You are on page 1of 28

Concrete Planning

Date : 05 June 2020


Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 8 June 2020 10:00 Block B

Tuesday 2 9 June 2020 10:00 Block B


9 June 2020 13:00 Block A

Wednesday 3 10 June 2020 10:00 Block C


10 June 2020 10:00 Block B

Thursday 4 11 June 2020 09:00 Spa Block

Friday 6 12 June 2020 10:00 Spa Block


8 12 June 2020 11:00 Restaurant and BoH

Saturday

Note :

Please plan for a


tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply only SCREED 4 Slope for RWP

Supply Only Screed 4 Slope for RWP


Supply and Pump Slab 48 Slab and Beam

Supply and Pump Overflow 11.5 Overflow wall and bases


Supply Only Screed 4 Slope for RWP

Supply Only Screed 4 Slope for RWP

Supply Only Screed 4 Slope for RWP


Supply and Pump G30 15 Roof

Please plan for a supply only 4m3 everyday (in the afternoon). Same shall be confirmed via telecom.
Penetron Admixture Slump Required On site Additional Comments
Not Applicable Lab Tech Required

Not Required S2 Class Lab Tech Required


Not required S2 Class Lab Technician required

Required S2 Class Lab Techn Required


Not required S2 Class Lab Techn Required

Not applicable S2 Class Lab Tech Required

Not required S2 Class Lab Tech Required


Not required S2 Class Lab Tech Required

nfirmed via telecom.


Long Pump

Long Pump

WILL be confirmed on the eve


Concrete Planning
Date : 04.10.2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 7 October 2019 13:00 Anxiliary Works

Tuesday 2 8 October 2019 11:00 Pool Wall


3 8 October 2019 13:00 Boundary Wall
4 8 October 2019 14:00 Anxiliary Works

Wednesday 5 9 October 2019 12:00 Block A


6 9 October 2019 12:00 Block B + Boundary Wall
7 9 October 2019 14:00 Anxiliary Works

Thursday 7 17 October 2019 09:00 Pool bar


9 10 October 2019 12:00 Block A
10 10 October 2019 13:00 Spa Treatment

Friday 11 11 October 2019 11:00 Restaurant and BoH


12 11 October 2019 14:00 Anxiliary Works

Saturday 13 12 October 2019 10:00 Restaurant And boh


14 19 October 2019 11:00 To Be confirmed
19 October 2019
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply only G30 8 Columns Beam and Staircase

Supply and Pump G30 7.5 Swimming Pool


Supply And Pump G30 5 Base
Supply Only G30 4

Supply and Pump G30 12 Surface Bed


Supply and Pump G30 6 Columns
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 7 Beam


Supply and Pump G40 18 Bedroom Surface Bed
Supply and Pump G40 7 Beam

Supply and Pump G30 40 Surface Bed - 3rd Bed


Supply only G40 4 To be confirmed by Phone

Supply and Pump G30 30 Surface Bed - 4th part


Supply Only G40 4
Penetron Admixture Slump Required On site Additional Comments
Not Applicable S2 Class Lab Tech Required

Penetron Required S2 Class Lab Tech Required


Not Required S2 Class Lab Tech Required

Not required S2 Class Lab Techn Required


Not required S2 Class Lab Techn Required
Not required S2 Class Lab Techn Required

Not applicable S2 Class Lab Tech Required


Not applicable S2 class Lab Tech Required
Not Applicable S2 class Lab Tech Required

Not required S2 Class Lab Tech Required


Lab Tech Required
Not required

WILL be Confirmed on 11.10.2019


None
None
Full day attendance of Pump

Half Day Attendance of Pump


Concrete Planning
Date : 12.10.2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 14 October 2019 13:00 Anxiliary Works

2 15 October 2019 10:30 Beam


3 15 October 2019 09:00 Boundary Wall

Wednesday 4 16 October 2019 11:00 Restaurant , Gym, BoH


5 16 October 2019 13:00 Block A
6 16 October 2019 14:00 Anxiliary Works

7 17 October 2019 09:00 Pool bar


Thursday 8 17 October 2019 12:00 Block B
9 17 October 2019 12:00 Block B
10 17 October 2019 13:00 Anxiliary Works

Friday 11 18 October 2019 11:00 Block C


12 18 October 2019 14:00 Anxiliary Works

Saturday 13 19 October 2019 10:00 Block Ca Part 2


14 19 October 2019 11:00 To Be confirmed
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply only G30 6 Columns Beam and Staircase

Supply And Pump G30 7.5 Block A


Supply And Pump G30 5 Base

Supply and Pump G30 5 Surface Bed


Supply and Pump G30 7.5 Beam
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 7 Beam


Supply and Pump G40 14 Corridor
Supply and Pump G40 29 Bedroom
Supply Only G30 7 Beam

Supply and Pump G40 12 Beam and slab


Supply only G30 6 To be confirmed by Phone

Supply and Pump G40 12.5


Supply Only G30 4
Penetron Admixture Slump Required On site Additional Comments
Not Applicable S2 Class Lab Tech Required

Not Required S2 Class Lab Tech Required

Not required S2 Class Lab Techn Required


Not required S2 Class Lab Techn Required
Not required S2 Class Lab Techn Required

Not applicable S2 Class Lab Tech Required


Not applicable S2 class Lab Tech Required
Not applicable S2 class Lab Tech Required
Not Applicable S2 class Lab Tech Required

Not required S2 Class Lab Tech Required


Not required S2 Class Lab Tech Required

None WILL be Confirmed on 18.10.2019


None
Full day attendance of Pump

Half Day Attendance of Pump


Concrete Planning
Date : 04.10.2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 7 October 2019 13:00 Anxiliary Works

Tuesday 2 8 October 2019 11:00 Pool Wall


3 8 October 2019 13:00 Boundary Wall
4 8 October 2019 14:00 Anxiliary Works

Wednesday 5 9 October 2019 12:00 Block A


6 9 October 2019 12:00 Block B + Boundary Wall
7 9 October 2019 14:00 Anxiliary Works

Thursday 7 17 October 2019 09:00 Pool bar


9 10 October 2019 12:00 Block A
10 10 October 2019 13:00 Spa Treatment

Friday 11 11 October 2019 11:00 Restaurant and BoH


12 11 October 2019 14:00 Anxiliary Works

Saturday 13 12 October 2019 10:00 Restaurant And boh


14 19 October 2019 11:00 To Be confirmed
19 October 2019
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply only G30 8 Columns Beam and Staircase

Supply and Pump G30 7.5 Swimming Pool


Supply And Pump G30 5 Base
Supply Only G30 4

Supply and Pump G30 12 Surface Bed


Supply and Pump G30 6 Columns
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 7 Beam


Supply and Pump G40 18 Bedroom Surface Bed
Supply and Pump G40 7 Beam

Supply and Pump G30 40 Surface Bed - 3rd Bed


Supply only G40 4 To be confirmed by Phone

Supply and Pump G30 30 Surface Bed - 4th part


Supply Only G40 4
Penetron Admixture Slump Required On site Additional Comments
Not Applicable S2 Class Lab Tech Required

Penetron Required S2 Class Lab Tech Required


Not Required S2 Class Lab Tech Required

Not required S2 Class Lab Techn Required


Not required S2 Class Lab Techn Required
Not required S2 Class Lab Techn Required

Not applicable S2 Class Lab Tech Required


Not applicable S2 class Lab Tech Required
Not Applicable S2 class Lab Tech Required

Not required S2 Class Lab Tech Required


Lab Tech Required
Not required

WILL be Confirmed on 11.10.2019


None
None
Full day attendance of Pump

Half Day Attendance of Pump


Concrete Planning
Date : 21 September 2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 23 September 2019 13:00 Block B
2 23 September 2019 14:00 Anxiliary Works

Tuesday 3 24 September 2019 09:00 Block B


4 24 September 2019 12:00 Spa Gym

Wednesda 5 25 September 2019 10:00 Block B


6 25 September 2019 11:00 Spa Reception
7 25 September 2019 14:00 Anxiliary Works

Thursday 8 26 September 2019 10:00 Block C


9 26 September 2019 13:00 Block A - Beam
10 26 September 2019 14:00 Security Hut

Friday 10 27 September 2019 13:00 Block C


11 27 September 2019 10:00 Restaurant and BoH
12 27 September 2019 14:00 Anxiliary Works

Saturday 13 28 September 2019 10:00 To Be confirmed


14 28 September 2019 11:00 To Be confirmed
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply only G30 12 Beam


Supply only G30 6 To be confirmed by Phone

Supply and Pump G30 14.5 Floor for Corridor


Supply and Pump G30 9 Surface Bed

Supply and Pump G30 30.5 Floor for Bedroom


Supply and Pump G30 5 Surface Bed
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 7.5 Pool Wall


Supply and Pump G30 7.5 Beam
Supply and Pump G30 4.5 Surface Bed

Supply and Pump G30 10 Beam


Supply and Pump G30 50 Surface bed
Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 12


Supply Only G30 4
Penetron Admixture Slump Required On site Additional Comments
Not Applicable S2 Class Lab Tech Required
Not Applicable S2 Class

Not Required S2 Class Lab Tech Required


Not Required S2 Class Lab Tech Required

Not required S2 Class Lab Techn Required


Not required S2 Class Lab Techn Required
Not required S2 Class Lab Techn Required

Penetron Required S3 Class Lab Tech Required


Not applicable S2 class Lab Tech Required
Not applicable S2 class Lab Tech Required

Not required S2 class Lab Tech Required


Not required S2 Class Lab Tech Required
Lab Tech Required
Concrete Planning
Date : 43722
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Monday 1 16 September 2019 14:00 Spa Block + Block A North
2 16 September 2019 14:00 Anxiliary Works

Tuesday 3 17 September 2019 13:00 Block A South


4 17 September 2019 14:00 Anxiliary Works

Wednesda 5 18 September 2019 10:00 Block C2


6 18 September 2019 11:00 Block C2
7 18 September 2019 15:00 Anxiliary Works

Thursday 8 19 September 2019 14:00 Block C1 and Beam


9 19 September 2019 14:00 Anxiliary Works

Friday 10 20 September 2019 10:00 Block C2


11 20 September 2019 11:00 Block A
12 20 September 2019 14:00 Anxiliary Works

Saturday 13 21 September 2019 10:00 To Be confirmed


14 21 September 2019 11:00 To Be confirmed
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply and Pump G30 10 Surface Bed + Column


Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 12 Footing for veranda


Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 6 Pool Wall


Supply and Pump G30 15 Surface Bed
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 11 FRC Columns and Beam


Supply only G30 4 To be confirmed by phone

Supply and Pump G30 6 Pool Wall


Supply and Pump G30 4 FRC Columns
Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 12 To be confirmed by 20/09/2019


Supply Only G30 4 To be confirmed by 20/09/2019
Penetron Admixture Slump Required On site Additional Comments
Not Applicable S2 Class Lab Tech Required

Not Required S3 Class Lab Tech Required

Required S3 Class Lab Techn Required


Not required S2 Class
Not required

Not required S3 Class Lab Tech Required


Not applicable

Required S3 Class
Not required S2 Class
Concrete Planning
Date : 06.09.2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
Mardi 1 10 September 2019 14:00 Pool Bar
2 10 September 2019 13:00 Block A and Block B
3 10 September 2019 14:00 Anxiliary Works

Mercredi 4 11 September 2019 12:00 Block C1


5 11 September 2019 13:00 Block A and Block B
6 11 September 2019 14:00 Block B
7 11 September 2019 14:00 Anxiliary Works

Jeudi 7 12 September 2019 10:00 Block A


8 12 September 2019 12:00 Block C2
9 12 September 2019 13:30 Block B
10 12 September 2019 15:00 Anxiliary Works

Vendredi 11 13 September 2019 12:00 Block C2


12 13 September 2019 13:00 Block A
13 13 September 2019 14:00 Anxiliary Works

Samdi 9 14 September 2019 10:00 To Be confirmed


10 14 September 2019 11:00 To Be confirmed
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted

Supply and Pump G30 18 Footing and Bases


Supply and Pump G30 7.5 Footing and Column + Ground Beam
Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 14 Pool Raft


Supply and Pump G30 15 Columns + Stairs
Supply and Pump G30 4 Beam
Supply only G30 4 To be confirmed by Phone

Supply and Pump G30 12 Surface Bed Corridor


Supply and Pump G30 5 Tie Beam
Supply and Pump G30 4 Columns
Supply Only G30 4 To be confirmed by phone

Supply and Pump G30 6 Wall


Supply and Pump G30 18 Surface Bed Bedroom
Supply only G30 4 To be confirmed by phone

Supply and Pump G30 12 To be confirmed by 13/09/2019


Supply Only G30 4 To be confirmed by 13/09/2019
Penetron Admixture Slump Required On site Additional Comments

S2 Class Lab Tech Required


Not Applicable
S2 Class Lab Tech Required

Required S3 Class Lab Tech Required


Not Required S2 Class Lab Tech Required
Not Required S2 Class

Not Applicable S2 Class Lab Techn Required


Not Applicable S3 Class Lab Techn Required
Not Applicable S2 Class

Required S3 Class Lab Tech Required


Not applicable S2 Class
Not applicable
Concrete Planning
Date : 30.08.2019
Name Ponnen Nadarajen
Company REHM Grinaker Construction Company Ltd
Phone Number 59868400

Planned Casting
S.N Date Location
Starts
1 2 September 2019 13:00
2 2 September 2019 13:00

3 3 September 2019 14:00 Block C2

4 4 September 2019 10:00 Pool Bar


5 4 September 2019 13:00 Block C2
6 4 September 2019 13:30 Anciliary Works

7 5 September 2019 12:00 SPA Treatment 1 and 2


8 5 September 2019 13:00 Anciliary Works

9 6 September 2019 12:00 Gym and Reception


10 6 September 2019 13:00 Block C2
11 6 September 2019 13:30 Ancilliary Works

12 7 September 2019 10:00 Block C2


13 7 September 2019 11:15 Anciliary Works
tion Company Ltd

Method of Casting Concrete Grade Quantity Item to be casted Penetron Admixture

Supply and Pump G30 15


Not Applicable
Supply Only G30 10

Supply and Pump G30 17 Footing Not Applicable

Supply and Pump G30 12 Footing and Base


Supply and Pump G30 6.5 Pool Raft Penetron Admix Required
Supply Only G30 8 Manholes

Supply and Pump G30 15 Surface Bed Not applicable


Supply Only G30 8 Manholes Not applicable

Supply and Pump G30 12 Surface Bed


Supply and Pump G30 8 Walls Penetron Admix Required
Supply only G30 6 Cover Slab

Supply and Pump G30 12 Beam and Columns Not Applicable


Supply only G30 4 Manhole
Slump Required On side Additional Comments

S2 Class Lab Tech Required


S2 Class To be confirmed

S3 Class To Be confirmed on 03/09/2019

S2 Class Lab Techn Required


S3 Class
S2 Class To be confirmed

S2 Class Lab Tech Required


S2 Class To be confirmed

S2 Class Lab Tech Required


S3 Class
S2 Class To be confirmed

S2 Class
S2 Class Will be confirmed on 06/07/2019