You are on page 1of 1

RALGO INDUSTRIES, INC.

AIR CONDITIONING & VENTILLATION


406 Tandang Sora Ave. cor. Cassanova, Q. C.
Tel. Nos. 931-1306 / 932-3271 / 453-3566 to 67
Telefax: 931-1405 E-mail : ralgo@pldtdsl.net

Attention : Engr. Joseph Kabigting


CE Con – Project Manager

Thru : Engr. Junell Faustino


CE Con – Project incharge

Subject : FILINVEST AXIS TOWER 4 MECHANICAL WORKS (LIQUIDATED DAMAGES) REPORT

Good day!

These are the following percentage status and cause of delay for mechanical works completion of our project for

your reference.

COMMITMENT DATE SCHEDULE RELATIVE


CAUSE OF DELAY
(COMPLETION) WEIGHT (%)
DELIVERY OF FAN COIL UNIT BY LG AND CHILLED
1ST COMMITMENT APRIL 30, 2020 79.06%
WATER PUMP BY XELLEX
2ND COMMITMENT OCTOBER 30, 2020 91.45% FCU DATE DELIVERED - JUNE 17, 2020
FCU VIBRATION ISOLATOR 1ST DELIVERY - JULY 6, 2020
FCU VIBRATION ISOLATOR COMPLETION DELIVERY -
AUGUST 6, 2020
CHILLED WATER PUMP DELIVERED - JULY 22, 2020
3RD COMMITMENT MARCH 31, 2021 STATUS (ONGOING)

Very truly yours,

Engr. Elton John Evangelista


PIC FAT 4 – Ralgo Industries Inc.

You might also like