Koefisien Bangunan

You might also like

You are on page 1of 81

PEKERJAAN PERSIAPAN

UITZET BLOUPLANK / m'


KEBUTUHAN BAHAN :
- Papan 2/20x 2 Sengon = 0.500 btg
- Bambu = 0.375 btg
- Paku = 0.050 kg

PEKERJAAN GALIAN DAN URUGAN

URUGAN PASIR BAWAH FONDASI DAN LANTAI / m3


KEBUTUHAN BAHAN :
- Pasir = 1.000 m3

CUT AND FILL / m3


SEWA ALAT :
- Bechoe = 0.021 jam
- Dump Truck = 0.042 jam
- Buldozer = 0.042 jam
- Solar = 3.100 ltr

PEKERJAAN PASANGAN

FONDASI BATU KALI / m3


Campuran : Semen Kapur Pasir
1 3 8
Proporsi Batu Kali : Spesi 70% 30%
KEBUTUHAN BAHAN :
- Batu Kali = 1.05 m3
- Semen = 0.80 zak
- Kapur = 3.00 zak
- Pasir = 0.20 m3
- Besi Dia. 08 = 0.03 btg

DINDING TRASRAM DAN KM/WC / M3


Campuran : Semen Pasir Uk. Bata = 0.04 0.1 0.23
1 5 Vol = 0.0009 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.055 0.1 0.245
- Bata Merah = 779 bh Vol = 0.0013
- Semen = 1.692 zak Proposi Bata : Spesi = 68% 32%
- Pasir = 0.291 m3
DINDING BIASA / M3 - LT 01
Campuran : Semen Kapur Pasir Uk. Bata = 0.04 0.1 0.23
1 3 8 Vol = 0.0009 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.055 0.1 0.245
- Bata Merah = 779 bh Vol = 0.0013
- Semen = 0.846 zak Proposi Bata : Spesi = 68% 32%
- Kapur = 3.173 zak
- Pasir = 0.233 m3
- Bambu = 1.000 bh

DINDING BIASA / M3 - LT 02
Campuran : Semen Kapur Pasir Uk. Bata = 0.04 0.1 0.23
1 3 8 Vol = 0.0009 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.055 0.1 0.245
- Bata Merah = 779 bh Vol = 0.0013
- Semen = 0.846 zak Proposi Bata : Spesi = 68% 32%
- Kapur = 3.173 zak
- Pasir = 0.233 m3
- Bambu = 1.200 bh

DINDING BATAKO
Campuran : Semen Kapur Pasir Uk. Batako = 0.2 0.1 0.35
1 3 8 Vol = 0.0070 m3
KEBUTUHAN BAHAN : Dgn Spesi = 0.215 0.1 0.365
- Batako = 134 bh Vol = 0.0078
- Semen = 0.288 zak Proposi Bata : Spesi = 89% 11%
- Kapur = 1.080 zak
- Pasir = 0.079 m3

PLESTERAN TRASRAM + KM/WC / M2 ACIAN KEBUTUHAN BAHAN :


Campuran : Semen Pasir Tbl Acian = 0.0075 m - Semen = 0.373 zak
1 5 Volume = 0.0075 m3 - Pasir = 0.023 m3
Tebal Plesteran = 0.025 m Semen = 0.240 zak
Volume = 0.025 m3
- Semen = 0.133 zak
- Pasir = 0.023 m3

PLESTERAN BIASA / M2 - LT 01 ACIAN KEBUTUHAN BAHAN :


Campuran : Semen Kapur Pasir Campuran : Semen Mill - Semen = 0.199 zak
1 3 8 1 1 - Kapur = 0.250 zak
Tebal Plesteran = 0.025 m Tbl Acian = 0.0075 m - Pasir = 0.018 m3
Volume = 0.025 m3 Volume = 0.0075 m3 - Mill = 0.206 zak
- Semen = 0.067 zak - Semen = 0.132 zak - Bambu = 0.100 bh
- Kapur = 0.250 zak - Mill = 0.206 zak
- Pasir = 0.018 m3
PLESTERAN BIASA / M2 - LT 02 ACIAN KEBUTUHAN BAHAN :
Campuran : Semen Kapur Pasir Campuran : Semen Mill - Semen = 0.199 zak
1 3 8 1 1 - Kapur = 0.250 zak
Tebal Plesteran = 0.025 m Tbl Acian = 0.0075 m - Pasir = 0.018 m3
Volume = 0.025 m3 Volume = 0.0075 m3 - Mill = 0.225 zak
- Semen = 0.067 zak - Semen = 0.132 zak - Bambu = 0.120 bh
- Kapur = 0.250 zak - Mill = 0.225 zak
- Pasir = 0.018 m3
SPONENGAN SUDUT / M'
Campuran : Semen Mill
1 1
Tbl Acian = 0.0075 m
Lebar = 0.02 m
Volume = 0.00015 m3
KEBUTUHAN BAHAN :
- Semen = 0.002 zak
- Mill = 0.004 zak

TALI AIR BESAR


Campuran : Semen Mill
1 1
Tbl Acian = 0.0075 m
Lebar = 0.05 m
Volume = 0.00038 m3
KEBUTUHAN BAHAN :
- Semen = 0.006 zak
- Mill = 0.009 zak

ORNAMEN DINDING / M' ACIAN KEBUTUHAN BAHAN :


Campuran : Semen Pasir Tbl Acian = 0.0075 m Semen = 0.275 zak
1 5 Volume = 0.0075 m3 Pasir = 0.002 m3
Uk Ornamen 0.02 0.1 Semen = 0.264 zak
Volume = 0.002 m3
- Semen = 0.011 zak
- Pasir = 0.002 m3

BATU ALAM / M2
Tbl Acian = 0.02 m
Volume = 0.020 m3
KEBUTUHAN BAHAN :
- Batu Alam = 1.1 m2
- Semen = 0.768 zak

KORAL SIKAT GARASI / M2 ACIAN KEBUTUHAN BAHAN :


Campuran : Semen Pasir Tbl Acian = 0.0150 m - Koral Sikat = 1.500 bks
1 4 Volume = 0.0150 m3 - Semen = 0.720 zak
Tebal Screeding = 0.03 m Semen = 0.528 zak - Pasir = 0.024 m3
Volume = 0.03 m3
- Semen = 0.192 zak
- Pasir = 0.024 m3
BAK KONTROL / BH
Ukuran : 0.5 0.5 0.4 Uk. Bata = 0.045 0.105 0.23
Volume Bata = 0.120 m3 Vol = 0.0011 m3
Volume Plesteran = 1.300 m2 Dgn Spesi = 0.06 0.105 0.245
Vol = 0.0015
Proposi Bata : Spesi = 70% 30%
KEBUTUHAN BAHAN :
- Bata Merah = 78.000 bh
- Semen = 0.360 zak
- Kapur = 0.706 zak
- Pasir = 0.052 m3
- Mill = 0.268 zak
-
SCREEDING DAN WATERPROFING / M2 ACIAN KEBUTUHAN BAHAN :
Campuran : Semen Pasir Tbl Acian = 0.0075 m - Semen = 0.411 zak
1 5 Volume = 0.0075 m3 - Pasir = 0.023 m3
Tebal Plesteran = 0.025 m Semen = 0.264 zak - Waterprofing = 0.500 kg
Volume = 0.025 m3
- Semen = 0.147 zak
- Pasir = 0.023 m3

BAK KONTROL JALAN / BH


Ukuran : 0.5 0.5 0.4 Uk. Bata = 0.04 0.1 0.23
Volume Bata = 0.120 m3 Vol = 0.0009 m3
Volume Plesteran = 1.300 m2 Dgn Spesi = 0.055 0.1 0.245
Vol = 0.0013
Proposi Bata : Spesi = 68% 32%
KEBUTUHAN BAHAN :
- Bata Merah = 90.000 bh
- Semen = 0.360 zak
- Kapur = 0.706 zak
- Pasir = 0.052 m3
- Tutup Bak Kontrol = 1.000 bh

CONBLOCK JALAN / m2
KEBUTUHAN BAHAN :
Conblock = 1.000 m2
Pasir = 1.000 m3

PEKERJAAN BETON

FOOT PLATE 60/60 / m3


BEKISTING BESI
Ukuran Foot Plate = 0.60 0.60 0.25 m Arah - x = 4.00 bh
Luas Bekisting = 0.96 m2 Arah - y = 4.00 bh
Ukuran Papan = 0.24 m2 Pjg Arah x = 6.80 m'
Vol Foot Plate = 0.09 m3 Pjg Arah y = 6.80 m'
Jumlah FP / m3 = 11.11 bh
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 23.00 lbr - Besi Dia 8 = 7.60 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 7.20 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
FOOT PLATE 80/80 / m3
BEKISTING BESI
Ukuran Foot Plate = 0.80 0.80 0.25 m Arah - x = 6.00 bh
Luas Bekisting = 1.28 m2 Arah - y = 6.00 bh
Ukuran Papan = 0.24 m2 Pjg Arah x = 12.60 m'
Vol Foot Plate = 0.16 m3 Pjg Arah y = 12.60 m'
Jumlah FP / m3 = 6.25 bh
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 8 = 7.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 7.50 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
FOOT PLATE 100/100 / m3
BEKISTING BESI
Ukuran Foot Plate = 1.00 1.00 0.25 m Arah - x = 7.00 bh
Luas Bekisting = 1.6 m2 Arah - y = 7.00 bh
Ukuran Papan = 0.24 m2 Pjg Arah x = 17.50 m'
Vol Foot Plate = 0.25 m3 Pjg Arah y = 17.50 m'
Jumlah FP / m3 = 4.00 bh
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 14.00 lbr - Besi Dia 8 = 7.00 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 6.70 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
FOOT PLATE 80/120 / m3
BEKISTING BESI
Ukuran Foot Plate = 0.80 1.20 0.25 m Arah - x = 6.00 bh
Luas Bekisting = 1.6 m2 Arah - y = 8.00 bh
Ukuran Papan = 0.24 m2 Pjg Arah x = 12.60 m'
Vol Foot Plate = 0.24 m3 Pjg Arah y = 23.20 m'
Jumlah FP / m3 = 4.17 bh
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 14.00 lbr - Besi Dia 8 = 7.50 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 7.20 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
SLOOF 15/25 - 4D10+2D8 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 08 = 5.00 btg Jumlah = 136 bh
Dia. 08 = 2 bh DIA. 10 = 9.90 btg Dia. 6 = 9.9 btg
Dia. 10 = 4 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 9.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 5.00 btg - Pasir = 0.54 m3
- Besi Dia 10 = 9.90 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg

SLOOF 15/20 - 4D8 / m3


DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 08 = 12.40 btg Jumlah = 171 bh
Dia. 08 = 4 bh DIA. 10 = 0.00 btg Dia. 6 = 10.9 btg
Dia. 10 = 0 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 12.40 btg - Pasir = 0.54 m3
- Besi Dia 10 = 0.00 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
SLOOF 15/20 - 4D10 / m3
DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 08 = 0.00 btg Jumlah = 171 bh
Dia. 08 = 0 bh DIA. 10 = 12.40 btg Dia. 6 = 10.9 btg
Dia. 10 = 4 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 0.00 btg - Pasir = 0.54 m3
- Besi Dia 10 = 12.40 btg - Kerikil = 0.72 m3
- Bendrat = 1.50 kg
RINGBALK 15/25 - 5D10+2D8 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 08 = 5.00 btg Jumlah = 136 bh
Dia. 08 = 2 bh DIA. 10 = 12.30 btg Dia. 6 = 9.9 btg
Dia. 10 = 5 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 9.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 5.00 btg - Pasir = 0.54 m3
- Besi Dia 10 = 12.30 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
RING BALK 15/20 - 4D10 / m3
DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 08 = 0.00 btg Jumlah = 171 bh
Dia. 08 = 0 bh DIA. 10 = 12.40 btg Dia. 6 = 10.9 btg
Dia. 10 = 4 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 0.00 btg - Pasir = 0.54 m3
- Besi Dia 10 = 12.40 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg

RING BALK 15/15 - 4D8 / m3


DIMENSI = 0.15 0.15 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 45.00 m' DIA. 08 = 16.40 btg Jumlah = 226 bh
Dia. 08 = 4 bh DIA. 10 = 0.00 btg Dia. 6 = 12.4 btg
Dia. 10 = 0 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 12.40 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 16.40 btg - Pasir = 0.54 m3
- Besi Dia 10 = 0.00 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg

RING BALK 15/20 - 4D8 / m3


DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 08 = 13.00 btg Jumlah = 171 bh
Dia. 08 = 4 bh DIA. 10 = 0.00 btg Dia. 6 = 10.9 btg
Dia. 10 = 0 bh
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 8 = 13.00 btg - Pasir = 0.54 m3
- Besi Dia 10 = 0.00 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg

BALOK LATEI / SEISMIC BEAM CAMP. 1:2:3 / M3 - ATAS KUSEN


DIMENSI = 0.12 0.10 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 84.00 m' DIA. 10 = 15.30 btg Jumlah = 421 bh
Dia. 10 = 2 bh Dia. 6 = 8.5 btg
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 21.00 lbr - Besi Dia 6 = 8.50 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 15.30 btg - Pasir = 0.54 m3
- Bendrat = 1.50 kg - Kerikil = 0.72 m3
KOLOM PRAKTIS 15/15 - 4D8 / m3
DIMENSI = 0.15 0.15 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 45.00 m' DIA. 08 = 16.40 btg Jumlah = 226 bh
Dia. 08 = 4 bh Dia. 6 = 14 btg
Stek Dia. 06 = 90 bh Panjang 25 cm setiap jarak 50 cm
Begel Dia. 6 jarak = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 14.00 btg - Semen = 7.00 zak
- Paku = 1.50 kg - Besi Dia 8 = 16.40 btg - Pasir = 0.54 m3
- Bendrat = 1.50 kg - Kerikil = 0.72 m3
KOLOM 15/15 - 4D10 / m3
DIMENSI = 0.15 0.15 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 45.00 m' DIA. 10 = 16.40 btg Jumlah = 258 bh
Stek Dia. 06 = 90 bh Panjang 25 cm setiap jarak 50 cm Dia. 6 = 14.2 btg
Dia. 10 = 4 bh DIA. 08 = 0.00 btg
Dia. 08 = 0 bh
Begel Dia. 06 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 14.20 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 16.40 btg - Pasir = 0.54 m3
- Besi Dia 8 = 0.00 btg - Kerikil = 0.72 m3
- Bendrat = 1.50 kg
KOLOM 15/30 - 6D12 / m3
DIMENSI = 0.15 0.30 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 23.00 m' DIA. 12 = 12.60 btg Jumlah = 132 bh
Stek Dia. 06 = 46 bh Panjang 25 cm setiap jarak 50 cm Dia. 6 = 11 btg
Dia. 12 = 6 bh
Begel Dia. 06 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 26.00 lbr - Besi Dia 6 = 11.00 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 12 = 12.60 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
KOLOM 15/20 - 4D12 / m3
DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 12 = 12.40 btg Jumlah = 195 bh
Stek Dia. 06 = 68 bh Panjang 25 cm setiap jarak 50 cm Dia. 6 = 14 btg
Dia. 12 = 4 bh
Begel Dia. 06 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 14.00 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 12 = 12.40 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
KOLOM 15/25 - 6D10 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 10 = 15.00 btg Jumlah = 155 bh
Stek Dia. 06 = 54 bh Panjang 25 cm setiap jarak 50 cm Dia. 6 = 12.6 btg
Dia. 10 = 6 bh
Begel Dia. 06 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 22.00 lbr - Besi Dia 6 = 12.60 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 15.00 btg - Pasir = 0.54 m3
- Bendrat = 2.00 kg - Kerikil = 0.72 m3
KOLOM 15/25 - 4D10+2D8 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 10 = 11.00 btg Jumlah = 155 bh
Stek Dia. 06 = 54 bh Panjang 25 cm setiap jarak 50 cm Dia. 6 = 12.6 btg
Dia. 10 = 4 bh DIA. 08 = 6.00 btg
Dia. 08 = 2 bh
Begel Dia. 06 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 22.00 lbr - Besi Dia 6 = 12.60 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 11.00 btg - Pasir = 0.54 m3
- Besi Dia 08 = 6.00 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/35 - 5D12+2D8 GANTUNG / m3
DIMENSI = 0.15 0.35 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 20.00 m' DIA. 08 = 3.70 btg Jumlah = 115 bh
Dia. 8 = 2 bh DIA. 12 = 9.10 btg Dia. 6 = 10.6 btg
Dia. 12 = 5 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 27.00 lbr - Besi Dia 6 = 10.60 btg - Semen = 7.00 zak
- Bambu = 22.40 btg - Besi Dia 8 = 3.70 btg - Pasir = 0.54 m3
- Paku = 2.00 kg - Besi Dia 12 = 9.10 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/30 - 5D12+2D10 / m3
DIMENSI = 0.15 0.30 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 23.00 m' Dia. 10 = 4.20 btg Jumlah = 132 bh
Dia. 10 = 2 bh Dia. 12 = 10.50 btg Dia. 6 = 10.9 btg
Dia. 12 = 5 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 26.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 4.20 btg - Pasir = 0.54 m3
- Besi Dia 12 = 10.50 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK TANGGA 15/30 - 6D12 / m3
DIMENSI = 0.15 0.30 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 23.00 m' Dia. 10 = 0.00 btg Jumlah = 132 bh
Dia. 10 = 0 bh Dia. 12 = 12.60 btg Dia. 6 = 10.9 btg
Dia. 12 = 6 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 26.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 8.50 zak
- Paku = 2.00 kg - Besi Dia 10 = 0.00 btg - Pasir = 0.54 m3
- Besi Dia 12 = 12.60 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/30 - 4D12+2D10 / m3
DIMENSI = 0.15 0.30 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 23.00 m' DIA. 10 = 4.20 btg Jumlah = 132 bh
Dia. 10 = 2 bh DIA. 12 = 8.40 btg Dia. 6 = 10.9 btg
Dia. 12 = 4 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 26.00 lbr - Besi Dia 6 = 10.90 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 4.20 btg - Pasir = 0.54 m3
- Besi Dia 12 = 8.40 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/25 - 5D12 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 10 = 0.00 btg Jumlah = 155 bh
Dia. 10 = 0 bh DIA. 12 = 12.30 btg Dia. 6 = 11.3 btg
Dia. 12 = 5 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 26.00 lbr - Besi Dia 6 = 11.30 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 0.00 btg - Pasir = 0.54 m3
- Besi Dia 12 = 12.30 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/25 - 4D12 / m3
DIMENSI = 0.15 0.25 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 27.00 m' DIA. 10 = 0.00 btg Jumlah = 155 bh
Dia. 10 = 0 bh DIA. 12 = 9.90 btg Dia. 6 = 11.3 btg
Dia. 12 = 4 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 22.00 lbr - Besi Dia 6 = 11.30 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 0.00 btg - Pasir = 0.54 m3
- Besi Dia 12 = 9.90 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
BALOK 15/20 - 4D10 / m3
DIMENSI = 0.15 0.20 m2 TULANGAN POKOK = BEGEL =
Panjang / m3 = 34.00 m' DIA. 10 = 12.40 btg Jumlah = 195 bh
Dia. 10 = 4 bh DIA. 12 = 0.00 btg Dia. 6 = 12.5 btg
Dia. 12 = 0 bh
Begel Dia. 6 jarak = 0.175 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 17.00 lbr - Besi Dia 6 = 12.50 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Besi Dia 10 = 12.40 btg - Pasir = 0.54 m3
- Besi Dia 12 = 0.00 btg - Kerikil = 0.72 m3
- Bendrat = 2.00 kg
PLAT LANTAI t=12cm /m3
Tebal = 0.12 m2 TULANGAN POKOK =
Luas / m3 = 8.33 m2 DIA. 08 = 10.80 btg
Besi 10 Arah - x = 41 bh DIA. 10 = 10.80 btg
Besi 8 Arah - y = 41 bh
Jarak Tulangan = 0.15 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Multiplek 9 mm = 2.00 lbr - Besi Dia 8 = 10.80 btg - Semen = 7.00 zak
- Bambu = 23.00 btg - Besi Dia 10 = 10.80 btg - Pasir = 0.54 m3
- Usuk 5/7 - 4 Glugu = 4.00 btg - Bendrat = 2.00 kg - Kerikil = 0.72 m3
- Usuk 5/7 - 3 Glugu = 3.00 btg
- Paku = 3.00 kg

TANGGA / UNIT
Tebal Plat Tangga = 0.15 m2 TULANGAN POKOK =
Volume Tangga = = 1.13 m3 DIA. 08 = 9.30 btg
Besi 8 Arah - x = 51 bh DIA. 10 = 5.20 btg
Besi 10 Arah - y = 15 bh
Jarak Tulangan = 0.15 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Multiplek 9 mm = 1.50 lbr - Besi Dia 8 = 9.30 btg - Semen = 8.99 zak
- Bambu = 8.00 btg - Besi Dia 10 = 5.20 btg - Pasir = 0.72 m3
- Usuk 5/7 - 4 Glugu = 3.00 btg - Bendrat = 2.00 kg - Kerikil = 0.81 m3
- Usuk 5/7 - 3 Glugu = 4.00 btg
- Paku = 2.50 kg

Pasangan Bata
Jumlah Anak Tangga = 18.000 Uk. 0.15 0.15
Vol Bata = 0.045 m3

Plesteran
Jumlah Anak Tangga = 18.000 Uk. 0.15 0.15
Luas Plesteran = 5.400 m2

PLAT LEUFEL TALANG T=10 cm


Tebal = 0.10 m2 TULANGAN POKOK =
Luas / m3 = 10.00 m2 DIA. 08 = 23.30 btg
Besi 8 Arah - x = 10 bh DIA. 10 = 9.00 btg
Besi 10 Arah - y = 112 bh
Besi 8 Arah - y = 112 bh
Jarak Tulangan = 0.15 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Multiplek 9 mm = 2.50 lbr - Besi Dia 8 = 23.30 btg - Semen = 7.00 zak
- Bambu = 27.00 btg - Besi Dia 10 = 9.00 btg - Pasir = 0.54 m3
- Usuk 5/7 - 4 Glugu = 6.00 btg Bendrat = 2.00 kg - Kerikil = 0.72 m3
- Usuk 5/7 - 3 Glugu = 2.00 btg
Paku = 3.00 kg

PLAT LEUFEL T=7 cm


Tebal = 0.07 m2 TULANGAN POKOK =
Luas / m3 = 14.29 m2 DIA. 08 = 17.40 btg
Besi 8 Arah - x = 4 bh DIA. 10 = 0.00 btg
Besi 10 Arah - y = 0 bh
Besi 8 Arah - y = 120 bh
Jarak Tulangan = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Multiplek 9 mm = 2.50 lbr - Besi Dia 8 = 17.40 btg - Semen = 7.00 zak
- Bambu = 23.00 btg - Besi Dia 10 = 0.00 btg - Pasir = 0.54 m3
- Usuk 5/7 - 4 Glugu = 8.00 btg Bendrat = 1.50 kg - Kerikil = 0.72 m3
Paku = 2.00 kg

MEJA DAPUR T=7 cm BETON BERTULANG CAMP. 1:2:3 / M3


Tebal = 0.07 m2 TULANGAN POKOK DIA. 06
Luas / m3 = 14.29 m2 Arah - X = 8.70 btg
Besi 6 Arah - x = 4 bh Arah - Y = 6.60 btg
Besi 6 Arah - y = 121 bh
Jarak Tulangan = 0.2 m
KEBUTUHAN BAHAN :
BEKISTING BESI BETON
- Papan Cor = 21.00 lbr - Besi Dia 6 = 15.30 btg - Semen = 7.00 zak
- Paku = 2.00 kg - Bendrat = 2.00 kg - Pasir = 0.54 m3
- Kerikil = 0.72 m3
RABAT BETON CAMP. 1:3:5 / M3
Campuran : Semen Pasir Kerikil
1 3 5

KEBUTUHAN BAHAN :
BETON
- Semen = 3.56 zak
- Pasir = 0.33 m3
Kerikil = 0.56 m3

PEKERJAAN RANGKA ATAP

PEKERJAAN GORDING, NOK, MURPLAT, KUDA2 / M3


KEBUTUHAN BAHAN :
- Kayu 8/12-4 = 1.05 m3
- Paku = 2.70 kg 104.167
- Plat Sambungan = 6.75 kg
- Residu = 8.33 kg
41.667
PEKERJAAN GORDING, NOK, MURPLAT, KUDA2 / M3
KEBUTUHAN BAHAN :
- Kayu 6/12-4 = 1.05 m3
- Paku = 2.70 kg 138.88888889
- Plat Sambungan = 6.75 kg
- Residu = 6.25 kg

PEKERJAAN USUK DAN RENG / M2


KEBUTUHAN BAHAN :
- Usuk 5/7-4 = 0.75 btg
- Reng 3/5-2 = 2.75 btg
- Paku = 0.20 kg
- Residu = 0.34 kg

PEKERJAAN TALANG JURAI / M1


KEBUTUHAN BAHAN :
- Papan 2/20-4 = 0.50 lbr
- Seng BJLS 30 = 1.00 m'
- Paku = 0.25 kg
- Residu = 0.16 kg

PEKERJAAN PAPAN REUTER / M1

KEBUTUHAN BAHAN :
- Papan 2/20-4 = 0.25 lbr
- Plastik = 1.00 m'
- Paku = 0.15 kg
- Residu = 0.08 kg

PEKERJAAN PAPAN LISPLANK / M1

KEBUTUHAN BAHAN :
- Papan 2/20-4 = 0.50 lbr
- Paku = 0.15 kg

PEKERJAAN PENUTUP ATAP

PEKERJAAN GENTENG BETON

KEBUTUHAN BAHAN :
- Genteng Natural = 10.00 bh
- Cat Genteng = 0.13 kg

PEKERJAAN GENTENG GLAZUR

KEBUTUHAN BAHAN :
- Genteng Glazur = 15.00 bh

PEKERJAAN KERPUS GENTENG BETON


Campuran : Semen Pasir
1 4
Luas Spesi = 0.02 m
Volume = 0.02 m3
- Semen = 0.141 zak
- Pasir = 0.021 m3
KEBUTUHAN BAHAN :
- Kerpus = 4.00 bh
- Cat Genteng = 0.05 kg
- Semen = 0.14 zak
- Pasir = 0.02 m3
- Plastik = 1.00 m'
PEKERJAAN KERPUS GENTENG GLAZUR
Campuran : Semen Pasir
1 4
Luas Spesi = 0.02 m
Volume = 0.02 m3
- Semen = 0.141 zak
- Pasir = 0.021 m3
KEBUTUHAN BAHAN :
- Kerpus = 5.00 bh
- Semen = 0.14 zak
- Pasir = 0.02 m3
- Plastik = 1.00 m'

PEKERJAAN PLAFOND

PEKERJAAN RANGKA PLAFOND / M2


KEBUTUHAN BAHAN :
- Kaso 4/6-4 = 1.25 btg
- Reng 3/5-2 = 0.50 btg
- Paku = 0.20 kg
- Residu = 0.30 kg

PEKERJAAN PLAFOND GYPSUMBOARD / M2


KEBUTUHAN BAHAN :
- Gypsum 9mm = 1.00 m2
- Compond = 1.00 m2

PEKERJAAN PLAFOND ETERNIT / M2


KEBUTUHAN BAHAN :
- Eternit = 1.00 lbr
- Paku = 0.05 kg

PEKERJAAN KERAMIK

KERAMIK LANTAI RUANG DALAM 40 x 40 / M2


Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 6 - Keramik = 1.146 Dus
Tebal Spesi = 0.025 m - Semen = 0.126 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.126 zak - Pasir = 0.026 m3
- Kapur = 0.000 zak - Grouting = 0.150 kg
- Pasir = 0.026 m3

KERAMIK LANTAI RUANG DALAM 30 x 30 / M2


Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 6 - Keramik = 1.111 Dus
Tebal Spesi = 0.025 m - Semen = 0.126 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.126 zak - Pasir = 0.028 m3
- Kapur = 0.000 zak - Grouting = 0.250 kg
- Pasir = 0.028 m3
PLINT KERAMIK 10 x 40 / M1
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Keramik = 0.104 Dus
Tebal Spesi = 0.015 m - Semen = 0.086 zak
Volume = 0.00225 m3 - Kapur = 0.000 zak
- Semen = 0.086 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.100 kg
- Pasir = 0.000 m3

PLINT KERAMIK 10 x 30 / M1
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Keramik = 0.101 Dus
Tebal Spesi = 0.015 m - Semen = 0.086 zak
Volume = 0.00225 m3 - Kapur = 0.000 zak
- Semen = 0.086 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.100 kg
- Pasir = 0.000 m3

KERAMIK GARASI / M2
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 5 - Keramik = 1.050 Dus
Tebal Spesi = 0.025 m - Semen = 0.147 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.147 zak - Pasir = 0.027 m3
- Kapur = 0.000 zak - Grouting = 0.200 kg
- Pasir = 0.027 m3

KERAMIK LANTAI 20 x 20 KM/WC / M2


Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 5 - Keramik = 1.100 Dus
Tebal Spesi = 0.025 m - Semen = 0.147 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.147 zak - Pasir = 0.027 m3
- Kapur = 0.000 zak - Grouting = 0.300 kg
- Pasir = 0.027 m3

KERAMIK DINDING 20 x 25 KM/WC / M2


Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Keramik = 1.100 Dus
Tebal Spesi = 0.015 m - Semen = 0.576 zak
Volume = 0.015 m3 - Kapur = 0.000 zak
- Semen = 0.576 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.275 kg
- Pasir = 0.000 m3
LIS / BORDER KERAMIK 7 x 20 DINDING KM/WC / M1
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Lis Keramik = 5.000 bh
Tebal Spesi = 0.015 m - Semen = 0.058 zak
Volume = 0.0015 m3 - Kapur = 0.000 zak
- Semen = 0.058 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.100 kg
- Pasir = 0.000 m3
KERAMIK MEJA DAPUR 20x20 / M2
Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 6 - Keramik = 1.100 Dus
Tebal Spesi = 0.025 m - Semen = 0.137 zak
Volume = 0.025 m3 - Kapur = 0.000 zak
- Semen = 0.137 zak - Pasir = 0.028 m3
- Kapur = 0.000 zak - Grouting = 0.300 kg
- Pasir = 0.028 m3

KERAMIK DINDING DAPUR 20x20 / M2


Campuran : Semen Kapur Pasir KEBUTUHAN BAHAN :
1 0 0 - Keramik = 1.100 Dus
Tebal Spesi = 0.015 m - Semen = 0.576 zak
Volume = 0.015 m3 - Kapur = 0.000 zak
- Semen = 0.576 zak - Pasir = 0.000 m3
- Kapur = 0.000 zak - Grouting = 0.300 kg
- Pasir = 0.000 m3

PEKERJAAN CAT

CAT DINDING DALAM CATYLAC/SETARA / m2


KEBUTUHAN BAHAN :
Cat Tembok = 0.354 kg
Plamir tembok = 0.139 kg
Amplas = 0.250 lbr

CAT DINDING LUAR DULUX / m2


KEBUTUHAN BAHAN :
Cat Tembok = 0.278 kg
Amplas = 0.250 lbr

CAT DINDING LUAR CATYLAC + SPEKTRUM / m2


KEBUTUHAN BAHAN :
Cat Tembok = 0.347 kg
Cat Tembok Luar = 0.139 kg
Amplas = 0.250 lbr

CAT DINDING LUAR MOWILEX WEATHER SHIELD / m2


KEBUTUHAN BAHAN :
Cat Tembok = 0.253 kg
Amplas = 0.250 lbr

CAT PLAFOND CATYLAC/SETARA / m2


KEBUTUHAN BAHAN :
Cat Tembok = 0.304 kg
Amplas = 0.250 lbr

CAT POLITUR KUSEN PINTU DAN JENDELA / m'


KEBUTUHAN BAHAN :
Cat Politur = 0.102 kg
Dempul Kayu = 0.024 kg
Amplas = 0.500 lbr

CAT POLITUR DAUN PINTU / m2


KEBUTUHAN BAHAN :
Cat Politur = 0.340 kg
Dempul Kayu = 0.100 kg
Amplas = 1.000 lbr

CAT POLITUR RAM JENDELA / m2


KEBUTUHAN BAHAN :
Cat Politur = 0.213 kg
Dempul Kayu = 0.100 kg
Amplas = 1.000 lbr

CAT POLITUR ROSTER / bh


KEBUTUHAN BAHAN :
Cat Politur = 0.085 kg
Dempul Kayu = 0.050 kg
Amplas = 0.500 lbr

PEKERJAAN INSTALASI AIR

INSTALASI AIR BERSIH 1" / m'


KEBUTUHAN BAHAN :
- Pipa PVC Dia. 1" = 0.25 btg
- Knee/Tee/Sock = 0.50 bh
- Lem Pipa = 0.30 bh

INSTALASI AIR BERSIH 3/4" / m'


KEBUTUHAN BAHAN :
- Pipa PVC 3/4 " = 0.25 btg
- Knee/Tee = 1 bh
- Lem Pipa = 0.3 bh

INSTALASI AIR KOTOR 3" / m'


KEBUTUHAN BAHAN :
- Pipa PVC 3" = 0.25 btg
- Knee/Tee = 0.50 bh
- Lem Pipa = 0.40 bh

INSTALASI TALANG TEGAK 2" / m'


KEBUTUHAN BAHAN :
- Pipa PVC 2" = 0.25 btg
- Knee/Tee = 0.60 bh
- Lem Pipa = 0.40 bh

INSTALASI AIR TINJA 4" / m'


KEBUTUHAN BAHAN :
- Pipa PVC 4" = 0.25 btg
- Knee/Tee = 0.50 bh
- Lem Pipa = 0.40 bh

INSTALASI POMPA DAN WATERTORN / Unit


KEBUTUHAN BAHAN :
- Pipa PVC 1 1/4" = 4 btg
- Pipa PVC 1 " = 5 btg
- Stop Kran = 3 bh
- Knee/Tee = 16 bh
- Lem Pipa = 3 bh
- Watertorn = 1 unit
- Radar Otomatis = 1 unit

KRAN AIR / BH
KEBUTUHAN BAHAN :
- Kran Air 3/4 = 1 bh
- Knee/Verlop Sock = 3 bh
- Saltip TBA = 1.00 bh

SEPTIC TANK / UNIT


KEBUTUHAN BAHAN :
- Bus Beton Dia. 100 cm = 5 bh
- Pipa PVC 3/4 " = 1 btg
- Pipa PVC 4 " = 0.20 btg
- Knee/Tee = 3 bh
- Lem Pipa = 0.40 bh
- Semen = 1.63 zak
- Pasir = 0.13 m3
- Kerikil = 0.17 m3
- Besi Dia. 08 = 3.00 btg

PERESAPAN / UNIT
KEBUTUHAN BAHAN :
- Bus Beton Dia. 100 cm = 4 bh
- Pipa PVC 4 " = 0.50 btg
- Semen = 0.82 zak
- Pasir = 0.06 m3
- Kerikil = 0.59 m3
- Besi Dia. 08 = 2.00 btg
- Ijuk = 30.00 ikat

SUMUR AIR BERSIH / UNIT


KEBUTUHAN BAHAN :
- Bus Beton Dia. 100 cm = 24 bh
- Semen = 0.82 zak
- Pasir = 0.06 m3
- Kerikil = 0.09 m3
- Besi Dia. 08 = 2.00 btg

PEKERJAAN SANITAIR

DUDUKAN CLOSED JONGKOK / unit


Ukuran : 1 0.8 0.2 Uk. Bata = 0.04 0.1 0.23
Volume Bata = 0.160 m3 Vol = 0.0009 m3
Volume Plesteran = 0.020 m3 Dgn Spesi = 0.055 0.1 0.245
Camp Semen Pasir Vol = 0.0013
1 6 Proposi Bata : Spesi = 68% 32%
KEBUTUHAN BAHAN :
- Bata Merah = 119 bh
- Semen = 0.323 zak
- Pasir = 0.064 m3

DUDUKAN BATHUP / unit


Ukuran : 1 0.8 2 Uk. Bata = 0.04 0.1 0.23
Volume Bata = 0.720 m3 Vol = 0.0009 m3
Volume Plesteran = 0.096 m2 Dgn Spesi = 0.055 0.1 0.245
Camp Semen Pasir Vol = 0.0013
1 6 Proposi Bata : Spesi = 68% 32%
KEBUTUHAN BAHAN :
- Bata Merah = 535 bh
- Semen = 1.483 zak
- Pasir = 0.932 m3

BAK MANDI
Ukuran : 0.7 0.7 0.75 Uk. Bata = 0.04 0.1 0.23
Volume Bata = 0.158 m3 Vol = 0.0009 m3
Volume Plesteran = 0.042 m3 Dgn Spesi = 0.055 0.1 0.245
Camp Semen Pasir Vol = 0.0013
1 5 Proposi Bata : Spesi = 68% 32%
KEBUTUHAN BAHAN :
- Bata Merah = 117 bh
- Semen = 0.405 zak
- Pasir = 0.057 m3
- Keramik 20/25 = 2.590 dus

FINISHING MEJA DAPUR


Ukuran : 0.6 3 0
Volume Acian = 0.014 m3 Camp Semen Mill
Volume Plesteran = 0.045 m3 1 2
Camp Semen Pasir
1 6
KEBUTUHAN BAHAN :
- Semen = 0.370 zak
- Pasir = 0.046 m3
Mill = 0.360 zak
URAIAN PEKERJAAN BAHAN KOEF UNIT

PEKERJAAN PERSIAPAN
UITZET BLOUPLANK / m'
Papan 2/20x 2 Sengon 0.500 btg
Bambu 0.375 btg
Paku 0.050 kg

PEKERJAAN GALIAN DAN URUGAN

URUGAN PASIR BAWAH FONDASI DAN LANTAI / m3


Pasir 1.050 m3

PEKERJAAN PASANGAN

FONDASI BATU KALI / m3


Camp. 1:3:8 Batu Kali 1.05 m3
Semen 0.80 zak
Kapur 3.00 zak
Pasir 0.20 m3
Besi Dia. 08 0.03 btg

DINDING TRASRAM DAN KM/WC / M3


Camp. 1:5 Bata Merah 779 bh
Semen 1.692 zak
Pasir 0.291 m3

DINDING BIASA / M3 - LT 01
Camp. 1:3:8 Bata Merah 779 bh
Semen 0.846 zak
Kapur 3.173 zak
Pasir 0.233 m3
Bambu 1.000 bh

DINDING BIASA / M3 - LT 02
Camp. 1:3:6 Bata Merah 779 bh
Semen 0.846 zak
Kapur 3.173 zak
Pasir 0.233 m3
Bambu 1.200 bh

DINDING BATAKO
Batako 134 bh
Semen 0.288 zak
Kapur 1.080 zak
Pasir 0.079 m3

PLESTERAN TRASRAM + KM/WC / M2


Camp. 1:5 Semen 0.373 zak
Pasir 0.023 m3

PLESTERAN BIASA / M2 - LT 01
Camp. 1:3:8 Semen 0.199 zak
Kapur 0.250 zak
Pasir 0.018 m3
Mill 0.206 zak
Bambu 0.100 bh
PLESTERAN BIASA / M2 - LT 02
Semen 0.199 zak
Kapur 0.250 zak
Pasir 0.018 m3
Mill 0.225 zak
Bambu 0.120 bh

SPONENGAN SUDUT / M'


Camp. 1:1 Semen 0.002 zak
Mill 0.004 zak

TALI AIR BESAR


Semen 0.006 zak
Mill 0.009 zak

ORNAMEN DINDING / M'


Camp. 1:5 Semen 0.275 zak
Pasir 0.002 m3

BATU ALAM / M2
Batu Alam 1.10 m2
Semen 0.77 zak

KORAL SIKAT GARASI / M2


Camp. 1:4 Koral Sikat 1.50 bks
Semen 0.72 zak
Pasir 0.02 m3

BAK KONTROL / BH
Uk. Luar 50 x 50 x 40 cm3 Bata Merah 78.00 bh
Semen 0.360 zak
Kapur 0.706 zak
Pasir 0.052 m3
Mill 0.268 zak

SCREEDING DAN WATERPROFING / M2


Semen 0.411 zak
Pasir 0.023 m3
Waterprofing 0.500 kg

BAK KONTROL JALAN / BH


Bata Merah 90.000 bh
Semen 0.360 zak
Kapur 0.706 zak
Pasir 0.052 m3
Tutup Bak Kontrol 1.000 bh

PEKERJAAN BETON

FOOT PLATE 60/60 / m3


Tulangan Arah-X : Semen 7.00 zak
Dia. 10 Jarak 15 cm - 2 lapis Pasir 0.54 m3
Tulangan Arah-Y : Kerikil 0.72 m3
Dia. 08 Jarak 15 cm - 2 lapis Besi Dia 8 7.60 btg
Besi Dia 10 7.20 btg
Bendrat 2.00 kg
Papan Cor 23.00 lbr
Paku 2.000 kg

FOOT PLATE 80/80 / m3


Tulangan Arah-X : Semen 7.00 zak
Dia. 10 Jarak 15 cm - 2 lapis Pasir 0.54 m3
Tulangan Arah-Y : Kerikil 0.72 m3
Dia. 08 Jarak 15 cm - 2 lapis Besi Dia 8 7.90 btg
Besi Dia 10 7.50 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

FOOT PLATE 100/100 / m3


Tulangan Arah-X : Semen 7.00 zak
Dia. 10 Jarak 15 cm - 2 lapis Pasir 0.54 m3
Tulangan Arah-Y : Kerikil 0.72 m3
Dia. 08 Jarak 15 cm - 2 lapis Besi Dia 8 7.00 btg
Besi Dia 10 6.70 btg
Bendrat 2.00 kg
Papan Cor 14.000 lbr
Paku 2.000 kg

FOOT PLATE 80/120 / m3


Tulangan Arah-X : Semen 7.00 zak
Dia. 10 Jarak 15 cm - 2 lapis Pasir 0.54 m3
Tulangan Arah-Y : Kerikil 0.72 m3
Dia. 08 Jarak 15 cm - 2 lapis Besi Dia 8 7.50 btg
Besi Dia 10 7.20 btg
Bendrat 2.00 kg
Papan Cor 14.000 lbr
Paku 2.000 kg

SLOOF 15/25 - 4D10+2D8 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 9.90 btg
Besi Dia 8 5.00 btg
Besi Dia 10 9.90 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

SLOOF 15/20 - 4D8 / m3


Semen 7.000 zak
Pasir 0.540 m3
Kerikil 0.720 m3
Besi Dia 6 10.900 btg
Besi Dia 8 12.400 btg
Bendrat 2.000 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

SLOOF 15/20 - 4D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.90 btg
Besi Dia 10 12.40 btg
Bendrat 1.50 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

RINGBALK 15/25 - 5D10+2D8 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 9.90 btg
Besi Dia 8 5.00 btg
Besi Dia 10 12.30 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

RING BALK 15/20 - 4D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.90 btg
Besi Dia 10 12.40 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

RING BALK 15/15 - 4D8 / m3


Semen 7.000 zak
Pasir 0.540 m3
Kerikil 0.720 m3
Besi Dia 6 12.400 btg
Besi Dia 8 16.400 btg
Bendrat 2.000 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

RING BALK 15/20 - 4D8 / m3


Semen 7.000 zak
Pasir 0.540 m3
Kerikil 0.720 m3
Besi Dia 6 10.900 btg
Besi Dia 8 13.000 btg
Bendrat 2.000 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

BALOK LATEI / SEISMIC BEAM CAMP. 1:2:3 / M3 - ATAS KUSEN


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 8.50 btg
Besi Dia 10 15.30 btg
Bendrat 1.50 kg
Papan Cor 21.000 lbr
Paku 2.000 kg

KOLOM PRAKTIS 15/15 - 4D8 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 14.00 btg
Besi Dia 8 16.40 btg
Bendrat 1.50 kg
Papan Cor 17.000 lbr
Paku 1.500 kg

KOLOM 15/15 - 4D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 14.20 btg
Besi Dia 10 16.40 btg
Bendrat 1.50 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

KOLOM 15/30 - 6D12 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 11.00 btg
Besi Dia 12 12.60 btg
Bendrat 2.00 kg
Papan Cor 26.000 lbr
Paku 2.000 kg

KOLOM 15/20 - 4D12 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 14.00 btg
Besi Dia 12 12.40 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

KOLOM 15/25 - 6D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 12.60 btg
Besi Dia 10 15.00 btg
Bendrat 2.00 kg
Papan Cor 22.000 lbr
Paku 2.000 kg

KOLOM 15/25 - 4D10+2D8 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 12.60 btg
Besi Dia 10 11.00 btg
Besi Dia 08 6.00 btg
Bendrat 2.00 kg
Papan Cor 22.000 lbr
Paku 2.000 kg

BALOK 15/35 - 5D12+2D8 GANTUNG / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.60 btg
Besi Dia 8 3.70 btg
Besi Dia 12 9.10 btg
Bendrat 2.00 kg
Papan Cor 27.000 lbr
Bambu 22.400 btg
Paku 2.000 kg

BALOK 15/30 - 5D12+2D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.90 btg
Besi Dia 10 4.20 btg
Besi Dia 12 10.50 btg
Bendrat 2.00 kg
Papan Cor 26.000 lbr
Paku 2.000 kg

BALOK TANGGA 15/30 - 6D12 / m3


Semen 8.50 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.90 btg
Besi Dia 12 12.60 btg
Bendrat 2.00 kg
Papan Cor 26.000 lbr
Paku 2.000 kg
BALOK 15/30 - 4D12+2D10 / m3
Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 10.90 btg
Besi Dia 10 4.20 btg
Besi Dia 12 8.40 btg
Bendrat 2.00 kg
Papan Cor 26.000 lbr
Paku 2.000 kg

BALOK 15/25 - 5D12 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 11.30 btg
Besi Dia 12 12.30 btg
Bendrat 2.00 kg
Papan Cor 26.000 lbr
Paku 2.000 kg

BALOK 15/25 - 4D12 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 11.30 btg
Besi Dia 12 9.90 btg
Bendrat 2.00 kg
Papan Cor 22.000 lbr
Paku 2.000 kg

BALOK 15/20 - 4D10 / m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 12.50 btg
Besi Dia 10 12.40 btg
Bendrat 2.00 kg
Papan Cor 17.000 lbr
Paku 2.000 kg

PLAT LANTAI t=12cm /m3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 8 10.80 btg
Besi Dia 10 10.80 btg
Bendrat 2.00 kg
Multiplek 9 mm 2.000 lbr
Bambu 23.000 btg
Usuk 5/7 - 4 Glugu 4.000 btg
Usuk 5/7 - 3 Glugu 3.000 btg
Paku 3.000 kg
PLAT LEUFEL TALANG T=10 cm
Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 8 23.30 btg
Besi Dia 10 9.00 btg
Bendrat 2.00 kg
Multiplek 9 mm 2.500 lbr
Bambu 27.000 btg
Usuk 5/7 - 4 Glugu 6.000 btg
Usuk 5/7 - 3 Glugu 2.000 btg
Paku 3.000 kg

TANGGA / UNIT
Semen 8.986 zak
Pasir 0.717 m3
Kerikil 0.810 m3
Besi Dia 8 9.300 btg
Besi Dia 10 5.200 btg
Bendrat 2.000 kg
Multiplek 9 mm 1.500 lbr
Bambu 8.000 btg
Usuk 5/7 - 4 Glugu 3.000 btg
Usuk 5/7 - 3 Glugu 4.000 btg
Paku 2.500 kg

PLAT LEUFEL T=7 cm


Semen 7.000 zak
Pasir 0.540 m3
Kerikil 0.720 m3
Besi Dia 8 17.400 btg
Bendrat 1.500 kg
Multiplek 9 mm 2.500 lbr
Bambu 23.000 btg
Usuk 5/7 - 4 Glugu 8.000 btg
Paku 2.000 kg

MEJA DAPUR T=7 cm BETON BERTULANG CAMP. 1:2:3 / M3


Semen 7.00 zak
Pasir 0.54 m3
Kerikil 0.72 m3
Besi Dia 6 15.30 0
Bendrat 2.00 kg
Papan Cor 21.000 lbr
Paku 2.000 kg

RABAT BETON CAMP. 1:3:5 / M3


Semen 3.556 zak
Pasir 0.333 m3
Kerikil 0.556 m3

PEKERJAAN RANGKA ATAP


PEKERJAAN GORDING, NOK, MURPLAT, KUDA2 / M3
Kayu 6/12-4 1.050 m3
Paku 2.700 kg
Plat Sambungan 6.750 kg
Residu 6.250 kg

PEKERJAAN USUK DAN RENG / M2


Usuk 5/7-4 0.750 btg
Reng 3/5-2 2.750 btg
Paku 0.200 kg
Residu 0.336 kg

PEKERJAAN TALANG JURAI / M1


Papan 2/20-4 0.500 lbr
Seng BJLS 30 1.000 m'
Paku 0.250 kg
Residu 0.160 kg

PEKERJAAN PAPAN REUTER / M1


Papan 2/20-4 0.250 lbr
Plastik 1.000 m'
Paku 0.150 kg
Residu 0.080 kg

PEKERJAAN PAPAN LISPLANK / M1


Papan 2/20-4 0.500 lbr
Paku 0.150 kg

PEKERJAAN PENUTUP ATAP

PEKERJAAN GENTENG BETON


Genteng Natural 10.000 bh
Cat Genteng 0.125 kg

PEKERJAAN GENTENG GLAZUR


Genteng Glazur 15.000 bh

PEKERJAAN KERPUS GENTENG BETON


Kerpus 4.000 bh
Cat Genteng 0.050 kg
Semen 0.141 zak
Pasir 0.021 m3
Plastik 1.000 m'

PEKERJAAN KERPUS GENTENG GLAZUR


Kerpus 5.000 bh
Semen 0.141 zak
Pasir 0.021 m3
Plastik 1.000 m'

PEKERJAAN PLAFOND
PEKERJAAN RANGKA PLAFOND / M2
Kaso 4/6-4 1.250 btg
Reng 3/5-2 0.500 btg
Paku 0.200 kg
Residu 0.300 kg

PEKERJAAN PLAFOND GYPSUMBOARD / M2


Gypsum 9mm 1.000 m2
Compond 1.000 m2

PEKERJAAN PLAFOND ETERNIT / M2


Eternit 1.000 lbr
Paku 0.050 kg

PEKERJAAN KERAMIK

KERAMIK LANTAI RUANG DALAM 40 x 40 / M2


Keramik 1.146 Dus
Semen 0.126 zak
Pasir 0.026 m3
Grouting 0.150 kg

KERAMIK LANTAI RUANG DALAM 30 x 30 / M2


Keramik 1.111 Dus
Semen 0.126 zak
Pasir 0.028 m3
Grouting 0.250 kg

PLINT KERAMIK 10 x 40 / M1
Keramik 0.104 Dus
Semen 0.086 zak
Grouting 0.100 kg

PLINT KERAMIK 10 x 30 / M1
Keramik 0.101 Dus
Semen 0.086 zak
Grouting 0.100 kg

KERAMIK GARASI / M2
Keramik 1.050 Dus
Semen 0.147 zak
Pasir 0.027 m3
Grouting 0.200 kg

KERAMIK LANTAI 20 x 20 KM/WC / M2


Keramik 1.100 Dus
Semen 0.147 zak
Pasir 0.027 m3
Grouting 0.300 kg

KERAMIK DINDING 20 x 25 KM/WC / M2


Keramik 1.100 Dus
Semen 0.576 zak
Grouting 0.275 kg

LIS / BORDER KERAMIK 7 x 20 DINDING KM/WC / M1


Lis Keramik 5.000 bh
Semen 0.058 zak
Grouting 0.100 kg

KERAMIK MEJA DAPUR 20x20 / M2


Keramik 1.100 Dus
Semen 0.137 zak
Pasir 0.028 m3
Grouting 0.300 kg

KERAMIK DINDING DAPUR 20x20 / M2


Keramik 1.100 Dus
Semen 0.576 zak
Grouting 0.300 kg

PEKERJAAN CAT

CAT DINDING DALAM CATYLAC/SETARA / m2


Cat Tembok 0.354 kg
Plamir tembok 0.139 kg
Amplas 0.350 lbr

CAT DINDING LUAR DULUX / m2


Cat Tembok 0.278 kg
Amplas 0.250 lbr

CAT DINDING LUAR CATYLAC + SPEKTRUM / m2


Cat Tembok 0.347 kg
Cat Tembok Luar 0.139 kg
Amplas 0.250 lbr

CAT DINDING LUAR MOWILEX WEATHER SHIELD / m2


Cat Tembok 0.253 kg
Amplas 0.250 lbr

CAT PLAFOND CATYLAC/SETARA / m2


Cat Tembok 0.304 kg
Amplas 0.250 lbr

CAT POLITUR KUSEN PINTU DAN JENDELA / m'


Cat Politur 0.102 kg
Dempul Kayu 0.024 kg
Amplas 0.500 lbr

CAT POLITUR DAUN PINTU / m2


Cat Politur 0.340 kg
Dempul Kayu 0.100 kg
Amplas 1.000 lbr
CAT POLITUR RAM JENDELA / m2
Cat Politur 0.213 kg
Dempul Kayu 0.100 kg
Amplas 1.000 lbr

CAT POLITUR ROSTER / bh


Cat Politur 0.085 kg
Dempul Kayu 0.050 kg
Amplas 0.500 lbr

PEKERJAAN INSTALASI AIR

INSTALASI AIR BERSIH 1" / m'


Pipa PVC Dia. 1" 0.250 btg
Knee/Tee/Sock 0.500 bh
Lem Pipa 0.300 bh

INSTALASI AIR BERSIH 3/4" / m'


Pipa PVC 3/4 " 0.250 btg
Knee/Tee 1.000 bh
Lem Pipa 0.300 bh

INSTALASI AIR KOTOR 3" / m'


Pipa PVC 3" 0.250 btg
Knee/Tee 0.500 bh
Lem Pipa 0.400 bh

INSTALASI TALANG TEGAK 2" / m'


Pipa PVC 2" 0.250 btg
Knee/Tee 0.600 bh
Lem Pipa 0.400 bh

INSTALASI AIR TINJA 4" / m'


Pipa PVC 4" 0.250 btg
Knee/Tee 0.500 bh
Lem Pipa 0.400 bh

INSTALASI POMPA DAN WATERTORN / Unit


Pipa PVC 1 1/4" 4.000 btg
Pipa PVC 1 " 5.000 btg
Stop Kran 3.000 bh
Knee/Tee 16.000 bh
Lem Pipa 2.500 bh
Watertorn 1.000 set
Radar Otomatis 1.000 unit

KRAN AIR / BH
Kran Air 3/4 1.000 bh
Knee/Verlop Sock 3.000 bh
Saltip TBA 1.000 bh

SEPTIC TANK / UNIT


Bus Beton Dia. 100 cm 5.000 bh
Pipa PVC 3/4 " 1.000 btg
Pipa PVC 4 " 0.200 btg
Knee/Tee 3.000 bh
Lem Pipa 0.400 bh
Semen 1.632 zak
Pasir 0.130 m3
Kerikil 0.173 m3
Besi Dia. 08 3.000 btg

PERESAPAN / UNIT
Bus Beton Dia. 100 cm 4.000 bh
Pipa PVC 4 " 0.500 btg
Semen 0.816 zak
Pasir 0.065 m3
Kerikil 0.589 m3
Besi Dia. 08 2.000 btg
Ijuk 30.000 ikat

SUMUR AIR BERSIH / UNIT


Bus Beton Dia. 100 cm 24.000 bh
Semen 0.816 zak
Pasir 0.065 m3
Kerikil 0.086 m3
Besi Dia. 08 2.000 btg

PEKERJAAN SANITAIR

DUDUKAN CLOSED JONGKOK / unit


Bata Merah 119.000 bh
Semen 0.323 zak
Pasir 0.064 m3

DUDUKAN BATHUP / unit


Bata Merah 535.000 bh
Semen 1.483 zak
Pasir 0.932 m3

PEKERJAAN BAK MANDI KERAMIK


Bata Merah 117.000 bh
Semen 0.405 zak
Pasir 0.057 m3
Keramik 20/25 2.590 dus
PEKERJAAN PERSIAPAN

PEMBERSIHAN LOKASI / m2
TENAGA KERJA Upah
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 3,500 Rp 3,500
UITZET BLOUPLANK / m'
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.020 org Rp 35,000 Rp 700
- Pekerja = 0.020 org Rp 25,000 Rp 500
Rp 2,200 Rp 2,200

PEKERJAAN GALIAN DAN URUGAN

GALIAN TANAH FONDASI / m3


TENAGA KERJA
- Mandor = 0.063 org Rp 50,000 Rp 3,125
- Pekerja = 0.313 org Rp 25,000 Rp 7,813
Rp 10,938 Rp 11,000
GALIAN TANAH FOOT PLAT / m3
TENAGA KERJA
- Mandor = 0.083 org Rp 50,000 Rp 4,167
Pekerja = 0.417 org Rp 25,000 Rp 10,417
Rp 14,583 Rp 14,600
URUGAN TANAH KEMBALI / m3
TENAGA KERJA
- Mandor = 0.031 org Rp 50,000 Rp 1,563
- Pekerja = 0.156 org Rp 25,000 Rp 3,906
Rp 5,469 Rp 5,500
URUGAN PASIR BAWAH LANTAI DAN FONDASI / m3
TENAGA KERJA
- Mandor = 0.080 org Rp 50,000 Rp 4,000
- Pekerja = 0.400 org Rp 25,000 Rp 10,000
Rp 14,000 Rp 14,000

PEKERJAAN PASANGAN

FONDASI BATU KALI / m3


TENAGA KERJA
- Mandor = 0.060 org Rp 50,000 Rp 2,976
- Tukang Batu = 0.476 org Rp 35,000 Rp 16,667
- Pekerja = 0.714 org Rp 25,000 Rp 17,857
Rp 37,500 Rp 37,500
DINDING TRASRAM DAN KM/WC / M3
TENAGA KERJA
- Mandor = 0.112 org Rp 50,000 Rp 5,580
- Tukang Batu = 1.190 org Rp 35,000 Rp 41,667
- Pekerja = 1.042 org Rp 25,000 Rp 26,042
Rp 73,289 Rp 73,300
DINDING BIASA / M3 - LANTAI 1
TENAGA KERJA
- Mandor = 0.071 org Rp 50,000 Rp 3,571
- Tukang Batu = 1.190 org Rp 35,000 Rp 41,667
- Pekerja = 1.190 org Rp 25,000 Rp 29,762
Rp 75,000 Rp 75,000
DINDING BIASA / M3 - LANTAI 2
TENAGA KERJA
- Mandor = 0.083 org Rp 50,000 Rp 4,167
- Tukang Batu = 1.389 org Rp 35,000 Rp 48,611
- Pekerja = 1.389 org Rp 25,000 Rp 34,722
Rp 87,500 Rp 87,500
PLESTERAN TRASRAM + KM/WC / M2
TENAGA KERJA
- Mandor = 0.021 org Rp 50,000 Rp 1,071
- Tukang Batu = 0.143 org Rp 35,000 Rp 5,000
- Pekerja = 0.071 org Rp 25,000 Rp 1,786
Rp 7,857 Rp 7,900
PLESTERAN BIASA / M2 -LANTAI 1
TENAGA KERJA
- Mandor = 0.023 org Rp 50,000 Rp 1,154
- Tukang Batu = 0.154 org Rp 35,000 Rp 5,385
- Pekerja = 0.077 org Rp 25,000 Rp 1,923
Rp 8,462 Rp 8,500
PLESTERAN BIASA / M2 - LANTAI 2
TENAGA KERJA
- Mandor = 0.024 org Rp 50,000 Rp 1,218
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.077 org Rp 25,000 Rp 1,923
Rp 8,974 Rp 9,000
SPONENGAN KOSEN / M'
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
Rp 4,000 Rp 4,000
SUDUTAN/TALI AIR / M'
TENAGA KERJA
- Mandor = 0.007 org Rp 50,000 Rp 333
- Tukang Batu = 0.067 org Rp 35,000 Rp 2,333
Rp 2,667 Rp 2,700

TALI AIR BESAR / M'


TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.200 org Rp 35,000 Rp 7,000
Rp 8,000 Rp 8,000
ORNAMEN DINDING / M'
TENAGA KERJA
- Mandor = 0.040 org Rp 50,000 Rp 2,000
- Tukang Batu = 0.200 org Rp 35,000 Rp 7,000
- Pekerja = 0.200 org Rp 25,000 Rp 5,000
Rp 14,000 Rp 14,000
BATU ALAM / M2
TENAGA KERJA
- Mandor = 0.100 org Rp 50,000 Rp 5,000
- Tukang Batu = 0.500 org Rp 35,000 Rp 17,500
- Pekerja = 0.500 org Rp 25,000 Rp 12,500
Rp 35,000 Rp 35,000
KORAL SIKAT GARASI / M2
TENAGA KERJA
- Mandor = 0.067 org Rp 50,000 Rp 3,333
- Tukang Batu = 0.333 org Rp 35,000 Rp 11,667
- Pekerja = 0.333 org Rp 25,000 Rp 8,333
Rp 23,333 Rp 23,400
LISPLANK GRC / M'
TENAGA KERJA
- Mandor = 0.025 org Rp 50,000 Rp 1,250
- Tukang Batu = 0.125 org Rp 35,000 Rp 4,375
- Pekerja = 0.125 org Rp 25,000 Rp 3,125
Rp 8,750 Rp 8,800
LIS PROFIL KOLOM TERAS / M'
TENAGA KERJA
- Mandor = 0.017 org Rp 50,000 Rp 833
- Tukang Batu = 0.083 org Rp 35,000 Rp 2,917
- Pekerja = 0.083 org Rp 25,000 Rp 2,083
Rp 5,833 Rp 5,900
BORDER JENDELA / M'
TENAGA KERJA
- Mandor = 0.023 org Rp 50,000 Rp 1,125
- Tukang Batu = 0.125 org Rp 35,000 Rp 4,375
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 8,000 Rp 8,000
LIS PROFIL LENGKUNG / BH
TENAGA KERJA
- Mandor = 0.030 org Rp 50,000 Rp 1,500
- Tukang Batu = 0.200 org Rp 35,000 Rp 7,000
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 11,000 Rp 11,000

LIS PLAT LEUFEL / M'


TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 7,000 Rp 7,000

BAK KONTROL / BH
TENAGA KERJA
- Mandor = 0.150 org Rp 50,000 Rp 7,500
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
- Pekerja = 0.500 org Rp 25,000 Rp 12,500
Rp 55,000 Rp 55,000
SCREEDING DAN WATERPROFING / m2
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 7,000 Rp 7,000

PEKERJAAN BETON

FOOT PLATE - 60/60 1 m3 = 12 bh


TENAGA KERJA
BEKISTING / m3 FOOT PLATE
- Mandor = 0.120 org Rp 50,000 Rp 6,000
- Tukang Kayu = 1.200 org Rp 35,000 Rp 42,000
Rp 48,000 Rp 48,000
PEMBESIAN / m3 FOOT PLATE
- Mandor = 0.540 org Rp 50,000 Rp 27,000
- Tukang Besi = 3.000 org Rp 35,000 Rp 105,000
- Pekerja = 2.400 org Rp 25,000 Rp 60,000
Rp 192,000 Rp 192,000
PENGECORAN / m3 FOOT PLATE
- Mandor = 0.343 org Rp 50,000 Rp 17,143
- Tukang Batu = 1.714 org Rp 35,000 Rp 60,000
- Pekerja = 1.714 org Rp 25,000 Rp 42,857
Rp 120,000 Rp 120,000
TOTAL UPAH = Rp 360,000

FOOT PLATE - 80/80 1 m3 = 7 bh


TENAGA KERJA
BEKISTING / m3 FOOT PLATE
- Mandor = 0.100 org Rp 50,000 Rp 5,000
- Tukang Kayu = 1.000 org Rp 35,000 Rp 35,000
Rp 40,000 Rp 40,000
PEMBESIAN / m3 FOOT PLATE
- Mandor = 0.583 org Rp 50,000 Rp 29,167
- Tukang Besi = 3.500 org Rp 35,000 Rp 122,500
- Pekerja = 2.333 org Rp 25,000 Rp 58,333
Rp 210,000 Rp 210,000
PENGECORAN / m3 FOOT PLATE
- Mandor = 0.280 org Rp 50,000 Rp 14,000
- Tukang Batu = 1.400 org Rp 35,000 Rp 49,000
- Pekerja = 1.400 org Rp 25,000 Rp 35,000
Rp 98,000 Rp 98,000
TOTAL UPAH = Rp 348,000

FOOT PLATE - 80/120 1 m3 = 5 bh


TENAGA KERJA
BEKISTING / m3 FOOT PLATE
- Mandor = 0.083 org Rp 50,000 Rp 4,167
- Tukang Kayu = 0.833 org Rp 35,000 Rp 29,167
Rp 33,333 Rp 33,400
PEMBESIAN / m3 FOOT PLATE
- Mandor = 0.450 org Rp 50,000 Rp 22,500
- Tukang Besi = 2.500 org Rp 35,000 Rp 87,500
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 160,000 Rp 160,000
PENGECORAN / m3 FOOT PLATE
- Mandor = 0.400 org Rp 50,000 Rp 20,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 140,000 Rp 140,000
TOTAL UPAH = Rp 333,400

FOOT PLATE - 100/100 1 m3 = 4 bh


TENAGA KERJA
BEKISTING / m3 FOOT PLATE
- Mandor = 0.080 org Rp 50,000 Rp 4,000
- Tukang Kayu = 0.800 org Rp 35,000 Rp 28,000
Rp 32,000 Rp 32,000
PEMBESIAN / m3 FOOT PLATE
- Mandor = 0.400 org Rp 50,000 Rp 20,000
- Tukang Besi = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 140,000 Rp 140,000
PENGECORAN / m3 FOOT PLATE
- Mandor = 0.400 org Rp 50,000 Rp 20,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 140,000 Rp 140,000
TOTAL UPAH = Rp 312,000

SLOOF 15/25 - 4D10+2D8


DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh

TENAGA KERJA
BEKISTING / m3 SLOOF 15/25
- Mandor = 0.198 org Rp 50,000 Rp 9,900
- Tukang Kayu = 1.080 org Rp 35,000 Rp 37,800
- Pekerja = 0.900 org Rp 25,000 Rp 22,500
Rp 70,200 Rp 70,200
PEMBESIAN / m3 SLOOF 15/25
- Mandor = 0.427 org Rp 50,000 Rp 21,368
- Tukang Besi = 2.263 org Rp 35,000 Rp 79,188
- Pekerja = 2.011 org Rp 25,000 Rp 50,278
Rp 150,833 Rp 150,900
PENGECORAN / m3 SLOOF 15/25
- Mandor = 0.203 org Rp 50,000 Rp 10,125
- Tukang Batu = 0.675 org Rp 35,000 Rp 23,625
- Pekerja = 1.350 org Rp 25,000 Rp 33,750

Rp 67,500 Rp 67,500

TOTAL UPAH = Rp 288,600


SLOOF 15/20 - 4D10
DIMENSI = 0.15 0.20 m2
Panjang / m3 = 34.00 m'
Jumlah Begel = 228 bh
TENAGA KERJA
BEKISTING / m3 SLOOF 15/20
- Mandor = 0.135 org Rp 50,000 Rp 6,750
- Tukang Kayu = 0.675 org Rp 35,000 Rp 23,625
- Pekerja = 0.675 org Rp 25,000 Rp 16,875
Rp 47,250 Rp 47,300
PEMBESIAN / m3 SLOOF 15/20
- Mandor = 0.570 org Rp 50,000 Rp 28,500
- Tukang Besi = 2.850 org Rp 35,000 Rp 99,750
- Pekerja = 2.850 org Rp 25,000 Rp 71,250
Rp 199,500 Rp 199,500
PENGECORAN / m3 SLOOF 15/20
- Mandor = 0.255 org Rp 50,000 Rp 12,750
- Tukang Batu = 0.850 org Rp 35,000 Rp 29,750
- Pekerja = 1.700 org Rp 25,000 Rp 42,500

Rp 85,000 Rp 85,000

TOTAL UPAH = Rp 331,800

RING BALK 15/20 - 4D10


DIMENSI = 0.15 0.20 m2
Panjang / m3 = 34.00 m'
Jumlah Begel = 228 bh
TENAGA KERJA
BEKISTING / m3 RING BALK
- Mandor = 0.283 org Rp 50,000 Rp 14,167
- Tukang Kayu = 1.133 org Rp 35,000 Rp 39,667
- Pekerja = 1.700 org Rp 25,000 Rp 42,500
Rp 96,333 Rp 96,400
PEMBESIAN / m3 RING BALK
- Mandor = 0.428 org Rp 50,000 Rp 21,375
- Tukang Besi = 2.850 org Rp 35,000 Rp 99,750
- Pekerja = 2.850 org Rp 25,000 Rp 71,250
Rp 192,375 Rp 192,400
PENGECORAN / m3 RING BALK
- Mandor = 0.170 org Rp 50,000 Rp 8,500
- Tukang Batu = 1.133 org Rp 35,000 Rp 39,667
- Pekerja = 2.267 org Rp 25,000 Rp 56,667
Rp 104,833 Rp 104,900
TOTAL UPAH = Rp 393,700
RING BALK 15/25 - 5D10+2D8
DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh
TENAGA KERJA
BEKISTING / m3 RING BALK
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Kayu = 1.350 org Rp 35,000 Rp 47,250
- Pekerja = 1.350 org Rp 25,000 Rp 33,750
Rp 94,500 Rp 94,500
PEMBESIAN / m3 RING BALK
- Mandor = 0.517 org Rp 50,000 Rp 25,857
- Tukang Besi = 2.586 org Rp 35,000 Rp 90,500
- Pekerja = 2.586 org Rp 25,000 Rp 64,643
Rp 181,000 Rp 181,000
PENGECORAN / m3 RING BALK
- Mandor = 0.405 org Rp 50,000 Rp 20,250
- Tukang Batu = 1.350 org Rp 35,000 Rp 47,250
- Pekerja = 2.700 org Rp 25,000 Rp 67,500
Rp 135,000 Rp 135,000
TOTAL UPAH = Rp 410,500

BALOK LATEI ATAS KUSEN - 2D10


DIMENSI = 0.12 0.10 m2
Panjang / m3 = 84.00 m'
Jumlah Begel = 561 bh
TENAGA KERJA
BEKISTING / m3 BALOK LATEI
- Mandor = 0.420 org Rp 50,000 Rp 21,000
- Tukang Kayu = 2.100 org Rp 35,000 Rp 73,500
- Pekerja = 2.100 org Rp 25,000 Rp 52,500
Rp 147,000 Rp 147,000
PEMBESIAN / m3 BALOK LATEI
- Mandor = 0.561 org Rp 50,000 Rp 28,050
- Tukang Besi = 2.805 org Rp 35,000 Rp 98,175
- Pekerja = 2.805 org Rp 25,000 Rp 70,125
Rp 196,350 Rp 196,400
PENGECORAN / m3 BALOK LATEI
- Mandor = 0.210 org Rp 50,000 Rp 10,500
- Tukang Batu = 0.700 org Rp 35,000 Rp 24,500
- Pekerja = 1.400 org Rp 25,000 Rp 35,000
Rp 70,000 Rp 70,000
TOTAL UPAH = Rp 413,400
KOLOM PRAKTIS - 4D8
DIMENSI = 0.15 0.15 m2
Panjang / m3 = 45.00 m'
Jumlah Begel = 301 bh
TENAGA KERJA
BEKISTING / m3 KOLOM PRAKTIS
- Mandor = 0.225 org Rp 50,000 Rp 11,250
- Tukang Kayu = 1.125 org Rp 35,000 Rp 39,375
- Pekerja = 1.125 org Rp 25,000 Rp 28,125
Rp 78,750 Rp 78,800
PEMBESIAN / m3 KOLOM PRAKTIS
- Mandor = 0.669 org Rp 50,000 Rp 33,444
- Tukang Besi = 3.344 org Rp 35,000 Rp 117,056
- Pekerja = 3.344 org Rp 25,000 Rp 83,611
Rp 234,111 Rp 234,200
PENGECORAN / m3 KOLOM PRAKTIS
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Batu = 0.900 org Rp 35,000 Rp 31,500
- Pekerja = 1.800 org Rp 25,000 Rp 45,000
Rp 90,000 Rp 90,000
TOTAL UPAH = Rp 403,000
KOLOM BETON 15/15 - 4D10
DIMENSI = 0.15 0.15 m2
Panjang / m3 = 45.00 m'
Jumlah Begel = 301 bh
TENAGA KERJA
BEKISTING / m3 KOLOM 15/15
- Mandor = 0.225 org Rp 50,000 Rp 11,250
- Tukang Kayu = 1.125 org Rp 35,000 Rp 39,375
- Pekerja = 1.125 org Rp 25,000 Rp 28,125
Rp 78,750 Rp 78,800
PEMBESIAN / m3 KOLOM 15/15
- Mandor = 0.669 org Rp 50,000 Rp 33,444
- Tukang Besi = 3.344 org Rp 35,000 Rp 117,056
- Pekerja = 3.344 org Rp 25,000 Rp 83,611
Rp 234,111 Rp 234,200
PENGECORAN / m3 KOLOM 15/15
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Batu = 0.900 org Rp 35,000 Rp 31,500
- Pekerja = 1.800 org Rp 25,000 Rp 45,000
Rp 90,000 Rp 90,000
TOTAL UPAH = Rp 403,000
KOLOM 15/30 - 6D12
DIMENSI = 0.15 0.30 m2
Panjang / m3 = 23.00 m'
Jumlah Begel = 155 bh
TENAGA KERJA
BEKISTING / m3 KOLOM 15/30
- Mandor = 0.230 org Rp 50,000 Rp 11,500
- Tukang Kayu = 1.533 org Rp 35,000 Rp 53,667
Rp 65,167 Rp 65,200
PEMBESIAN / m3 KOLOM 15/30
- Mandor = 0.620 org Rp 50,000 Rp 31,000
- Tukang Besi = 3.100 org Rp 35,000 Rp 108,500
- Pekerja = 3.100 org Rp 25,000 Rp 77,500
Rp 217,000 Rp 217,000
PENGECORAN / m3 KOLOM 15/30
- Mandor = 0.460 org Rp 50,000 Rp 23,000
- Tukang Batu = 1.533 org Rp 35,000 Rp 53,667
- Pekerja = 3.067 org Rp 25,000 Rp 76,667
Rp 153,333 Rp 153,400
TOTAL UPAH = Rp 435,600
KOLOM 15/20 - 4D12
DIMENSI = 0.15 0.20 m2
Panjang / m3 = 34.00 m'
Jumlah Begel = 228 bh
TENAGA KERJA
BEKISTING / m3 KOLOM 15/20
- Mandor = 0.227 org Rp 50,000 Rp 11,333
- Tukang Kayu = 2.267 org Rp 35,000 Rp 79,333
Rp 90,667 Rp 90,700
PEMBESIAN / m3 KOLOM 15/20
- Mandor = 0.570 org Rp 50,000 Rp 28,500
- Tukang Besi = 2.850 org Rp 35,000 Rp 99,750
- Pekerja = 2.850 org Rp 25,000 Rp 71,250
Rp 199,500 Rp 199,500
PENGECORAN / m3 KOLOM 15/20
- Mandor = 0.408 org Rp 50,000 Rp 20,400
- Tukang Batu = 1.360 org Rp 35,000 Rp 47,600
- Pekerja = 2.720 org Rp 25,000 Rp 68,000
Rp 136,000 Rp 136,000
TOTAL UPAH = Rp 426,200
KOLOM 15/25 - 6D10
DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh
TENAGA KERJA
BEKISTING / m3 KOLOM 15/25
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Kayu = 2.700 org Rp 35,000 Rp 94,500
Rp 108,000 Rp 108,000
PEMBESIAN / m3 KOLOM 15/25
- Mandor = 0.517 org Rp 50,000 Rp 25,857
- Tukang Besi = 2.586 org Rp 35,000 Rp 90,500
- Pekerja = 2.586 org Rp 25,000 Rp 64,643
Rp 181,000 Rp 181,000
PENGECORAN / m3 KOLOM 15/25
- Mandor = 0.405 org Rp 50,000 Rp 20,250
- Tukang Batu = 1.350 org Rp 35,000 Rp 47,250
- Pekerja = 2.700 org Rp 25,000 Rp 67,500
Rp 135,000 Rp 135,000
TOTAL UPAH = Rp 424,000
KOLOM 15/25 - 4D10+2D8
DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh
TENAGA KERJA
BEKISTING / m3 KOLOM 15/25
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Kayu = 2.700 org Rp 35,000 Rp 94,500
Rp 108,000 Rp 108,000
PEMBESIAN / m3 KOLOM 15/25
- Mandor = 0.517 org Rp 50,000 Rp 25,857
- Tukang Besi = 2.586 org Rp 35,000 Rp 90,500
- Pekerja = 2.586 org Rp 25,000 Rp 64,643
Rp 181,000 Rp 181,000
PENGECORAN / m3 KOLOM 15/25
- Mandor = 0.405 org Rp 50,000 Rp 20,250
- Tukang Batu = 1.350 org Rp 35,000 Rp 47,250
- Pekerja = 2.700 org Rp 25,000 Rp 67,500
Rp 135,000 Rp 135,000
TOTAL UPAH = Rp 424,000
BALOK 15/35 -5D12+2D8
DIMENSI = 0.15 0.35 m2
Panjang / m3 = 20.00 m'
Jumlah Begel = 135 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/35
- Mandor = 0.267 org Rp 50,000 Rp 13,333
- Tukang Kayu = 2.667 org Rp 35,000 Rp 93,333
Rp 106,667 Rp 106,700
PEMBESIAN / m3 BALOK 15/35
- Mandor = 0.418 org Rp 50,000 Rp 20,893
- Tukang Besi = 2.250 org Rp 35,000 Rp 78,750
- Pekerja = 1.929 org Rp 25,000 Rp 48,214
Rp 147,857 Rp 147,900
PENGECORAN / m3 BALOK 15/35
- Mandor = 0.600 org Rp 50,000 Rp 30,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 4.000 org Rp 25,000 Rp 100,000
Rp 200,000 Rp 200,000
TOTAL UPAH = Rp 454,600
BALOK 15/30 - 5D12+2D10
DIMENSI = 0.15 0.30 m2
Panjang / m3 = 23.00 m'
Jumlah Begel = 155 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/30
- Mandor = 0.307 org Rp 50,000 Rp 15,333
- Tukang Kayu = 3.067 org Rp 35,000 Rp 107,333
Rp 122,667 Rp 122,700
PEMBESIAN / m3 BALOK 15/30
- Mandor = 0.480 org Rp 50,000 Rp 23,988
- Tukang Besi = 2.583 org Rp 35,000 Rp 90,417
- Pekerja = 2.214 org Rp 25,000 Rp 55,357
Rp 169,762 Rp 169,800
PENGECORAN / m3 BALOK 15/30
- Mandor = 0.471 org Rp 50,000 Rp 23,548
- Tukang Batu = 1.643 org Rp 35,000 Rp 57,500
- Pekerja = 3.067 org Rp 25,000 Rp 76,667
Rp 157,714 Rp 157,800
TOTAL UPAH = Rp 450,300
BALOK BORDES 15/30 - 6D12
DIMENSI = 0.15 0.30 m2
Panjang / m3 = 23.00 m'
Jumlah Begel = 155 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/30
- Mandor = 0.307 org Rp 50,000 Rp 15,333
- Tukang Kayu = 3.067 org Rp 35,000 Rp 107,333
Rp 122,667 Rp 122,700
PEMBESIAN / m3 BALOK 15/30
- Mandor = 0.443 org Rp 50,000 Rp 22,143
- Tukang Besi = 2.214 org Rp 35,000 Rp 77,500
- Pekerja = 2.214 org Rp 25,000 Rp 55,357
Rp 155,000 Rp 155,000
PENGECORAN / m3 BALOK 15/30
- Mandor = 0.471 org Rp 50,000 Rp 23,548
- Tukang Batu = 1.643 org Rp 35,000 Rp 57,500
- Pekerja = 3.067 org Rp 25,000 Rp 76,667
Rp 157,714 Rp 157,800
TOTAL UPAH = Rp 435,500
BALOK 15/25 -5D12
DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/25
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Kayu = 2.700 org Rp 35,000 Rp 94,500
Rp 108,000 Rp 108,000
PEMBESIAN / m3 BALOK 15/25
- Mandor = 0.453 org Rp 50,000 Rp 22,625
- Tukang Besi = 2.263 org Rp 35,000 Rp 79,188
- Pekerja = 2.263 org Rp 25,000 Rp 56,563
Rp 158,375 Rp 158,400
PENGECORAN / m3 BALOK 15/25
- Mandor = 0.476 org Rp 50,000 Rp 23,824
- Tukang Batu = 1.588 org Rp 35,000 Rp 55,588
- Pekerja = 3.176 org Rp 25,000 Rp 79,412
Rp 158,824 Rp 158,900
TOTAL UPAH = Rp 425,300
BALOK 15/25 - 4D12
DIMENSI = 0.15 0.25 m2
Panjang / m3 = 27.00 m'
Jumlah Begel = 181 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/25
- Mandor = 0.270 org Rp 50,000 Rp 13,500
- Tukang Kayu = 2.700 org Rp 35,000 Rp 94,500
Rp 108,000 Rp 108,000
PEMBESIAN / m3 BALOK 15/25
- Mandor = 0.453 org Rp 50,000 Rp 22,625
- Tukang Besi = 2.263 org Rp 35,000 Rp 79,188
- Pekerja = 2.263 org Rp 25,000 Rp 56,563
Rp 158,375 Rp 158,400
PENGECORAN / m3 BALOK 15/25
- Mandor = 0.476 org Rp 50,000 Rp 23,824
- Tukang Batu = 1.588 org Rp 35,000 Rp 55,588
- Pekerja = 3.176 org Rp 25,000 Rp 79,412
Rp 158,824 Rp 158,900
TOTAL UPAH = Rp 425,300
BALOK 15/20 - 4D10
DIMENSI = 0.15 0.20 m2
Panjang / m3 = 34.00 m'
Jumlah Begel = 228 bh
TENAGA KERJA
BEKISTING / m3 BALOK 15/20
- Mandor = 0.170 org Rp 50,000 Rp 8,500
- Tukang Kayu = 1.700 org Rp 35,000 Rp 59,500
Rp 68,000 Rp 68,000
PEMBESIAN / m3 BALOK 15/20
- Mandor = 0.570 org Rp 50,000 Rp 28,500
- Tukang Besi = 2.850 org Rp 35,000 Rp 99,750
- Pekerja = 2.850 org Rp 25,000 Rp 71,250
Rp 199,500 Rp 199,500
PENGECORAN / m3 BALOK 15/20
- Mandor = 0.363 org Rp 50,000 Rp 18,133
- Tukang Batu = 1.360 org Rp 35,000 Rp 47,600
- Pekerja = 2.267 org Rp 25,000 Rp 56,667
Rp 122,400 Rp 122,400
TOTAL UPAH = Rp 389,900
PLAT LANTAI T=12 cm / m3
Tebal = = 0.12 m
Luas / m3 = 8.33 m2
Besi 10 Arah - x = 41 bh
Besi 8 Arah - y = 41 bh
Jarak Tulangan = 0.15 m
TENAGA KERJA
BEKISTING / m3 PLAT LANTAI
- Mandor = 0.417 org Rp 50,000 Rp 20,833
- Tukang Kayu = 4.167 org Rp 35,000 Rp 145,833
Rp 166,667 Rp 166,700
PEMBESIAN / m3 PLAT LANTAI
- Mandor = 0.820 org Rp 50,000 Rp 41,000
- Tukang Besi = 4.100 org Rp 35,000 Rp 143,500
- Pekerja = 4.100 org Rp 25,000 Rp 102,500
Rp 287,000 Rp 287,000
PENGECORAN / m3 PLAT LANTAI
- Mandor = 0.417 org Rp 50,000 Rp 20,833
- Tukang Batu = 2.083 org Rp 35,000 Rp 72,917
- Pekerja = 2.083 org Rp 25,000 Rp 52,083
Rp 145,833 Rp 145,900
TOTAL UPAH = Rp 599,600
PLAT LEUFEL T=10 cm / m3
Tebal = = 0.10 m
Luas / m3 = 10.00 m2
Besi 10 Arah - x = 23 bh
Besi 8 Arah - y = 67 bh
Jarak Tulangan = 0.15 m
TENAGA KERJA
BEKISTING / m3 PLAT LEUFEL
- Mandor = 0.333 org Rp 50,000 Rp 16,667
- Tukang Kayu = 3.333 org Rp 35,000 Rp 116,667
Rp 133,333 Rp 133,400
PEMBESIAN / m3 PLAT LEUFEL
- Mandor = 0.810 org Rp 50,000 Rp 40,500
- Tukang Besi = 3.600 org Rp 35,000 Rp 126,000
- Pekerja = 4.500 org Rp 25,000 Rp 112,500
Rp 279,000 Rp 279,000
PENGECORAN / m3 PLAT LEUFEL
- Mandor = 0.400 org Rp 50,000 Rp 20,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 140,000 Rp 140,000
TOTAL UPAH = Rp 552,400
MEJA DAPUR T= 7 cm / m3
Tebal = = 0.07 m2
Luas / m3 = 14.29 m2
Besi 6 Arah - x = 4 bh
Besi 6 Arah - y = 121 bh
Jarak Tulangan = 0.2 m
TENAGA KERJA
BEKISTING / m3 MEJA DAPUR
- Mandor = 0.286 org Rp 50,000 Rp 14,286
- Tukang Kayu = 2.857 org Rp 35,000 Rp 100,000
Rp 114,286 Rp 114,300
PEMBESIAN / m3 MEJA DAPUR
- Mandor = 0.492 org Rp 50,000 Rp 24,620
- Tukang Besi = 2.500 org Rp 35,000 Rp 87,500
- Pekerja = 2.424 org Rp 25,000 Rp 60,600
Rp 172,720 Rp 172,800
PENGECORAN / m3 MEJA DAPUR
- Mandor = 0.190 org Rp 50,000 Rp 9,524
- Tukang Batu = 0.952 org Rp 35,000 Rp 33,333
- Pekerja = 0.952 org Rp 25,000 Rp 23,810
Rp 66,667 Rp 66,700
TOTAL UPAH = Rp 353,800
RABAT BETON CAMP. 1:3:5 / M3
Tebal = = 0.07 m
Luas / m3 = 14.29 m2
TENAGA KERJA
- Mandor = 0.286 org Rp 50,000 Rp 14,286
- Tukang Batu = 1.429 org Rp 35,000 Rp 50,000
- Pekerja = 1.429 org Rp 25,000 Rp 35,714
Rp 100,000 Rp 100,000

PEKERJAAN KUSEN DAN DAUN PINTU JENDELA

KUSEN PINTU DAN JENDELA / m'


TENAGA KERJA
- Mandor = 0.005 org Rp 50,000 Rp 250
- Tukang Kayu = 0.050 org Rp 35,000 Rp 1,750
Rp 2,000 Rp 2,000
DAUN JENDELA / BH
TENAGA KERJA
- Mandor = 0.033 org Rp 50,000 Rp 1,667
- Tukang Kayu = 0.333 org Rp 35,000 Rp 11,667
Rp 13,333 Rp 13,400
DAUN PINTU / BH
TENAGA KERJA
- Mandor = 0.050 org Rp 50,000 Rp 2,500
- Tukang Kayu = 0.500 org Rp 35,000 Rp 17,500
Rp 20,000 Rp 20,000

ROSTER / BH
TENAGA KERJA
- Mandor = 0.005 org Rp 50,000 Rp 250
- Tukang Batu = 0.050 org Rp 35,000 Rp 1,750
Rp 2,000 Rp 2,000

PEKERJAAN ACCESORIS PINTU DAN JENDELA

SLOT DAN HANDLE PINTU / BH


TENAGA KERJA
- Mandor = 0.050 org Rp 50,000 Rp 2,500
- Tukang Kayu = 1.000 org Rp 35,000 Rp 35,000
Rp 37,500 Rp 37,500
ENGSEL PINTU DAN JENDELA / BH
TENAGA KERJA
- Mandor = 0.005 org Rp 50,000 Rp 250
- Tukang Kayu = 0.100 org Rp 35,000 Rp 3,500
Rp 3,750 Rp 3,800
GRENDEL PINTU DAN JENDELA / BH
TENAGA KERJA
- Mandor = 0.003 org Rp 50,000 Rp 125
- Tukang Kayu = 0.050 org Rp 35,000 Rp 1,750
Rp 1,875 Rp 1,900
GRENDEL TANAM PINTU DOUBLE / SET
TENAGA KERJA
- Mandor = 0.033 org Rp 50,000 Rp 1,667
- Tukang Kayu = 0.667 org Rp 35,000 Rp 23,333
Rp 25,000 Rp 25,000
HAK ANGIN
TENAGA KERJA
- Mandor = 0.003 org Rp 50,000 Rp 125
- Tukang Kayu = 0.050 org Rp 35,000 Rp 1,750
Rp 1,875 Rp 1,900

PEKERJAAN RANGKA ATAP

PEKERJAAN GORDING, NOK, MURPLAT, KUDA2 / M3


Panjang 1 m3 Kayu 8/12 = 105 m'
TENAGA KERJA
- Mandor = 1.167 org Rp 50,000 Rp 58,333
- Tukang Kayu = 8.750 org Rp 35,000 Rp 306,250
- Pekerja = 2.917 org Rp 25,000 Rp 72,917
Rp 437,500 Rp 437,500
PEKERJAAN USUK DAN RENG / M2
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Kayu = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 7,000
PEKERJAAN TALANG JURAI / M1
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Kayu = 0.050 org Rp 35,000 Rp 1,750
- Pekerja = 0.050 org Rp 25,000 Rp 1,250
Rp 3,500 Rp 3,500
PEKERJAAN PAPAN REUTER / M1
TENAGA KERJA
- Mandor = 0.005 org Rp 50,000 Rp 250
- Tukang Kayu = 0.025 org Rp 35,000 Rp 875
- Pekerja = 0.025 org Rp 25,000 Rp 625
Rp 1,750 Rp 1,800
PEKERJAAN PAPAN LISPLANK / M1
TENAGA KERJA
- Mandor = 0.019 org Rp 50,000 Rp 938
- Tukang Kayu = 0.125 org Rp 35,000 Rp 4,375
- Pekerja = 0.063 org Rp 25,000 Rp 1,563
Rp 6,875 Rp 6,900

PEKERJAAN PENUTUP ATAP

PEKERJAAN GENTENG BETON


Jumlah 1 m2 = 9 bh
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Kayu = 0.050 org Rp 35,000 Rp 1,750
- Pekerja = 0.050 org Rp 25,000 Rp 1,250
Rp 3,500 Rp 3,500
PEKERJAAN GENTENG GLAZUR
Jumlah 1 m2 = 14.5 bh
TENAGA KERJA
- Mandor = 0.013 org Rp 50,000 Rp 667
- Tukang Kayu = 0.067 org Rp 35,000 Rp 2,333
- Pekerja = 0.067 org Rp 25,000 Rp 1,667
Rp 4,667 Rp 4,700
PEKERJAAN KERPUS GENTENG BETON
TENAGA KERJA
- Mandor = 0.034 org Rp 50,000 Rp 1,714
- Tukang Batu = 0.200 org Rp 35,000 Rp 7,000
- Pekerja = 0.143 org Rp 25,000 Rp 3,571
Rp 12,286 Rp 12,300
PEKERJAAN KERPUS GENTENG GLAZUR
TENAGA KERJA
- Mandor = 0.040 org Rp 50,000 Rp 2,000
- Tukang Batu = 0.200 org Rp 35,000 Rp 7,000
- Pekerja = 0.200 org Rp 25,000 Rp 5,000
Rp 14,000 Rp 14,000

PEKERJAAN PLAFOND

PEKERJAAN RANGKA PLAFOND / M2


TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Kayu = 0.200 org Rp 35,000 Rp 7,000
Rp 8,000 Rp 8,000
PEKERJAAN PLAFOND GYPSUMBOARD / M2
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Gypsum = 0.100 org Rp 35,000 Rp 3,500
Rp 4,000 Rp 4,000
PEKERJAAN PLAFOND ETERNIT / M2
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Gypsum = 0.100 org Rp 35,000 Rp 3,500
Rp 4,000 Rp 4,000
PEKERJAAN LIS PLAFOND GYPSUM / m'
TENAGA KERJA
- Mandor = 0.007 org Rp 50,000 Rp 333
- Tukang Gypsum = 0.067 org Rp 35,000 Rp 2,333
Rp 2,667 Rp 2,700

PEKERJAAN KERAMIK

KERAMIK LANTAI - 01 / M2
TENAGA KERJA
- Mandor = 0.022 org Rp 50,000 Rp 1,111
- Tukang Batu = 0.111 org Rp 35,000 Rp 3,889
- Pekerja = 0.111 org Rp 25,000 Rp 2,778
Rp 7,778 Rp 7,800
KERAMIK LANTAI - 02 / M2
TENAGA KERJA
- Mandor = 0.026 org Rp 50,000 Rp 1,278
- Tukang Batu = 0.128 org Rp 35,000 Rp 4,472
- Pekerja = 0.128 org Rp 25,000 Rp 3,194
Rp 8,944 Rp 9,000
PLINT KERAMIK LANTAI - 01 / M'
TENAGA KERJA
- Mandor = 0.017 org Rp 50,000 Rp 833
- Tukang Batu = 0.083 org Rp 35,000 Rp 2,917
- Pekerja = 0.083 org Rp 25,000 Rp 2,083
Rp 5,833 Rp 5,900
PLINT KERAMIK LANTAI - 02 / M'
TENAGA KERJA
- Mandor = 0.018 org Rp 50,000 Rp 917
- Tukang Batu = 0.092 org Rp 35,000 Rp 3,208
- Pekerja = 0.092 org Rp 25,000 Rp 2,292
Rp 6,417 Rp 6,500
KERAMIK LANTAI KM 20/20 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.029 org Rp 50,000 Rp 1,458
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.125 org Rp 25,000 Rp 3,125
Rp 10,417 Rp 10,500
KERAMIK LANTAI KM 20/20 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.032 org Rp 50,000 Rp 1,604
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.138 org Rp 25,000 Rp 3,438
Rp 11,458 Rp 11,500
KERAMIK DINDING 20/20 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.033 org Rp 50,000 Rp 1,667
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.167 org Rp 25,000 Rp 4,167
Rp 11,667 Rp 11,700
KERAMIK DINDING 20/20 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.037 org Rp 50,000 Rp 1,833
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.183 org Rp 25,000 Rp 4,583
Rp 12,833 Rp 12,900
KERAMIK DINDING 20/25 - LANTAI 01 / M2
TENAGA KERJA
- Mandor = 0.032 org Rp 50,000 Rp 1,603
- Tukang Batu = 0.167 org Rp 35,000 Rp 5,833
- Pekerja = 0.154 org Rp 25,000 Rp 3,846
Rp 11,282 Rp 11,300
KERAMIK DINDING 20/25 - LANTAI 02 / M2
TENAGA KERJA
- Mandor = 0.035 org Rp 50,000 Rp 1,763
- Tukang Batu = 0.183 org Rp 35,000 Rp 6,417
- Pekerja = 0.169 org Rp 25,000 Rp 4,231
Rp 12,410 Rp 12,500
LIS BORDER 7 x 20 / M1
TENAGA KERJA
- Mandor = 0.011 org Rp 50,000 Rp 556
- Tukang Batu = 0.111 org Rp 35,000 Rp 3,889
Rp 4,444 Rp 4,500
KERAMIK MEJA DAPUR 20/20 / M2
TENAGA KERJA
- Mandor = 0.050 org Rp 50,000 Rp 2,500
- Tukang Batu = 0.250 org Rp 35,000 Rp 8,750
- Pekerja = 0.250 org Rp 25,000 Rp 6,250
Rp 17,500 Rp 17,500

PEKERJAAN CAT

CAT DINDING LANTAI - 01


TENAGA KERJA
- Mandor = 0.013 org Rp 50,000 Rp 625
- Tukang Cat = 0.125 org Rp 32,000 Rp 4,000
Rp 4,625 Rp 4,700
CAT DINDING LANTAI - 02
TENAGA KERJA
- Mandor = 0.017 org Rp 50,000 Rp 833
- Tukang Cat = 0.167 org Rp 32,000 Rp 5,333
Rp 6,167 Rp 6,200
CAT PLAFOND
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Cat = 0.100 org Rp 32,000 Rp 3,200
Rp 3,700 Rp 3,700

PEKERJAAN INSTALASI AIR

PEMASANGAN INSTALASI AIR BERSIH / m'


TENAGA KERJA
- Mandor = 0.013 org Rp 50,000 Rp 667
- Tukang Batu = 0.067 org Rp 35,000 Rp 2,333
- Pekerja = 0.067 org Rp 25,000 Rp 1,667
Rp 4,667 Rp 4,700
PEMASANGAN INSTALASI AIR KOTOR / m'
TENAGA KERJA
- Mandor = 0.020 org Rp 50,000 Rp 1,000
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 7,000 Rp 7,000

PEMASANGAN INSTALASI POMPA DAN TOWER AIR


TENAGA KERJA
- Mandor = 0.300 org Rp 50,000 Rp 15,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 1.000 org Rp 25,000 Rp 25,000
Rp 110,000 Rp 110,000

SEPTIC TANK / unit


TENAGA KERJA
- Tukang Sumur = 2.000 org Rp 40,000 Rp 80,000 Rp 52,600
- Tukang Batu 0.400 org Rp 35,000 Rp 14,000
- Pekerja = 1.500 org Rp 25,000 Rp 37,500
Rp 131,500 Rp 131,500

PERESAPAN / unit
TENAGA KERJA
- Tukang Sumur = 1.500 org Rp 40,000 Rp 60,000 Rp 58,750
- Tukang Batu 0.500 org Rp 35,000 Rp 17,500
- Pekerja = 1.600 org Rp 25,000 Rp 40,000
Rp 117,500 Rp 117,500
SUMUR AIR BERSIH / unit
TENAGA KERJA
- Tukang Sumur = 10.000 org Rp 40,000 Rp 400,000 Rp 52,375
- Tukang Batu 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 9.000 org Rp 25,000 Rp 225,000
Rp 628,500 Rp 628,500

PEKERJAAN SANITAIR

DUDUKAN CLOSED JONGKOK / unit


TENAGA KERJA
- Mandor = 0.200 org Rp 50,000 Rp 10,000
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
- Pekerja = 1.000 org Rp 25,000 Rp 25,000
Rp 70,000 Rp 70,000

BAK MANDI KERAMIK


TENAGA KERJA
- Mandor = 0.250 org Rp 50,000 Rp 12,500
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 0.500 org Rp 25,000 Rp 12,500
Rp 95,000 Rp 95,000

SETTING DAN PEMASANGAN INSTALASI MONOBLOK / unit


TENAGA KERJA
- Mandor = 0.750 org Rp 50,000 Rp 37,500
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
Rp 72,500 Rp 72,500
DUDUKAN BATHUP / unit
TENAGA KERJA
- Mandor = 0.400 org Rp 50,000 Rp 20,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 140,000 Rp 140,000
SETTING DAN PEMASANGAN INSTALASI BATHUP / unit
TENAGA KERJA
- Mandor = 1.000 org Rp 50,000 Rp 50,000
- Tukang Batu = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 170,000 Rp 170,000
SETTING SHOWER / unit
TENAGA KERJA
- Mandor = 0.050 org Rp 50,000 Rp 2,500
- Tukang Batu = 0.500 org Rp 35,000 Rp 17,500
Rp 20,000 Rp 20,000
SETTING DAN PEMASANGAN INSTALASI WASTAFEL / unit
TENAGA KERJA
- Mandor = 0.100 org Rp 50,000 Rp 5,000
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
Rp 40,000 Rp 40,000
PEMASANGAN KRAN AIR
TENAGA KERJA
- Mandor = 0.010 org Rp 50,000 Rp 500
- Tukang Batu = 0.100 org Rp 35,000 Rp 3,500
Rp 4,000 Rp 4,000
SETTING KITCHEN ZINK DAN FINISHING MEJA DAPUR
TENAGA KERJA
- Mandor = 0.100 org Rp 50,000 Rp 5,000
- Tukang Batu = 1.000 org Rp 35,000 Rp 35,000
Rp 40,000 Rp 40,000

PEKERJAAN INSTALASI LISTRIK

INSTALASI TITIK LAMPU / ttk


TENAGA KERJA
- Mandor = 0.073 org Rp 50,000 Rp 3,667
- Tukang Listrik = 0.400 org Rp 35,000 Rp 14,000
- Pekerja = 0.333 org Rp 25,000 Rp 8,333
Rp 26,000 Rp 26,000
INSTALASI STOP KONTAK / ttk
TENAGA KERJA
- Mandor = 0.073 org Rp 50,000 Rp 3,667
- Tukang Listrik = 0.400 org Rp 35,000 Rp 14,000
- Pekerja = 0.333 org Rp 25,000 Rp 8,333
Rp 26,000 Rp 26,000
INSTALASI METERAN DAN MCB / ttk
TENAGA KERJA
- Mandor = 0.100 org Rp 50,000 Rp 5,000
- Tukang Listrik = 0.500 org Rp 35,000 Rp 17,500
- Pekerja = 0.500 org Rp 25,000 Rp 12,500
Rp 35,000 Rp 35,000

PEKERJAAN LAIN-LAIN

SETTING TANGGA PUTAR / set


TENAGA KERJA
- Mandor = 0.500 org Rp 50,000 Rp 25,000
- Tukang Besi = 2.000 org Rp 35,000 Rp 70,000
- Pekerja = 3.000 org Rp 25,000 Rp 75,000
Rp 170,000 Rp 170,000
SETTING RAILING TANGGA / m'
TENAGA KERJA
- Mandor = 0.300 org Rp 50,000 Rp 15,000
- Tukang Besi = 1.000 org Rp 35,000 Rp 35,000
- Pekerja = 2.000 org Rp 25,000 Rp 50,000
Rp 100,000 Rp 100,000
SETTING LANSEKAP / m2
TENAGA KERJA
- Tukang Taman = 0.100 org Rp 35,000 Rp 3,500
- Pekerja = 0.100 org Rp 25,000 Rp 2,500
Rp 6,000 Rp 6,000
URAIAN PEKERJAAN KEAHLIAN KOEF UNIT

PEKERJAAN PERSIAPAN

PEMBERSIHAN LOKASI / m2
Mandor 0.02 org
Pekerja 0.1 org

UITZET BLOUPLANK / m'


Mandor 0.02 org
Tukang Batu 0.02 org
Pekerja 0.02 org

PEKERJAAN GALIAN DAN URUGAN

GALIAN TANAH FONDASI / m3


Mandor 0.063 org
Pekerja 0.313 org

GALIAN TANAH FOOT PLAT / m3


Mandor 0.083 org
Pekerja 0.417 org

URUGAN TANAH KEMBALI / m3


Mandor 0.031 org
Pekerja 0.156 org

URUGAN PASIR BAWAH LANTAI DAN FONDASI / m3


Mandor 0.080 org
Pekerja 0.400 org

PEKERJAAN PASANGAN

FONDASI BATU KALI / m3


Mandor 0.060 org
Tukang Batu 0.476 org
Pekerja 0.714 org

DINDING TRASRAM DAN KM/WC / M3


Mandor 0.112 org
Tukang Batu 1.190 org
Pekerja 1.042 org

DINDING BIASA / M3 - LANTAI 1


Mandor 0.071 org
Tukang Batu 1.190 org
Pekerja 1.190 org

DINDING BIASA / M3 - LANTAI 2


Mandor 0.083 org
Tukang Batu 1.389 org
Pekerja 1.389 org

PLESTERAN TRASRAM + KM/WC / M2


Mandor 0.021 org
Tukang Batu 0.143 org
Pekerja 0.071 org

PLESTERAN BIASA / M2 -LANTAI 1


Mandor 0.023 org
Tukang Batu 0.154 org
Pekerja 0.077 org

PLESTERAN BIASA / M2 - LANTAI 2


Mandor 0.024 org
Tukang Batu 0.167 org
Pekerja 0.077 org

SPONENGAN KOSEN / M'


Mandor 0.010 org
Tukang Batu 0.100 org

SUDUTAN/TALI AIR / M'


Mandor 0.007 org
Tukang Batu 0.067 org

TALI AIR BESAR / M'


Mandor 0.020 org
Tukang Batu 0.200 org

ORNAMEN DINDING / M'


Mandor 0.040 org
Tukang Batu 0.200 org
Pekerja 0.200 org

BATU ALAM / M2
Mandor 0.100 org
Tukang Batu 0.500 org
Pekerja 0.500 org

KORAL SIKAT GARASI / M2


Mandor 0.067 org
Tukang Batu 0.333 org
Pekerja 0.333 org

LISPLANK GRC / M'


Mandor 0.025 org
Tukang Batu 0.125 org
Pekerja 0.125 org
LIS PROFIL KOLOM TERAS / M'
Mandor 0.017 org
Tukang Batu 0.083 org
Pekerja 0.083 org

BORDER JENDELA / M'


Mandor 0.023 org
Tukang Batu 0.125 org
Pekerja 0.100 org

LIS PROFIL LENGKUNG / BH


Mandor 0.030 org
Tukang Batu 0.200 org
Pekerja 0.100 org

LIS PLAT LEUFEL / M'


Mandor 0.020 org
Tukang Batu 0.100 org
Pekerja 0.100 org

BAK KONTROL / BH
Mandor 0.150 org
Tukang Batu 1.000 org
Pekerja 0.500 org

SCREEDING DAN WATERPROFING / m2


Mandor 0.020 org
Tukang Batu 0.100 org
Pekerja 0.100 org

PEKERJAAN BETON

FOOT PLATE - 60/60


BEKISTING / m3 FOOT PLATE
Mandor 0.120 org
Tukang Kayu 1.200 org
PEMBESIAN / m3 FOOT PLATE
Mandor 0.540 org
Tukang Besi 3.000 org
Pekerja 2.400 org
PENGECORAN / m3 FOOT PLATE
Mandor 0.343 org
Tukang Batu 1.714 org
Pekerja 1.714 org

FOOT PLATE - 80/80


BEKISTING / m3 FOOT PLATE
Mandor 0.100 org
Tukang Kayu 1.000 org
PEMBESIAN / m3 FOOT PLATE
Mandor 0.583 org
Tukang Besi 3.500 org
Pekerja 2.333 org
PENGECORAN / m3 FOOT PLATE
Mandor 0.280 org
Tukang Batu 1.400 org
Pekerja 1.400 org

FOOT PLATE - 80/120


BEKISTING / m3 FOOT PLATE
Mandor 0.083 org
Tukang Kayu 0.833 org
PEMBESIAN / m3 FOOT PLATE
Mandor 0.450 org
Tukang Besi 2.500 org
Pekerja 2.000 org
PENGECORAN / m3 FOOT PLATE
Mandor 0.400 org
Tukang Batu 2.000 org
Pekerja 2.000 org

FOOT PLATE - 100/100


BEKISTING / m3 FOOT PLATE
Mandor 0.080 org
Tukang Kayu 0.800 org
PEMBESIAN / m3 FOOT PLATE
Mandor 0.400 org
Tukang Besi 2.000 org
Pekerja 2.000 org
PENGECORAN / m3 FOOT PLATE
Mandor 0.400 org
Tukang Batu 2.000 org
Pekerja 2.000 org

SLOOF 15/25 - 4D10+2D8


BEKISTING / m3 SLOOF 15/25
Mandor 0.198 org
Tukang Kayu 1.080 org
Pekerja 0.900 org

PEMBESIAN / m3 SLOOF 15/25


Mandor 0.427 org
Tukang Besi 2.263 org
Pekerja 2.011 org

PENGECORAN / m3 SLOOF 15/25


Mandor 0.203 org
Tukang Batu 0.675 org
Pekerja 1.350 org
SLOOF 15/20 - 4D10
BEKISTING / m3 SLOOF 15/20
Mandor 0.135 org
Tukang Kayu 0.675 org
Pekerja 0.675 org
PEMBESIAN / m3 SLOOF 15/20
Mandor 0.570 org
Tukang Besi 2.850 org
Pekerja 2.850 org
PENGECORAN / m3 SLOOF 15/20
Mandor 0.255 org
Tukang Batu 0.850 org
Pekerja 1.700 org

RING BALK 15/20 - 4D10


BEKISTING / m3 RING BALK
Mandor 0.283 org
Tukang Kayu 1.133 org
Pekerja 1.700 org
PEMBESIAN / m3 RING BALK
Mandor 0.428 org
Tukang Besi 2.850 org
Pekerja 2.850 org
PENGECORAN / m3 RING BALK
Mandor 0.170 org
Tukang Batu 1.133 org
Pekerja 2.267 org

RING BALK 15/25 - 5D10+2D8


BEKISTING / m3 RING BALK
Mandor 0.270 org
Tukang Kayu 1.350 org
Pekerja 1.350 org
PEMBESIAN / m3 RING BALK
Mandor 0.517 org
Tukang Besi 2.586 org
Pekerja 2.586 org
PENGECORAN / m3 RING BALK
Mandor 0.405 org
Tukang Batu 1.350 org
Pekerja 2.700 org

BALOK LATEI ATAS KUSEN - 2D10


BEKISTING / m3 BALOK LATEI
Mandor 0.420 org
Tukang Kayu 2.100 org
Pekerja 2.100 org
PEMBESIAN / m3 BALOK LATEI
Mandor 0.561 org
Tukang Besi 2.805 org
Pekerja 2.805 org
PENGECORAN / m3 BALOK LATEI
Mandor 0.210 org
Tukang Batu 0.700 org
Pekerja 1.400 org

KOLOM PRAKTIS - 4D8


BEKISTING / m3 KOLOM PRAKTIS
Mandor 0.225 org
Tukang Kayu 1.125 org
Pekerja 1.125 org
PEMBESIAN / m3 KOLOM PRAKTIS
Mandor 0.669 org
Tukang Besi 3.344 org
Pekerja 3.344 org
PENGECORAN / m3 KOLOM PRAKTIS
Mandor 0.270 org
Tukang Batu 0.900 org
Pekerja 1.800 org

KOLOM BETON 15/15 - 4D10


BEKISTING / m3 KOLOM 15/15
Mandor 0.225 org
Tukang Kayu 1.125 org
Pekerja 1.125 org
PEMBESIAN / m3 KOLOM 15/15
Mandor 0.669 org
Tukang Besi 3.344 org
Pekerja 3.344 org
PENGECORAN / m3 KOLOM 15/15
Mandor 0.270 org
Tukang Batu 0.900 org
Pekerja 1.800 org

KOLOM 15/30 - 6D12


BEKISTING / m3 KOLOM 15/30
Mandor 0.230 org
Tukang Kayu 1.533 org

PEMBESIAN / m3 KOLOM 15/30


Mandor 0.620 org
Tukang Besi 3.100 org
Pekerja 3.100 org

PENGECORAN / m3 KOLOM 15/30


Mandor 0.460 org
Tukang Batu 1.533 org
Pekerja 3.067 org
KOLOM 15/20 - 4D12
BEKISTING / m3 KOLOM 15/20
Mandor 0.227 org
Tukang Kayu 2.267 org
PEMBESIAN / m3 KOLOM 15/20
Mandor 0.570 org
Tukang Besi 2.850 org
Pekerja 2.850 org
PENGECORAN / m3 KOLOM 15/20
Mandor 0.408 org
Tukang Batu 1.360 org
Pekerja 2.720 org

KOLOM 15/25 - 6D10


BEKISTING / m3 KOLOM 15/25
Mandor 0.270 org
Tukang Kayu 2.700 org
PEMBESIAN / m3 KOLOM 15/25
Mandor 0.517 org
Tukang Besi 2.586 org
Pekerja 2.586 org
PENGECORAN / m3 KOLOM 15/25
Mandor 0.405 org
Tukang Batu 1.350 org
Pekerja 2.700 org

KOLOM 15/25 - 4D10+2D8


BEKISTING / m3 KOLOM 15/25
Mandor 0.270 org
Tukang Kayu 2.700 org
PEMBESIAN / m3 KOLOM 15/25
Mandor 0.517 org
Tukang Besi 2.586 org
Pekerja 2.586 org
PENGECORAN / m3 KOLOM 15/25
Mandor 0.405 org
Tukang Batu 1.350 org
Pekerja 2.700 org

BALOK 15/35 -5D12+2D8


BEKISTING / m3 BALOK 15/35
Mandor 0.267 org
Tukang Kayu 2.667 org
PEMBESIAN / m3 BALOK 15/35
Mandor 0.418 org
Tukang Besi 2.250 org
Pekerja 1.929 org
PENGECORAN / m3 BALOK 15/35
Mandor 0.600 org
Tukang Batu 2.000 org
Pekerja 4.000 org

BALOK 15/30 - 5D12+2D10


BEKISTING / m3 BALOK 15/30
Mandor 0.307 org
Tukang Kayu 3.067 org
PEMBESIAN / m3 BALOK 15/30
Mandor 0.480 org
Tukang Besi 2.583 org
Pekerja 2.214 org
PENGECORAN / m3 BALOK 15/30
Mandor 0.471 org
Tukang Batu 1.643 org
Pekerja 3.067 org

BALOK BORDES 15/30 - 6D12


BEKISTING / m3 BALOK 15/30
Mandor 0.307 org
Tukang Kayu 3.067 org
PEMBESIAN / m3 BALOK 15/30
Mandor 0.443 org
Tukang Besi 2.214 org
Pekerja 2.214 org
PENGECORAN / m3 BALOK 15/30
Mandor 0.471 org
Tukang Batu 1.643 org
Pekerja 3.067 org

BALOK 15/25 -5D12


BEKISTING / m3 BALOK 15/25
Mandor 0.270 org
Tukang Kayu 2.700 org
PEMBESIAN / m3 BALOK 15/25
Mandor 0.453 org
Tukang Besi 2.263 org
Pekerja 2.263 org
PENGECORAN / m3 BALOK 15/25
Mandor 0.476 org
Tukang Batu 1.588 org
Pekerja 3.176 org

BALOK 15/25 - 4D12


BEKISTING / m3 BALOK 15/25
Mandor 0.270 org
Tukang Kayu 2.700 org
PEMBESIAN / m3 BALOK 15/25
Mandor 0.453 org
Tukang Besi 2.263 org
Pekerja 2.263 org
PENGECORAN / m3 BALOK 15/25
Mandor 0.476 org
Tukang Batu 1.588 org
Pekerja 3.176 org

BALOK 15/20 - 4D10


BEKISTING / m3 BALOK 15/20
Mandor 0.170 org
Tukang Kayu 1.700 org
PEMBESIAN / m3 BALOK 15/20
Mandor 0.570 org
Tukang Besi 2.850 org
Pekerja 2.850 org
PENGECORAN / m3 BALOK 15/20
Mandor 0.363 org
Tukang Batu 1.360 org
Pekerja 2.267 org

PLAT LANTAI T=12 cm / m3


BEKISTING / m3 PLAT LANTAI
Mandor 0.417 org
Tukang Kayu 4.167 org
PEMBESIAN / m3 PLAT LANTAI
Mandor 0.820 org
Tukang Besi 4.100 org
Pekerja 4.100 org
PENGECORAN / m3 PLAT LANTAI
Mandor 0.417 org
Tukang Batu 2.083 org
Pekerja 2.083 org

PLAT LEUFEL T=10 cm / m3


BEKISTING / m3 PLAT LEUFEL
Mandor 0.333 org
Tukang Kayu 3.333 org
PEMBESIAN / m3 PLAT LEUFEL
Mandor 0.810 org
Tukang Besi 3.600 org
Pekerja 4.500 org
PENGECORAN / m3 PLAT LEUFEL
Mandor 0.400 org
Tukang Batu 2.000 org
Pekerja 2.000 org

MEJA DAPUR T= 7 cm / m3
BEKISTING / m3 MEJA DAPUR
Mandor 0.286 org
Tukang Kayu 2.857 org
PEMBESIAN / m3 MEJA DAPUR
Mandor 0.492 org
Tukang Besi 2.500 org
Pekerja 2.424 org
PENGECORAN / m3 MEJA DAPUR
Mandor 0.190 org
Tukang Batu 0.952 org
Pekerja 0.952 org

RABAT BETON CAMP. 1:3:5 / M3


Mandor 0.286 org
Tukang Batu 1.429 org
Pekerja 1.429 org

PEKERJAAN KUSEN DAN DAUN PINTU JENDELA

KUSEN PINTU DAN JENDELA / m'


Mandor 0.005 org
Tukang Kayu 0.050 org

DAUN JENDELA / BH
Mandor 0.033 org
Tukang Kayu 0.333 org

DAUN PINTU / BH
Mandor 0.050 org
Tukang Kayu 0.500 org

ROSTER / BH
Mandor 0.005 org
Tukang Batu 0.050 org

PEKERJAAN ACCESORIS PINTU JENDELA

SLOT DAN HANDLE PINTU / BH


Mandor 0.050 org
Tukang Kayu 1.000 org

ENGSEL PINTU DAN JENDELA / BH


Mandor 0.005 org
Tukang Kayu 0.100 org

GRENDEL PINTU DAN JENDELA / BH


Mandor 0.003 org
Tukang Kayu 0.050 org

GRENDEL TANAM PINTU DOUBLE / SET


Mandor 0.033 org
Tukang Kayu 0.667 org

HAK ANGIN
Mandor 0.003 org
Tukang Kayu 0.050 org

PEKERJAAN RANGKA ATAP

PEKERJAAN GORDING, NOK, MURPLAT, KUDA2 / M3


Mandor 1.167 org
Tukang Kayu 8.750 org
Pekerja 2.917 org

PEKERJAAN USUK DAN RENG / M2


Mandor 0.020 org
Tukang Kayu 0.100 org
Pekerja 0.100 org

PEKERJAAN TALANG JURAI / M1


Mandor 0.010 org
Tukang Kayu 0.050 org
Pekerja 0.050 org

PEKERJAAN PAPAN REUTER / M1


Mandor 0.005 org
Tukang Kayu 0.025 org
Pekerja 0.025 org

PEKERJAAN PAPAN LISPLANK / M1


Mandor 0.019 org
Tukang Kayu 0.125 org
Pekerja 0.063 org

PEKERJAAN PENUTUP ATAP

PEKERJAAN GENTENG BETON


Mandor 0.010 org
Tukang Kayu 0.050 org
Pekerja 0.050 org

PEKERJAAN GENTENG GLAZUR


Mandor 0.013 org
Tukang Kayu 0.067 org
Pekerja 0.067 org

PEKERJAAN KERPUS GENTENG BETON


Mandor 0.034 org
Tukang Batu 0.200 org
Pekerja 0.143 org

PEKERJAAN KERPUS GENTENG GLAZUR


Mandor 0.040 org
Tukang Batu 0.200 org
Pekerja 0.200 org

PEKERJAAN PLAFOND

PEKERJAAN RANGKA PLAFOND / M2


Mandor 0.020 org
Tukang Kayu 0.200 org

PEKERJAAN PLAFOND GYPSUMBOARD / M2


Mandor 0.010 org
Tukang Gypsum 0.100 org

PEKERJAAN PLAFOND ETERNIT / M2


Mandor 0.010 org
Tukang Gypsum 0.100 org

PEKERJAAN LIS PLAFOND GYPSUM / m'


Mandor 0.007 org
Tukang Gypsum 0.067 org

PEKERJAAN KERAMIK

KERAMIK LANTAI - 01 / M2
Mandor 0.022 org
Tukang Batu 0.111 org
Pekerja 0.111 org

KERAMIK LANTAI - 02 / M2
Mandor 0.026 org
Tukang Batu 0.128 org
Pekerja 0.128 org

PLINT KERAMIK LANTAI - 01 / M'


Mandor 0.017 org
Tukang Batu 0.083 org
Pekerja 0.083 org

PLINT KERAMIK LANTAI - 02 / M'


Mandor 0.018 org
Tukang Batu 0.092 org
Pekerja 0.092 org

KERAMIK LANTAI KM 20/20 - LANTAI 01 / M2


Mandor 0.029 org
Tukang Batu 0.167 org
Pekerja 0.125 org

KERAMIK LANTAI KM 20/20 - LANTAI 02 / M2


Mandor 0.032 org
Tukang Batu 0.183 org
Pekerja 0.138 org

KERAMIK DINDING 20/20 - LANTAI 01 / M2


Mandor 0.033 org
Tukang Batu 0.167 org
Pekerja 0.167 org

KERAMIK DINDING 20/20 - LANTAI 02 / M2


Mandor 0.037 org
Tukang Batu 0.183 org
Pekerja 0.183 org

KERAMIK DINDING 20/25 - LANTAI 01 / M2


Mandor 0.032 org
Tukang Batu 0.167 org
Pekerja 0.154 org

KERAMIK DINDING 20/25 - LANTAI 02 / M2


Mandor 0.035 org
Tukang Batu 0.183 org
Pekerja 0.169 org

LIS BORDER 7 x 20 / M1
Mandor 0.011 org
Tukang Batu 0.111 org

KERAMIK MEJA DAPUR 20/20 / M2


Mandor 0.050 org
Tukang Batu 0.250 org
Pekerja 0.250 org

PEKERJAAN CAT

CAT DINDING LANTAI - 01


Mandor 0.013 org
Tukang Cat 0.125 org

CAT DINDING LANTAI - 02


Mandor 0.017 org
Tukang Cat 0.167 org

CAT PLAFOND
Mandor 0.010 org
Tukang Cat 0.100 org

PEKERJAAN INSTALASI AIR

PEMASANGAN INSTALASI AIR BERSIH / m'


Mandor 0.013 org
Tukang Batu 0.067 org
Pekerja 0.067 org

PEMASANGAN INSTALASI AIR KOTOR / m'


Mandor 0.02 org
Tukang Batu 0.10 org
Pekerja 0.10 org

PEMASANGAN INSTALASI POMPA DAN TOWER AIR


Mandor 0.300 org
Tukang Batu 2.000 org
Pekerja 1.000 org

SEPTIC TANK / unit


Tukang Sumur 2.00 org
Tukang Batu 0.40 org
Pekerja 1.50 org

PERESAPAN / unit
Tukang Sumur 1.500 org
Tukang Batu 0.500 org
Pekerja 1.600 org

SUMUR AIR BERSIH / unit


Tukang Sumur 10.00 org
Tukang Batu 0.10 org
Pekerja 9.00 org

PEKERJAAN SANITAIR

DUDUKAN CLOSED JONGKOK / unit


Mandor 0.20 org
Tukang Batu 1.00 org
Pekerja 1.00 org

BAK MANDI KERAMIK


Mandor 0.25 org
Tukang Batu 2.00 org
Pekerja 0.50 org

SETTING DAN PEMASANGAN INSTALASI MONOBLOK / unit


Mandor 0.75 org
Tukang Batu 1.00 org

DUDUKAN BATHUP / unit


Mandor 0.40 org
Tukang Batu 2.00 org
Pekerja 2.00 org
SETTING DAN PEMASANGAN INSTALASI BATHUP / unit
Mandor 1.00 org
Tukang Batu 2.00 org
Pekerja 2.00 org

SETTING SHOWER / unit


Mandor 0.05 org
Tukang Batu 0.50 org

SETTING DAN PEMASANGAN INSTALASI WASTAFEL / unit


Mandor 0.10 org
Tukang Batu 1.00 org

PEMASANGAN KRAN AIR


Mandor 0.01 org
Tukang Batu 0.10 org

SETTING KITCHEN ZINK DAN FINISHING MEJA DAPUR


Mandor 0.10 org
Tukang Batu 1.00 org

PEKERJAAN INSTALASI LISTRIK

INSTALASI TITIK LAMPU / ttk


Mandor 0.073 org
Tukang Listrik 0.400 org
Pekerja 0.333 org

INSTALASI STOP KONTAK / ttk


Mandor 0.073 org
Tukang Listrik 0.400 org
Pekerja 0.333 org

INSTALASI METERAN DAN MCB / ttk


Mandor 0.100 org
Tukang Listrik 0.500 org
Pekerja 0.500 org

PEKERJAAN LAIN-LAIN

SETTING TANGGA PUTAR / set


Mandor 0.500 org
Tukang Besi 2.000 org
Pekerja 3.000 org

SETTING RAILING TANGGA / m'


Mandor 0.300 org
Tukang Besi 1.000 org
Pekerja 2.000 org

SETTING LANSEKAP / m2
Tukang Taman 0.100 org
Pekerja 0.100 org

You might also like