INSPECTION TEST RECORD (ITR) - C


NITROGEN PURGING P16-C
Project No.
Project Title
Facilities
INFORMATION
Test Packages No Purging Medium
System Purging Duration
Sub System
Location
INSPECTION / TEST OK N/A P/L No
Verify the Reinstatement Leak Test for the system/sub system /test
1
package above have been completed and accepted
THE SYSTEM SHOWN ON THE ATTACHED P&ID (TEST PACKAGE) HAS
BEEN PURGED ANCHIVED 7% O2 CONTENT.
Signature:

Name:
2
Title:- Site Representative

Company:

Date:

COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY CONFIRMED BY


Designation Contractor Representative PCSB Inspector Operation
Company PETRONAS Carigali PETRONAS Carigali
Name
Signature
Date