Professional Documents
Culture Documents
Training Manual-Piping: Piping Study Piperack Piping
Training Manual-Piping: Piping Study Piperack Piping
: 29040-PI-UPS-1011
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 1
CONTENTS
Page
List of illustrations 2
1.0 General 3
5.0 Illustrations 7
Applicable Revision:
Prepared: Checked: Approved:
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 2
LIST OF ILLUSTRATIONS
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 3
1.0 GENERAL
The piperack general arrangement is finalised during the development of overall plot plan. The
exact width of the piperack, numbers of levels and elevations, the access and maintenance
platforms are finalised during piperack piping study.
Normally, the piperack piping study, with its structural and platform requirements is the first priority
item for detail engineering of a process unit.
The piperack may be an integral part of a process unit located in the middle of the unit or it may be
an arterial part connecting several services of other process unit.
The following data and drawings are required to be studied before starting the detailed design of
piperack piping study:
Unit Plot Plan / Overall Plot Plan
Piping and Instrumentation diagrams
Plant layout specification
Client specification
Material of construction
Fireproofing requirements
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 4
2.4 After analysing all the requirements and arrangements, the dimensions are to be rounded off to the
next whole number. Based on the economics, the width and the number levels e.g. two tier of 30
ft. wide or three tier of 20 ft. wide rack will be decided.
The gap between the tiers shall be decided on the basis of the largest diameter pipeline and its
branching. The difference between the bottom line of pipe in the rack and the bottom of a branch
as it leaves the rack shall be decided carefully, to avoid any interference due to support, insulation,
size of branch etc. All branch lines from the main lines on piperack shall be taken aesthetically on
a common top of steel (TOS).
With the above considerations, the conceptual arrangement of piperack are to be finalised.
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 5
4.4 Pipelines in the piperack are classified as process lines, relief-line headers and utility headers.
Process lines :
Process lines are those
(a) which interconnect nozzles on process equipment more than 20ft. apart (closer process
equipment can be directly interconnected with pipelines)
(b) Product lines which run from vessels, exchangers, or more often from pumps to the unit limits
to storage or header arrangement outside the plant.
(c) Crude or other charge lines which enter the unit and usually run in the yard before connecting
to exchangers, furnaces or other process equipment e.g. holding drums or booster pumps.
Relief-line headers
Individual relief lines, blow down lines and flare lines should be self draining from all relief valve
outlets to knock-out drum, flare stack or to a point at the plant limit. A pocketed relief line system
is more expensive, because usually an extra condensate pot is required with instruments, valves
and pumps. To eleminate pockets some relief line headers must be placed at higher elevation
above the main yard usually on a tee support on the extended piperack column. However, on
some noncondensing gas systems self drainage is not so essential. Relief lines can be individual,
some with large diameters and occasionally high temperatures.
Utility lines
Utility lines in the piperack can be put in two groups :
(a) Utility headers serving equipment in the whole plant. Such lines are : low and high pressure
steam lines, steam condensate, plant air and instrument air lines. If required, cooling water
supply and return and service water can also be arranged on the piperack.
(b) Utility lines serving individually one or two equipment items or a group of similar equipment
(furnaces, compressors) in the plant. Such lines are : boiler feedwater, smoothering steam,
compressor starting air, various fuel oil lines, lubricating oil, cooling oil, fuel gas, inert gas and
chemical treating lines.
Steam header should drain to the steam separator for more effective condensate collection.
Branch connections to steam headers usually connect to the top to avoid condensate drainage
to equipment.
Instrument lines and Electrical cables
Instrument lines and Electrical cables are often supported in the yard and extra space should be
provided for these facilities. The best instrument line arrangement eleminates almost all elevation
changes between the plant and the control room. This can be easily achieved when instrument
lines are supported outside the piperack column on a suitable elevation.
4.5 Line Location
• Refer sketch No.PRP20. It shows single-level yard piping.
Regardless of service, heavy lines (very large diameter lines, large lines full of liquid) are placed
over or near the piperack columns. Centrally loaded column and reduced bending moment on the
beam will result in a lighter structural design. Next to these lines are placed all process lines and
relief lines. Utility lines are in the centre portion of the yard. A general sequence of uitility lines is
also shown on the sketch PRP-20.
• It is advantageous, from point of view of support, to group hot lines requiring expansion loops.
Refer sketch No.PRP-13, PRP-14. Loops elevated horizontally over the yard is the most common
adopted design, having the hottest and largest diameter line outside.
Line guides, line stops and anchor points are usually required along a hot line somewhere in the
piperack.
TRAINING MANUAL- PIPING DOC No. : 29040-PI-UPS-1011
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 6
Pipe expansion forces, at some of these points, will affect yard support design.
• Those process lines which interconnect equipment on the same side of the yard should be near
the edges of the yard bank. Lines which interconnect equipment located on both sides of the yard
should be closer to the utility lines and can be placed either side of the yard. Position of product
lines is influenced by their routing after leaving the plant limit.
Right(left) turning lines should be on the right(left) hand side of yard.
Utility lines serving individually one or two equipment items should be on the same side of the yard
as the equipment to which they connect.
4.6 Piperack Elevation
Refer sketch No.PRP-2 and PRP-3 for typical cross-section of piperack piping.
Elevation of yard piping is determined by the highest requirement of the following :
a) Headroom over a main road.
b) Headroom for access to equipment under the piperack.
c) Headroom under lines interconnecting the piperack and equipment outside the piperack.
The size of beam supporting the piperack piping should also be taken into account when
considering headroom.
Generally those process lines should be located in the top tier which interconnect two nozzles
elevated higher than the top tier. Process lines with one end lower than the bottom tier elevation
can run either in the top or the bottom rack. If both ends of a process line are lower than the
bottom tier elevation, the line should be located in the bottom tier.
The elevation of a line can also be influenced by valves and instruments in the line. Often a more
convenient access platform can be provided for valves arranged in the top tier of piperack. The
preferred location of lines with orifice runs is near the edge of the piperack with orifice flanges near
the column for more convenient protable ladder access. Refer sketch No.PRP-8.
The sketch No.PRP-2, upper right corner shows platform and walkway arrangements to valves,
relief valves and instruments located in the piperack.
4.7 Piperack Piping Economy
The economy in piperack piping depends primarily on the length of lines arranged on the rack.
Fittings, valves and instrument are relatively few in the piperack compared to pipelength.
Sketch No.PRP-2 shows those critical dimensions (A,B,C,D & E) which will influence piping cost
from piperack piping layout point of view. These dimensions depend on the overall plant layout
and should be carefully considered when the plot is developed.
Dimension 'A' is the total length of the piperack and is governed by the number and size of
equipment, structure and buildings arranged along both sides of the piperack. On an average,
about 10 feet of rack length is required per process equipment (exchanger, drum, tower, unhoused
compressor etc.)
A control room located along the rack will increase the piperack piping cost because all lines must
pass by without really being associated with the relatively long control room.
To shorten piperack length (Dimension 'A'), various methods are applied viz. equipment in pairs,
stacked exchangers, exchangers under elevated drums, drums or exchangers supported on
towers with common platforms, drums supported on exchangers, process equipment located
under the rack etc. These arrangements not only shorten the process interconnecting equipment
directly but also shorten those lines which pass through this area and utility headers serving this
area.
TRAINING MANUAL- PIPING DOC No. : 29040-PI-UPS-1011
Rev. : R0
PIPING STUDY
Uhde India Limited PIPERACK PIPING Page : 7
Dimension 'B' and 'C' should be carefully selected to minimise pipelength between the piperack
and process equipment and pipelength interconnecting equipment on opposite sides of the
piperack. 'C' is usually 6 to 7 feet.
Dimension 'D' and 'E' should be decided based on what is minimum necessary to reduce the
vertical piping lengths.
For economical design of piperack structure, an evaluation by a structural expert should be done.
This expert can determine whether steel or concrete or a combination of the two is the most
desirable choice and what span and spacing will give the most economical arrangement.
5.0 ILLUSTRATIONS
Various illustrations shown on the sketches are general guidelines to develop the piperack
arrangement specific for a plant. Free hand sketches should be made based on the analysis of
the plant and the concept visualised for the piping arrangement with its support. The piping
branching out should be taken at a specific TOS to give a aesthetic cross-sectional view as well as
ease of support.
TRAINING MANUAL - PIPING DOC NO. : 29040-PI-UPS-1011
Rev. : R0
PIPING STUDY
Uhde India Limited PIPE RACK PIPING Page : 1 OF 1
DWG. NO. : PRP1
ROAD ROAD
COMPR. CONTR. RM
HOUSE
ROAD ROAD
A. DEAD END YARD . LINES ENTER B. STRAIGHT THROUGH YARD . LINES CAN
AND LEAVE ONE END OF YARD. ENTER AND LEAVE BOTH ENDS OF YARD.
N
CONTR. RM
COMP.
HO.
CONTR. RM
COMP. HO.
HEATERS
CONTR.
HO.
CONTR. RM
COMP. HO
COMP.
HO.
CONTR.
RM HEATERS
: R0
PLATFORM CATWALK
PLATFORM
INSTR.
LINES
PLAN
ALTERNATE
ROUTE
STEAM
INSTR.
CONTROL
D
LINES
VALVE
C B C
DIMENSIONS A,B,C,D&E DEPEND ON OVERALL PLANT LAYOUT AND INFLUENCE PIPING COST.
: 29040-PI-UPS-1011
: R0
LEAVE SPACE TO
EXTEND STRUCTURAL COLUMN
UTILITY LINES
ON TOP ROW
1500
CANTILEVERED
IF NECESSARY
750
PROCESS LINES
ON BOTTOM ROW
GRADE
: R0
UTILITY LINES
PROCESS LINES
LIFTING BEAM
ELECTRICAL CABLE
TO STARTER
ACCESS WAY
CONTROL VALVE
(TYP)
: R0
1" / 25
STAGGER FLANGES
UNINSULATED
FLANGES
INSULATED
FLANGES
NOTES:
: R0
NO MOVEMENT
MUST CLEAR
AFTER 63 MM
LINE GROWTH
CHECK FOR
POSSIBLE INTER-
FERENCE
LINE GUIDES
*
STAGGER LOCATION
* IF INSUFFICIENT
SPACE BETWEEN LINES
MUST CLEAR
AFTER 63 MM
LINE GROWTH
63 MM MOVEMENT 63 MM MOVEMENT
: 29040-PI-UPS-1011
: R0
ELEVATION 1
SHOE-LINE A
SHOE-LINE B
ELEVATION 2
END VIEW
LINE "B"
LINE "A"
ELEVATION 1
ELEVATION 2
45° ELBOW
SIDE VIEW
: 29040-PI-UPS-1011
: R0
ORIFICE FLANGES
LADDER
: 29040-PI-UPS-1011
: R0
RELIEF HEADER,
PREFERRED
LOCATION NEAR CENTRE OF RACK
TOP LEVEL
: 29040-PI-UPS-1011
: R0
PRESENT FUTURE
: 29040-PI-UPS-1011
: R0
150 150
C
L
COL
PLAN
900
: 29040-PI-UPS-1011
: R0
BATTERY LIMIT
CATWALK
PLAN
COMMON
CENTRELINE
EXTENSION STEM
AS REQUIRED
1200
1000
ELEVATION
: 29040-PI-UPS-1011
: R0
10"-CS at 450°F
LINE BRANCHES
8"-CS at 390°F
6"-CS at 350°F
6"
8"
10"
LOCATE THE LINE REQUIRING THE LARGEST LOOP ON THE OUTSIDE
: R0
PUMPS
PLAN
ANCHOR STRUCTURE
K-BRACING TO ALLOW
PASSAGE/MOVEMENT
ELEVATION
NOTE: GROUP LINES WITH EXPANSION LOOPS. HOTTEST AND LARGEST LINE OUTSIDE.
: 29040-PI-UPS-1011
: R0
EXPN. LOOP
E
OP
SL STEAM TRAP
DRIP LEG
E
OP
SL
: 29040-PI-UPS-1011
: R0
WRONG
: R0
#3
#4
#5
#2
FLAT TURNS ELEVATION #1
DIFFERENCE
#1
#2
#3
#4
#5
: 29040-PI-UPS-1011
: R0
RACK INTERSECTION
SECONDARY
PIPE RACK
: R0
OPERATOR ACCESS
LIGHTING
PANEL
CONTROL
STATIONS
UTILITY
STATION
ELECTRICAL
PULL BOX
ROTAMETER
EA
AR
ESS
C
AC
S.
OL
CLC
450
-60
NS 0
TIO
STA
CL
: 29040-PI-UPS-1011
: R0
Steam
Instrument Duct
: 29040-PI-UPS-1011
: R0
TOWER
TOWER
C B C
DEPENDING ON
MAX. PIPE DIA
750 TO 1000
DRUM
INSTRUMENT LINES
E
ELEVATION OF
LINES TO ADJACENT
EQUIPMENT
EXCHANGER
D
CONTROL
VALVE
PUMP SUCTION ACCESS TO ORIFICE IN LINES WITH BOTH ENDS LOWER
PUMPS VERTICAL LINE THAN BOTTOM YARD BANK
ARE LOCATED ON THE LOWER LEVEL