You are on page 1of 6

TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.

TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 1 of 6

METHOD STATEMENT FOR CONSTRUCTION OF CAST IN-


SITU CONCRETE WATER TANK

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD...............................................................................................................................3
2. PURPOSE...............................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 2 of 6

4. REFERENCES........................................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS..........................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................4
6. RESPONSIBILITIES................................................................................................................................4
6.1. Project Manager.................................................................................................................................4
6.2. Project Engineer.................................................................................................................................5
6.3. QA/QC Engineer / Inspector...............................................................................................................5
6.4. Surveyor.............................................................................................................................................5
6.5. HSE Engineer/Officer.........................................................................................................................5
7. EQUIPMENTS/ TOOLS / MANPOWER..................................................................................................6
7.1. List of tools..........................................................................................................................................6
7.2. List of Manpower................................................................................................................................6
8. PROCEDURE..........................................................................................................................................6
9. HEALTH, SAFETY AND ENVIRONMENT..............................................................................................7
10. ATTACHMENTS......................................................................................................................................7
10.1. Inspection Checklists..........................................................................................................................7
10.2. Inspection Test Plan...........................................................................................................................7
10.3. Risk Assessment................................................................................................................................7
10.4. Technical Data sheet (TDS)...............................................................................................................7
10.5. Material Safety Data Sheet (MSDS)...................................................................................................7

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 3 of 6

Signature field
Revision
Revision
Number
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager

2. PURPOSE
1. The purpose of this Method Statement is to define the procedure for the preparation and construction of Cast in Place
Concrete Works for water tank in accordance with the requirements specified in the relevant specifications, procedures
and drawings, considering safety and quality of the work activities.
3. SCOPE OF WORKS
CONCRETE WORK FOR WATER TANK
4. REFERENCES
1. Drawings
2. Drawings Issued for Construction Dated 15 January 2007 (ORCHID VILLA)
3. Technical Specifications
4. Tender Specs. issued May 2006, Section 3300, 3300.3.10
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 4 of 6

5. Tender Specs issued Dated May 2006, Section 2315.3, page 2315-3; Section 2315.3.12.1,
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
5.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1.Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with Company policies and in accordance
with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the requirements of this
Quality plan.
3. To ensure that all the equipment required to execute the works according to the construction programme are
available, in good condition, and provide any additional equipment that might be required.
4. To co-ordinate with the construction manager, project engineer, safety engineer, Foreman and Surveyor for a safe
and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
6.2.Project Engineer
1. The engineer will carry out his duties in a manner that will be co-ordinated by the project manager on a daily basis,
and will ensure proper distribution of the workforce and equipment at required locations.
2. To be aware of test frequencies related to the formation level.
3. To control disposal of waste excavated material according to the instructions received from the project manager.
4. To co-ordinate with the Safety Officer to maintain safe working and proper housekeeping of the site. To comply
with the safety measures and ensure that all Safety Officer Teams are aware of the same to prevent accident and
loss.
5. To inform the QC Inspector of the areas ready for inspection.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 5 of 6

6.3.QA/QC Engineer / Inspector


1. Ensuring that consultant/client inspection requests are implemented.
2. Compilation of all necessary quality control checklists
3. Assisting Consultants during the Inspections.
4. Coordinating with the third party lab regarding tests and results.
5. The control of work performance by means of checking the work before consultants’ inspection and issuing RFIs &
punch lists as necessary.
6. Completion of documentation to verify the work performed.
7. Controlling all inspection activities on-site in line with ITPs.
8. Ensuring that all test equipment including surveying equipment is calibrated and is suitable for use on-site.
6.4.Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level markings and follow
up with regular checks.
2. Co-ordinate with the project engineer / Foreman and ensure the approved shop drawings/construction drawings will
be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the project manager of
any deviation from the drawings.
6.5.HSE Engineer/Officer
1. To ensure implementation of all safety measures related to the nature of works being carried out, and in
accordance with the Project Safety Plan.
2. To ensure that all the persons involved in the works are aware of their responsibilities, and that they have enough
understanding of the safety procedures.
3. The safety officer in co-ordination with the project manager will ensure that all the implemented safety measures
are effective enough to maintain safe working on the site.
4. To maintain continuous inspections of the site activities, advise and train persons on a daily basis to prevent
accidents and personnel injury.
5. To give special concern to housekeeping, and ensure that the site is maintained clean and tidy.
6. To ensure all the relevant safety sign boards for different works are in place.
7. EQUIPMENTS/ TOOLS / MANPOWER
7.1.List of tools
1. JCB
2. Dump Truck used for disposal of debris
3. Truck Load Mixer (Concrete supplier)
4. Vibrators
5. Concrete Pumps
6. Masonry tools
7.2.List of Manpower
1. Project Manager
2. Project Engineer
3. QA/QC Engineer / Inspector
4. Safety Engineer/Officer
5. Lab Technicians
6. Foremen
7. Equipment Operators
8. Skilled and unskilled labourers
Note: Quantity of manpower and equipment will be submitted on the daily
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for construction of cast in-situ Rev. Date NA
concrete water tank Pages 6 of 6

Progress report.
8. PROCEDURE
1. Surveyor start markings, gridlines, level and lay-out of concrete blinding for water tank location.
2. Excavation works are carried out based on the issued for construction drawings and specs. section 2315.3, page
2315-3.
3. Termite control application based on the manufacturer recommendation and product specification and same
procedure apply on the tie beams and pile cap with approval by the consultant.
4. For Concrete Blinding – same procedure and material on the blinding for Tie Beams.
5. Apply the water proofing as per drawings and the procedure for application of water proofing is based on the
manufacturer recommendation and product specification with approval by the consultant.
6. Provide protection screed as per issued for construction drawings and material approval by the consultant.
7. Surveyor start markings and lay-out of water tank location.
8. Fix the reinforcement in accordance to the drawings issued for construction. Provide concrete covering for the
reinforcement based on the approved drawings. Submit the ITR prior to fix the formworks.
9. Install the water stop as per drawings and approval by the consultant.
10. Check the Plumbing Pipe Sleeves for water tank and other MEP sleeves if any. The contractor should not fix the
formworks without the approval from QA/QC and consultant. Sign-off the ITR by both parties.
11. Clean the area and removed waste materials prior to fix the formworks. Formworks should be complying with
relevant specs and standards. Submit the ITR after the formwork installation prior to pour the concrete.
12. Pouring of concrete on the water tank using concrete pump after the consultant approved the previous activities.
Provide enough vibrators during concreting works.
13. Curing and removal of formworks for concrete water tank as per tender specification section 3300 and apply the
waterproofing as per the previous procedure.
14. Clean and remove all debris prior to start the waterproofing application.
9. HEALTH, SAFETY AND ENVIRONMENT
10. ATTACHMENTS
10.1. Inspection Checklists
1. Concrete Works / Pre – Pour Check list
10.2. Inspection Test Plan
2. Inspection and Test Plan for cast in place concrete works, Part 2
10.3. Risk Assessment
10.4. Technical Data sheet (TDS)
10.5. Material Safety Data Sheet (MSDS)

You might also like