PROJECT: PROJECT NAME SITE NO.

COMMISSIONING CHECK SHEET FOR CHILLED WATER Sheet No.


DISTRIBUTION SYSTEM

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Avoid line air lock.
2 Provide air vents at top points.
3 Remove spades from flanges.
4 Mark distribution of flow and return on pipes.
5 Open all isolating valves after flushing with water.
6 Check for free rotation of pump impeller.
7 Check starter overload setting and electrical
connections are tight.
8 Start pumps.
9 Check current, priming of pump motor.
10 Check head developed by pump.
11 Circulate water through all equipment for four
hours and flush the system.
12 Clean strainers.
13 Repeat above until clear water is observed.
14 Check that water reaches all equipment.
15 Balance water flow through equipment and in
branches.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature