26 days November 2, 2015 November 28, 2015
107 2.5.3 Dragchain conveyor (521.420 & 521.423) 22 days November 26, 2015 December 17, 2015
108 2.5.4 Chutes in limetransport and changeover gate (522.407) 16 days January 3, 2016 January 19, 2016
109 2.5.5 Make up lime hopper (521.475) preassembly 15 days November 1, 2015 November 16, 2015
110 2.5.6 Make up lime hopper and extraction feeder (521.480) erection 6 days November 16, 2015 November 22, 2015
111 2.5.7 Erection Crusher (521.485) 5 days November 20, 2015 November 24, 2015
112 2.5.8 Erect dragchain conveyor (521.490) 22 days November 25, 2015 December 16, 2015
113 2.5.9 Chutes and slidegate (521.490) 15 days December 17, 2015 December 31, 2015
114 2.5.10 Dragchain conveyor (521.425) 22 days December 18, 2015 January 8, 2016
115 2.5.11 Chutes and slidegates (521.421 & 552.421) 15 days January 7, 2016 January 21, 2016
116 2.5.12 Dedust filter (521.452) and fan (521.453/451) 11 days December 20, 2015 December 31, 2015
117 2.5.13 Dedusting system preassembly 31 days November 1, 2015 December 2, 2015
118 2.5.14 Dedusting system erection 22 days December 30, 2015 January 20, 2016
119 2.5.15 Insulation of dedust pipes and equipment 30 days January 21, 2016 February 19, 2016
120 2.6 Burner System Kiln #1 99 days October 30, 2015 February 5, 2016
122 2.6.2 Burner suspension (521.522) 6 days January 13, 2016 January 18, 2016
123 2.6.3 Assembly of Burner (521.522) 16 days December 27, 2015 January 12, 2016
124 2.6.4 Burner erection 9 days January 19, 2016 January 27, 2016
125 2.6.5 Valve trains for natural gas, HFO, methanol, H2, Propane 22 days October 30, 2015 November 20, 2015
126 2.6.6 Primary air fan (521.540) 7 days November 30, 2015 December 6, 2015
127 2.6.7 Cooling air fan (521.535) 4 days December 5, 2015 December 9, 2015
128 2.6.8 Primary air ducts 11 days January 26, 2016 February 5, 2016
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Progress
Project : Lime Kiln Mechanical Erection Schedule Rev.01
Date : May 17,2015 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Slippage
Milestone External Tasks Inactive Milestone Duration-only Start-only Baseline Manual Progress
130 2.6.10 Oil tank Erection 6 days November 25, 2015 November 30, 2015
131 2.6.11 Oil Prehater (521.557) 5 days December 1, 2015 December 5, 2015
132 2.6.12 Oil Pump unit (521.555) 3 days December 6, 2015 December 9, 2015
133 3 Lime Kiln #2 299 days June 20, 2015 April 14, 2016
134 3.1 Kiln Shell #2 (521.100), including refractory 299 days June 20, 2015 April 14, 2016
135 3.1.1 Kiln Shell Transport to Assembly Area qty = 12 Pcs 10 days June 24, 2015 July 3, 2015
136 3.1.2 Kiln Shell & live rings Transport to Assembly Area qty = 16 Pcs 14 days June 20, 2015 July 4, 2015
137 3.1.3 Pre-assembly Fit-up & Welding of kiln shell on ground qty= 3 Joint 30 days July 5, 2015 August 4, 2015
138 3.1.3.1 Fit-up Kiln shell (no.3 to no.4) qty= 1 Joint 7 days July 5, 2015 July 12, 2015
139 3.1.3.2 Fit-up Kiln shell (no.6 to no.7) qty= 1 Joint 6 days July 13, 2015 July 18, 2015
140 3.1.3.3 Fit-up Kiln shell (no.9 to no.10) qty= 1 Joint 6 days July 20, 2015 July 25, 2015
141 3.1.3.4 Welding of kiln shell (no.3 to no.4)qty= 1 Joint 7 days July 14, 2015 July 20, 2015
142 3.1.3.5 Welding of kiln shell (no.6 to no.7) qty= 1 Joint 7 days July 21, 2015 July 27, 2015
143 3.1.3.6 Welding of kiln shell (no.9 to no.10) qty= 1 Joint 7 days July 28, 2015 August 3, 2015
144 3.1.4 Install Anchor bolt on Piers (from fire end) 50 days June 25, 2015 August 13, 2015
146 3.1.4.2 Pier II 7 days July 15, 2015 July 21, 2015
147 3.1.4.3 Pier III 8 days July 10, 2015 July 17, 2015
149 3.1.5 Erect and align base plate on Piers (from fire end) 42 days July 3, 2015 August 13, 2015
150 3.1.5.1 Pier I 3 days August 11, 2015 August 13, 2015
151 3.1.5.2 Pier II 3 days July 26, 2015 July 29, 2015
152 3.1.5.3 Pier III 3 days July 13, 2015 July 15, 2015
154 3.1.6 Pouring around anchor bolt & base plate on Piers (from fire end) 54 days July 9, 2015 August 31, 2015
155 3.1.6.1 Pier I 6 days August 26, 2015 August 31, 2015
157 3.1.6.3 Pier III 6 days July 18, 2015 July 24, 2015
159 3.1.7 Erect and align bearings and support roller 33 days August 30, 2015 October 2, 2015
160 3.1.8 Grouting of base plate 11 days October 2, 2015 October 13, 2015
161 3.1.9 Erect temporary supports for the kilnshell erection 43 days September 6, 2015 October 19, 2015
162 3.1.10 Erect liverings on kilnshell on ground qty = 4 Pcs 24 days October 9, 2015 November 1, 2015
163 3.1.10.1 Erect liverings #I 6 days October 9, 2015 October 14, 2015
164 3.1.10.2 Erect liverings #II 6 days October 15, 2015 October 20, 2015
165 3.1.10.3 Erect liverings #III 6 days October 21, 2015 October 26, 2015
166 3.1.10.4 Erect liverings #IV 6 days October 27, 2015 November 1, 2015
167 3.1.11 Erect trust roller 2 days October 12, 2015 October 13, 2015
168 3.1.12 Lifting of kilnshells 15 days October 19, 2015 November 2, 2015
169 3.1.13 adjustment of trust roller 12 days November 11, 2015 November 22, 2015
170 3.1.14 Erect kiln gear and drive station temporary aligned 22 days November 23, 2015 December 14, 2015
171 3.1.15 Barring motor and temporary power available for rotation of kiln 1 day December 13, 2015 December 14, 2015
172 3.1.16 Aligment of kilnshell and liverings 15 days December 18, 2015 January 1, 2016
173 3.1.17 Welding of kilnshell and removal of stiffening cross and brackets 36 days December 27, 2015 February 1, 2016
174 3.1.18 Kiln Internal 15 days February 1, 2016 February 16, 2016
175 3.1.19 UT checking of welds and general control of shell alignment 6 days January 31, 2016 February 6, 2016
176 3.1.20 Welding guiderings for liverings 20 days February 5, 2016 February 24, 2016
177 3.1.21 Final erection and alignment of kiln drive including gearguad 8 days February 25, 2016 March 3, 2016
178 3.1.22 inlet and outlet sectors 2 days January 31, 2016 February 2, 2016
179 3.1.23 Refractory lining kiln 42 days March 4, 2016 April 14, 2016
180 3.2 Precipitator #2 (521.610) 148 days October 30, 2015 March 25, 2016
181 3.2.1 Preassembly of ESP casing, stairtower platforms etc. 42 days October 30, 2015 December 10, 2015
182 3.2.2 Erect support structure 9 days December 5, 2015 December 14, 2015
183 3.2.3 Erect casing and bottom hopper 40 days December 14, 2015 January 23, 2016
184 3.2.4 Erect inlet and outlet hood 7 days January 23, 2016 January 30, 2016
185 3.2.5 Erect collecting and electrode system 25 days January 28, 2016 February 21, 2016
186 3.2.6 Erect rapping system 15 days February 22, 2016 March 7, 2016
187 3.2.7 Erect roof structure complete with railling 31 days February 18, 2016 March 19, 2016
188 3.2.8 Erect stairtower and platforms 40 days December 30, 2015 February 7, 2016
189 3.2.9 Erect dragchain (521.615) and airsluice (521.620) and chute 16 days December 11, 2015 December 26, 2015
190 3.2.10 Erect airsluices (521.630) dragchain (521.635) to dustsilo 22 days December 27, 2015 January 18, 2016
191 3.2.11 Insulation ESP 40 days February 14, 2016 March 25, 2016
192 3.2.12 Erect ID Fan (522.660) 25 days January 14, 2016 February 7, 2016
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Progress
Project : Lime Kiln Mechanical Erection Schedule Rev.01
Date : May 17,2015 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Slippage
Milestone External Tasks Inactive Milestone Duration-only Start-only Baseline Manual Progress
194 3.2.14 Recirculation duct 25 days February 3, 2016 February 27, 2016
195 3.2.15 Insulation of ducts 36 days February 19, 2016 March 25, 2016
196 3.3 Kiln Feed System/flash Kiln #2 103 days November 30, 2015 March 11, 2016
197 3.3.1 Preassembly of smockerchamber,flash,cyclone 22 days November 30, 2015 December 21, 2015
198 3.3.2 Smockchamber (521.060) 5 days December 21, 2015 December 25, 2015
199 3.3.3 Flash,riser pipe and cyclone (521.060) 22 days December 25, 2015 January 15, 2016
200 3.3.4 Downpipe and Sluice Valve (521.060) 15 days January 16, 2016 January 30, 2016
202 3.3.6 Refractory smoke chamber and flash preheater 36 days January 15, 2016 February 19, 2016
203 3.3.7 Insulation flash and cyclone and downpipe and michelanous equipment 41 days January 31, 2016 March 12, 2016
204 3.3.8 Kiln Inlet seal 15 days February 19, 2016 March 4, 2016
205 3.3.9 Lime mud feedscrew (521.050) slidegate (521.050) 8 days January 15, 2016 January 22, 2016
206 3.3.10 Water injection system (521.070) 8 days January 24, 2016 February 1, 2016
207 3.4 Lime cooler (521.210) Hydraulic roller breaker (521.250) #2 155 days November 8, 2015 April 11, 2016
208 3.4.1 Checking of foundations, setting out lines, general preparations etc 15 days November 8, 2015 November 23, 2015
209 3.4.2 Grouting of alignment plates and anchor bolts for CB Cooler 6 days November 22, 2015 November 28, 2015
210 3.4.3 Erection of bottom frame structure and location of hydraulic pipe system 15 days November 27, 2015 December 11, 2015
211 3.4.4 Erection and alignment of grate level 22 days December 11, 2015 January 1, 2016
212 3.4.5 Preassembly of kilnhood and cooler casing,cyclones and duct 31 days December 6, 2015 January 6, 2016
213 3.4.6 Erection of cooler casing 29 days January 1, 2016 January 29, 2016
214 3.4.7 Erection of kiln hood 8 days January 31, 2016 February 8, 2016
215 3.4.8 Kiln outlet seal, sealing air fan (521.100) 46 days February 7, 2016 March 24, 2016
216 3.4.9 Erection of cyclone (521.300) duct and dampers 36 days January 10, 2016 February 15, 2016
217 3.4.10 Hydraulic system including oilflushing 22 days January 10, 2016 February 1, 2016
218 3.4.11 Erection of HRB (521.250) 5 days January 29, 2016 February 2, 2016
219 3.4.12 Dedusting fan (521.320) 76 days December 27, 2015 March 12, 2016
220 3.4.13 Cooling Fans (521.240/241/242/243) and duct and dampers 84 days December 13, 2015 March 6, 2016
221 3.4.14 Walkways and platforms 23 days January 29, 2016 February 20, 2016
222 3.4.15 Refractory lining cooler and kilnhood 40 days January 29, 2016 March 8, 2016
223 3.4.16 Insulation of cyclone, Fans and Duct 36 days March 6, 2016 April 11, 2016
224 3.5 Lime Transport #2 80 days November 30, 2015 February 17, 2016
225 3.5.1 Lime silos to be in place 1 day November 30, 2015 November 30, 2015
226 3.5.2 Bucket elevator (521.435) including top platform 26 days November 30, 2015 December 25, 2015
227 3.5.3 Dragchain conveyor (521.420 & 521.423) 22 days December 25, 2015 January 15, 2016
228 3.5.4 Chutes in limetransport and changeover gate (522.407) 16 days January 15, 2016 January 30, 2016
229 3.5.5 Dragchain conveyor (521.425) 22 days January 15, 2016 February 5, 2016
230 3.5.6 Dedust filter (521.452) and fan (521.453/451) 11 days January 17, 2016 January 28, 2016
231 3.5.7 Dedusting system preassembly 31 days November 30, 2015 December 30, 2015
232 3.5.8 Dedusting system erection 22 days January 27, 2016 February 17, 2016
233 3.5.9 Insulation of dedust pipes and equipment 31 days November 30, 2015 December 30, 2015
234 3.6 Burner System Kiln #2 83 days November 30, 2015 February 20, 2016
236 3.6.2 Burner suspension (521.522) 6 days February 7, 2016 February 13, 2016
237 3.6.3 Assembly of Burner (521.522) 16 days January 17, 2016 February 2, 2016
238 3.6.4 Burner erection 9 days February 12, 2016 February 20, 2016
239 3.6.5 Valve trains for natural gas, HFO, methanol, H2, Propane 22 days November 30, 2015 December 21, 2015
240 3.6.6 Primary air fan (521.540) 6 days December 30, 2015 January 4, 2016
241 3.6.7 Cooling air fan (521.535) 5 days January 4, 2016 January 8, 2016
242 3.6.8 Primary air ducts 10 days November 30, 2015 December 9, 2015
243 3.6.9 Oil Prehater (521.557) 5 days December 30, 2015 January 3, 2016
244 3.6.10 Oil Pump unit (521.555) 4 days January 3, 2016 January 7, 2016
245 3.7 Steel & Platforms 150 days June 30, 2015 November 26, 2015
246 3.7.1 Walkway along the kiln, handrails around kiln piers, stairs 31 days June 30, 2015 July 30, 2015
247 3.7.2 Stairtower between limesilos 31 days October 26, 2015 November 25, 2015
248 4 Piping Installation 153 days September 30, 2015 February 29, 2016
249 4.1 Piping Fabrication 111 days September 30, 2015 January 18, 2016
250 4.2 Piping Installation 139 days October 14, 2015 February 29, 2016
251 5 EI, DCS and Instrument Installation 145 days October 14, 2015 March 6, 2016
252 5.1 Kiln #1 124 days October 14, 2015 February 14, 2016
253 5.1.1 MVAC (33 kV) 12 days October 30, 2015 November 10, 2015
254 5.1.2 MV distribution 46 days October 30, 2015 December 14, 2015
255 5.1.3 LVAC 19 days November 11, 2015 November 29, 2015
256 5.1.4 LV distribution (MCC) Hz converters, ESP panel, CB panel 60 days October 30, 2015 December 28, 2015
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Progress
Project : Lime Kiln Mechanical Erection Schedule Rev.01
Date : May 17,2015 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Slippage
Milestone External Tasks Inactive Milestone Duration-only Start-only Baseline Manual Progress
258 5.1.6 Cabling 93 days October 30, 2015 January 30, 2016
259 5.1.7 Connecting Cables 47 days December 30, 2015 February 14, 2016
261 5.2.1 MVAC (33 kV) 13 days November 15, 2015 November 28, 2015
263 5.2.3 LVAC 19 days November 30, 2015 December 18, 2015
264 5.2.4 LV distribution (MCC) Hz converters, ESP panel, CB panel 62 days November 15, 2015 January 16, 2016
265 5.2.5 Cable Routing 80 days November 1, 2015 January 20, 2016
266 5.2.6 Cabling 94 days November 15, 2015 February 17, 2016
267 5.2.7 Connecting Cables 48 days January 19, 2016 March 6, 2016
268 6 DCS 117 days November 16, 2015 March 11, 2016
269 6.1 Instrumentation Kiln #1 89 days November 16, 2015 February 12, 2016
270 6.1.1 Field Instruments, CO/O2 Installation 44 days November 16, 2015 December 29, 2015
272 6.1.3 Cabling 41 days December 16, 2015 January 25, 2016
273 6.1.4 Termination 32 days January 13, 2016 February 13, 2016
274 6.2 Instrumentation Kiln #2 90 days December 13, 2015 March 12, 2016
275 6.2.1 Field Instruments, CO/O2 Installation 44 days December 13, 2015 January 26, 2016
277 6.2.3 Cabling 41 days January 10, 2016 February 20, 2016
278 6.2.4 Termination 32 days February 10, 2016 March 12, 2016
279 7 Commissioning and Start-up 160 days December 25, 2015 June 1, 2016
280 7.1 Training 58 days December 25, 2015 February 20, 2016
281 7.2 Loopchecking, commissioning (by customer and installtion companies) 69 days January 22, 2016 March 30, 2016
282 7.3 Check-out (by Metso) 76 days February 12, 2016 April 27, 2016
283 7.4 Idle test and heating kiln 1 24 days March 15, 2016 April 7, 2016
285 7.6 Idle test and heating kiln 2 16 days April 20, 2016 May 5, 2016
287 7.8 Mill start-up period 61 days April 2, 2016 June 2, 2016
288 7.9 Tuning and hand over test 22 days May 7, 2016 May 29, 2016
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Progress
Project : Lime Kiln Mechanical Erection Schedule Rev.01
Date : May 17,2015 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Slippage
Milestone External Tasks Inactive Milestone Duration-only Start-only Baseline Manual Progress