1. Type Tests
2. Routine Tests
3. Special Tests
Tests done at Site:
1. Dielectric Tests
2. Measurement of zero-sequence impedance of three-phase transformers
3. Short-Circuit Test
4. Measurement of acoustic noise level
5. Measurement of the harmonics of the no-load current
6. Measurement of the power taken by the fans and oil pumps
7. Tests on bought out components / accessories such as Buchhloz relay,
temperature indicators, pressure relief devices, oil preservation system
etc.
Pre-Commissioning test of transformer
In addition to these, the transformer also goes through some other tests,
performed on it, before actual commissioning of the transformer at site. The
transformer testing performed before commissioning the transformer at site is
called pre- commissioning test of transformer.
These tests are done to assess the condition of transformer after installation
and compare the test results of all the low voltage tests with the factory test
reports.