PEKERJAAN PASANGAN
DINDING BIASA / M3 - LT 02
Campuran : Semen Kapur Pasir Uk. Bata = 0.04 0.1 0.23
1 3 8 Vol = 0.0009 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.055 0.1 0.245
- Bata Merah = 779 bh Vol = 0.0013
- Semen = 0.846 zak Proposi Bata : Spesi = 68% 32%
- Kapur = 3.173 zak
- Pasir = 0.233 m3
- Bambu = 1.200 bh
DINDING BATAKO
Campuran : Semen Kapur Pasir Uk. Batako = 0.2 0.1 0.35
1 3 8 Vol = 0.0070 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.215 0.1 0.365
- Batako = 134 bh Vol = 0.0078
- Semen = 0.288 zak Proposi Bata : Spesi = 89% 11%
- Kapur = 1.080 zak
- Pasir = 0.079 m3
BATU ALAM / M2
Tbl Acian = 0.02 m
Volume = 0.020 m3
KEBUTUHAN BAHAN :
- Batu Alam = 1.1 m2
- Semen = 0.768 zak
CONBLOCK JALAN / m2
KEBUTUHAN BAHAN :
Conblock = 1.000 m2
Pasir = 1.000 m3
PEKERJAAN BETON
TANGGA / UNIT
Tebal Plat Tangga = 0.15 m2 TULANGAN POKOK =
Volume Tangga = = 1.13 m3 DIA. 08 = 9.30 btg
Besi 8 Arah - x = 51 bh DIA. 10 = 5.20 btg
Besi 10 Arah - y = 15 bh
Jarak Tulangan = 0.15 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Multiplek 9 mm = 1.50 lbr - Besi Dia 8 = 9.30 btg - Semen = 8.99 zak
- Bambu = 8.00 btg - Besi Dia 10 = 5.20 btg - Pasir = 0.72 m3
- Usuk 5/7 - 4 Glugu = 3.00 btg - Bendrat = 2.00 kg - Kerikil = 0.81 m3
- Usuk 5/7 - 3 Glugu = 4.00 btg
- Paku = 2.50 kg
Pasangan Bata
Jumlah Anak Tangga = 18.000 Uk. 0.15 0.15
Vol Bata = 0.045 m3
Plesteran
Jumlah Anak Tangga = 18.000 Uk. 0.15 0.15
Luas Plesteran = 5.400 m2
KEBUTUHAN BAHAN :
BETON
- Semen = 3.56 zak
- Pasir = 0.33 m3
Kerikil = 0.56 m3
KEBUTUHAN BAHAN :
- Papan 2/20-4 = 0.25 lbr
- Plastik = 1.00 m'
- Paku = 0.15 kg
- Residu = 0.08 kg
KEBUTUHAN BAHAN :
- Papan 2/20-4 = 0.50 lbr
- Paku = 0.15 kg
KEBUTUHAN BAHAN :
- Genteng Natural = 10.00 bh
- Cat Genteng = 0.13 kg
KEBUTUHAN BAHAN :
- Genteng Glazur = 15.00 bh
PEKERJAAN PLAFOND
PEKERJAAN KERAMIK
PLINT KERAMIK 10 x 30 / M1
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Keramik = 0.101 Dus
Tebal Spesi = 0.015 m - Semen = 0.086 zak
Volume = 0.00225 m3 - Kapur = 0.000 zak
- Semen = 0.086 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.100 kg
- Pasir = 0.000 m3
KERAMIK GARASI / M2
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 5 - Keramik = 1.050 Dus
Tebal Spesi = 0.025 m - Semen = 0.147 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.147 zak - Pasir = 0.027 m3
- Kapur = 0.000 zak - Grouting = 0.200 kg
- Pasir = 0.027 m3
PEKERJAAN CAT
KRAN AIR / BH
KEBUTUHAN BAHAN :
- Kran Air 3/4 = 1 bh
- Knee/Verlop Sock = 3 bh
- Saltip TBA = 1.00 bh
PERESAPAN / UNIT
KEBUTUHAN BAHAN :
- Bus Beton Dia. 100 cm = 4 bh
- Pipa PVC 4 " = 0.50 btg
- Semen = 0.82 zak
- Pasir = 0.06 m3
- Kerikil = 0.59 m3
- Besi Dia. 08 = 2.00 btg
- Ijuk = 30.00 ikat
PEKERJAAN SANITAIR
BAK MANDI
Ukuran : 0.7 0.7 0.75 Uk. Bata = 0.04 0.1 0.23
Volume Bata = 0.158 m3 Vol = 0.0009 m3
Volume Plesteran = 0.042 m3 Dgn Spesi = 0.055 0.1 0.245
Camp Semen Pasir Vol = 0.0013
1 5 Proposi Bata : Spesi = 68% 32%
KEBUTUHAN BAHAN :
- Bata Merah = 117 bh
- Semen = 0.405 zak
- Pasir = 0.057 m3
- Keramik 20/25 = 2.590 dus
PEKERJAAN PERSIAPAN
UITZET BLOUPLANK / m'
Papan 2/20x 2 Sengon 0.500 btg
Bambu 0.375 btg
Paku 0.050 kg
PEKERJAAN PASANGAN
DINDING BIASA / M3 - LT 01
Camp. 1:3:8 Bata Merah 779 bh
Semen 0.846 zak
Kapur 3.173 zak
Pasir 0.233 m3
Bambu 1.000 bh
DINDING BIASA / M3 - LT 02
Camp. 1:3:6 Bata Merah 779 bh
Semen 0.846 zak
Kapur 3.173 zak
Pasir 0.233 m3
Bambu 1.200 bh
DINDING BATAKO
Batako 134 bh
Semen 0.288 zak
Kapur 1.080 zak
Pasir 0.079 m3
PLESTERAN BIASA / M2 - LT 01
Camp. 1:3:8 Semen 0.199 zak
Kapur 0.250 zak
Pasir 0.018 m3
Mill 0.206 zak
Bambu 0.100 bh
PLESTERAN BIASA / M2 - LT 02
Semen 0.199 zak
Kapur 0.250 zak
Pasir 0.018 m3
Mill 0.225 zak
Bambu 0.120 bh
BATU ALAM / M2
Batu Alam 1.10 m2
Semen 0.77 zak
BAK KONTROL / BH
Uk. Luar 50 x 50 x 40 cm3 Bata Merah 78.00 bh
Semen 0.360 zak
Kapur 0.706 zak
Pasir 0.052 m3
Mill 0.268 zak
PEKERJAAN BETON
TANGGA / UNIT
Semen 8.986 zak
Pasir 0.717 m3
Kerikil 0.810 m3
Besi Dia 8 9.300 btg
Besi Dia 10 5.200 btg
Bendrat 2.000 kg
Multiplek 9 mm 1.500 lbr
Bambu 8.000 btg
Usuk 5/7 - 4 Glugu 3.000 btg
Usuk 5/7 - 3 Glugu 4.000 btg
Paku 2.500 kg
PEKERJAAN PLAFOND
PEKERJAAN RANGKA PLAFOND / M2
Kaso 4/6-4 1.250 btg
Reng 3/5-2 0.500 btg
Paku 0.200 kg
Residu 0.300 kg
PEKERJAAN KERAMIK
PLINT KERAMIK 10 x 40 / M1
Keramik 0.104 Dus
Semen 0.086 zak
Grouting 0.100 kg
PLINT KERAMIK 10 x 30 / M1
Keramik 0.101 Dus
Semen 0.086 zak
Grouting 0.100 kg
KERAMIK GARASI / M2
Keramik 1.050 Dus
Semen 0.147 zak
Pasir 0.027 m3
Grouting 0.200 kg
PEKERJAAN CAT
KRAN AIR / BH
Kran Air 3/4 1.000 bh
Knee/Verlop Sock 3.000 bh
Saltip TBA 1.000 bh
PERESAPAN / UNIT
Bus Beton Dia. 100 cm 4.000 bh
Pipa PVC 4 " 0.500 btg
Semen 0.816 zak
Pasir 0.065 m3
Kerikil 0.589 m3
Besi Dia. 08 2.000 btg
Ijuk 30.000 ikat
PEKERJAAN SANITAIR
PEMBERSIHAN LOKASI / m2
TENAGA KERJA Upah
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 3,500 Rp 3,500
UITZET BLOUPLANK / m'
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.020 org Rp 35,000 Rp 700
- Pekerja = 0.020 org Rp 25,000 Rp 500
Rp 2,200 Rp 2,200
PEKERJAAN PASANGAN
BAK KONTROL / BH
TENAGA KERJA
- Mandor = 0.150 org Rp 50,000 Rp 7,500
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
- Pekerja = 0.500 org Rp 25,000 Rp 12,500
Rp 55,000 Rp 55,000
SCREEDING DAN WATERPROFING / m2
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 7,000 Rp 7,000
PEKERJAAN BETON
TENAGA KERJA
BEKISTING / m3 SLOOF 15/25
- Mandor = 0.198 org Rp 50,000 Rp 9,900
- Tukang Kayu = 1.080 org Rp 35,000 Rp 37,800
- Pekerja = 0.900 org Rp 25,000 Rp 22,500
Rp 70,200 Rp 70,200
PEMBESIAN / m3 SLOOF 15/25
- Mandor = 0.427 org Rp 50,000 Rp 21,368
- Tukang Besi = 2.263 org Rp 35,000 Rp 79,188
- Pekerja = 2.011 org Rp 25,000 Rp 50,278
Rp 150,833 Rp 150,900
PENGECORAN / m3 SLOOF 15/25
- Mandor = 0.203 org Rp 50,000 Rp 10,125
- Tukang Batu = 0.675 org Rp 35,000 Rp 23,625
- Pekerja = 1.350 org Rp 25,000 Rp 33,750
Rp 67,500 Rp 67,500
Rp 85,000 Rp 85,000
ROSTER / BH
TENAGA KERJA
- Mandor = 0.005 org Rp 50,000 Rp 250
- Tukang Batu = 0.050 org Rp 35,000 Rp 1,750
Rp 2,000 Rp 2,000
PEKERJAAN PLAFOND
PEKERJAAN KERAMIK
KERAMIK LANTAI - 01 / M2
TENAGA KERJA
- Mandor = 0.022 org Rp 50,000 Rp 1,111
- Tukang Batu = 0.111 org Rp 35,000 Rp 3,889
- Pekerja = 0.111 org Rp 25,000 Rp 2,778
Rp 7,778 Rp 7,800
KERAMIK LANTAI - 02 / M2
TENAGA KERJA
- Mandor = 0.026 org Rp 50,000 Rp 1,278
- Tukang Batu = 0.128 org Rp 35,000 Rp 4,472
- Pekerja = 0.128 org Rp 25,000 Rp 3,194
Rp 8,944 Rp 9,000
PLINT KERAMIK LANTAI - 01 / M'
TENAGA KERJA
- Mandor = 0.017 org Rp 50,000 Rp 833
- Tukang Batu = 0.083 org Rp 35,000 Rp 2,917
- Pekerja = 0.083 org Rp 25,000 Rp 2,083
Rp 5,833 Rp 5,900
PLINT KERAMIK LANTAI - 02 / M'
TENAGA KERJA
- Mandor = 0.018 org Rp 50,000 Rp 917
- Tukang Batu = 0.092 org Rp 35,000 Rp 3,208
- Pekerja = 0.092 org Rp 25,000 Rp 2,292
Rp 6,417 Rp 6,500
KERAMIK LANTAI KM 20/20 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.029 org Rp 50,000 Rp 1,458
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.125 org Rp 25,000 Rp 3,125
Rp 10,417 Rp 10,500
KERAMIK LANTAI KM 20/20 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.032 org Rp 50,000 Rp 1,604
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.138 org Rp 25,000 Rp 3,438
Rp 11,458 Rp 11,500
KERAMIK DINDING 20/20 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.033 org Rp 50,000 Rp 1,667
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.167 org Rp 25,000 Rp 4,167
Rp 11,667 Rp 11,700
KERAMIK DINDING 20/20 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.037 org Rp 50,000 Rp 1,833
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.183 org Rp 25,000 Rp 4,583
Rp 12,833 Rp 12,900
KERAMIK DINDING 20/25 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.032 org Rp 50,000 Rp 1,603
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.154 org Rp 25,000 Rp 3,846
Rp 11,282 Rp 11,300
KERAMIK DINDING 20/25 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.035 org Rp 50,000 Rp 1,763
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.169 org Rp 25,000 Rp 4,231
Rp 12,410 Rp 12,500
LIS BORDER 7 x 20 / M1
TENAGA KERJA
- Mandor = 0.011 org Rp 50,000 Rp 556
- Tukang Batu = 0.111 org Rp 35,000 Rp 3,889
Rp 4,444 Rp 4,500
KERAMIK MEJA DAPUR 20/20 / M2
TENAGA KERJA
- Mandor = 0.050 org Rp 50,000 Rp 2,500
- Tukang Batu = 0.250 org Rp 35,000 Rp 8,750
- Pekerja = 0.250 org Rp 25,000 Rp 6,250
Rp 17,500 Rp 17,500
PEKERJAAN CAT
PERESAPAN / unit
TENAGA KERJA
- Tukang Sumur = 1.500 org Rp 40,000 Rp 60,000 Rp 58,750
- Tukang Batu 0.500 org Rp 35,000 Rp 17,500
- Pekerja = 1.600 org Rp 25,000 Rp 40,000
Rp 117,500 Rp 117,500
SUMUR AIR BERSIH / unit
TENAGA KERJA
- Tukang Sumur = 10.000 org Rp 40,000 Rp 400,000 Rp 52,375
- Tukang Batu 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 9.000 org Rp 25,000 Rp 225,000
Rp 628,500 Rp 628,500
PEKERJAAN SANITAIR
PEKERJAAN LAIN-LAIN
PEKERJAAN PERSIAPAN
PEMBERSIHAN LOKASI / m2
Mandor 0.02 org
Pekerja 0.1 org
PEKERJAAN PASANGAN
BATU ALAM / M2
Mandor 0.100 org
Tukang Batu 0.500 org
Pekerja 0.500 org
BAK KONTROL / BH
Mandor 0.150 org
Tukang Batu 1.000 org
Pekerja 0.500 org
PEKERJAAN BETON
MEJA DAPUR T= 7 cm / m3
BEKISTING / m3 MEJA DAPUR
Mandor 0.286 org
Tukang Kayu 2.857 org
PEMBESIAN / m3 MEJA DAPUR
Mandor 0.492 org
Tukang Besi 2.500 org
Pekerja 2.424 org
PENGECORAN / m3 MEJA DAPUR
Mandor 0.190 org
Tukang Batu 0.952 org
Pekerja 0.952 org
DAUN JENDELA / BH
Mandor 0.033 org
Tukang Kayu 0.333 org
DAUN PINTU / BH
Mandor 0.050 org
Tukang Kayu 0.500 org
ROSTER / BH
Mandor 0.005 org
Tukang Batu 0.050 org
HAK ANGIN
Mandor 0.003 org
Tukang Kayu 0.050 org
PEKERJAAN PLAFOND
PEKERJAAN KERAMIK
KERAMIK LANTAI - 01 / M2
Mandor 0.022 org
Tukang Batu 0.111 org
Pekerja 0.111 org
KERAMIK LANTAI - 02 / M2
Mandor 0.026 org
Tukang Batu 0.128 org
Pekerja 0.128 org
LIS BORDER 7 x 20 / M1
Mandor 0.011 org
Tukang Batu 0.111 org
PEKERJAAN CAT
CAT PLAFOND
Mandor 0.010 org
Tukang Cat 0.100 org
PERESAPAN / unit
Tukang Sumur 1.500 org
Tukang Batu 0.500 org
Pekerja 1.600 org
PEKERJAAN SANITAIR
PEKERJAAN LAIN-LAIN
SETTING LANSEKAP / m2
Tukang Taman 0.100 org
Pekerja 0.100 org