PURPOSE:
To lay down the procedure for the operation and Maintenance of Water Purification system.
SCOPE:
RESPONSIBILITIES:
Section Pharmacist
Machine Operator
PROCEDURE:
Put on the main switch, which is located at the backside of the Elix by this green indicator light indicates
that power supply is ON.
Press continuously OPERATE / STANDBY button located on the front panel of the system.
After the completion of the flush cycle the system produces purified water and is stored in the reservoir.
Once the tank is full the system displays TANK FULL and Elix system stops.
If the water level is decreases in the reservoir, Elix will operate to transfer water to the reservoir.
Before collection of the water from the tap provided in the reservoir make sure that the reservoir tank
contains sufficient water by confirming with the display of Elix (minimum of 20%)
SIGNATURE:
DATE:
THE BEST LABORATORIES,PAK
STANDARD OPERATING PROCEDURE
DOCUMENT STATUS BLOCK
TITLE: Operating and cleaning Reverse
EFFECTIVE DATE: JAN- 2021 REVISION NO: 3
Osmosis System
DOCUMENT NO:
DEPARTMENT QC department Page 2 of 3
TBL/PRD/SOP/SYP/04
Put on the main switch, which is located at the backside of the Milli-Q A10. Green indicator light glows,
indicates that power supply is ON.
To collect the water move the trigger on the dispenser towards the downward direction.
After collection of water from the system, push the trigger back to the upward direction to stop the water.
Frequency: Weekly.
Again take 100 Liter of RO water in filling tank and give a trial run to wash the filling machine nozzles till all the tap
water is used in washing.
Then take 100 liter of RO water in the filling tank and give a trial run to wash the filling machine nozzles till all the
RO water is used in washing.
Again rinse the machine and tank with RO water before use.
Clean compressed air pipe with dry clean lint free duster.
Drench the duster with IPA and clean the control panel of machine including window and display screen.
WRITTEN BY: REVIEWED BY: APPROVED BY:
DESIGNATION: Section Incharge Production Manager Quality Control Manager
SIGNATURE:
DATE:
THE BEST LABORATORIES,PAK
STANDARD OPERATING PROCEDURE
DOCUMENT STATUS BLOCK
TITLE: Operating and cleaning Reverse
EFFECTIVE DATE: JAN- 2021 REVISION NO: 3
Osmosis System
DOCUMENT NO:
DEPARTMENT QC department Page 3 of 3
TBL/PRD/SOP/SYP/04
Complete cleaning is essential to be carried out after each product change or after three consecutive batches of
same products.
After completion of cleaning inform your Section Incharge & QA officer to get Cleaned Tag of Liquid Filling
Machine.
PRECAUTIONS:
SIGNATURE: