Professional Documents
Culture Documents
Volume: II
April 2019
Prepared by:
Joint Venture of
Environment and
Resource
Management
Consultant (P) Ltd.
Address: (ERMC)
Gangadevi Marga, Buddhanagar,
Kathmandu
Report Preparation and Quality Check up
Project Name: Detailed Engineering Design of Siwa Khola Small Hydropower Project
Client: : Ministry of Energy, Water Resource and Irrigation, Department of Electricity Development
(DoED)
Consultant: JV of Hydro-Consult Engineering Limited and ERMC P Ltd.
Types of Report: Detail Project Report (Draft) Report Submitted on:
No. of Copies:
Quality Control Assurance
Report Prepared and Checked by the Key Professionals
Designation Name Signature Date
1. Team Leader Manohar Shrestha
2. Project Manager/ Shyam Prasad Bhusal
Hydraulic Engineer
3. Hydropower Engineer Saroj Lal Shrestha
4. Engineering Geologist Diwakar Khadka
5. Hydrologist Bandhu Dhakal
6. Electrical Engineer Ram Bhakta Karki
7. Environmental Engineer Pranav Acharya
This report has been prepared based on available updated data collected from relevant line agencies
from concerned experts as described above
Authorized Person of the Consultant:
1. Name: Manohar Shrestha
Designation: CEO, Hydro-Consult Engineering Ltd. Seal
(Project Coordinator)
Signature:
Signature:
Department of Electricity Development, DoED Detail Design of Siwa Khola Small Hydropower Project
Structural Design Report
LIST OF ACRONYMS
AMSL above Mean Sea Level
ASCE American Society of Civil Engineers
AR Access Road
B/C Benefit/Cost
BL Base Line
BM Bench Mark
BoQ Bill of Quantities
BPC Butwal Power Company
CBR California Bearing Ratio
DBM Design Base Memorandum
DC Direct Current
DCPT Dynamic Core Penetration Test
DDR Detailed Design Report
DEM Digital Elevation Model
DHM Department of Hydrology and Meteorology
DoED Department of Electricity Development
EDR Eastern Development Region
EIA Environmental Impact Assessment
EIRR Economic Internal Rate of Return
EPC Engineering, Procurement, Construction
ERMC Environment and Resource Management Consultant
ERT Electric Resistivity Tomography
FAT Factory Acceptance Tests
FDC Flow Duration Curve
FIDIC International Federation of Consulting Engineers
FSR Feasibility Study Report
GLOF Glacial Lake Outburst Floods
GoN Government of Nepal
GPS Global Positioning System
GWh Gigawatt Hour
S Siwa
SA Siwa Adit
HCE Hydro-Consult Engineering
HEC-RAS Hydrologic Engineering Centres River Analysis System
HFT Himalayan Frontal Thrust
SI Siwa Intake
SP Siwa Powerhouse
HRT Head Race Tunnel
H/W Headworks
lEC International Electrotechnical Commission
lEE Initial Environment Examination
IEO International Electro Technical Commission
INPS Integrated Nepal Power System
IPP Independent Power Producers
Table of Content
List of Acronyms ........................................................................................................... i
List of Figures .............................................................................................................. ix
List of tables ................................................................................................................. xi
1 INTRODUCTION ................................................................................................ 1
1.1 Background ................................................................................................................................................ 1
1.2 Project information .................................................................................................................................. 1
1.3 Salient Features of the Project .............................................................................................................. 2
2 DIVERSION WEIR AND STILLING BASIN ..................................................... 7
2.1 General description ................................................................................................................................. 7
2.1.1 Diversion Weir..................................................................................................................................... 7
2.1.2 Stilling basin ........................................................................................................................................... 7
2.2 Hydraulic Design....................................................................................................................................... 8
2.3 Stability Analysis and Structural Design .............................................................................................. 8
2.3.1 Approach of Stability Analysis ........................................................................................................... 8
2.3.2 Seismic consideration.......................................................................................................................... 9
2.3.3 Subsoil Conditions ............................................................................................................................ 10
2.3.4 Loads .................................................................................................................................................... 11
2.3.5 Structural analysis and design ......................................................................................................... 12
2.3.6 Load Cases.......................................................................................................................................... 12
2.3.7 Results of stability analysis .............................................................................................................. 13
2.3.8 Results of structural design analysis ............................................................................................. 14
2.3.9 Design Codes and Guidelines Referred ...................................................................................... 15
3 FLOOD PROTECTION WALLS ...................................................................... 16
3.1 General Description .............................................................................................................................. 16
3.2 Stability and structural analysis ............................................................................................................ 18
3.2.1 Approach of Stability analysis ......................................................................................................... 18
3.2.2 Seismic consideration....................................................................................................................... 19
3.2.3 Subsoil Conditions ............................................................................................................................ 19
3.2.4 Loads .................................................................................................................................................... 19
3.2.5 Load Cases for Counterfort Flood wall ...................................................................................... 20
LIST OF FIGURES
Figure 2-1: Weir and stilling basin profile................................................................................................................. 8
Figure 3-1General arrangement of U/S flood wall .............................................................................................. 17
Figure 3-2 Longitudinal section of Upstream Flood wall ................................................................................... 17
Figure 3-3 Typical cross section of Upstream Flood wall ................................................................................. 18
Figure 3-4 General arrangement of flood walls along powerhouse and switchyard ................................. 25
Figure 3-5 Longitudinal section of Flood wall along powerhouse and switchyard ..................................... 25
Figure 3-6 Typical cross section of Flood wall along powerhouse and switchyard ................................... 26
Figure 4-1: Undersluice section ............................................................................................................................... 29
Figure 4-2: Trash passage section............................................................................................................................ 30
Figure 4-3:Undersluice SAP model ......................................................................................................................... 35
Figure 5-1 Intake and Gravel Trap sectional view ............................................................................................... 41
Figure 5-2: 3D SAP2000 Model of Intake and Gravel Trap .............................................................................. 45
Figure 5-3: Profile of Gravel trap flushing system ............................................................................................... 49
Figure 5-4: Gravel flushing culvert Section (Separate culvert) and Section (Merged culvert) .................. 49
Figure 5-5: SAP model of flushing culvert.............................................................................................................. 50
Figure 5-6: Profile of Gravel trap flushing gate operating structure ............................................................... 52
Figure 5-7: 3D Shell model of Gravel trap flushing gate operating structure ............................................... 52
Figure 6-1: Typical section of settling basin .......................................................................................................... 59
Figure 6-2: 2D SAP model of settling basin main section .................................................................................. 60
Figure 6-3: 3D SAP2000 Model of Settling Basin main section ........................................................................ 60
Figure 6-4: Typical section of Headpond ............................................................................................................... 66
Figure 6-5: 3D SAP2000 Model of Headpond ...................................................................................................... 67
Figure 7-1: Inlet portal Section ................................................................................................................................ 70
Figure 8-1 Arrangement of Surge Shaft ................................................................................................................. 75
Figure 8-2: 3D SAP2000 Model of Surge Shaft..................................................................................................... 81
Figure 9-1: Powerhouse Machine Floor plan with service bay and control building................................... 85
Figure 9-2: Longitudinal Section of Powerhouse ................................................................................................. 86
Figure 9-3: Cross section of Powerhouse ............................................................................................................. 86
Figure 9-4: AutoCAD 3D model of the proposed powerhouse machine foundation ............................... 89
Figure 9-5: Super structure frame ........................................................................................................................... 93
Figure 9-6: Purlin and sheet dead load in roof truss......................................................................................... 101
LIST OF TABLES
Table 1-1: Salient features of the project ................................................................................................................. 2
Table 2-1: Criteria for stability analysis for Weir................................................................................................... 8
Table 2-2: Value of basic seismic coefficient for different zones ........................................................................ 9
Table 2-3: Value of Importance Factor, I ............................................................................................................... 10
Table 2-4: Value of β for different soil-Foundation system............................................................................... 10
Table 2-5: Results of Stability analysis of Weir .................................................................................................... 14
Table 2-6: Results of Structural analysis of Weir ................................................................................................ 14
Table 3-1: Retaining wall stability criteria .............................................................................................................. 18
Table 3-2: Load condition ......................................................................................................................................... 20
Table 3-3: Stable flood wall section details of Upstream Flood Wall ............................................................. 22
Table 3-4: Structural analysis output for counterfort, H=9.8 m ...................................................................... 23
Table 3-5: Structural design summary of counterfort, H=9.8 m ..................................................................... 24
Table 3-6: Stable flood wall section details along Switchyard area ................................................................. 26
Table 3-7: Stable flood wall section details along Powerhouse area .............................................................. 27
Table 3-8: Stable flood wall section details of Tailrace area ............................................................................. 27
Table 3-9 : Stability analysis summary for Counterfort wall, H=14.1 m ........................................................ 27
Table 3-10: Structural analysis output for Cantilever Floodwall ..................................................................... 28
Table 3-11 : Structural design summary of Cantilever Floodwall, H=7.0m .................................................. 28
Table 4-1: Criteria for stability analysis for Undersluice ................................................................................... 31
Table 4-2: Load Cases used in SAP 2000 Model ................................................................................................. 37
Table 4-3: Load Combination................................................................................................................................... 37
Table 4-4: Results of stability analysis..................................................................................................................... 38
Table 4-5: Results of structural analysis ................................................................................................................. 38
Table 5-1: Criteria for stability analysis for Intake and Gravel Trap .............................................................. 41
Table 5-2: Stability Analysis Load Conditions for Intake and Gravel Trap.................................................... 43
Table 5-3: Load Cases used in SAP 2000 Model ................................................................................................. 46
Table 5-4: Load combinations .................................................................................................................................. 46
Table 5-5: Result of stability analysis ...................................................................................................................... 47
Table 5-6: Results of Structural design .................................................................................................................. 48
Table 5-7: Load cases for Structural analysis of Gravel trap flushing culvert ............................................... 50
1 INTRODUCTION
1.1 Background
This report has been prepared as a part of agreement signed between Department of Electricity
Development, DoED and JV of Hydro consult Engineering and ERMC for Detail engineering design of
Siwa Khola Small hydropower Project. The report describes the outcome of Structural analysis and
design of various components of the project. The stability analysis, structural analysis, design and
their results have been provided in the report. The hydraulic design, energy calculation, plant
optimization, and project evaluation have been included in Project description report.
A two chambered settling basin is designed to settle the suspended sediments of size greater than
0.15 mm. Flushing arrangements have been provided at the end of each bay to flush the settled
sediments back in to the river through a flushing culvert.
The design discharge of 5.49 m3/s will be conveyed to the headrace tunnel through a power culvert
from a headpond provided at the outlet of settling basin. The length of headrace tunnel before Surge
Shaft about 4635.31m. Whereas, the tunnel length after Surge shaft is about 85.46m. An underground
Surge Shaft is provided to subside the surge before reaching to the headrace pipe. The invert level of
Surge Shaft is at an elevation of about 1611.94 masl and it is connected to the headrace pipe through
an offset pipe of length about 21 m. The length of penstock pipe is about 1198m which feds the
water to the two sets of horizontal pelton turbines inhoused in the powerhouse located at right bank
of Mewa Khola to produce 26.86 MW of power. The tail water coming out of the powerhouse will
be diverted to the Mewa Khola through a tailrace Culvert of length 72.80 m.
1 Project Location
Development Region Eastern
Zone Mechi
District Taplejung
2 General
Name of River Siwa Khola
Nearest Town Taplejung Bazar
Type of Scheme Run-of-river
Gross Head 582.50 m
Rated Net Head 568.08 m
3 Hydrology
Catchment Area 131.56 km2
Catchment Area Below 3000 35.07 km2
Catchment Area above 3000 and below 5000 96.48 km2
Catchment Area above 5000 0.00 km2
Design Discharge (41.9% exceedance flow) 5.49 m3/s
Long term annual average flow 43.03 m3/s
Snow Covered Area Not Seen km2
Possibility of GOLF No threat is seen
Design flood at intake (1 in 100 Years) 326.31 m3/s
Design flood at tailrace (1 in 100 Years) 1133.45 m3/s
JV of Hydro-Consult Engineering & ERMC Page 2
Department of Electricity Development, DoED Detail Design of Siwa Khola Small Hydropower Project
Structural Design Report
Telemetric Station
Location and Rular Municipality Meringden Rural Municipality,
Ward No.-6 (Nalbu VDC),
Pandolun
Transmitter Unit
Latitude 27°29'30.34"N
Longitude 87°35'48.80"E
Receiver Unit
Latitude 27°29'29.04"N
Longitude 87°35'54.35"E
5 Weir
Broad crested Sloping Glacis
Weir Type Free flow
Weir Crest Length (excluding undersluice) 27.50 m
Weir Height (from U/S river bed) 4.50 m
Weir Crest Elevation 1628.50 masl
Operation Platform Elevation 1634.20 masl
Stilling Basin Length 28.80 m
6 Undersluice
Size of Undersluice Opening (b x h)
Width (b) 3.00 m
Height (h) 3.00 m
No of undersluice gates 1.00 nos.
Invert Level 1624.00 masl
7 Intake
Type of Intake Side Intake
Size of Intake Opening
Width (b) 3.60 m
Height (h) 1.50 m
Number of Openings 2.00 nos.
Invert Level 1626.00 masl
JV of Hydro-Consult Engineering & ERMC Page 3
Department of Electricity Development, DoED Detail Design of Siwa Khola Small Hydropower Project
Structural Design Report
8 Gravel Trap
No of Hopper 2.00 nos
Width of Each Hopper at Top 3.60 m
Uniform Length of Gravel Trap at base 4.00 m
Total Length of Gravel Trap 13.85 to 18.90 m
Total Width of Gravel Trap at Top (including
m
the divide wall between both Traps) 8.20
Width of hopper 1.00 m
Width of Flushing Gate 1.00 m
Height of Flushing Gate 1.00 m
Length of Flushing Culvert 32.09 m
9 Approach Canal
No of approach canal 2 nos
Bottom width of canal 3.60 m
Top width of canal 3.60 m
Water height in canal 1.00 m
Provided Bed Slope 1 in 500.0
Length of canal 3.20 m
Normal water level at canal inlet 1628.40 masl
Canal invert level at inlet 1627.40 masl
10 Settling basin
Sediment size to be settled 0.15 mm
Number of bays 2.00
Length of Settling Basin (Main Section) 65.00 m
Width of Settling Basin 9.00 m
Efficiency 90.04%
Water Depth 2.30 m
11 Power Culvert
Length 40.05 m
Width 3.00 m
Height 3.00 m
12 Portals
Inlet Portal 3.00 x 3.00 m
3042914.75 N
557665.15 E
13 Tunnel
Shape D-Shaped
Total length ( inlet to outlet portal) 4720.77 m
Headrace Tunnel 4635.31 m
Penstock Tunnel 85.46 m
Adit Tunnel 577.7 m
Width 3.00 m
Height 3.00 m
14 Surge Shaft
Finished Diameter 5.00 m
Upsurge Level 1637.00 masl
Downsurge level 1618.75 masl
Top Level of Surge Shaft including freeboard 1641.11 masl
Bottom Invert level of Surge Shaft 1611.94 masl
Total height including freeboard and
m
submergence 29.17
15 Penstock Pipe
Diameter 1.40 m
Length (including the embedded penstock and
m
the branch pipes after bifurcation) 1198.22
17 Tailrace Culvert
Tailrace Length 72.80 m
Shape Rectangular Box Culvert
Width 2.00 m
Height 1.60 m
Slope before confluence 1 in 400
Slope after confluence 1 in 200
Chute at outlet 1 in 4
18 Turbine
Type Horizontal Shaft PeltonTurbine
Number of units 2
Efficiency 90.50%
19 Generator
Number of Units 2
Efficiency 97%
Voltage 11 kV
10 Switchyard
Width 24.50 m
Length 50.50 m
21 Transmission Line
Length 17.0 Km
Voltage 132 kV
21 Economic Indicator
B/C Ratio of the project 1.76
IRR on the project 16.23%
IRR on equity 20.75%
from IS codes and other reliable literatures. However, the bearing pressure shall not exceed 250
KN/m2 at surface. In case of rocks, suitable values will be taken following codes and practices and
depending on the geological investigation data, if any.
Unit weight of dry soil = 13 KN/m3
Unit weight of saturated soil =19 KN/m3
Unit weight of submerged soil = 9 KN/m3
Angle of repose for the soil (f) = 30˚
The above mentioned soil parameters have been used for computation of active and passive pressure
due to soil for Weir components of the head work.
2.3.4 Loads
Following loads were applied for stability analysis and structural analysis.
Dead load
The dead load includes loads that are relatively constant over time, including the weight of the
structure itself. This type of load may also include the weight and invariable loads attached to the
structure. The weight of a structure has been calculated in per meter basis for stability analysis
whereas it is calculated and applied to SAP 2000 by software itself. The plan geometry has been
modeled in SAP whereas thickness and the material weight properties were defined for each
structure. The material properties and dimensions used are as follows:
Concrete specific weight = 25 KN/m3
Dead load taken in Stability analysis and structural analysis (SAP model)
Dead
Weight of soil
Upthrust
Surcharge load
Weight of boulder
Active earth pressure
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure.
Live load used for Stability analysis and structural analysis (SAP model) in this project are:
Hydrostatic load in normal flow
Hydrostatic load in average monsoon
Hydrostatic load in 200 year flood
Uplift load in normal flow
Uplift load in average monsoon
Uplift load in 200 year flood
JV of Hydro-Consult Engineering & ERMC Page 11
Department of Electricity Development, DoED Detail Design of Siwa Khola Small Hydropower Project
Structural Design Report
Seismic loads:
These loads are the loads due to the effect of the earthquake on the structure and the surrounding.
The earthquake load has been calculated on the basis of IS: 1893- 1984 and applied manually as a
uniformly varying load or point load depending on the structure. The horizontal seismic coefficient
has been taken as 0.24 and the base shear thus obtained has been applied as a uniformly varying load
on the member or as point load.
Dead Load
Reservoir water surface elevation 1629.41 masl
Earth Pressure(Active)
Uplift Pressure
Dead Load
Reservoir water surface elevation 1629.41 masl
Earth Pressure(Active)
Uplift Pressure
Seismic Load(Horizontal and Vertical)
Hydrodynamic Force
Dead Load
Reservoir water surface elevation 1632.20 masl
Earth Pressure(Active)
Uplift Pressure
The Downstream Flood wall plan, profile and cross section are presented below. For detail
drawings of the Flood Wall plan, profile and sections refer “Detail Project Report: Volume VII:
Part A: Civil Drawings, Drawing No: 78/04/22C01-03”
3.2.4 Loads
Following loads were applied for stability analysis and structural analysis.
Dead load
The dead load includes loads that are relatively constant over time, including the weight of the
structure itself. This type of load may also include the weight and invariable loads attached to the
structure. The weight of a structure has been calculated in per meter basis .The material properties
and dimensions used are as follows:
Concrete specific weight = 25 KN/m3
Dead load taken in Stability analysis and structural analysis
Self-weight of Structure
Weight of soil
Surcharge load (considered only in Switchyard area)
Active earth pressure
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure.
Live load used for Stability analysis and structural analysis in this project are:
Hydrostatic load in dry condition
Hydrostatic load in annual monsoon
Hydrostatic load in 100 year flood
3.2.6.6 Design for tension at the interface of counter fort and vertical wall
Tu= 0.87*fy*Ast
Tu=1.5*Ka*Ys*h*c/c spacing of counter forts
Where, Tu ultimate maximum tension in 1m height of wall at critical section.
3.2.6.7 Design for tension at the interface of counter fort and heel slab
Tu =1.5*Net pressure at the end of heel slab*spacing of counter forts
For base slab, load case which gives maximum bearing pressure is considered into account.
Structural Analysis is done considering the optimization of use of steel as well as maintaining
the safety of structure being on the pessimistic side.
Partial factor of safety for concrete is taken as 1.5
Partial factor of safety for steel is taken as 1.15
While structural design, being pessimist a slight higher value of area of steel is taken.
The structural members are designed by using limit state method in which the structure shall
withstand safely all loads liable to act on it throughout its life. It shall also satisfy the serviceability
requirements such as limitations on cracking.
The moment, shear force in the above cases has been calculated manually, The design of the
structure has been done according to the maximum moment and shear force among all the required
combinations.
The area of steel has been calculated from the relation given below:
100 Ast
Pt
bd
Where Pt =
And
The designed wall has been also checked for safety in shear forces.
Vu
Shear stress in concrete has been calculated as v
bd
Where,
Vu=Maximum shear force
b = width of the designed member, taken for 1 m width
d = thickness of the designed member
Allowable shear stress for the required grade of concrete and above designed main
reinforcement bars were taken from IS 456:2000 – Table 19.
Concrete
Grade: C25
Clear Concrete cover: 50 mm
Reinforcements
Grade : Fe 500
Development length : 50Ф
Crack width
The maximum crack width allowed for any structural element is 0.2 mm as per IS 456. The crack
width has been calculated by using ANNEX F of IS 456:2000.
Table 3-3: Stable flood wall section details of Downstream Flood Wall
Name Height Base Heel Toe Bottom stem Top stem Backfill Type
Design of Downstream flood wall has been done to acquire optimum output. Here below enlisted
summary tables are for counterfort wall having height 9.8m. For detail calculation, refer “Detail
Project Report – Volume VI: Annex G”.
Flood
Considering Considering
Without EQ EQ Without EQ EQ Without EQ
789.837 789.837 649.551 649.551 639.592
Total Vertical load,
KN
Total Horizontal
load, KN -195.194 -299.223 -165.419 -260.089 -150.676
Resisting Moment,
KNm 3357.058 3357.058 4204.252 4204.252 4780.235
Overturning
Moment, KNm 637.634 954.450 2024.177 2321.806 2572.521
Max. Pressure 143.163 144.855 109.735 132.394 116.724
Min. Pressure 99.863 98.172 90.127 67.468 80.074
Eccentricity (e) -0.193 0.208 -0.106 0.352 -0.202
F.O.S. against Sliding 2.83 1.85 2.75 1.75 2.97
F.O.S. against
Overturning 5.26 3.52 2.08 1.81 1.86
F.O.S against
Floatation - - 2.59 2.59 2.15
Remaining sections which are mentioned above in Table 3-73 in the downstream of weir are
Counterfort Retaining Wall, which are also safe against sliding, overturning, bearing and floatation.
Along Powerhouse
In this portion we have dealt with retaining wall as per the need of site conditions and for
optimization of the section. 153.5m long Flood Wall been provided at the Powerhouse along the
right bank taking the 100 year return period design flood 1041.43 masl . The height of 7.0m has been
provided from the scour depth calculation and with the starting from Switchyard along Powerhouse
to Tailrace. The height of the Flood wall throughout the section is 7.0 m with the provision of 40cm
thick hard stone lining correspondence to the design of downstream of Weir. Total length of Flood
wall at Switchyard and Powerhouse along the right bank is 156.5m. 100 years design flood along the
switchyard is fixed at 1041.43 masl for the design of Flood wall of length 30m and 1040.22 masl for
the designed Floodwall of length 35. Similarly, 100 years design flood along the Powerhouse is fixed
at 1039.71 masl for the design of Flood wall of length 25m and 1038.50 masl for the designed
Floodwall of length 12m. Also, 100 years design flood along the Tailrace is fixed at 1037.66 masl for
the design of Flood wall of length 29.5m. The Floodwall has been designed as concrete structure with
uniform thickness and uniform height. The structural concrete used in all the cases is C25 grade
concrete.
Basic assumptions considered for flood wall stability analysis:
Level of backfill height is 1046.60 masl which should be strictly followed in highest Floodwall
The back fill soil is assumed to be fully saturated upto the river water level considering the
unit weight 19 KN/m2 and the weight of remaining backfill is calculated considering the unit
weight 15 KN/m2 .
Provision of perforated pipe is assumed in the backfill.
Passive earth pressure at the toe from the river side is ignored.
The upstream Flood wall plan, profile and cross section are presented in Figure 3-4, Figure 3-5
and Figure 3-6 respectively. For etail drawings of the Flood Wall plan, profile and sections refer
“Detail Project Report: Volume VIII: Part A: Civil Drawings, Drawing No: 78/04/43C01-C06”
Figure 3-4 General arrangement of flood walls along powerhouse and switchyard
Figure 3-5 Longitudinal section of Flood wall along powerhouse and switchyard
Figure 3-6 Typical cross section of Flood wall along powerhouse and switchyard
Table 3-6: Stable flood wall section details along Switchyard area
Height Base Heel Toe Bottom stem Top stem Backfill Type
Table 3-7: Stable flood wall section details along Powerhouse area
Design of Switchyard and Powerhouse flood wall has been done to acquire optimum output. Here
below enlisted summary tables are for cantilever floodwalls having height 7.0m. For detail calculation,
refer “Detail Project Report – Volume VI: Annex I”.
Remaining sections which are mentioned above in Table 3-7 and Table 3-8 in the Powerhouse and
Tailrace area respectively are Cantilever Retaining Wall, which are also safe against sliding,
overturning, bearing and floatation.
4.1.1 Undersluice
The undersluice has been proposed at right bank of Siwa Khola, parallel to the weir axis. It has been
intended for prevention of large amount of sediment entering into the intake and to pass a portion of
high flood discharge through its conduit along with the flushing of large size sediments to the
downstream of the river. It has been provisioned with a single radial gate of opening size 3m x 3m
(W x H). The gate regulation of undersluice will guide the design discharge flow through intake
during the low flow season with least amount of sediment during flood. Considering the size of
boulders available at headworks site, it is assumed that the river will carry the boulders of size above
1.5 m rarely. It should be wide enough to keep the approach velocities sufficiently lower than critical
velocities to ensure maximum settling of suspended sediment load at intake while it remains closed.
Since the floor and the walls of the undersluice are highly susceptible to abrasion, the walls will be
steel lined and the floor will be lined with 50cm hard stone along with alternate concrete beams. The
proposed undersluice profile is shown in Figure 4-1. For detail civil drawing of the undersluice refer
“Detailed Project Report, Volume VII: Part A: Civil Drawings, Drawing No: 078/04/21C01 and
21C02”.
4.3.4 Loads
Following loads were applied for stability analysis and structural analysis.
Dead load
The dead load includes loads that are relatively constant over time, including the weight of the
structure itself. This type of load may also include the weight and invariable loads attached to the
structure. The weight of a structure has been calculated in per meter basis for stability analysis
whereas it is calculated and applied to SAP 2000 by software itself. The plan geometry has been
modeled in SAP whereas thickness and the material weight properties were defined for each
structure. The material properties and dimensions used are as follows:
Concrete specific weight = 25 KN/m3
Dead load taken in Stability analysis and structural analysis (SAP model)
Dead
Weight of soil
Upthrust
Surcharge load
Weight of boulder
Active earth pressure
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure.
Live load used for Stability analysis and structural analysis (SAP model) in this project are:
Hydrostatic load in normal flow
Hydrostatic load in average monsoon
Hydrostatic load in 200 year flood
Uplift load in normal flow
Uplift load in average monsoon
Uplift load in 200 year flood
Seismic loads:
These loads are the loads due to the effect of the earthquake on the structure and the surrounding.
The earthquake load has been calculated on the basis of IS: 1893-1984 and applied manually as a
uniformly varying load or point load depending on the structure. The horizontal seismic coefficient
has been taken as 0.24 and the base shear thus obtained has been applied as a uniformly varying load
on the member or as point load.
y Ast
M lim 0.87 y Ast d 1
b d f ck
The area of steel has been calculated from the above relation.
The designed wall has been also checked for safety in shear forces.
Vu
c
Shear stress in concrete has been calculated as bd
Where,
Vu=Maximum shear force
b = width of the designed member, taken for 1 m width
d = thickness of the designed member
Allowable shear stress for the thickness and above designed main reinforcement bars were
taken from IS 456:2000 – Table 23.
Concrete
Grade: C25
Clear Concrete cover: 75 mm (For structure’s surface exposed to backfilling and water)
: 50mm (For remaining surface)
Reinforcements
Grade : Fe 500
Development length : 50Ф
Deflection criteria
The maximum allowable deflection for all the structural members should comply with the deflection
criteria given in IS 456:2000 (chapter 23.2).
Crack width
The maximum crack width allowed for any structural element is 0.2 mm as per IS 456. The crack
width has been calculated by using IS ANNEX F of 456:2000.
Dead Load
Reservoir water surface elevation 1629.41 masl
Earth Pressure(Active)
Uplift Pressure
Dead Load
Reservoir water surface elevation 1628.5 masl
Earth Pressure(Active)
Uplift Pressure
Seismic Load(Horizontal and Vertical)
Hydrodynamic Force
Dead Load
Reservoir water surface elevation 1629.41 masl
Earth Pressure(Active)
Uplift Pressure
Seismic Load(Horizontal and Vertical)
Hydrodynamic Force
Dead Load
Reservoir water surface elevation 1632.2 masl
Earth Pressure(Active)
Uplift Pressure
Following are the load cases used in SAP2000 model for structural analysis.
16 mm dia @150
25 mm dia @150 mm c/c Refer structural
3 Breast wall mm c/c spacing on
spacing on both faces drawings
both faces
16 mm dia @150
20 mm dia @150 mm c/c Refer structural
4 Floor Slab mm c/c spacing on
spacing on both faces drawings
both faces
12 mm dia @150
16 mm dia @150 mm c/c Refer structural
5 Operation Platform mm c/c spacing on
spacing on both faces drawings
both faces
Trunion Block (along 16 mm dia, 1 layer
25 mm dia, 1 Layer @150 Refer structural
6 horizontal @150 mm c/c
mm c/c spacing drawings
Direction) spacing
16 mm dia @150
Trunion Block (along 16 mm dia @150 mm c/c Refer structural
7 mm c/c spacing on
Vertical Direction spacing on both faces drawings
both faces
Note: The lap length shall be maintained at least 50 times the larger size rebar dia.
5.1.1 Intake
A submerged orifice type side intake with two openings is designed to draw the discharge of 6.863
m3/s (including 25% additional discharge, required for flushing of gravel trap and settling basin and
canal overrating) at the normal water level 1628.50 masl (water level at weir crest level).The flow
velocity through the intake orifice at normal water level is limited to 0.775 m/s. A coarse trash rack
consisting of 20 mm thick bars spaced at 100mm center to center will be kept at an inclination of 80°
with the horizontal direction. The invert level of intake orifice has been kept 2 m above the invert
level of undersluice, at a level of 1626.00 masl to prevent the entry of bed load into the intake
chamber from the river. The water will enter a small culvert of the intake through two openings of
size 3.6m x 1.5m and then flow to the gravel trap. Top level of the intake gate will be at 1 m below
the weir crest level to prevent the entry of floating debris into the intake. The upper part of the
intake above the trash racks will have a breast wall to control the entrance of flood water into the
water conveyance system. The intake gate is operated to control the entry of excessive discharge
into the intake during high flow in the river. The plant will be operated only up to the 10 year flood.
A trash passage structure is provided at the left side of the intake. For detail Civil drawings, refer
“Detail Project Report, Volume VII: Part A: Civil Drawings, Drawing No: 78/04/23C01-C06”.
Table 5-1: Criteria for stability analysis for Intake and Gravel Trap
Intake and Gravel Trap stability criteria
h I o
Where,
αh= horizontal seismic coefficient
β = a coefficient depending upon soil foundation system = 1 (for boulder mixed soil foundation on
raft footings)
I = importance factor depending upon type of structure = 3 (as intake is one of the most important
structures in the project)
αo= basic horizontal seismic coefficient = 0.08 (for zone V)
The horizontal seismic coefficient αh =0.24
5.3.4 Loads
Following loads were applied for stability analysis and structural analysis.
Dead load
The dead load includes loads that are relatively constant over time, including the weight of the
structure itself. This type of load may also include the weight and invariable loads attached to the
structure. The weight of a structure has been calculated in per meter basis for stability analysis
whereas it is calculated and applied to SAP 2000 by software itself. The plan geometry has been
modeled in SAP whereas thickness and the material weight properties are defined for each structure.
The material properties and dimensions used are as follows:
Concrete specific weight = 25 KN/m3
Dead load taken in Stability analysis and structural analysis (SAP model)
Dead
Weight of soil
Upthrust
Surcharge load
Active earth pressure
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure.
Live load used for Stability analysis and structural analysis (SAP model) in this project are:
Hydrostatic load in normal flow
Hydrostatic load in annual monsoon condition
Hydrostatic load in 200 yr flood
Uplift load in normal flow
Uplift load in annual monsoon condition
Uplift load in 200 yr flood
Seismic loads:
These loads are the loads due to the effect of the earthquake on the structure and the surrounding.
The earthquake load has been calculated on the basis of IS: 1893-1984 and applied manually as a
uniformly varying load or as a point load. The horizontal seismic coefficient has been taken as 0.24
and the base shear thus obtained has been applied as a uniformly varying load on the member or as
point load.
y Ast
Resisting Moment, M 0.87 y Ast d 1
b d f ck
The area of steel has been calculated from the above relation.
The designed wall has been also checked for safety in shear forces.
Vu
Shear stress in concrete has been calculated as c
bd
Where,
Vu=Maximum shear force
b = width of the designed member, taken for 1 m width
d = thickness of the designed member
Allowable shear stress for the thickness and above designed main reinforcement bars were
taken from IS 456:2000 – Table 23.
Concrete
Grade: C25
Clear Concrete cover: 75 mm (For structure’s surface exposed to backfilling and water)
: 50mm (For remaining surface)
Reinforcements
Grade : Fe 500
Development length: 50Ф
Deflection criteria
The maximum allowable deflection for all the structural members complies with the deflection
criteria given in IS 456:2000 (chapter 23.2).
Crack width
The maximum crack width allowed for any structural element is 0.2 mm as per IS 456. The crack
width has been calculated by using ANNEX F of IS 456:2000.
Normal Flow
Annual
Monsoon
200 yr flood
opened
High flood water level
and Gate Closed
Normal Operation
water level and gate
closed during
1.2(Dead Load + Live Earthquake
3 1.2*( A+B+C+D+E+F+G+H±(I+J))
Load± EQ)
Average Monsoon
water level during
Earthquake
**The extreme loading case in Intake gate portion is during High flood level at U/S and intake gate is
closed; such that no water at immediate d/s of gate.
Minimum Maximum
FOS
FOS against Bearing Bearing
S.No Condition against
Overturning pressure pressure
Sliding
(KN/m2) (KN/m2)
1 Normal Condition 2.71 4.72 105.21 118.28
2 Annual Monsoon Condition 2.46 3.68 106.68 109.59
16 mm dia @150 mm
Intake & Gravel Trap 16 mm dia @150 mm
4 c/c spacing on both faces
Side Wall c/c spacing on both faces
for bottom half
20 mm dia @150 mm
16 mm dia @150 mm
10 Middle Pier Inlet c/c spacing on both faces
c/c spacing on both faces
for bottom half
16 mm dia @150 mm
c/c spacing on both faces
for upper half
20 mm dia @150 mm
16 mm dia @150 mm
12 Middle pier outlet c/c spacing on both faces
c/c spacing on both faces
for bottom half
16 mm dia @150 mm
c/c spacing on both faces
for upper half
Note: The lap length shall be maintained at least 50 times the larger size rebar dia.
Table 5-7: Load cases for Structural analysis of Gravel trap flushing culvert
C Uplift
D Water load
Culvert Empty
Culvert Full
E Bearing pressure
Culvert Empty
Culvert Full
2 Side Wall (0.6m) 16 mm dia @150 mm c/c 12 mm dia @150 mm Both sides
spacing on both faces c/c spacing on both faces
Note: The lap length shall be maintained at least 50 times the maximum size rebar dia.
Figure 5-6: Profile of Gravel trap flushing Figure 5-7: 3D Shell model of Gravel trap
gate operating structure flushing gate operating structure
Table 5-10: Load cases for Structural analysis of Gravel trap flushing gate operating
structure
C Bearing pressure
Culvert Empty
Culvert Full
E Operation Load
Note: The lap length shall be maintained at least 50 times the maximum size rebar dia.
6.1.3 Headpond
Outlet transition of the settling basins has been used as headpond to maintain tranquil water level at
the start of the power culvert. Headpond is a 10m high wall creating a ponding at outlet of settling
basin in order to guide the water inside penstock pipe. A fine trash rack of size 4m wide and 4m high
with bar spacing of 30 mm has been provided at the end of head pond located at outlet of settling
basin. The inclination of the rack is 80⁰with the horizontal. Below the base slab, starting from settling
basin outlet, flushing culvert has been placed which ends at 45m downstream from the outlet basin.
Since the cohesion intercept value is unknown, the factor of safety in sliding without considering
cohesion intercept value has been considered as shown in Table 6-1.
Table 6-1: Criteria for stability analysis for Settling Basin and Headpond
Stability Criteria
Earthquake
3 (Extreme) 1.3 1.2 1.2 <1.33*Qsafe B
h I o
Where,
αh= horizontal seismic coefficient
β = a coefficient depending upon soil foundation system = 1 (for boulder mixed soil foundation on
raft footings)
I = importance factor depending upon type of structure = 1.5 (for water towers and tanks)
αo= basic horizontal seismic coefficient = 0.08(for zone V)
JV of Hydro-Consult Engineering & ERMC Page 56
Department of Electricity Development, DoED Detail Design of Siwa Khola Small Hydropower Project
Structural Design Report
6.3.4 Loads
Following loads were applied for stability analysis and structural analysis of the structures.
Dead load
The dead load includes loads that are relatively constant over time, including the weight of the
structure itself. This type of load may also include the weight and invariable loads attached to the
structure. The weight of a structure has been calculated in per meter basis for stability analysis
whereas it is calculated and applied to SAP 2000 by software itself. The plan geometry has been
modeled in SAP2000whereas thickness and the material weight properties were defined for each
structure. The material properties and dimensions used are as follows:
Concrete specific weight = 24 KN/m3
Dead load taken in Stability analysis and structural analysis (SAP2000 model)
Dead
Active Earth pressure
Passive Earth Pressure
Uplift
Bearing
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure.
Live load used for Stability analysis and structural analysis (SAP2000model) in this project are:
Weight of water
Hydrostatic load
Hydrodynamic load
Seismic loads:
These loads are the loads due to the effect of the earthquake on the structure and the surrounding.
The earthquake load has been calculated on the basis of IS: 1893-1984 and applied manually as a
uniformly varying load. The horizontal seismic coefficient has been taken as 0.12 and has been applied
as a uniformly varying load on the member.
y Ast
Resisting Moment, M 0.87 y Ast d 1
b d f ck
The area of steel has been calculated from the above relation.
The designed wall has been also checked for safety in shear forces.
Vu
Shear stress in concrete has been calculated as c
bd
Where,
Vu=Maximum shear force
b = width of the designed member, taken for 1 m width
d = thickness of the designed member
Allowable shear stress for the thickness and above designed main reinforcement bars were
taken from IS 456:2000 – Table 23.
Concrete
Grade: C25
Table 6-2: Load considered for stability and structural analysis of Settling Basin
load
Active Earth pressure on
B G Hydrostatic load in right bay
left wall
Passive Earth pressure on Hydrodynamic load in left
C H
flushing culvert walls bay
Hydrodynamic load in right
D Uplift I
bay
E Bearing J Water weight in left bay
K Water weight in right bay
Maximum Minimum
FOS FOS Bearing Bearing
Cases Description pressure pressure
Sliding Overturning
(KN/ m2) (KN/m2)
Bar Bar
Structure Component Location Type diameter spacing
(mm) (mm)
Main 20 150
vertical wall
Distribution 16 150
vertical wall
Settling basin inlet transition
Main 16 150
hopper Whole component
Distribution 16 150
Main 16 150
Bottom slab Whole component
Distribution 16 150
Hunch bar Whole component 16
Cap bar Whole component 12
Main 20 150
4.5 m from the starting of vertical wall
Vertical Side walls and Distribution 16 150
divide walls Main 16 150
Remaining height
Distribution 16 150
Main 16 150
Settling basin Main section Hopper Inclined slab Whole structure
Distribution 16 150
Flushing culvert wall and Main 16 150
Whole structure
slab Distribution 16 150
Hunch bars Whole structure 16 150
Cap bars Whole structure 12 150
Base Slab
Distribution bar 25 150
Note: The lap length shall be maintained at least 50 times the larger size rebar dia.
Table 7-1 Rock mass distribution prediction along the headrace tunnel
De =
The excavation support ratio is related to the use for which the excavation is intended and the extent
to which some degree of risk is acceptable. For hydropower tunnels the ESR is 1.6, and for
underground power stations the ESR is 1.0. According to the handbook published by NGI in 2013, ESR
value is taken as 1when the value of Q is < 0.1.
The Equivalent Dimension, De is plotted against the value of ‘Q’ to define a number of support
categories. Barton’s chart was updated by Grimstad and Barton (2002) and has been reproduced as
shown hereunder in Error! Reference source not found., which is used for rock support estimation.
According to Barton et al. (1974), the length of rockbolt can be estimated from the excavation width B
and the Excavation Support Ratio ESR:
0.15B
L=2+
ESR
The length is also derived from using Palmstrom formula, which is for block diameter (Db) of 0.1m, we
get a required rock bolt length {Lb(roof)} of 1.4+0.16Dt(1+0.1/Db) ≈ 2.5 m. A Db of 0.1m would
correspond to extremely poor rock. Likewise, for Db 0.25 m, Lb is ≈2.2 m which resemble to poor to
fair rock. With a Db of 0.5 m we get a required Lb (roof) of ≈2.1 m which resemble to fair to good
rock. The same rock bolt length for both crown and wall are used for convenience.
Based on all those relevant studies, field observations and the rock mass quality assessment the most
appropriate rock support design has been finally carried and presented in the Table 7-2Error!
Reference source not found..
8 SURGE SHAFT
Type C25
Characteristic Strength of Concrete, fck 25 N/mm2
Modulus of Elasticity of Concrete (EC) 2.50E+05 kg/cm2
Poisson's Ratio of concrete (νc) 0.2
Permissible Tensile Stress in C25 concrete (Direct
Tension σtd) 13 kg/cm2
Permissible Tensile Stress in C25 concrete (Tension
due to Bending) 18 kg/cm2
Permissible Stress in C25 concrete (Direct
Compression σcc) 60 kg/cm2
Permissible stress in C25 concrete (Bending
Compression σcbc) 85 kg/cm2
Ultimate compressive strength of concrete prism (u)-
for crack width 167.5 kg/cm2
Type Fe 500
Yield Strength fy For Fe500 5000.00 kg/cm2
Permissible Tensile Stress (σst) 2750.00 kg/cm2
Modulus of Elasticity (ES) 2.00E+06 kg/cm2
8.3.3 Loads
Following loads were applied for stability analysis and structural analysis.
Dead load
The dead load includes weight of the structure only in the case of surge shaft. Since the structure is
underground and constructed in rock no other loads are considered for the dead load
Live loads
Live loads are the variable load on the structure that adds on to the dead or intrinsic load of the
structure. In case of the surge shaft, the hydraulic load and the grouting load are considered as the live
loads.
Live load cases for the structural analysis in SAP2000 are;
a. Internal hydrostatic load and
b. External hydrostatic load
Internal and external hydrostatic load is considered due to water pressure from the water till the
maximum upsurge elevation.
Seismic loads:
In surge shafts, seismic factors are of no practical importance when lining is in contact with rock.
However, IS: 1893 is considered for the design of surge shaft under seismic condition. Elements not in
contact with rock and those in overburden should be checked against seismic forces.
The reinforced concrete lining provided transmits pressure to the surrounding rock under ideal
condition of no void and infinite elastic rock mass. The load shared by the rock can be determined by
the following formula by equating the displacements of outer circumference of the concrete ring with
the extension of rock boundary;
(1 r ) (1 c )( E R / E C )
K
(1 r ) (1 c )( E R / E C )
pr a 2 (1 k )
pi b 2 a 2 k
Where,
r = poisson’s ratio of rock
c = poisson’s ratio of concrete
E R = Modulus of deformation of rock
E C = Modulus of elasticity of concrete
a = internal radius of the shaft
b = external radius of the shaft
pr = load shared by the rock
The surge shaft is considered as a thick walled pipe, the circumferential stress in the lining can be
determined by the following formula;
b2 a2
Act. ct P
b2 a2
Where,
Act. ct = actual compressive stress
P = Total external pressure (external water pressure + external grout pressure)
a = internal radius of the shaft
b = external radius of the shaft
The concrete thickness of the lining as provided at any point shall be greater than
Minimum thickness of 0.3m
Thickness required to resist maximum external pressure
Reinforcement in the concrete lining
The hoop reinforcement for the circular tank shall be able to withstand the total hoop force due to net
maximum internal water pressure and shall be given by the following formula,
( Pi Pr ) a
Ast
st
Where,
Ast = Area of steel required for internal pressure
pr = load shared by the rock
pi = net internal pressure
a = internal radius of the shaft
st = permissible tensile stress in steel
The hoop reinforcement to be provided shall be the greater of the following
0.3 percent of the concrete area of lining
Hoop reinforcement required for the net normal design head taking permissible tensile stress in
steel
Depending upon the geology and rock cover, hoop reinforcement worked out for the maximum
design head neglecting the supporting action of the rock, with higher stresses in steel.
Longitudinal reinforcement for the percentage of main reinforcement shall be provided in the
longitudinal direction as specified in IS: 456-2000.
Anchorage
The anchorage shall be done to prevent failure due to local bulging and for safety during construction,
anchors shall be provided along the periphery with suitable horizontal and vertical spacing depending
upon the rock encountered during construction.
Grouting
Contact grouting shall be done first. Consolidation grouting where considered necessary shall follow.
Where grout consumption in contact grouting is heavy, a second contact grouting after a suitable time
interval is beneficial to fill up the gaps caused by shrinkage of grout. Grouting shall be done in
accordance with IS: 5878 (Part VII)-1972.
The grout pressure for contact grouting shall be considered to be at least of 2.5 kgf/cm2 or equal to the
external water pressure whichever is larger.
The grout pressure for consolidation grouting shall be considered to be with the range of 2.5 kgf/cm 2 to
7 kgf/cm2 depending upon the depth of the section.
Deflection criteria
The maximum allowable deflection for all the structural members complies with the deflection criteria
given in IS 456:2000 (chapter 23.2).
Crack width
The maximum crack width allowed for any structural element is 0.2 mm as per IS 456. The crack width
has been calculated by using ANNEX F of IS 456:2000.
Note: The lap length shall be maintained at least 50 times the larger size rebar dia.
The crack width and tensile stress in surge shaft concrete and steel at different locations are given in
Table 8-7
9.1 Powerhouse
A Surface powerhouse has been proposed in SKSHP, considering through various alternative
locations. After several investigation it was found that, the surface option near the Sankranti village
will be more feasible. The proposed powerhouse is located on the right bank of the Mewa Khola
with its design ground level, (at about 1046.60 masl) sufficiently high above 1000 year’s flood level.
The general arrangement of the power house is shown in Figure 9-1.
9.1.1 General
Figure 9-1: Powerhouse Machine Floor plan with service bay and control building
Considering the head and flow availability in the site, Pelton turbine with horizontal alignment has
been selected. The longitudinal span of 37.30m, width of 17.50m and height of 20.5m (12.60m for
superstructure plus 7.90m for machine foundation / sump pit) has been proposed which will
accommodate 2 units, set assembly of Pelton turbine with generator, and a service/erection bay. A
6.80m wide control building runs along the length of the powerhouse on the west side.
Retaining structures is provided at the east side of the powerhouse for providing access and flood
protection. Further, the entrance to powerhouse has been provided from the southern direction.
The general arrangement, profile and sections of the powerhouse cavern are shown in: “Detail
Project report, Volume VII: Part A: Civil Drawings, Drawing No: 78/04/40C01-C06”.
Figure 9-2 and Figure 9-3 shows the longitudinal and cross-section along the designed power house
structure where roof truss covered with CGI sheet is placed at top as a roof structure. In Figure 9-3
we can also see that the powerhouse structure is arranged for the crane movement both in
transverse and longitudinal direction. The crane is supported on the rails so that the crane can move
following the track confined by the rail in the longitudinal direction of the Powerhouse. The rails are
over the crane beam girders which rest on with the corbel. The corbel transfers the loads to the
columns and the columns further transfer loads to the substructure. The substructure portion
transfers loads to the machine foundation and then all the loads finally spreads over the soil mass
beneath the machine foundation.
Roofing
The roof of the Powerhouse is made up of truss to economize the design as there is very less
possibility of earth and rock masses. Whereas, the control building is made of reinforced concrete.
The scopes of the detail structural design of power house are as follows:
Modeling of the structure and analysis by the finite element method in SAP2000 using two
nodded frame elements to model beams and columns and three to four nodded thin shell
elements to model sub structure (floor slabs walls and shear walls)
Calculations of the loads to withstand by the structures and determination of the structural
system of the powerhouse to undertake the vertical and horizontal loads
Identification of load cases and load combinations as per the Code
Study of the structural response of the proposed systems for different loading patterns
Development of construction procedure for the proposed structure
Matching the design with national code compliance issues
i. Stability Analysis
The stability analysis of the machine block which consists of 2 units (assembly of horizontal axis
Pelton turbine and generator) and a service bay has been carried out considering it as monolithic
block. The expansion joint has been kept at the end of the erection / service bay, which separates
the machine block with the control building. Further assumptions and considerations has been
discussed below.
Major Assumptions:
i) Static equilibrium equations for stability analysis has been used.
ii) The machine block is RCC of concrete grade C25.
iii) Since the machine foundation rests on soil, allowable bearing capacity of 150 KN/m2
has been adopted.
iv) Total head considered for analysis = H gross + H surge (25% of H gross)
v) Uplift force has been considered since the foundation is soil.
vi) The weight of the electromechanical components is assumed from reference of the
similar projects which may vary when the detail information from the supplier is
received.
ii. Loadings
Horizontal Forces
The Horizontal force governed by hydrostatic pressure due to static and surge head has been
considered for the stability analysis. In addition to that, 25% impact load has also been added to total
horizontal force acting at the inlet valve.
Horizontal force due to water head = Apipe x 𝛾water x HTotal =11248.94 KN
Where,
Apipe ( Area of the penstock pipe after bifurcation near to the inlet valve in m2) = 0.785 m2
𝛾water (Specific weight of water in KN/m3)=9.81KN/m3
HTotal (Total head (Static / gross head + surge head) in m=584m+146m=730m
Vertical Forces
The vertical force due to the self-weight of machine block including the electromechanical
components and superstructure has been considered as the resisting force in the stability.
Unbalanced Force
A static unbalance (sometimes called a force unbalance) occurs when the inertial axis of a rotating
mass is displaced from and parallel to the axis of rotation. Balance quality grade for turbo generators
assumed is G2.5 with an eccentricity of 2mm.
Unbalanced Force = m x e x w2=27.87KN
Where, m = mass of rotating machine in kg = 70.42 Kg
e= eccentricity in mm= 0.1mm
w= angular velocity in rad/sec = 62.83 rad/sec
iii. Vibrational Analysis
The machine block is mounted by the various electromechanical components which are subjected to
vibrations caused by rotating unbalanced machine forces as well as the static weight of the machine.
If these vibrations are excessive, they may damage the machine and adversely affect the super
structure unless their frequency and amplitude are controlled. Thus vibration analysis has been
carried out to ensure that frequency and amplitude of the system is under limiting value and no
resonance is occurred during the operation. The detail calculation is presented in Annex:
Major Assumptions:
i) The system is taken to be undergoing purely vertical vibrations and thus considered
to have single degree of freedom.
ii) The “lumped-mass method” has been used to obtain the resonance frequency and
amplitude of vibration of the machine block.
iii) The unbalance force has been calculated considering the eccentricity of 2mm.
iv) The un-damped natural frequency of the foundation system is obtained for the
vertical motion.
fn=
Where, k = spring constant and m =combined mass of machine and foundation
The value of spring constant “k” is taken from Table 20-2, Pg. No. 750,
Foundation Analysis and Design by J.E. Bowels.
The stability and vibration analysis of the powerhouse machine foundation will be presented in the
detail design report along with the structural drawings.
For two way movement of the crane along the crane beam girder of the power house, maximum axle
wheel load calculations for various probable placements of wheels and crab of the crane was carried out
for input on the SAP2000 model.
The main power house building and control building were modeled separately with the provision of 100
mm joint in-between them. The analysis for RCC superstructure was carried out assuming the existing
columns fixed on the ground and the results were sorted out. The superstructure frame was modeled
with different loadings like dead, live, earthquake, crane load following the IS Codes.
The earthquake load was applied to the superstructure only so that the masses were lumped at the
upper floor level only. The P delta function was not added to the superstructure model as the height of
powerhouse structure was not significantly high and also the columns on the superstructures were
short columns. The final analysis after all the amendments in the property and sections was carried out
in 3D for the design, the design output was also extracted from the SAP2000 with the necessary
overwrites and verified through manual calculations.
TURBNPro KC4 has also been used to determine the turbine and machine block size which has
been verified with the calculation as per IS 12800:1993 (PART 1)-(Guidelines for Selection of
Turbines) and IS 12837:1989.
Grade C25 for all frame and shell elements Fe 500 and Fe 415
Dense concrete 25
Plain concrete 24
Steel 78.5
Soil 19
Brick wall 20
9.1.5 LOADINGS
9.1.5.1 General
Soil type: III
Seismic importance factor: 1.5
Vertical irregularity type: irregular type
Plan irregularity type: irregular type
Structural system : no height restrictions floor height differs
Seismic zone: V
Response reduction factor: 5
Seismic zone factor: 0.36
Combo Name Combo Type Case Type Case Name Scale Factor
1.5DL Linear Add Linear Static DEAD 1.5
Linear Static wall load 1.5
Linear Static Roof dead 1.5
Linear Static Railing 1.5
Lin Moving Crane Load 1.5
1.5(DL+LL) Linear Add Linear Static DEAD 1.5
Linear Static wall load 1.5
Linear Static Roof dead 1.5
Lin Moving Crane Load 1.5
Linear Static Railing 1.5
Linear Static Roof live 1.5
1.2(DL+IL+EQx) Linear Add Linear Static DEAD 1.2
Linear Static EQx 1.2
Linear Static wall load 1.2
Linear Static Roof dead 1.2
Lin Moving Crane Load 0.25
Linear Static Railing 1.2
Linear Static Roof live 1.2
1.2(DL+IL-EQx) Linear Add Linear Static DEAD 1.2
Linear Static EQx -1.2
Linear Static wall load 1.2
Linear Static Roof dead 1.2
Lin Moving Crane Load 0.25
Linear Static Railing 1.2
Linear Static Roof live 1.2
1.2(Dl+IL+EQy) Linear Add Linear Static DEAD 1.2
Linear Static EQy 1.2
Linear Static wall load 1.2
Linear Static Roof dead 1.2
Lin Moving Crane Load 0.25
Linear Static Railing 1.2
Linear Static Roof live 1.2
1.2(Dl+IL-EQy) Linear Add Linear Static DEAD 1.2
9.1.6.1 Methodology
The powerhouse is designed and constructed to resist the effects of design lateral force specified in
7.5.3 (IS 1893-Part I). The design lateral force is computed for the building as a whole. This design lateral
force is distributed to the various floor levels. The overall design seismic force thus obtained at each
level is distributed to individual lateral load resisting elements depending upon the floor diaphragm
action especially for control building. For our case the time period and the seismic forces was left to be
determined by SAP2000 itself.
For the power house, dynamic analysis is performed to obtain the design seismic force and is distributed
to different levels along the height of the building and to the various lateral load resisting elements. The
dynamic analysis was performed by the Response Spectrum Method. However, in either method, the
design base shear (VB) is compared with base shear (V’B) calculated using seismic coefficient method.
Where VB is less than V’B, all the response quantities (for example member forces, displacements,
storey forces, storey shears and base shear is multiplied with the factor (V’B/ VB).The value of the
damping for the power house was taken 5 percent of the critical, for the purposes of dynamic analysis of
the powerhouse building.
The total damping ratio of 5% of critical is used for the structural load calculations
The total 20 modes are considered to meet 90 % of the modal mass in the design.
The earthquake load is applied in both x and y directions with both positive and negative values.
Loads are applied only to the superstructure and the floor slabs below the ground level is given
the rigid diaphragm.
The modal participation ratios and factors are given in Table 9-12 and Table 9-13.
Table 9-12 : Modal load participation ratios
If the shear stress in the member for specified grade of concrete exceeds the value given in above table,
the member should be redesigned.
The concrete grade adopted for the powerhouse was C25. So the value for Tc max was taken equal to
3.1 N/mm2 and it was found that the value of Tc max was not crossed the value of 3.1 N/mm2 for the
designed powerhouse.
Dynamic loads
There should be no resonance; that is, the natural frequency of the machine-foundation-soil
system should not coincide with the operating frequency of the machine. In fact, a zone of
resonance is generally defined and the natural frequency of the system must lie outside this
zone. The foundation is high tuned when its fundamental frequency is greater than the operating
speed or low tuned when its fundamental frequency is lower than the operating speed.
The amplitudes of motion at operating frequencies should not exceed the limiting amplitudes,
which are generally specified by machine manufacturers. If the computed amplitude is within
tolerable limits, but the computed natural frequency is close to the operating frequency, it is
important that this situation be avoided.
The natural frequency of the foundation –soil system should not be whole number multiple of
the operating frequency of the machine to avoid resonance with the higher harmonics.
The vibrations must not be annoying to the persons working in the shops or damaging to the
other precision machines. The nature of vibrations that are perceptible, annoying, or harmful
depends upon the frequency of the vibrations and the amplitude of the motion.
The detail calculation of vibration analysis and stability is shown in “Detail Project Report – Volume
VI: Annex I”
All the details of the beams were taken from the values designed by SAP2000 later verified through
manual calculations. The reinforcement details at top corner, top center, bottom corner and bottom
center part of each beam element were found as per the output given by SAP2000 following
IS13920:1993-Ductile Detailing of Reinforced Concrete Structures Subjected to Seismic Forces-Code of
Practice. According to this Code, the minimum reinforcement at bottom corner of each beam element
was taken 50% of the reinforcement at top corner. The details of remaining parts of the beam elements
were as per the results shown by the SAP2000.
The calculation for the design of the corbel has been presented in “Detail Project Report – Volume VI:
Annex I”.
Location Floor Rebar Ties dia, mm Stirrup legs in Stirrup legs No of Spacing,
longer in Shorter Ties mm
Dia-Nos
direction direction
Left Mid Right Left Mid Right Left Mid Right Left Mid Right
First 20-3 20-3 20-3 20-3 20-3 20-3 10 10 10 100 150 100
floor
16-2 16-2
beam
Second 16-3 16-3 16-3 16-3 16-3 16-3 10 10 10 100 150 100
floor
16-2 16-2
beam
Third 16-3 16-3 16-3 16-3 16-3 16-3 8 8 8 100 150 100
floor
12-2 12-2
beam
Top 12-3 12-3 12-3 12-3 12-3 12-3 8 8 8 100 150 100
Floor
Beam
Left Mid Right Left Mid Right Left Mid Right Left Mid Right
9.2.1 General
Analysis and design of control building is same as that of main power house super structure excluding
the moving load in the analysis part. The control building is placed in the powerhouse cavern and
separated from machine foundation with an expansion joint. The control building size is 37.3m X 6.8m.
The RC design has been performed with the help of the software SAP2000. The design is done
according to IS456:2000 and detailing is done according to IS13920:1993. British code has also been
utilized during the rebar detailing. The design calculation according to the algorithm of SAP2000 has
been followed again which follows the IS codes IS-456:2000 and IS13920:1993.
Figure 9-19: The live load intensity applied at control building slab
moment and axial force of columns. The combined footing has been designed since the isolated footing
would encroach the corresponding footing’s area.
Summary of footing design
Bearing pressure : 150 kN/m2
Raft foundation depth : 0.6 m
Combined Footing size : 6.8 m* 2 m
Main reinforcement : 16 mm @ 150 c/c spacing
Distribution bar : 16 mm @ 150 c/c spacing
20 8 10 2 2 150
Left Mid Right Left Mid Right Left Mid Right Left Mid Right
Plinth 12-6 12-3 12-6 12-3 12-3 12-3 8 8 8 100 150 100
and First
floor
beam
Roof 12-3 12-3 12-3 12-3 12-3 12-3 8 8 8 100 150 100
beam
C. Design of Slab
Slab has been modeled in this building model. The intensity of 5kN/m2 has been applied as a live load to
the slab. The slab dead load and live loads were also calculated manually as a two way slab following the
IS: 456-2000. The calculation detail has been presented in Detailed Project Report: Volume VI- Annex I.
Design summary of slab
Main reinforcement : 10 mm @ 150 c/c spacing
Distribution bar : 10 mm @ 150 c/c spacing
Distribution bar : 10 mm @ 150 c/c spacing
10 TAILRACE
2 Lateral soil pressure at normal condition, kN/m 16.17 at top to 38.20 at bottom
(Trapezoidal)
1 Empty 1.5
2 Full 1.5
3 Envelope 1
Base 400 with 300mm 25mm dia at 150mm 16mm dia with
Slab haunch at two side c/c spacing 150mm c/c spacing
wall junction
Side 400 mm thick two 16mm dia at 150mm 12mm dia with
Walls side wall c/c spacing 150mm c/c spacing
Top 400 with 300mm 16mm dia at 150mm 12mm dia with
Slab haunch at two side c/c spacing 150mm c/c spacing
wall junction