SAMIR Recommendations Ref. # 600117373
FINDINGS #11-Contractor Runover Fatality Incident Provided (tick by ü)
Not Provided (tick by X)
PMT Target completion of
A contractor was fatally injured after getting run over by a dump truck at a Action By Required Evidences evidences for LPD
construction site. The victim was resting under the truck when the driver Prime Contractors assessment
moved it to resume work after the end of lunch break without performing a
360-degree walkaround.
CPP_ NGCP SAIPEM TEKFEN TR SAMSUNG NESMA NESIC CAT RTCC AKS AZMEEL
1. Provide PMT focus/audit inspection (using checklist) on Contractor's CSSP in general and work permit
procedure per GI 2.100 par. 5.3.5 & 7.15
Conduct an audit on all contractors CSSP in general and work permit PMT FCC /
30-Mar
LPD Comments:
R1 procedure in particular to comply with Saudi Aramco work permit G.I 2.100 ALL PRIME 2. Work Permit Analysis- Gap Analysis, ensure to align in GI 2.100
paragraph 5.3.5 and 7.15. CONTRACTORS -mandate Contractor to conduct a gap analysis to their Subcontractors and share the reports or evidences. List
down all the Subcontractors.
3. Prime Contractor to provide evidence for the Subcontrators performance assessment.
Conduct a comprehensive review on the work and safety supervision PMT FCC / 1. Daily basis of site monitoring and safety coverage by the Prime Contractors. Provide evidence of site safety
30-Mar
supervision monitoring, ensuring compliance to the safety to manpower ratio of each work location. (PMT &
R2 adequacy considering the nature of the project and geographic area ALL PRIME Contractors)
coverage. CONTRACTORS 2. Review the qualification of Supervisor at the site.
Note: Prime Contractors must conduct 1 & 2 to their Subcontractors
Perform a documented assessment of the escalation process for identified PMT FCC /
30-Mar
1. Provide PMT Site inspections or audits and its escallation process (i.e. thru email correspondence or official
R3 corrective action, and introduce timely and effective measures to address ALL PRIME letters) to address to the Contractors for a timely corrective actions.
the issues. CONTRACTORS 2. Prime Contractors must also conduct to their Subcontractors.
1. Provide PMT focus/audits (using checklist) on the Contractor's training materials to ensure the language
challenges are addressed and the visual illustrations are clear and adequate.
2. Life Saving Rules multi-languages to distributed to all Subcontractors.
Perform reviews on the contractors training materials to ensure the PMT FCC /
30-Mar
Note: Prioritize the training materials as minimum
R4 language challenges are addressed and the visual illustrations are clear and ALL PRIME 1. MMI
adequate. CONTRACTORS 2. Heat Stress
3. Journey Management
4. Safety Inductions & refresher trainings
-make sure the visual aid are present.
1. Provide PMT focus/audits (using CSAR checklist) on the Contractor's availability and adequacy of the rest
30-Mar
Evaluate availability and adequacy of the rest areas for compliance with the areas for compliance with the requirements of CSAR paragraph 11.4. Heat Stress must be integrated.
R5 requirements of CSAR paragraph 11.4. PMT FCC 2. Finding reports completed and corrective actions taken by Contractor. More focus in the pipe line and road
construction.
1. Provide a training needs analysis implementation specific for the Contractor Supervisors that focuses on JOB
Design and deploy a training program targeting contractor supervisors that PMT FCC / SPECIFIC, Hazard identification, and requirements. Training materials to provided and must be reviewed by
30-Mar
PMT.
R6 focuses on Pre-job Briefing, Hazard identification, and requirements when ALL PRIME 2. LPD to attend the part of the training. PMT to conduct Prime Contractors and Prime Contractors to conduct to
leaving the job site. CONTRACTORS Subcontractors.
3. Deliverabls are the following: communication and evaluations:
PMT FCC /
30-Mar
Review all Gas Compression Project contract packages for CSSP approval by 1. Provide Contractor CSSP (must be reviewed by LPD)
R7 LPD. ALL PRIME 2. Provide the feedback of the comments by LPD by the Contractors.
CONTRACTORS Note: RTCC & Azmeel remaining.
30-Mar
Review contractor ERP to ensure including scenario for incident out of ALL PRIME 1. Provide the approved Contractor ERP. Ensure to include scenario for incident out of normal working hours.
R9 normal working hours. CONTRACTORS (during weekends, extended hours, or night shift if any), must address in the pre-incident plans
1. Provide evidences of Contractor Campaign for Driver/Operator Awareness regarding 360-degree check.(i.e.
Campaign- MMI, Safe Location-LPD 8 Life saving Rules)
R10 Design
30-Mar
and conduct a campaign to increase the awareness of drivers ALL PRIME Note: Campaign for 1 month.
regarding 360-degree check. CONTRACTORS Inlcude campaign materials…
1. Worker not to sleep underneath the equipment
2. Ensure all preacautions are inlcuded in the training materials
Conduct documented assessment to ensure contractor employees in general 1. Provide assessment records for the drivers and equipment operators ensuring job qualification requirements
30-Mar
ALL PRIME are met. Prime and Subcontractors.
R11 are meeting the job qualification requirements with the focus on drivers and CONTRACTORS 2. Pre-mobilization inspection program for all equipment and vehicle including rentals. Provide evidence.
equipment operators. 3. Equipment verification prior to issue PTW.
% Completion
R1 100%
R2 100% % Data Gathering Completio
R3 100%
R4 100% 100% 100% 100% 100% 100% 1
R5 100% 100%
R7 100% 90%
R8 100% 80%
70%
R9 100%
60%
R10 100%
50%
R11 100%
40%
R12 100%
30%
R15 100%
20%
10%
0%
R1 R2 R3 R4 R5
Respondent
Rec#
SMS Process Descriptions Recommendations Required Dept./PMT/ Evidences Provided LPD Comments PMT Response / Additional Documents Needed Action must taken by LPD Close-out Target REMARKS
Element # Owner Evidences Prime date
Contractors
CPP-FPPS Submitted
CPP-NGCP PL Submitted
1. Perform a gap analysis between current risk analysis All (CPP FFPS, CPP NGCP,
records, contractor activities, and field conditions to Gap Analysis SAIPEM Submitted All Division and Contractors 9/17/2020
address unidentified risks Saipem, Tekfen, TR)
TEKFEN Submitted
CPP-FPPS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
CPP-NGCP PL Submitted
Provide completed/approved
4. Ensure senior project personnel (e.g., Sr. Project Method of Statement (MS)
Engineers, Sr. Quality Inspector and Sr. Safety Personnel) w/ PMT/ All (CPP FFPS, CPP SAIPEM Submitted All Division and Contractors 9/17/2020
are participating in constructability studies and Proof of involvement of the NGCP, Saipem, Tekfen, TR)
development of method statements
PMT
TECNICAS REUNIDAS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
Contractor implementation
5. Implement all identified control measures to manage per MS CPP-NGCP PL Submitted
the risks associated with construction activities by 1. Provide copies of Work
requiring contractors to develop detailed method Permit specific to the MS All (CPP FFPS, CPP NGCP, All Division and Contractors
statements to include, but not limited to, mobilization, activity. Saipem, Tekfen, TR) SAIPEM Submitted Division Safety Lead to Communicate to all PMT's 9/17/2020
civil works, steel erection, pre-commissioning for both 2. Provide copies of JSA &
departmental and contractor personnel Toolbox talks specific for the TECNICAS REUNIDAS Submitted
MS
TEKFEN Submitted
CPP-FPPS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
CPP-NGCP PL Submitted
2. Conduct camp and project support facility assessments Provide Camp Approval
with SMEs (e.g., FrPD, EPD, LPD and Community Services) GI 298.010 (FORM C) All (CPP FFPS, CPP NGCP, SAIPEM Submitted All Division and Contractors 9/17/2020
Saipem, Tekfen, TR)
and document findings
TECNICAS REUNIDAS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
CPP-NGCP PL Submitted
Tracking and Closeout
5. Track actions to closure and maintain records Records (Corrective Actions PMT SAIPEM Submitted All Division and Contractors 9/17/2020
from the CS checklist)
TECNICAS REUNIDAS Submitted
TEKFEN Submitted
CPP-FPPS Submitted
CPP-NGCP PL Submitted
TEKFEN Submitted
CPP-FPPS Submitted
Provide completed Fire
1. Regularly verify (e.g., through contractors’ monthly Protection Inspection
inspection reports, and Community Services Checklist
monthly/quarterly/annual camp inspection reports) that 1. Fire Pump
contractors maintain the required fire protection 2. Fire hydrant CPP-FPPS / TCF4
equipment in accordance with GI 1781.001, Inspection, 3. Fire Alarm PMT TCF4/ CPP FFPS, TR
Tekfen, TR) TECNICAS REUNIDAS Submitted 9/17/2020
Testing, and Maintenance of Fire Protection Equipment. In 4. Fire Extinguisher TEKFEN
addition, audit and verify contractors implement a process 5. Fire suppression system if
to identify, maintain and test emergency response any
resources for readiness to ascertain compliance
# Saudi Aramco: Company General Use
Provide completed Fire
1. Regularly verify (e.g., through contractors’ monthly Protection Inspection
inspection reports, and Community Services Checklist
monthly/quarterly/annual camp inspection reports) that 1. Fire Pump
contractors maintain the required fire protection 2. Fire hydrant CPP-FPPS / TCF4
equipment in accordance with GI 1781.001, Inspection, 3. Fire Alarm PMT TCF4/ CPP FFPS, TR
#