Professional Documents
Culture Documents
System Requirements
Generation ⇒ Module 11
Load ⇒ Module 12
Transformer ⇒ Module 9
Busbar ⇒ Module 10
Source: ABB
External insulation
Line insulators
Equipment bushing
Internal insulation
…
Single-phase-to-ground Phase-to-phase 15 4
Phase-to-phase phase-phase-to-ground 10 2
Phase-to-phase-to-ground Three-phase-to-ground 5 1
Source: Cigre
Majority of faults are unbalanced
Causes
Broken conductor and joint failure of cables and overhead lines
Impact
Danger to the personnel
Danger (shock or burn) to the public from direct contact with the faulted equipment
Damages to adjacent plants (loss of generators) and loads (motors stall) due to voltage dips
Dislodging of windings and bus-bars due to high magnetic forces caused by short-circuit currents
Protection of people
Instrument transformers
CTs &
Protective relays VTs
Fault current interrupters
Circuit
Breakers
Battery
VT CT CB
CCVT
Shielding wires
Protective gaps
Lightning surges
Switching surges
Falling raindrops bring the negative charge to the bottom of the cloud and upward air
drafts carry the positively charged air to the top of the cloud.
Negative charges at the bottom of the cloud induce a positively charged region or
shadow on the earth directly below the cloud.
Lightning current typically rises to a peak value within 1 to 10𝜇𝑠, and then
diminishes to ½ the peak within 20 to 100 𝜇𝑠.
Causes
Energization
Opening and closing of circuit breakers for fault clearing and restoration
Source: Wikipedia
Module 1: Protection System Requirements PAGE 24
Termination with Cables
Source: Wikipedia
3-conductor
Potheads
Characteristics
Examples
SiC arrester
Insulators
Arresters
Lightning
arresters
If a number of supposedly identical tests are made on a number of supposedly identical insulation
samples, the breakdown voltage will vary from test to test.
Insulation coordination
Definition: Process of correlating electric equipment insulation strength with the protective
device characteristics so that the equipment is protected against overvoltages.
Objective: Design the insulation of a power system with all its components to minimize
damage and interruption of service in an economic fashion.
Volt-time curve: Joining the time of the breakdown and the peak of the voltage
supported during the test.
Critical flashover voltage (CFO): The voltage at which flashover occur 50% of
the time.
Volt-time curve of the protective device must be well below the volt-time curve
of the equipment to be protected.
Protective relays
Circuit breakers
Instrument transformers
Commissioning
The reliability of the protection system has priority over the protection cost.
The high capital cost of power system components in the transmission networks
justify the higher protection costs.
Duplicate protection is used to improve reliability.
Single phase tripping and reclosing may be required to restore system operation
in a timely manner.
Reliability
Selectivity
High Speed
Sensitivity
Availability
Simplicity
Flexibility
Redundancy
Dependability:
Security:
Defined as “ the degree of certainty that a relay will not operate incorrectly.
Power swings
Security
Example
Resulted in operation of R1
Defined as “the process of applying and setting the protective relays that
overreach other relays such that they operate as fast as possible within their
primary zone but have delayed operation in their backup zone”.
Selectivity can be achieved by
Time grading
Impedance grading
Unit protection
Transformers
Buses
Open protection zone: Zone of protection is not clearly defined by the CTs and
limit of the zone varies with the fault current.
Closed protection zone: Zone of protection is clearly defined.
Example:
Fault F2 lies in the closed protection zones of the transmission line and the bus ⇒ B1, B2, B3
and B4 trip.
Fault F3 lies in two open protection zones ⇒ B6 trips and B5 acts as the back up.
Sensitivity
Protection system capability to operate correctly even in a case of small fault currents and
high fault impedances
Availability
Simplicity
Flexibility
Primary protection system: Main protection system for a given protection zone
Backup
High cost of transducers and CBs in HV and EHV systems ⇒ Relays are duplicated
May use the same or different protection elements as the primary protection
CT
CT
Primary
Relay VT
VT
Circuit DC system,
Trip Coil e.g., battery
Breaker
Duplicate
relay
CT
Primary
Trip Coil
Relay VT
VT
Circuit
Breaker DC system,
e.g., battery
CT
Types
Local
Remote
If the fault current persists for longer than the timer setting, a trip signal is given to all local
and remote breakers that are required to clear the fault.
The timer is de-energized when the fault current through the breaker disappears.
CTs
CB Protective
(Failed) Relay
VTs
Example:
R2 :Duplicate relay (may use the same or different protection elements as R1)
R3: Local backup relay and slower than R1 and R2, provides breaker failure protection for B1.
It will first attempt to trip breaker B1 and then its breaker failure relay will trip breakers B5,
B6, B7, and B8.
Relays R9, R10, and R4 constitute the remote backup protection for R1.
PAGE 51