Professional Documents
Culture Documents
04 Bitumen Coating
04 Bitumen Coating
Method
task/operation being Task Carried assessment: Ongoing
Statement Action by
Sajimon KK assessed: out by? 15 January 09
by When?
Site
Ref No: Rev – 02 – RA – 2009 - Depa Cross reference to N.B. Residual risk:
SSOW/method Other on site The risk left
statement: (Highlight SSOW/Method statement control measures after all control
one below) Ref No: may be required measures have
Page No: due to weather been put in
YES NO M/S 001 conditions/other place – see
Risk Persons at risk reasons at time risk matrix at
severity of footer:
E C P Oth
(before task/operation:
Activity/ Significant ers
controls Control measures Work must not
Operation hazard
are in required: start until the
place) risks have
been assessed:
04 Flying High Yes Yes Yes Only the competent Project Site Engineer Medium
particle or No and trained personnel. Manager
Bitumen debris Supervisor
Coating To be followed the Construction
COSHH assessment. Manager Foreman