TESTING & COMMISSIONING

ENERGY WORKS WONDER ENERGYPAC ENGINEERING LTD

Equipment Test Report


Substation Name:
Bay/Feeder:

Circuit Breaker Test:


Serial No.:
1. Insulation Resistance Test:

Insulation Resistance Test


Connection Applied R Y B
Voltage
Top-Bottom (CB 5000V DC
Open)
Bottom -Earth 5000V DC
(CB Close)

2. Contact Resistance Test:


Contact Resistance Test
R Phase Y Phase B Phase

3. Timing Test:
Phase Closing time Opening time(TC1) Opening time(TC2)
R
Y
B
TESTING & COMMISSIONING
ENERGY WORKS WONDER ENERGYPAC ENGINEERING LTD

Current Transformer Test:


R Phase Ratio:
Serial No.: Y Phase        
B Phase        

1. Insulation Resistance Test:

Insulation Resistance Test


Applied
Connection
Voltage R Y B
Primary-Earth 5000V DC
Primary-Core 5000V DC
Core-Core 500V DC
Core-Earth 500V DC

2. Polarity & Ratio Test:


Machine Generated Report.

3. Excitation Curve Test:


Machine Generated Report.

4. Winding Resistance Test:


Machine Generated Report.
TESTING & COMMISSIONING
ENERGY WORKS WONDER ENERGYPAC ENGINEERING LTD

Potential Transformer Test:


R Phase Ratio:
Serial No.: Y Phase        
B Phase        

1. Insulation Resistance Test:

Insulation Resistance Test


Applied
Connection
Voltage R Y B
Primary-Earth 5000V DC
Primary-Core 5000V DC
Core-Core 500V DC
Core-Earth 500V DC

2. Ratio Test:
Machine Generated Report.

Isolator Test:
TESTING & COMMISSIONING
ENERGY WORKS WONDER ENERGYPAC ENGINEERING LTD

Serial No:

1. Insulation Resistance Test:


Insulation Resistance Test
 
Connection Applied R Y B
Voltage
Top-Earth 5000V DC

2. Contact Resistance Test:


Contact Resistance Test
R Phase Y Phase B Phase

Surge Arrestor Test:


R Phase
Serial No.: Y Phase
B Phase

1. Insulation Resistance Test:

Insulation Resistance Test


 
Connection Applied R Y B
Voltage
Top-Bottom 5000V DC

Bottom 5000V DC
-Earth