You are on page 1of 3

Page: 1 of 3

Project: CONSTRUCTION OF 306 VILLAS – AL SAAD


Date: 06.02.2019
Client: MUSANADA Contractor: Al Jaber Building
End User AADC
Testing Company: Alphapower
Consultant: Al Suweidi
SITE ACCEPTANCE TEST REPORT FOR 33 kV CABLE
From Station: NRMAH-GD Feeder No: A05 To Station: SAAD PY H06
From Joint loc. 33kV OHL Dead end terminal tower To Joint Loc. Joint location no.12

SITE ACCEPTANCE TEST REPORT FOR 33kV CABLE


1. CABLE PARAMETERS:

Location Reference As Per Soft Drawing: Circuit - 2


Cable Manufacturer Jeddah cables
Cable Type / Size CU/TR-XLPE/STA/PVC - 3C x 240 mm²
Cable From 33kV OHL Dead end terminal tower

Cable To Joint location no.12


Approximate cable length (Meters) 1409 m

2. VISUAL CHECKS:

Sl. No. Description Remarks


1 Physical Condition of the cable OK
2 Cable Earthing connection checks OK
3 Labels / Markings correctness checks OK
4 Cables installed as per the Approved drawings OK

3. PHASE IDENTIFICATION (CONTINUITY) OF CABLE CORES:

Phases R-phase Y-phase B-phase Remarks

Results OK OK OK

TESTED CARRIED BY WITNESSED BY APPROVED BY


COMPANY ALPHA POWER ALJABER AL SUWEIDI AADC AADC
NAME Jayaprakash M P

SIGNATURE
06.02.2020 06.02.2020 06.02.2020
DATE
Page: 2 of 3
Project: CONSTRUCTION OF 306 VILLAS – AL SAAD
Date: 06.02.2019
Client: MUSANADA Contractor: Al Jaber Building
End User AADC
Testing Company: Alphapower
Consultant: Al Suweidi
SITE ACCEPTANCE TEST REPORT FOR 33 kV CABLE
From Station: NRMAH-GD Feeder No: A05 To Station: SAAD PY H06
From Joint loc. 33kV OHL Dead end terminal tower To Joint Loc. Joint location no.12

4. INSULATION RESISTANCE TEST:


Ambient Temperature : 30.2°C

Insulation Resistance Value (GΩ)


Ref. Applied Voltage Duration
Before HV test After HV test
R – (Y+B+E) 329 105.1
Y – (B+R+E) 5000 V DC 60 sec 553 124.5
B – (R+Y+E) 701 162.5

5. CAPACITANCE MEASUREMENT: ( Measured by VLF HV test kit )

Phases R-phase Y-phase B-phase Remarks


Capacitance Value
310 311 312
(ƞF)

6. VLF TEST:
Leakage Current (mA)
Applied Freq
Ref. Duration
Voltage . 1 min 5 min 10 min 15 min 30 min

R-(Y+B+E) 7.87 7.87 7.87 7.87 7.88


40.4
0.1
Y-(B+R+E) kV 30 min 7.90 7.91 7.91 7.91 7.91
Hz
RMS
B-(R+Y+E) 7.91 7.91 7.91 7.91 7.92

TESTED CARRIED BY WITNESSED BY APPROVED BY


COMPANY ALPHA POWER ALJABER AL SUWEIDI AADC AADC
NAME Jayaprakash M P

SIGNATURE
06.02.2020 06.02.2020 06.02.2020
DATE
Page: 3 of 3
Project: CONSTRUCTION OF 306 VILLAS – AL SAAD
Date: 06.02.2019
Client: MUSANADA Contractor: Al Jaber Building
End User AADC
Testing Company: Alphapower
Consultant: Al Suweidi
SITE ACCEPTANCE TEST REPORT FOR 33 kV CABLE
From Station: NRMAH-GD Feeder No: A05 To Station: SAAD PY H06
From Joint loc. 33kV OHL Dead end terminal tower To Joint Loc. Joint location no.12

7. FORMULA USED:
Applied RMS Voltage = 3U0 / √2 kV
Where U0 = 33/√3 = 19.05 kV
Applied RMS Voltage = ( 3x19.05 )/ √2
= 40.4 kV RMS

8. REMARKS:

9. EQUIPMENT DETAILS:

Calibration
Sl.No Instrument Name Make / Model Serial No
Valid
1 IR Tester Megger/MIT515 101365331 11.06.2020

2 HV Test Kit HV Diagnostics/HVA60 GH5204.16B018 18.08.2020

3 Digital Multimeter Fluke/87V 36330028 21.06.2020

TESTED CARRIED BY WITNESSED BY APPROVED BY


COMPANY ALPHA POWER ALJABER AL SUWEIDI AADC AADC
NAME Jayaprakash M P

SIGNATURE
06.02.2020 06.02.2020 06.02.2020
DATE

You might also like