Preconditon:
Remark : Operartions mark in yellow are forbidden in case of thunder storm day
1 2.1 4 5 6 7 8 9 10 11 12
Perform microwave Prepare the
Check the materials Route POE(8core) Check the hardware antenna (diameter: installation for new Conduct a power-on
Connect oudoor PI POE cable Conduct a dialing test Make preparations before site visit Clean the site before leaving Commission a single microwave site
for Microwave cable for MW installation 0.6 m) alignment network deployment check (microwave)
(multimeter) scenarios
0:00 0:07 0:07 0:23 0:23 0:39 0:39 0:45 0:45 0:55 0:55 1:20 1:20 1:20 1:20 1:35 1:35 1:40 1:40 1:42 1:42 1:47
30Person*Minute 50Person*Minute 50Person*Minute 20Person*Minute 20Person*Minute 100Person*Minute 0Person*Minute 60Person*Minute 20Person*Minute 5Person*Minute 10Person*Minute
Person ABCD Person ABC Person ABC Person ABC Person AB Person ABCD Person ABCD Person ABCD Person ABCD Person AC Person BD
2.2 3
Install outdoor PI Prepare labels
Procedure
1. Check whether the model and number of onsite main
equipment, such as the cabinet, antennas, RRUs, BBU,
and DCDU, are consistent with that specified in the
engineering design file and material checklist (there is a
packing list attached to the equipment packaging), and
whether the appearance of packaging is intact.
2. If the inspection passes, unpack the packaging, and
check whether the number of materials is correct and
whether they are intact. In addition, request the logistics
service provider and implementation team to sign the DN.
3. Provide the NMC with the BBU ESN, which can be
obtained from the left mounting ear of the BBU.
4. Sort the materials and classify them as main equipment
and materials for the antenna system.
Notes
1. Do not unpack the packaging, and report the problem to
the project team in either of the following scenarios:
The model and number of onsite equipment are
Material placement inconsistent with the design file.
The packaging is seriously damaged or soaked.
3 4
Tools
1 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
1 Personnel
utes/Unit
In Route POE(8core)
3 50
s cable for MW
ul
Procedure
at
1.Connect P&E cable to ODU.
e 2.Lay out the P&E cable from up to down and bind the
2 d cable at the same time. Make a waterproof curve of the
P&E cable when the cable is routed under the RTN 300
P and before the cable is routed into the equipment room.
V Ensure that the bending radius of the P&E cable is larger
than 40 cm (15.7 inches). Bind the P&E cable at intervals of
C 1 m (3.28 feet).
ta
p
e
Notes
1.The PoE cable is routed without any overlapping or
crossover.
Tools
Long measuring Cable cutter Open-end
1 tape 2 and utility knife 3 wrench
Indoor 4 5 6
Outdoor Materials
Cable for outdoor
1 module 2 Cable tie
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
Connect oudoor PI
3 50
POE cable
Procedure
1.Route P&E,Power and GE cable(Option) into PI.
2.Remove the cover and press the shield layer using wire
clips, ground all the cable in PI.
3.Connect the P&E,Power and GE cable(Option) to PI
Notes
1.The shield layers of all PI cables must be grounded using
wire clips. Otherwise, the cables may be amaged by
lightning strikes.
Power
Tools
Long measuring Cable cutter Open-end
1 tape 2 and utility knife 3 wrench
4 5 6
Materials
Cable for outdoor
1 module 2 Cable tie
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1
Install outdoor PI 1 15
Procedure
1.There are 2 optional solutions to install the outdoor PI,
which depends on the actual situation.
2. For pole:Route the hose clamps through the PI
mounting holes, and circle the hose clamps around the
pole. Route the steel belts through the locking latch, and
partially tighten the screws.Use an M6 hexagon torque
screwdriver to tighten the screws.
3. For wall:drill hole on wall.then fix PI by srews
Notes
1. When tightening the hose clamps, use a lifting sling to
partially hoist the equipment to prevent the equipment from
falling off.
2. Use hose clamps that suit the pole.
2 Tools
4 5 6
Materials
1 Outdoor PI 2 Cable tie
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
Perform utes/Unit
microwave
antenna (diameter: 4 100
0.6 m) alignment
(multimeter)
Procedure
1. Set the multimeter to the 20 V mode and secure it to a
proper position (easy to observe the result) on the tower to
monitor the level changes during antenna commissioning.
2. Remove the waterproof cap from the ODU RSSI port and
connect the BNC connector to the ODU RSSI port. Then,
connect the two pens of the multimeter to the cable with the
BNC connector and wrap the joint with PVC insulation tape.
3. After the antenna for the remote site is secured, loosen
the nuts for the bolts of the fixing clamp on the local
antenna mounting support. Then, roughly adjust the
antenna azimuth in the horizontal direction. When the
resistance displayed on the multimeter reaches the peak
value, tighten the nuts.
4. Loosen the upper and lower nuts on the fixed azimuth
axis and tighten the level fine-adjustment nut. Then, within
adjustment range of the nut, tighten and loosen the
adjustment nut of the fine adjustment screw for fine
adjustment in the horizontal direction. When detecting the
maximum voltage in the horizontal direction, tighten the nut.
5. Loosen the connecting nut between the antenna and
mounting support, and use a wrench to rotate the pitch
Notes
angle adjustment bolt to adjust the antenna pitch angle.
When
1. Afterthe
themultimeter displays
commissioning the maximum
is complete, pitch
tighten all angle,
bolts.
tighten the nut. a bolt, ensure that the maximum signal
When tightening
receive level is not affected.
Tools
Open-end
1 Multimeter 2 wrench 3 Seat belts
Adjustable wrench
4 (12") 5 6
Materials
1 Microwave antenna 2 Cable tie
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1
Make preparations
4 0
before site visit
Procedure
1.1. Before visiting a site, check site preparations based on
Site Preparation Checklist. For example, check whether
materials arrive at the site, whether site access is
permitted, and whether transmission information, design
files, and tools are ready.
Notes
1. If onsite conditions are inconsistent with the conditions
described in the design file, contact Huawei site engineers
for confirmation.
2. If you encounter site access problems, contact Huawei
site engineers.
Tools
1 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 2 Prepare the utes/Unit
installation for new
network 4 60
deployment
scenarios
Procedure
1. After you arrive at a site, check and confirm related
information based on Site Preparation Checklist Onsite. For
example, check whether the site information and
installation environment are consistent with the design,
whether the materials are a whole set, and whether the
tools are a whole set, and check the responsibility scope.
2. Move installation auxiliaries and tools to the site, and
Material and tool transportation neatly arrange them by type.
to the site 3. Assign tasks based on actual situations.
4. Wear protective cloths and gloves, and set warning
signs.
Notes
1. If onsite conditions are inconsistent with the conditions
described in the design file, contact Huawei site engineers
Responsibility division
3 4 for confirmation.
2. Gently move the materials and protect the product
components from colliding with the door, wall, or goods
EHS protection shelf.
Tools
Helmet&Safet Paper and
1 Compass 2 y Shoes 3 pencil
Long
4 Seat belts 5 measuring 6
tape
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1
Prepare labels 1 25
Procedure
Label attachment 1. Choose proper labels (labels are classified into labels of
signal cables and labels of power cables) based on
application scenarios.
2. Fill in/prepare labels following label content rules agreed
by the customer.
3. Attach/secure prepared labels. Fold labels of signal
cables in the way specified in the figure, and bind labels of
power cables using in the delivered cable ties.
4.Ensure that the label orientation and installation location
Labels of power is easy for information query.
2 Labels of signal
cables cables
4
3 Notes
cable cable
Adhesive side 1. Labels are attached at the position 20 mm away from a
right folding connector by default.
right folding
Tools
cable
Three procedures 4 5 6
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 utes/Unit
Check the
hardware 2 20
installation
Procedure
1.Check the hardware installation based on the design
drawings and Hardware Installation Quality Checklist.
2. Check whether the equipment, cabinets, antennas, and
BBU are securely installed at specified positions and
whether their appearances are intact.
3. Check whether the cable routes are correct, whether the
feeder connectors are securely installed, and whether cable
labels are legible.
4. Check whether the downtilt angle and azimuth of the
antennas are correct.
5. Check whether the installation position and route of the
PGND cable are correct and whether the cable connectors
are securely installed.
6. Check whether connectors are reliably and securely
waterproofed.
2 3
Notes
1. The design drawings may be a TSSR for projects outside
China.
2. The project team needs to confirm and sign Hardware
Installation Quality Checklist with the customer and
subcontractors in advance.
4 5 6 Tools
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1 2 Conduct a dialing
1 20
test
Procedure
1. Set the test terminals and perform a dialing test for each
sector. Repeat steps 2 through 5 for each sector.
2. Perform mutual dialing tests for the terminals and check
whether the voice connection is normal, whether the voice
quality is good, and whether the call drop rate is low.
Voice Perform mutual video calling tests for the terminals and
check whether the voice connection is normal, whether the
test voice quality is good, whether the video is smooth, and
whether the call drop rate (if it exists) is low.
3. Visit WAP sites and check whether the site access rate
is normal.
4. Perform text message tests.
Notes
Tools
1 Test terminal 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 Tool sorting 2 Material sorting utes/Unit
Clean the site
4 20
before leaving
Procedure
1. Sort onsite tools.
2. Remove the redundant materials.
3. Clean the equipment room and the area for installing the
antenna system. Then, pack onsite garbage and take it
when leaving the site.
4. Based on requirements in Project PAT Document, take
photos, which will be used for preparing acceptance
documents.
5. Fill in the registration form for equipment room visit.
6. Lock the door of the equipment room, and notify the
3 Cleaning
Photograph
NMC engineer of alarm information checking. If no alarm is
4 generated, leave the site.
Notes
1. Customize Project PAT Document based on project
requirements before using it.
2. Ensure that no sundries are reserved onsite after project
implementation.
3. Before leaving the equipment room, check whether the
Registration form for equipment room live network works properly with the OMC engineer.
5 visit 6 Door locking before leaving the site
Tools
Broom and
1 dustpan 2 Camera 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1 2
Conduct a power-
on check 1 5
(microwave)
Procedure
1. Check whether the output voltage is within the normal
range before powering on the equipment.
2. Turn on the switch of the power equipment.
3. Turn on the system power switch of the PXC board in the
IDU and then turn off the IDU power switch of the IF board.
Notes
1. If the standard voltage is –48 V DC, the output voltage
must be within the range of –57.6 V DC to –38.4 V DC.
2. If an exception occurs, shut down the power switch,
rectify the fault, and power on the equipment.
3
Tools
1 Multimeter 2 3
On Off 4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 2 utes/Unit
Commission a
single microwave 1 10
site
Procedure
1. Set the IP address of the portable computer, connect it to
the commissioning port on the IDU, and log in to the web
LCT.
2. In the NE Search tab page, click NE Search and add an
NE.
3. Log in to the NE and change the NE ID based on the NE
ID design file.
4 5 4. Add all logical boards and configure the work modes of
3 the IF board and ODU.
5. set the transmit frequency, transmission and reception
interval, and transmit power based on the design file.
6. Configure the crossing connection and select a proper
clock source from the clock source list based on the design
file.
7. Configure the NE time synchronization.
8. Set the time to monitor NE performance.
9. Set ECC Extension Mode to Automatic.
6 7 Notes
1. The system will automatically restart after the NE ID is
changed. In this case, log in to the NE again for
subsequent configurations.
2. When the NE time is synchronized, ensure that the time
of the computer is the same as the local time.
8 Tools
9
1 Laptop 2 Multimeter 3
4 5 6
Materials
1 2
3 4
5 6
Main Item NO Item
Check PI
Install outdoor PI 1.1 installa
tion
Perform microwave
antenna (diameter: 0.6 1.1 alignmen
m) alignment t
(multimeter)
Installa
Prepare the installation tion
for new network 1.1
deployment scenarios tools
check
Check
the RRU
Power
cable
Prepare labels 1.1 label at
power
system
end(DCDU
)
Check
the CPRI
Prepare labels 1.1 cable
label at
bbu end
Check
the CPRI
Prepare labels 1.1 cable
label at
RRU End
Check
DCDU
power
Prepare labels 1.1 cable at
Power
system
end
Check
door-
Check the hardware 1.1 open
installation Cabinet
in front
view
Check
door-
Check the hardware close
1.1
installation Cabinet
in front
view
Check
Clean the site before the
leaving 1.1 cleanlin
ess
site
Clean the site before entrance
leaving 1.1 record
book
Site
Clean the site before 1.1 overview
leaving
photo
Check
Conduct a power-on check
(microwave) 1.1 the BBU
Light
Check
Conduct a power-on check the
(microwave) 1.1 IDU/RTN
Light
Guide Standard
AppCollection
SiteType Output
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi e 200 N N
deo
picture
Photo/Vi Primitiv
e 200 N N
deo picture
Photo/Vi Primitiv
e 200 N N
deo picture
Primitiv
Photo/Vi e 200 N N
deo
picture
Photo/Vi Primitiv
e 200 N N
deo picture
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi e 200 N N
deo
picture
Photo/Vi Primitiv
e 200 N N
deo picture
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi e 200 N N
deo
picture
Photo/Vi Primitiv
e 200 N N
deo picture
Primitiv
Photo/Vi
deo e 200 N N
picture
Primitiv
Photo/Vi
deo e 200 N N
picture
checkItem severity
ISEHS Default SamplePhotoPlaceholder
Type Level
N Critical
N Critical
N Major
N Major
N Minor
N Critical
N Major
N Major
N Major
N Major
N Major
N Major
N Major
N Major
N Critical
N Major
Installation Quick Guide
1.Check the materials for Microwave:Unpack the packaging, check the 5.Perform microwave antenna (diameter: 0.6 m) alignment
(multimeter):Install a multimeter to monitor signals. Then, adjust the 9.Check the hardware installation:Check hardware installation based
materials, and place them based on installation positions and
sequences. antenna horizontal angle and pitch angle. After the signal strength on the design drawings and quality requirements.
meets the design requirements, tighten the antenna.
6.Make preparations before site visit:Before visiting a site, check site 10.Conduct a dialing test:Set the test terminals and complete voice,
2.Route POE(8core) cable for MW: preparations, especially site access, design files, and materials, based SMS, and website access tests.
on Site Preparation Checklist Before Site Visit.
8.Prepare labels:Correctly fill in/prepare labels in compliance with the 12.Conduct a power-on check (microwave):Power on the equipment
4.Install outdoor PI:#N/A
specifications and attach/install them to cables and equipment. after verifying that the equipment and cables are correctly installed.
Installation Quick Guide
13.Commission a single microwave site:After the equipment is
powered on, connect a portable computer to the commissioning port
and commission the equipment.
Standard Inspect Procedure(SIP)
Site name: Date: Construction team: Supervisor: Overseer:
Cable Pole screw of battery line should be sure to tighten Visually Audit onsite 4
2 installatio Subcont
Signal Signal cable should not be damaged, fracture, tab, signal cable plug without
n ractor / Visually Audit onsite 4
cable damage, the plug connection are correct and reliable;
Huawei
Pigtail routed outside the cabinet, must take protective measures, such as adding
protection tube or channel.RRU equipment optical fiber (CPRI) into the window Visually Audit onsite 4
Subcont before have drip loop;
Without use of optical fiber head and single board interface should be protected by
ractor / Cable Visually Audit onsite 4
protective cap (plug);
Huawei
A tail fiber in the cabinet shall be neatly coiled fiber in disc box or wound into a
Visually Audit+Tape onsite 4
diameter greater than 8cm ring fixed;
Feeder, lightning arrester connection is reliable, outdoor do waterproof processing.
Feeder Subcont Visually Audit onsite 8
Should done drip loop before inter room.
3 installatio ractor / Feeder Feeder grounding in accordance with design, and waterproofing. Visually Audit onsite 4
n Huawei
Bending radius is not less than the diameter of the feeder 10 times. Visually Audit+Tape onsite 4
For 1.2m and above the microwave antenna must be installed reinforcing bar
Visually Audit onsite 4
Antenna Subcont correctly.
4 installatio ractor / Antenna Compare design
n Huawei Microwave /radio antenna model, caliber, hanging high file,visually audit or use onsite 8
telescope to check
Tag Subcont
Power line, ground line, signal cable , optical fiber sticking reliable and neat, label
5 specificat ractor / Tag Visually Audit onsite 4
filled out correctly, meet customer requirements.
ion Huawei
Check the site self-inspection
Hardware Subcont Self- After the subcontractor complete the site installation , according to installation reports,whether self-inspection onsite/
6 self- ractor / inspect standards on the site for the 100% self-inspect and output reports. results is the same whit onsite, remot 8
whether self-inspection
inspect Huawei report qualified to cutover network e
Subcont
Finished Site
7 ractor / The rack should be clean, no debris. Visually Audit onsite 4
cleaning cleaning
Huawei
Standard Tools
Antenna
install
ation
tool
Adjustable
Open-end wrench Hex key (S5)
Compass 1PCS 1PCS wrench (12")
1PCS
1PCS
Auxilia
ry
Tools
Paper and Broom and
Scissor 1PCS Camera 1PCS
pencil 1PCS dustpan 1PCS
Cable
connect
or
process
ing and
connect
ion Long measuring Cable cutter Diagonal pliers
Tools and utility knife
tape 1PCS 1PCS
1SET
Cabinet
s &
Module
Install
ation
Tools Inclinometer Multimeter
1PCS 1PCS
Testing
tools
Test terminal
Laptop 1PCS
1PCS
Standard Tools
EHS
Tools
Helmet&Safety
Seat belts 2PCS Shoes 4SET
Main Equipment List
Transmitting a
3Microwave antenna microwave signal 4 Outdoor PI Outdoor PI
receiving unit
Cable
5 for outdoor module
Special Requirement
CraftName Custom Requirement