66 11 11 22
Ongoing Defects
1 I33248/ log dist. 7595.235 37 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
2 I33258/ log dist. 8212.31 37 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
3 I33259/ log dist. 8214.01 37 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
4 I33260/ log dist. 8214.65 37 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
Type A Defect
5 I33313/ log dist. 10119.40 37 Completed Completed verified Completed Completed Completed Completed Completed Completed
on same trench
Awaiting
6 I33286/ log dist 9360.042 37 Completed Completed verified Completed
Sleeve
7 I332289/ log dist 9445.524 37 Completed Completed verified Completed Completed Ongoing
8 I332290/ log dist 9446.524 37 Completed Completed verified Completed Completed Ongoing
9 I332285/ log dist 9298.55 37 Completed Completed verified Completed Completed Completed
Project 41 Summary
Backfilling
Ongoing
Total Defects Completed Total
Defects
As on 11-Dec-20
95 5 14 19
Ongoing Defects
Type A Defect
1 I33314/ log dist. 10120.27 41 Completed Completed verified Completed Completed Completed Completed Completed Completed
on same trench
2 133327/ log dist. 11027.843 41 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
3 133329/ log dist. 11212.913 41 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
4 133336/ log dist. 11220.31 41 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
5 133337/ log dist. 11222.14 41 Completed Completed verified Completed Completed Completed Completed Completed Completed Completed
6 133341/ log dist. 11531.27 41 Completed Completed verified Completed Completed Completed Completed Completed Completed
7 133344/ log dist. 11722.84 41 Completed Completed verified Completed Completed Completed Completed Completed Completed
Awaiting
8 133346/ log dist. 11860.503 41 Completed Completed verified Completed Completed Completed Completed Completed - 3LPE Coating
materials
Sub-
Sr Manpower UOM Contractor Interruptions / Delays
Contractor
Sub-
Sr Equipment / Vehicles UOM Contractor PTW Status:
Contractor
Hot Cold
1 Excavators &JCB 2X2 Renwa N/A
Rashid Konnakkal
Page 1 of 2
SITE PHOTO (RENWA PROJECT)
MPI for Defect I33285 Buttering weld for defect I33289, Fillet weld for defect I33285
Backfilling for defect I33329,336&337 LS and Buttering weld completed for defect I33289, I33290 Fit up for Defect I33348
Fit up for Defect I33348 Fit up for Defect I33348 Excavation completed for defect I33354
Page 2 of 2