• Introduction
• Planning of Equipment
• Equipment Haul Cycle
• Required Job Productivity
• Specific Equipment Selection Factors
• Planning of Equipment Utilization
• In some cases, value of equipment > contract value – can be used for series
of job
https://dailytimes.com.pk/22570/neelumjhelum-hydropower-project/
• Not possible to own all types of and sizes of equipment for a particular
project
• Cranes of different types and capacity
• Question to be asked:
• Disposability of equipment?
• At end of useful life of equipment-should be buyer of equipment
• Standard Equipment's
• Special Equipment's
• Standard Equipment's:
• Commonly manufactured-available
• Delivery quicker-sales after services
• Can be used on more than one project
• Parts can be procured quickly and economically
• Disposed of easily and at reasonable price-life of equipment
• Project cannot be delayed due to no availability of equipment parts etc.
• Special Equipment's:
• Usually used on a single project or activity
• Total haul unit cycle time is found by summing the time required for each
of the following components of the haul cycle:
• Load—at the excavator/loader
• Haul—from the loader to the unloading site
• Dump—at the unloading site, including maneuvering
• Return—travel back to the loader
• Spot—move into loading position at the loader
https://www.youtube.com/watch?v=kO_JiApggYs https://www.youtube.com/watch?v=KS63t8zSCCA
https://www.youtube.com/watch?v=63rtN7U9iXk
https://www.youtube.com/watch?v=kuq4-WBCtfk
2. Contract Document
• Contract document may specify only expected result. In this case equipment choice
will be left to contractor
• In some cases, construction method and equipment are specified to avoid
undesirable results
• Indirect mention such as location of construction joints in drawing will decide the
amount of concrete to be poured in single stage
• Sometimes rate of concrete placement is mentioned to avoid cold joint formation
• This will indirectly influence the selection of equipment
3. Project Time Schedule
7. Mobility required
• Mobility while performing the required operation
• Mobility from one activity to other
• Mobility from one project to other
• For example: concrete placement with truck mounted pump in congested sites
• Example of activities on u-turns on Ferozepur road
• Piles at some location
• Girders in yard
• Pile caps at other locations
• Transom at some locations
3 shank ripper