Professional Documents
Culture Documents
Bituminous Surface Dressing
Bituminous Surface Dressing
Concrete
• Densegradedpremixedbituminousmixthatiswellc
ompactedtoformapavementsurfacecourse
• Whencooledresultsinahard,stableanddurabl
elayerthatwithstandsheavytraffic
• Absorbs vibrations
Procedures
• Surface Dressing
• Grouted or Penetration Macadam
• Built‐up Spray Grout
• Bitumen bound Macadam
• Bituminous Carpet
• Bituminous Concrete
Surface Dressing (BSD)
• Bitumengrades–80/100
• Construction Steps
– Surface Preparation
– Application of binder
– Application of stone chippings
– Rolling of first or final coat
• Spreadatatemperatureof1210C‐1630C
– Rolling – Initial – 8‐ 12 trolled &
intermediate– 15‐30t ; final– 8‐ 12t roller
– Quality Control– Bitumen grade,
temperature of aggregate, temperature
during mixing and compaction
Marshall Tests conducted
1 sampleoutofevery100tofmixdischarged is
tested
Forevery100 m2of compacted surface, one
field density test is done
Variation in thickness–6mm per
4.5mofconstruction
– Finished surface‐checked for
longitudinal undulations – not greater
than 8mm.
Cement Concrete Pavements
Pavement Slab
• Cement grouted layer Suitable for base
course
• Rolled concrete layer
• Cement Concrete slab
– Cement grouted layer
• Opengradedaggregatemixwithaggregat
eshavingmaximumsize–18‐25mm‐
dryrolled
• Cement grout is applied on the surface
‐ Rolled Concrete layer
‐ Lean mix concrete issued
Methods of Construction
• Alternate Bay Method–constructing a bay or one
slab in alternate succession leaving the next to
immediate bay to follow up after a gap of a
week
• Advantages
• Working convenience for slab laying
• Joint construction
easier Disadvantages
Large no of transverse joints to be provided
• Complete diversion of traffic necessary
Continuous Bay Method ‐ preferred
34
Material Specifications
• Internal Vibrators
• Straight Edge
• Belt
• Fibre Brush
• Edging Tool
Construction Steps