Global Project Group KrwTM15 - Project Milestone Schedule July 07, 2015

ID Task Name Duration Start Finish 2015 2016


May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 TM KARAWANG PROJECT SCHEDULE 564 days Jun 1 '14 Dec 16 '15
2 ENGINEERING DESIGN 223 days Jun 30 '14 Feb 7 '15
3 CAPEX Approval 0 days Jun 30 '14 Jun 30 '14 6/30
4 Civil Design 100 days Jun 30 '14 Oct 7 '14
5 MEIP Design 185 days Aug 7 '14 Feb 7 '15
6 PROCUREMENT 457 days Jun 1 '14 Aug 31 '15
7 TM PO 0 days Jun 1 '14 Jun 1 '14 6/1
8 TM DP 15 days Jun 1 '14 Jun 15 '14
9 TM L/C 61 days Jun 16 '14 Aug 15 '14
10 L/C 0 days Aug 15 '14 Aug 15 '14 8/15
11 Yankee Dryer DP 0 days Jul 13 '14 Jul 13 '14 7/13
12 Yankee Dryer L/C 64 days Jul 14 '14 Sep 15 '14
13 Yankee Dryer Fabrication 258 days Sep 16 '14 May 31 '15
14 Yankee Dryer Transportation 62 days Jun 1 '15 Aug 1 '15
15 YD Custom Clearance & Land transportation 30 days Aug 2 '15 Aug 31 '15
16 Yankee Dryer On site 0 days Aug 31 '15 Aug 31 '15 8/31
17 TM Order material 92 days Aug 16 '14 Nov 15 '14
18 TM Fabrication 181 days Oct 16 '14 Apr 14 '15
19 TM FOB(Last Delivery) 0 days Apr 14 '15 Apr 14 '15 4/14
20 TM Transport 48 days Apr 15 '15 Jun 1 '15
21 TM Custom Clearance 14 days Jun 2 '15 Jun 15 '15
22 TM ETA 0 days Jun 15 '15 Jun 15 '15 6/15
23 CONSTRUCTION 486 days Aug 18 '14 Dec 16 '15
24 Tender and Award Piling 44 days Aug 18 '14 Sep 30 '14
25 Piling Work 60 days Oct 1 '14 Nov 29 '14
26 Construction Permit 0 days Nov 29 '14 Nov 29 '14 11/29
27 Civil Work 275 days Nov 30 '14 Aug 31 '15
28 Mechanical installation 214 days May 1 '15 Nov 30 '15
29 Commissioning 15 days Dec 1 '15 Dec 15 '15
30 TM Start up 0 days Dec 16 '15 Dec 16 '15 12/16

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
P-KrwTM15-100-14-SCH-0001 R1 Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only