Professional Documents
Culture Documents
On
2020 – 2021
BRILLIANT INSTITUTE OF ENGINEERING & TECHNOLOGY
ABDULLAPUR (V), HAYATHNAGAR (M), RANGA REDDY (D)
CERTIFICATE
This is to certify that the dissertation entitled “DETAILED ESTIMATION & COSTING OF G+5
BUILDING”, being submitted by MAHANKALI ABHINAY -17QA1A0140, MUNUKUNTLA
NETHAJI -17QA1A0153, T RAJAN KUMAR -17QA1A0138, CHITLAPALLY
LAXMIKANTH -16QA1A0121 in partial fulfillment of the requirements for the award of degree of
Bachelor of Technology in Civil Engineering, , in partial fulfillment of the requirements for the
award of Bachelor Of Technology Degree in Civil Engineering at JNTU Hyderabad is an authentic
work carried out by them under my personal supervision and guidance. To the best of my knowledge
the matter embodied in this project review report has not been submitted in any college/institute for
awarding degree or diploma.
DECLARATION
I hereby declare that the Report of the Project Work entitled “DETAILED ESTIMATION &
COSTING OF G+5 BUILDING” which is being submitted to the Brilliant Institute of
Engineering & Technology, in partial fulfillment of the requirements for the award of the
Degree of Bachelor of Technology in Civil Engineering Department of Civil Engineering, is a
bonafide work carried out by us. The material contained in this Report has not been submitted
to any University or Institution for the award of any degree.
By:
We have immense pleasure in expressing our thanks and deep sense of gratitude to our
Head of the Department .B S RAKESH KUMAR REDDY (Department of Civil
Engineering, BRIL), for his valuable suggestions and unflinching cooperation
throughout course of the project work.
We also thank all teaching and non- teaching staff of Dept. of Civil Engineering
for their direct or indirect co-operation and encouragement.
Finally we express our sincere gratitude to all the members of faculty and our
friends who contributed their valuable advice and helped to complete the project work
successfully.
By:
ACKNOWLEDGEMENT i
ABSTRACT 1-2
COSTING 3-5
1.1 Historical Data 4
1.2 Literature 5
COSTING
2.1 Definition of Estimation And Costing 9
2.3 Procedure 9
2.4.1 Drawing 10
2.4.2 Specification 10
2.4.3 Rates 10
2.6 Lumpsum 11
3.3 Masonry 17
3.5 Flooring 17
3.6 Roofing 17
3.7 Plastering 17
3.8 Pointing 18
3.11 Painting 18
Estimate
5.2 Data 33
6.2 Location 41
6.9 Weather 44
PROPOSED CONSTRUCTION
INDEX
ABSTRACT
STATEMENT OF PROJECT
SALIENT FEARTURES:
1. Utility of building Residential Building
2. No. of floors Stilt + 5 Upper floors
3. Shape of building Rectangular
4. No. of stair case One
5. Type of construction R.C.C framed structure
6. Thickness of walls Outer walls 230mm and Inner walls 115mm
7. No. of lifts One
8. Geometric details:
Stilt floor 2.5 m for parking
9. Materials:
Concrete grade M20
CHAPTER-1
INTRODUCTION
1.INTRODUCTION
For all engineering works it is required to know before hand the probable cost of
construction known as the estimated cost. If the estimated cost is greater than the money
available, then attempts are made to reduce the cost by reducing the work or by changing
the specifications. In preparing an estimate, the quantities of different items of work are
calculated. One who understands and can read drawing may find out the dimensions-
lengths, breadths, heights, etc. from the drawing without difficulty and may calculate the
quantities. The calculations mainly consists of, length*breadth*height. Student, who is
weak in drawing, will gain in power or understanding of drawing and his knowledge of
drawing will be much improved. In preparing an estimate one has to go into details of
each item, big or small, nothing can be left or missed. Estimating makes one thorough,
superficial work does not do, one has to go deep into details.
Historical Data is used frequently by estimators when compiling cost estimates, with their
attendant advantages and disadvantages. There are some rules to be followed, which are
extremely important:
Always understand the source of the historical data.
Always understand what the historical data represent
Always understand what time period the historical data reflect.
Always understand fully how to update and project the historical data to the present time.
Always understand how to manipulate the data to represent your particular project, since
no
Two projects are the same.
Always be wary of working with historical data that you are not familiar with.
Various sources of historical data are available, such as published price books, cost
information publication services, trade journals, and, most important, cost feedback from actual
projects that the estimators firm has been involved with and therefore most knowledgeable of.
Actual cost feedback is the best information to use if it were recorded and documented
properly. The feedback cycle (see Fig 1.5) is of critical importance. In order for estimating to be
effective, feedback from the job site must occur. Actual costs should be compared with
estimated costs to inform the estimator of his or her performance during the estimating phase.
Unfortunately, the feedback process is not carried out effectively within the industry. To quote
the Business Round Table Report on modern management systems7: “Even within companies, a
feedback of actual costs is not consistently used to review and adjust the basis for estimating
future projects.”
Sound estimates are produced from a combination of experience and recorded cost data
of similar work previously performed. The cost data, if proper feedback procedures have been
adopted, will have been refined over time to reflect accurate costs for performing certain
operations. The estimator can use these data to formulate estimates accurately for future work.
If the data to formulate are incorrectly used or formulated, then mistakes will undoubtedly occur.
Ahuja et al. (1994) state that estimating is the primary function of the construction
industry; the accuracy of cost estimates starting from an early phase of a project through the
tender estimate can affect the success or failure of a construction project. They also state that
many failures of construction projects are caused by inaccurate estimates.
A cost estimate establishes the base line of the project cost at different stages of
development of the project. As Hendrickson et al. (1989) point out, a cost estimate at a given
stage of project development represents a prediction provided by the cost engineer or estimator
on the basis of available data. Gould (2005) defined estimate as an appraisal, an opinion, or an
approximation as to the cost of a project prior to its actual construction. According to Jelen et al.
(1983), estimating is the heart of the cost engineer’s work and consequently it has received
appropriate attention over the years.
Holm et al. (2005) lists several reasons for making estimate, including:
o Feasibility studies
o Appropriation of funds
A number of cost prediction models have been developed. Bell (1987) developed multiple
linear regression models for preliminary cost estimating to be used by Alabama Highway
Department (AHD) for long range cost forecasting. The total project cost per mile is the function
of a list of probable predictors comprising line items, such as quantities of work items per mile.
Mahamid et al. (2010) developed multiple linear regression models for preliminary cost
estimating of road construction activities as a function of project’s physical characteristics such
as terrain conditions, ground conditions and soil drill ability.
Hegazy et al., (1998) used a neural network approach to manage construction cost data and
develop a parametric cost estimating model for highway projects. They introduced two
alternative techniques to train network’s weights: simplex optimization (Excel’s inherent solver
function), and GAs (genetic algorithms).
Three cost prediction models were developed by Christian and Newton (1998) in order to
determine an accurate cost for road maintenance. These models were developed in the province
of New Brunswick based on historical data during the period 1965–1994. Based on the models
and the management review, it was concluded that maintenance funding needed to be increased
by 25%.
Lowe et al. (2006) developed linear regression models in order to predict the construction
cost of buildings, based on 286 sets of data collected in the United Kingdom. They identified 41
potential independent variables, and, through the regression process, showed five significant
influencing variables such as gross internal floor area (GIFA), function, duration, mechanical
installations, and piling.
Han et al (2008) investigated the actual budgeting process in highway construction
projects, under the research collaboration of the Korean Ministry of Construction and
Transportation. They then developed two-tiered cost estimation models of highway construction
projects, considering the target goals for forecasting, allowable accuracy, and available
information at each phase of a project budgeting and initiation.
Recent work reveals that there are still many problems in cost estimation at the conceptual
stage of a project cycle. The World Bank had developed an international database for road
construction cost in developing countries; the data was yielded in form of ROad Costs
Knowledge System (ROCKS). It was designed to develop an international knowledge system of
road work costs to obtain average and range unit costs based on historical data that could
ultimately improve the reliability of new cost estimates. In that study, data from 65 developing
countries were used to make comparisons between estimated costs at appraisal and actual cost at
completion. Among these projects 62% were overestimated, and the rest underestimated
(ROCKS, 2002).
CHAPTER-2
In case the funds available are less than the estimated cost the work is done in part
or by reducing it or specifications are altered, the following requirement are
necessary for preparing an estimate.
1. Estimate give an idea of the cost of the work and hence its feasibility can be
determined i.e. whether the project could be taken up with in the funds
available or not.
2. Estimate gives an idea of time required for the completion of the work.
3. Estimate is required to invite the tenders and Quotations and to arrange contract.
4. Estimate is also required to control the expenditure during the execution of work.
5. Estimate decides whether the proposed plan matches the funds available or not.
2. Specifications.
3. Rates.
2.4.1 DRAWINGS
If the drawings are not clear and without complete dimensions the
preparation of estimation become very difficult. So, it is very essential
before preparing an estimate.
2.4.2. SPECIFICATIONS
a) General Specifications: This gives the nature, quality, class and work and
materials in general terms to be used in various parts of work. It helps no form a
general idea of building.
b) Detailed Specifications: These gives the detailed description of the varies items
of work laying down the quantities and qualities of materials, their proportions, the
method of preparation workmanship and execution of work.
2.4.3 RATES:
For preparing the estimate the unit rates of each item of work are required.
Most of people think that the estimate of a structure includes cost of land, cost
of materials and labour, but many other direct and indirect costs included and
is shown below.
2.6 LUMPSUM:
In general, certain percentage on the cost of estimation is allotted for the above L.S
.Items Even if sub estimates prepared or at the end of execution of work, the actual
cost should not exceed the L.S. amounts provided in the main estimate.
Pricing reflects probable construction costs obtainable in the project locality on the date of
cost estimate of probable costs. This estimate is a determination of fair market value for the
construction of the project. It is not a prediction of low bid. Pricing assumes competitive bidding
for every portion of the construction work for all subcontractors and general contractors, with a
minimum of four bids for all items of subcontracted work and six to seven general contractor
bids. Experience indicates that a fewer number of bidders may result in higher bids, conversely
an increased number of bidders may result in more competitive bids.
Since the cost estimator has no control over the cost of labor, material, equipment, the
contractor's method of determining prices, or the competitive bidding or market conditions at the
time of bid, the cost estimate of probable construction cost is based on industry practice and the
estimator’s professional experience in the construction industry, and represents the professional
cost estimator’s best judgment. The accuracy clearly is dependent on various external factors, but
it is typically expected to be within 5% of the average bid.
CHAPTER-3
COMPONENTS OF WORK
3. COMPONENTS OF WORK
In case of preparation of detailed estimate, the whole project is divided in to various stages. Each
stage is divided into items of work. A main or principle items of Civil Engg. Works are explained
below.
a) Before excavation of foundations of structure , the site is leveled, after cleaning the site,
such as bushes, trees, grass, etc. Making convenient for marking with lime for actual
excavation.
b) The marking in the lime lines are made on the grounds as per plans in the drawings, and
makes ready for excavation with required width an depth.
c) The trenches for foundations should be excavated to the required width, the sides of
trenches are vertical, and top width and bottom width should be equal.
d) All the inner and outer measurements of trenches are measured accurately. The cross
measurements are tallied equally on both sides.
e) The loose earth on the trenches are removed and rammed and sprinkle the water.
f) The removed earth may be damped to the maximum distance possible to the outer side of
excavation, without causing inconvenient for further construction works.
g) If the soils of loose or collapsible nature, sides are protected by timber shuttering and
shoring.
h) During excavation care is being taken with out causing damage or loss to the pipe lines,
swear lines, telephone lines.
i) After construction items ie. Concreting, R.R. masonry in the foundations and up to plinth
beam level, the gaps in foundations are filled with excavated earth. Balance earth is use for
filling basement, with watering and ramming
R.R.C works are also estimated for complete work inclusive of steel, centering and
shuttering. Theframe works are separately be done for each item of work. EX:lintels with sufficient
bearing in walls, sunshade racks with monolithic connected from lintels or beams, for T.beams
over bed block restingon masonry walls, roof slabs, with suitable vertical and horizontal supports
with out gaps. Over it grass is spread over it clay wil spread and plastered with cement mortar and
cured for 2 or 3 day, and prepare to lay concrete over desired reinforcement is arranged on the
framework. The concrete is prepared with suitable ingredients like 20 cm size HB metal, sand,
cement and water which confirms to I.S.
3.5 FLOORING
Generally flooring in ground floor, basement is filled with sand, watering ramming is done. Over it
the slabs of 4 to 5 cms thick were laid duly cutting edges to the required level and edges of
cuddapah slabs are pointed with cement mortar (1:3) to full depth of cuddapah slabs for suitable
stabilization of cuddaph slabs. The quantity of work is calculated in square meters taking length
and breadth of room.
3.6 ROOFING:
The roofing is generally made with R.R.C. slab of suitable thickness 10 to 12 cms.
With required reinforcement. In some cases roofing is done, with Kurnool Terrace, Madras Terrace
with A.C sheet , mangalore tiles, pot tiles and pan tiles etc. the quantity of work is calculated in sq.
mts. In case of R.R.C slab is calculated in sq. mts, if thickness of slab is specified.
3.7 PLASTERING:
The plastering is done on either side of masonry to protect and improve the site of structure. For
stone masonry out side is pointing is done instead of plastering. The thickness of plastering and the
type of mortar are mentioned in the specification. Normally 12 mm thick plastering is done for
brick masonry and 20 mm thick for stone masonry with the cement mortar proportion of 1:4. The
pointing is done with cement mortar 1:3. Deductions are made for plastering for doors, windows,
ventilators, caboards, etc; one side only, considering vertical cross sections soffits and sells which
are not taken in to account.
3.8 POINTING
Generally pointing is done to external faces of masonry. The proportion of cement mortar adopted
in cement mortar is 1:3. Deductions are made similar to the case of plastering.
3.11 PAINTING:
The item of painting is calculated in sq. mts. For painting and varnishing the doors and windows
dimensions should be taken for outer dimensions of the chowkat. The area is measured flat,
separate measurements is taken for the chowkat, the area is same as the area of wall opening. For
iron grills etc; the area of clear opening inside the chowkat is taken. For both faces of doors and
windows, the single area as measured above is multiplied by the following factors, called
coefficients.
CHAPTER-4
UNITS OF MEASUREMENTS
4.UNITS OF MEASUREMENTS
1.Massive or volumetric items of work such as eart work, concrete for foundations,
R.R.masonry , brick masonry etc. the measurements length, breadth, height/depth shall be taken
to compute the volume or cubical contents.
2. Shallow thin items of work are expressed in areas , in sq.mts , the measurement of length and
breadth or height shall be taken to compute the areas.
Ex: plastering , white washing etc;
4. Same type of work under different conditions and nature shall be measured
separately under separate items.
5. The bill of quantities shall fully describe the materials, proportions, workmanships and
accurately represent the work to be executed.
6. In case of masonry (stone or brick) or structural concrete, the categories shall be
measured separately and the heights shall be described:
a) from foundation to plinth level
b) from plinth level to First floor level
c) from Fist floor to Second floor level and so on.
Department of Civil Engineering Page 20
Detailed estimation & costing of G+5 building
a) Single units work like doors, windows, trusses the etc., are expressed in numbers.
b) Works consists linear measurements involve length like cornice, fencing, hand rail,
bands of specified width etc., are expressed in (RM)
c) Works consists areal surface measurements involve area like plastering, white
washing, partitions of specified thickness etc., are expressed in square meters (m2)
d) Works consists cubical contents which involve volume like earthwork, cement
concrete, Masonry etc are expressed in Cubic metres.
VIII Roofing
1. R.C.C. and R.B. Slab cum per cum
roof (excluding steel)
2. L.C. roof over and inclusive of tiles or brick
or stone slab etc (thickness specified) sqm per sqm
3. Centring and shuttering sqm per sqm
4. A.C.Sheet roofing sqm per sqm
IX Plastering, points &finishing
1. Plastering-Cement or Lime Mortar sqm per sqm
2. Pointing
sqm per sqm
3. White washing, colour
sqm per sqm
washing cement wash (number of
coats specified)
4. Distempering (number of
coats specified) sqm per sqm
5. Painting, varnishing(number of
coats specified) sqm per sqm
X Flooring
1. 25mm cement concrete
over 75mm lime concrete sqm per sqm
floor (including L.C.)
2. 25mm or 40mm C.C. floor sqm per sqm
3. Doors and window sills(C.C. or cement sqm per sqm
mortar plain)
XI Rain water pipe /Plain pipe
1RM per RM
XII Steel wooden trusses
1No per 1No
XIII Glass pannels(supply)
sqm persqm
XIV Fixing of glass panels No per no.
or cleaning
The height of parapet wall should not be less than 0.60 m and more than 1.2 m above the
finished floor level.
Toilet 2.52
DOORS:
A door is a framework of wood, steel, aluminum, glass, low cost materials or a
combination of these materials. The purpose of door is to provide access to the inside of a
building or rooms of a building. Hence, doors should be placed in such a way that free of
movement into and outside the structure is ensured.
WINDOWS:
Windows are provided for lighting and ventilation in the building and for good prospect.
It is desirable that windows be located opposite to each other to give a rapid exchange of
air in the room.
1 2 3 4 5 6 7 8 9 10
1 Less than50 - 7 1.5 1.5 3 3 3 -
2 50-100 - 7 1.5 1.5 3 3 3 -
10 1.5 1.5 3 3 3 0.5
3 100-200 - 10 1.5 1.5 3 3 3 1
4 200-300 Stilt floor 7 2 3 3 4 5 1
10 2 3 3 5 6 1.5
5 300-400 Stilt floor 7 3 4 5 6 7.5 1.5
12 3 4 5 6 7.5 2
6 400-500 Stilt floor 7 3 4 5 6 7.5 2.5
12 3 4 5 6 7.5 2.5
7 500-600 Stilt floor 7 3 4 5 6 7.5 2.5
12 3 4 5 6 7.5 3
15 3 4 5 6 7.5 3.5
8 750-1000 Stilt + one 7 3 4 5 6 7.5 3
Stilt floor meant for parking is excluded from the permissible height in the above table.
Height of the stilt floor shall not be less than 2.5m. In case of parking floors where mechanical
system and lift are provided, height of such parking floors shall not be less than 4.5m.
In this method, the wall along the length of room is considered to be long wall while
the wall perpendicular to long wall is said to be short wall. To get the length of long
wall or short wall, calculate first the centre line lengths of individual walls. Then the
length of long wall, (out to out) may be calculated after adding half breadth at each end
to its centre line length. Thus the length of short wall measured into in and may be
found by deducting half breadth from its centre line length at each end. The length of
long wall usually decreases from earth work to brick work in super structure while the
short wall increases. These lengths are multiplied by breadth and depth to get quantities.
This method is suitable for walls of similar cross sections. Here the total centre
line length is multiplied by breadth and depth of respective item to get the total quantity
at a time. When cross walls or partitions or veranda walls join with main wall, the centre
line length gets reduced by half of breadth for each junction. such junction or joints are
studied carefully while calculating total centre line length. The estimates prepared by
this method are most accurate and quick.
The center line length of room =sum length of long wall and short wall
The C.L.of room =2(C.L.of long wall+C.L.of short wall)
The C.L of long wall =0.5*wall thickness*length*0.5wall thickness.
The C.L of long wall =0.5*wall thickness*width*0.5wall thickness
This method is adopted when external (i.e., all-round the building) wall is of one
thickness and the internal walls having different thicknesses. In such cases, centre line
method is applied to external walls and long wall-short wall method is used to internal
walls. This method suits for different thicknesses walls and different level of
foundations. Because of this reason, all Engineering departments are practicing this
method.
CHAPTER-5
TYPES OF ESTIMATES
5.2 DATA:
The process of working out the cost or rate per unit of each item is called as Data. In
preparation of Data, the rates of materials and labour are obtained from current standard
scheduled of rates and while the quantities of materials and labour required for one unit
of item are taken from Standard Data Book (S.D.B)
ii) Cost of labour: The exact number of labourers required for unit of work and the
multiplied by the wages/ day to get of labour for unit item work.
iii) Cost of equipment (T&P): Some works need special type of equipment, tools and
plant. In such case, an amount of 1 to 2% of estimated cost is provided.
iv) Overhead charges: To meet expenses of office rent, depreciation of equipment salaries
of staff postage, lighting an amount of 4% of estimate cost is allocated.
b) Cubical Contents Method: This method is generally used for multi-storeyed buildings. It is
more accurate that the other two methods viz., plinth area method and unit base method. The
cost of a structure is calculated approximately as the total cubical contents (Volume of
buildings) multiplied by Local Cubic Rate. The volume of building is obtained by Length x
breadth x depth or height. The length and breadth are measured out to out of walls excluding the
plinth off set. The cost of string course, cornice, corbelling etc., is neglected.
The cost of building= volume of buildings x rate/ unit volume.
c) Unit Base Method: According to this method the cost of structure is determined by
multiplying the total number of units with unit rate of each item. In case schools and
colleges, the unit considered to be as 'one student' and in case of hospital, the unit is
'one bed'. the unit rate is calculated by dividing the actual expenditure incurred or cost
of similar building in the nearby locality by the number of units.
Approximate cost of a hostel building for 100 students @ Rs. 10,000/- per student
works out as Rs. 10 lakhs.
Approximate cost of a two roomed quarter may be Rs. 60,000/- a three roomed quarter
may cost Rs.1 lakh.
Approximate cost of a 100 bed hospital @ Rs.50,000/- per bed comes to Rs. 50 lakhs.
Prepare the rough estimate for a proposed commercial complex for a municipal
corporation for the following data.
Plinth Area =
500m2/floor Ht of
each storey = 3.5m
No. of storeys = G+2
Cubical content rate = Rs. 1000/m3
Provided for a following as a percentage of structured cost
a) water supply & Sanitary arrangement -8%
b) Electrification -6%
c) Fluctuation of rates - 5%
d) Contractors profit - 10%
e) Petty supervision & contingencies - 3%
Sol : Cubical content = No. of storeys (Plinth Area x height of each storey)
= 3(500x3.5) = 5250m3
Structural cost = Cubical content x cubical content rate
= 5250 x 1000 = 52.5 Lakhs
other provisions:-
a) Water supply and sanitation = 52.5x8/100 = Rs.4.2 Lakhs
b) Electrification = 52.5 x 6/100 = Rs.3.15 lakhs
c) fluctuation of rates = 52.5 x 5/100 = Rs.2.625
Total = Rs. 9.975 Lakhs
Structural cost = Rs. 52.500 Lakhs
Total = Rs.62.475 Lakhs
d) P.S./& contingencies = 62.475 x 3/100 = Rs.1.874 Lakhs
e) Contractors Profit = 62.475 x 10/100 = Rs.6.247 Lakhs
CHAPTER-6
PROBLEMS IN ESTIMATING
6. PROBLEMS IN ESTIMATION
How does an estimator estimate the cost of a construction project? For those reader’s not
familiar with cost estimating, the process involved is complex. Learning about cost estimating
will help non-cost-estimators understand what is involved and what limitations exist when
reviewing cost data generated by cost estimators.
estimates attempting to hit the target, which is the actual cost. The subjective value chosen by
each estimator was considered to represent the resources required by each firm to complete an
example office-building project. We can see that the estimates are all scattered around the target
of actual cost. Hitting the target is not a common occurrence and is an inbuilt problem of
estimating.
Briefly, let us consider an estimator pricing a brickwork item.
What are the difficulties presented? They are as follows:
1. Choice of work method.
2. Output of crew (given the firm’s unique efficiency).
3. Cost of labor
4. Cost of material and selection of an appropriate wastage allowance.
5. Addition of overheads and profit
Problems 1-5 have been presented simply, but you can begin to imagine their complexity.
An estimator has to posses the skill and expertise to assemble the known facts and rationally
solve the estimating equation. The estimator selects a range of most likely values and, after a
process of fine tuning and “weighing up” of the situation, the estimator modifies his or her initial
crude selection and finally selects a value that he or she considers to be ‘most likely.”
Department of Civil Engineering Page 37
Detailed estimation & costing of G+5 building
The thought process previously described and shown in fig.1.2 and 1.3 applies to our
hypothetical brickwork example, but generally indicates how and estimator arrives at a solution
for each separate item of the cost estimate. A total cost estimate consists of numerous line items
and specific sections relating to various trades and specialists subcontractors. This thought
process will usually be repeated on numerous occasions during the compilation of one single
estimate or bills of quantity.
6.2 Location
Since a construction project’s location affects the final cost, an estimator must understand
what particular locational factors will be encountered and what considerations should be taken
into account when formulating the estimate. Estimators are aware that costs in Boston are
different that costs in Miami, but not everyone is aware that the locational variation within the
Boston area or within the Miami area also influence construction costs. For example, the project
location may be a restricted city center infill site or a remote country site, each having its own
particular difficulties that the contractor must overcome.
4. Weather
5. Design considerations (related to location).
6. Vandalism and site security
Remoteness
A remote construction site, for example, a project site located high in the Blue Ridge
Mountains of Virginia, poses a contracting organization with a difficult set of problems to cope
with.
distance. He also discovered that the bulk materials with low initial cost, such as sand and
gravel, tend to be the most adversely affected by distance and difficult transport conditions.
Ferry crossing or bridges with tolls increase the basic cost of materials.
labor involved in handling material. Since confined sites nearly always pose logistical problems,
the unit prices used by the estimator must account for the increased costs.
6.9 Weather
Since the building process is highly weather dependent, extreme conditions can greatly
affect building costs. These extreme weather conditions include large amount of rain or snow,
occurrences of ice and frost, and high humidity and heat. Their effects on cost include the
following situation. Concrete pours in temperatures below 40 degrees Fahrenheit require special
precaution. With cold weather concreting, the cost of admixtures, insulation the formwork,
removing ice from formwork, and protecting the freshly placed concrete from dropping below
the specified temperatures must be taken in to account by the estimator. Not only does cold
weather affect concrete, but hot weather concreting has its associated problems as well. During
periods when the temperature exceeds 80 degrees Fahrenheit, special precautions are required to
reduce and maintain the concrete below this temperature. For example, ingredients such as the
water may be cooled or chopped ice can be utilized. Another alternative is to use liquid nitrogen
to cool the concrete. Admixtures and low heat cement can be used to control the set and
hardening times of the concrete to achieve the design strength and quality. All these precautions
and procedures increase the cost of pouring, placing, and curing concrete.
Exposed sites may have problems associated with high winds, which affect crane and
hoisting operations, and the contractor’s dust control program. Additional temporary bracing to
partly completed structures may be required to prevent a collapse due to high wind gusts. In
areas where hurricanes occur, the estimator should consider the cost of temporary measures
required to prevent damage to a structure before, during, and after a hurricane. It would be
prudent to allow for the costs involved in bracing, tieing down structures providing sand banks,
garaging equipment, and storing particular materials such as doors and windows off the job site,
unless safe, dry, and secure storage exists on the project.
Labor productivity is also associated with the weather. During poor weather when it is
cold, damp, and windy, the morale of workers exposed to adverse elements, drops, which in turn
results in a decline of productivity. During days when it may be impossible to work, such as
during a torrential rain, the productivity is zero.
CHAPTER-7
RATE ANALYSIS
7.RATE ANALYSIS
Definition: In order to determine the rate of a particular item, the factors affecting the rate
of that item are studied carefully and then finally a rate is decided for that item. This process
of determining the rates of an item is termed as analysis of rates or rate analysis.
The costs of materials are taken as delivered at site inclusive of the transport local taxes and
other charges.
Purpose of Analysis of rates:
1. To work out the actual cost of per unit of the items.
2. To work out the economical use of materials and processes in completing the particulars item.
3. To work out the cost of extra items which are not provided in the contract bond, but are
to be done as per the directions of the department.
4. To revise the schedule of rates due to increase in the cost of material and labour or due
to change in technique.
The labour charges can be obtained from the standard schedule of rates 30% of the skilled labour
provided in the data may be taken as Ist class, remaining 70% as II class. The rates of materials for
Government works are fixed by the superintendent Engineer for his circle every year and approved
by the Board of Chief Engineers. These rates are incorporated in the standard schedule of rates.
Lead statement:
The distance between the source of availability of material and construction site is known as
"Lead " and is expected in Km. The cost of conveyance of material depends on lead. This
statement will give the total cost of materials per unit item. It includes first cost, conveyance
loading, unloading stacking, charges etc. The rate shown in the lead statement are for
metalled road and include loading and staking charges . The environment lead on the
metalled roads are arrived by multiplying by a factor
Overhead costs
Overhead cost includes general office expenses, rents, taxes, supervision and
other costs which are indirect expenses and not productive expenses on the job.
CHAPTER-8
PLAN DRAWINGS
CHAPTER-9
GROUND FLOOR
e) Plinth beams
7 37.00 0.75 1.00 194.25 cft
3 66.38 0.75 1.00 149.36 cft
1 7.00 0.75 1.00 5.25 cft
TOTAL 348.86 cft
f) Roof beams
7 37.00 0.75 1.50 291.38 cft
4 66.38 0.75 1.50 298.71 cft
1 7.00 0.75 1.00 5.25 cft
TOTAL 595.34 cft
g) roof slab 1 37.00 66.38 0.38 933.30 cft
Dedecuct stair case 1 12.38 7.00 0.38 32.93 cft
1 5.00 7.00 0.38 13.30 cft
Total 887.07 cft
4 Back fiiling with gravel and useful earth
upto plinth beam level with compaction
including cost of conveyance
of materials, labour charges etc.,
complete.
Columns pits 5 5.00 5.00 3.00 375.00 cft
13 5.00 5.00 3.00 975.00 cft
3 5.50 5.50 3.00 272.25 cft
1 4.00 4.00 3.00 48.00 cft
Underflooring 6 10.00 23.15 1.00 1389.00 cft
6 10.00 11.65 1.00 699.00 cft
Total 3758.25 cft
5 Supply & Fixing of SS Steel
Staircase railing for stpes including
cost and conveance of all materials
labour charges etc., complete.
FIRST FLOOR
Deductions (-)
Doors
M/D 2 3.50 0.75 7.00 36.75 cft
D 6 3.00 0.38 7.00 47.25 cft
D1 11 2.50 0.38 7.00 72.19 cft
Windows cft
W 1 5.00 0.75 4.00 15.00 cft
W1 4 4.00 0.75 4.00 48.00 cft
W2 2 2.00 0.75 4.00 12.00 cft
KW 2 3.00 0.75 2.50 11.25 cft
V 5 2.50 0.75 1.5 14.06 cft
Total 256.50 cft
Net total 2961.58 cft
Sunshedes
W1 7 5.00 1.50 0.25 13.13 cft
Total 49.69 cft
5 Laying of ceramic Tiles in bathroom
and kitchen walls and bathroom flooring
including cost and conveyance
of
all materials & labour, curing
etc.,
complete.
Toilet (1) wall 1 8 7.00 ---- 7.00 392.00 sft
Toilet (1) wall 2 8 4.50 ---- 7.00 252.00 sft
Toilet (2) wall 1 2 8.00 ---- 7.00 112.00 sft
Toilet (2) wall 2 2 4.00 ---- 7.00 56.00 sft
Toilet (1) Flooring 4 7.00 4.50 ---- 126.00 sft
Toilet (2) Flooring 1 8.00 4.00 ---- 32.00 sft
kitchen wall tiles 2 10.00 ---- 2.00 40.00 sft
Total 1010.00 sft
Deductions (-)
D1 7 2.50 ---- 7.00 122.50 sft
Net total 887.50 sft
Skirting deductions(-)
M/D 2 3.50 0.00 ---- 7.00 Rft
D 6 3.00 3.00 ---- 36.00 Rft
D1 11 2.50 2.50 ---- 55.00 Rft
Total 98.00 Rft
Total 298.72 Rft
8 Supply & fixing of teak wood frames
& teak wood shutters of section 4"x3"
and necessary fittings, including cost of
all materials & labour charges etc.,
complete. 2 3.50 ---- 7.00 49.00 sft
CHAPTER-10
CONCLUSION
STILT FLOOR
7 Compound Wall
8 Excavation 1088.00 6.00 Sft 6,528.00
9 P.C.C (1:4:8) 181.70 55.00 Sft 9,993.28
10 CRS Masonery 952.00 90.00 Sft 85,680.00
11 Brick work 960.00 85.00 Sft 81,600.00
12 Plastring 1484.00 16.00 Sft 23,744.00
13 Gate 90.00 455.00 Sft 40,950.00
TOTAL 14,10,119.98
Grand
SAY
Total 14,10,200.00
Electrification 12% 1,69,224.00
Plumbing 12% 1,69,224.00
17,48,648.00
SAY 17,48,700.00
RUPEES SEVENTEEN LAKHS FOURTY EIGHT THOUSAND AND SEVEN HUNDRED ONLY
FIRST FLOOR
1 R.C.C (1:1.5:3)
Columns upto roof level 123.19 185.00 Cft 22,790.15
2 Roof Beams 595.34 185.00 Cft 1,10,137.90
3 Roof slab 887.07 195.00 Cft 1,72,978.65
4 Brick work 2961.58 90.00 Cft 2,66,542.20
5 Plastering 11965.51 16.00 Sft 1,91,448.16
6 lintels and sunsheds 49.69 160.00 Cft 7,950.40
7 ceramic Tiles 887.50 145.00 Sft 1,28,687.50
8 Italian Marble flooring 1870.20 315.00 Sft 5,89,113.00
9 Marble Skirting 298.72 95.00 Rft 28,378.40
10 teak wood Main doors 49.00 725.00 Sft 35,525.00
11 Teak wood Door Frames 318.50 695.00 Sft 2,21,357.50
12 Teak wood Windows 127.75 858.00 Sft 1,09,609.50
13 Painting (External) 2145.14 12.00 Sft 25,741.68
14 Painting (Internal) 9197.67 12.00 Sft 1,10,372.04
15 RCM Racks 300.00 125.00 Sft 37,500.00
16 RCC Chajjas 60.00 125.00 Sft 7,500.00
17 Kitchen platform 40.00 250.00 Sft 10,000.00
18 SS Railing 97.92 555.00 Sft 54,345.60
19 Steel (hysd bars) 8596.21 55.00 kgs 4,72,791.55
TOTAL 26,02,769.23
Grand
SAY
Total 26,02,800.00
20 Electrification 15% 3,90,420.00
21 Plumbing 15% 3,90,420.00
33,83,640.00
SAY 33,83,700.00
RUPEES THIRTY THREE LAKHS EIGHTY THREE THOUSAND SEVEN HUNDRED ONLY
AS PER PLAN COST WILL BE THE SAME FOR REST OF THE FLOORS
TOTAL 1,90,42,200.00
(RUPEES ONE CRORE NINTY LAKHS FOURTY TWO THOUSAND TWO HUNDERED)
CHAPTER-11
REFERENCES
11.REFERENCES:
1. Standard Schedule of rates and standard data book by public works department.
2. I.S. 1200 (parts I to XXV-1974/method of measurement of building and civil
engineering works- B.I.S.)
3. Estimation ,costing and specification by M.Chakraborthi; Laxmi Publications.
4. National building code.
5. Estimation and costing by B.N.Dutta.UBS publishers,2000
6. Estimation and costing by G.S.Birdie