WAY.
2) ON THE CRACK, DRILLING WAS CARRIED OUT TO GAUGE THE DEPTH OF CRACK. IN CRACKED
PORTION THE DRILLING EFFORTS REQUIRED WILL BE LESS WHILE IN PARENT UNDISTURBED
4) BOTTOM OF V KNOTCH WAS CHECKED FOR FUTHER CRACK IF ANY. IN CASE OF VISIBLE
CRACK AT BOTTOM THE DEPTH OF V KNOTCH IS FURTHER CUT TILL CRACK DISAPPEARS.
5) THE DEVELOPED V KNOTCH IS CLEANED BY AIR BLOWER / PRESSURE WATER JET / AGAIN AIR
BLOWER.
AGENT BETWEEN OLD AND NEW CONCRETE. AFTER FEW MINUTES OF AIR CURING . THE
0.20. THE MIXED MATERIAL IS FILLED UP IN KNOTCH , COMPACTED & FINISHED TO LEVEL OF
PAVEMENT. AFTER INTIAL DRYING, MATCHING GROOVED FOR TEXTURE OF PAVEMENT ARE
MARKED.
8) SURFACE IS INTIALLY CURED & PROTECTED OVERNIGHT.
10) REPAIRED CRACK IS OBSERVED FOR FEW DAYS FOR ANY SETTLEMENT / SHRINKAGE.