S.NO. Equipment Details Test Details List of Pre-Commissioning Tests of Ac Equipments
S.NO. Equipment Details Test Details List of Pre-Commissioning Tests of Ac Equipments
CONFIRMITY TEST (1) Visual external damage to any part of the transformer (2) Buchholz alaram + trip
contacts (3) WTI & OTI alaram + trip contacts (4) MOG contacts (5) Phase Sequence Check (6) colour of
silica gel/Oil level/leakage, if any (7) Abnormality, if any.
Control Circuit & Operational checks (1) Manual charging of spring (2) Mechanical closing & tripping (3)
Charging of spring through motor (4) Tripping through relays/releases (5) Breaker close command
blocking when relay / releases is in operated condition (6) Abnormality, if any
Maintenance & general check-ups (1) Inspection for physical damage (2) cleaning & tightness of
breaker bolts (3) Alignment of breaker (4) Earthing connection (5) Gas pressure low operation (6)
Abnormality, if any
CT
IR TEST (P - E, S- E, P - S, S -S)
11 KV HT PANELS, RMU Winding Resistance Test
PANELS, C&R PANEL, RTCC Magnetization characteristic check
PANEL Ratio, Polarity & Circuit check
General checks 1) Inspection for physical damage 2) Continuity check for ammeter and/or relay circuits
PT
IR TEST (P - E, S- E, P - S, S -S)
Winding Resistance Test
Ratio, Polarity & Circuit check
General checks 1) Inspection for physical damage 2) Continuity check for Voltmeter and/or relay
circuits
LBS
IR TEST on each pole
Measurement of contact resistance for all three phases
Manual checking of operation (close or open) by Handle
Checking of Interlocks (mechanical and electrical)
HVDC Test
Bus Bars:- 1) IR TEST 2) Contact Resistance Test
CHECK UP OF ALL ALARAMS AND ANNUNCIATION
SPACE HEATER OPERATION CHECK
INTERFACE CHECK BETWEEN PANELS
4
TESTS OF PROTECTIVE RELAYS ON SETTINGS CONFIGURED
4
NUMERICAL Relay
1) Seconday Injection Test (according to service setting of relay)
a) Time Current characteristics tests for O/C unit
b) Instantaneous O/C unit protection
c) Time Current characteristics tests for E/F unit
d) Instantaneous E/F unit protection
2) General Checks:- Inspection for physical damage, wiring check, Resetting of LEDs with cover
Coil resistance test (1) Closing coil (2) Tripping coil-1 (3) Tripping coil-2 (4) Motor winding
5 SF6 CIRCUIT BREAKER Control Circuit & Operational checks (1) Manual charging of spring (2) Mechanical closing & tripping (3)
Charging of spring through motor (4) Tripping through relays/releases (5) Breaker close command
blocking when relay / releases is in operated condition (6) Abnormality, if any
Maintenance & general check-ups (1) Inspection for physical damage (2) cleaning & tightness of
breaker bolts (3) Alignment of breaker (4) Earthing connection (5) Gas pressure low operation (6)
Abnormality, if any 7) test for leakage of air / gas