These are the following percentage status and cause of delay for mechanical works completion of our project for
your reference.
COMMITMENT DATE SCHEDULE RELATIVE
CAUSE OF DELAY (COMPLETION) WEIGHT (%) DELIVERY OF FAN COIL UNIT BY LG AND CHILLED 1ST COMMITMENT APRIL 30, 2020 79.06% WATER PUMP BY XELLEX 2ND COMMITMENT OCTOBER 30, 2020 91.45% FCU DATE DELIVERED - JUNE 17, 2020 FCU VIBRATION ISOLATOR 1ST DELIVERY - JULY 6, 2020 FCU VIBRATION ISOLATOR COMPLETION DELIVERY - AUGUST 6, 2020 CHILLED WATER PUMP DELIVERED - JULY 22, 2020 3RD COMMITMENT MARCH 31, 2021 STATUS (ONGOING)