Daily Site diary & Progress Report

THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 254

Employer Engineer: Contractor

ON SITE STAFF & LABOUR RECORD Day: Monday Date: 2020/6/29 ON SITE PLANT & EQUIPMENT RECORD

No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs

1 Generl Manager 1 9 Weather Sunny Cloudy Rainy Windy Dusty 1 Loader 1 9

2 DGM 1 9 ● 2 Lorry 1 9

3 Contract manager 1 9 3 Mobile Crane 1 9

4 Engineering manager 1 9 Temperature Minimum 9C


:8 C Maximum28C
: 25 C 4 Generator 1 9

5 Safety director 1 9 5 Bar bender machine 2 9

6 MEP iManager 1 9 DELIVERY OF MATERIALS 6 Bar cutter machine 2 9

7 Construction manager 1 9 No. Material Qty. Unit 7 Concrete Pump 2 9

8 Commercial manager 1 9 1 8 Concret boom placer 2 9

9 Civil Engineer 4 9 2 9 Tower Crane 3 9

10 Financial Manager 1 9 3

11 Construction Staff 9 9 4

12 Office Staff 7 9 5

13 Site Works 170 9 6

14 7

15 8

VISITORS ON SITE DESCRIPTION OF WORKS DONE

No. Name Organization No. Qty.

1 1 Scaffolding and staircase work for the 7# staircae 50%

2 2 Backfilling for the 3# Tower crane area 57%

3 3 Formwork for the beam and slab at swimming pool area 60%
4 Reinforcement work for the beam and slab at swimming pool area 40%

5 5 Scaffolding work for the lobby at ground floor 100%

6 Formwork for the beam and slab for the lobby at ground floor 73%

REMARKS 7 Formwork for the beam and slab for the " H " block part 1 area 75%

The confirmed COVID-19 in Ethiopian from last month have seriously affected 8 Reinforcement work of the baeams and slabs for ”H“ block part 1 area 65%
the project progress .And it has resulted the mobilization delay of chinese
9 Formshutter close for the lift shaft at "F" block 100%
technican and local labor based the site progress and the local workers
have decreased rapidly at site.And it also resulted delay of the materials 10 Scaffolding work for the first floor at “E”block 30%
1 purcahse ,shipment and transportation .
11 Temporary access harden by concrete near the sewage equipment room area. 40%

12

13
Working time of the local workers has to be decreased from 9 hours to 8 hours
for one
2 day due to transportation problem caused by COVID-19 and they also need Submission : Noted :
more
payments such as special transportation fee for their work. Signed by: Song Baoliang Signature Signed by: Signature :