MOMENTO POR CARGA HL-93

L = 9.50 m
− Camión de Diseño(CD)

3.63 T 14.515 T 14.515 T R = 32.66 T


n = 2.85 m
1.42 m 2.85 m RA = 13.88 T
-0.23 m 0.71 m RB = 18.78 T
4.27 m 4.27 m Mm2 - ID = 40.57 T-m
4.04 4.75 1 Mm2 - DI = 40.57 T-m
L = 9.50 m Mm2 = 40.57 T-m

− Tanden de Diseño (TD)

11.34 T 11.34 T R = 22.68 T


n = 0.61 m
0.61 m 0.61 m RA = 10.62 T
4.4 m 0.3025 RB = 12.06 T
1.21 m Mm2 - ID = 47.22 T-m
Mm2 - DI = 47.22 T-m
L = 9.50 m Mm2 = 47.22 T-m

− Carril de Diseño (CC)

4.23 T R = 9.04 T
0.952 T-m
0.952 T-m RA = 4.52 T
RB = 4.52 T
4.45 m
Mm = 10.70 T-m
L = 9.50 m

− M(LL + IM)
CD = 40.57 T-m TD = 47.22 T-m CC = 10.70 T-m

M(LL + IM) = 47.22 T-m * 1.33 + 10.70 T-m = 73.50 T-m

MOMENTO POR CARGA DE FATIGA


L = 9.50 m
− Momento Fatiga:

3.63 T 18.15 T 14.52 T 0.00 T 0.00 T R = 18.15 T


3.42 m 0.85 m 0.00 m 0.00 m n = 0.85 m
0.43 m 0.43 m 0.00 m 0.00 m RA = 9.89 T
4.27 m 9.14 m RB = 8.26 T
4.75 m 4.75 m 0.00 m Mm2 - ID = 35.70 T-m
### Mm2 - DI = 35.70 T-m
RA L = 9.50 m RB M(LL+IM) = 41.06 T-m