FUTONG JETTY
PILE ECCENTRICTY CHECK AND REVIEW OF RECTIFICATION METHOD
INTERIM REPORT 1
(Volume 01 of 01)
0 FOR CLIENT REVIEW 19 JAN 2021 ACK LEO CKS
Rev. DESCRIPTION DATE BY CHECKED APPROVED
Owner: APRILASIA (PT. RIAU ANDALAN PULP AND PAPER) Project No: ES 2028
Client: APRILASIA (PT. RIAU ANDALAN PULP AND PAPER)
Project Ref.
No.:
-
Doc. No: ES2028-REP-01
ENGINEERS 9000 PTE LTD
Blk 211 Henderson Road
#12-01 Henderson Industrial Park
Singapore 159552
Tel: 6275 9000 Fax: 6275 7600
Email: e9000@e9000.com.sg
CONTENTS
1
INTRODUCTION.......................................................................
.......................................................3
2 REVIEW
PROCESS............................................................................
...............................................3
3 DESIGN BASIS
REVIEW ............................................................................
........................................5
3.3 PILE
DESIGN.............................................................................
...............................................6
4 IN-
HOUSECALCULATIONANDRECTIFICATIONREVIEW.............................................
....................7
5
PROGRESS ..........................................................................
............................................................8
6
CLARIFICATION......................................................................
.........................................................8
7
CONCLUSION.........................................................................
.........................................................8
2| Page
1 INTRODUCTION
Upon completion of Futong Jetty Extension, Aprilasia (PT. Riau Andalan Pulp and
Paper,
abbreviated as RAPP) as the owner of the said jetty, decided to carry out
engineering evaluation
to assess the structural adequacy of constructed jetty due to excessive pile
eccentricity and
inclination. From the latest report submitted by contractor, it is known that
significant number
of the constructed piles have exceeding their allowable limit as specified by the
Jetty�s design
consultant. Hence, there is a concern with regards to the Jetty�s structural
safety.
In order to address the concern, RAPP civil design team has carried out analysis &
design
check and produce a rectification proposal. To review and validate the proposal,
RAPP engaged
M/s Engineers 9000 Pte Ltd to perform independent analysis and review on their
proposal, if
the proposal is found to be not adequate, E9000 will propose enhancement to the
original
proposal. Analysis and design check will be carried out based on as-built
information that was
provided to us on 31st Dec 2021.
As the work is tedious and complex and the jetty platform structure is
significantly large, we
proposed to work by stages as stated in the following chapter. This interim report
is serves as
progress report to client and will be updated in future once we obtain analysis
results from our
independent model.
2 REVIEW PROCESS
Steps of our review process of reviewing through all the documents and drawings
provided,
listing all the information that were provided.
by client.
5) Upon re-modelling, review the original rectification design approach and propose
a
rectification plan as necessary.
6) Preparation of final report.
A.
As-built drawings (all file is in PDF UOS)
1) 1091-C-1121 rev.2.1 Jetty head-Piling layout plan_RHDV
2) 1091-C-1122 Jetty head-pile details D800-120_RHDHV
3) 1091-C-1123 Jetty head-pile details D1000-140_RHDHV
4) 1091-C-1124 Jetty head pile plug reinforcement_RHDV
5) 1091-C-1130 rev.2.1 Jetty head-general arrangement_RHDHV
6) 1091-C-1131 Jetty head suggested construction sequence_RHDV
3| Page
7)
1091-C-1132 Jetty head-typical sections (sheet 1)_RHDHV
8)
1091-C-1133 Jetty head-typical sections (sheet 2)_RHDHV
9)
1091-C-1134 Jetty head-typical sections (sheet 3)_RHDHV
14) 1091-C-1139 rev.2.1 Jeety head pc pilecap & fender beam unit details_RHDV
26) 1091-C-1152 jetty head-pc plank reinforcement type 1A, 1B & type 2_RHDHV
27) 1091-C-1153 Jetty head-pc plank reinforcement type 3,3A, 3B & 3C_RHDHV
1)_RHDHV
2)_RHDHV
3)_RHDHV
B.
Rectification sketches: (all file is in PDF UOS)
1) FJ-1000-C-0001-Layout
2) FJ-1000-C-SK-0001
3) FJ-1000-C-SK-0002
4) FJ-1000-C-SK-0003
5) FJ-1000-C-SK-0004
6) FJ-1000-C-SK-0005
7) FJ-1000-C-SK-0006
8) FJ-1000-C-SK-0007
9) FJ-1000-C-SK-0008
4| Page
10) FJ-1000-C-SK-0009
11) FJ-1000-C-SK-0010
12) FJ-1000-C-SK-0011
13) FJ-1000-C-SK-0012
14) FJ-1000-C-SK-0013
C.
Field survey(all file is in PDF UOS)
1) Firdaus piling2 16.12.20.dwg
2) horizontal eccentricity grid 1-10
3) horizontal eccentricity grid 11-20
4) horizontal eccentricity grid 21-30
5) VERTICAL 1-10
6) VERTICAL 11-20
7) VERTICAL 21-30
8) VERTICAL 31-40
D.
SITE VISIT REPORT OF EXTENDED PULP JETTY AT FUTONG PORT (151220)
Up to date, we have received 58 files (calculation and drawing) in total.
The size of new Jetty Head is 200m x 25m, it was designed as a deck on piles
structure with
precast reinforced concrete beams and slabs standing on driven precast hollow spun
piles. It
was planned to cater for maximum container vessel size of 65,000DWT.
The following codes, standards and guidelines used for berthing analysis.
� British Standards:
o BS EN-1990: Basis of Structural Design;
o BS EN-1991: Actions on Structures;
o BS EN-1992: Design of Concrete Structures;
o BS EN-1993: Design of Steel Structures;
o BS EN-1998: Seismic Design;
o BS 6349-1-1: Maritime works -General: Code of Practice for Planning and Design
for
Operations;
o BS 6349-1-2: Maritime works -General: Code of Practice for Assessment of Actions;
o BS
6349-1-4: Maritime works -General: Code of Practice for Materials;
5| Page
o BS 6349-2: Maritime works -Code of Practice for The Design of Quay Walls, Jetties
and
Dolphins;
� Other design supplementary design codes, standards and guidelines:
o SNI 03 1726-2012 Standar Perencanaan Ketahanan Gempa untuk Struktur Bangunan
Gedung dan Non-Gedung. Bandung: Badan Standarisasi Nasional Indonesia;
o JIS A 5373 Precast pre-stressed concrete product;
o ACI 543R-00 Design, manufacture and installation of concrete piles;
o ASCE/COPRI 61-14 Seismic Design of Piers and Wharves.
3.2 DESIGN LOAD AND COMBINATION
Design load considered in the original design is as follows:
� Dead loads:
� Live loads: New Jetty: 40kN/m2 , Trestle: 20kN/m2
� Equipment loads
� Mooring and berthing loads
� Environmental loads
� Seismic load.
We will adopt the above loads which have been derived by original designer into our
model.
3.3 PILE DESIGN
The original analysis was considering a range of fixity levels. The length of the
pile below the
level of seabed is represented in the model by applying a vertical spring stiffness
coefficient at
the node at the end of the pile element.
There are two size of piles used in this project. Below picture shows the size and
locations of
spun piles.
6| Page
IN-HOUSE CALCULATION AND RECTIFICATION REVIEW
We noted that there are only five load combination were considered according to SNI
Code
in the Site Visit and Rectification Report for Extended Pulp Jetty Futong Port.
Five load combinations for serviceability and ultimate limit state is shown as
below:
1. SLS1=1.0DL+1.0LL+1.0Ex
2. SLS2=1.0DL+1.0LL-1.0Ex
3. ULS1=1.2DL+1.6LL
4. ULS2=1.2DL+1.0LL+1.0Ex
5. ULS3=1.2DL+1.0LL-1.0Ex
In order to obtain a more accurate and economical result, we will be considered all
load
combinations required by Euro Code with actual as-built piles� eccentricities to
assess the
jetty structure and the proposed rectification, and provide modified rectification,
if required.
The computer analysis based on the SNI Code by the In-house engineering team is
adequate
for preliminary assessment, as it provides quick and simple approach by calculating
the load
taking using tributary area and ignoring horizontal load.
We envisage that the jetty design has to be re-modelled with the as-built pile
location due to
large eccentricity and the rectification solution could then be derived upon
obtaining
computer analysis results.
7| Page
5 PROGRESS
Basing on the information provided, we have now completed the 3D remodelling of the
jetty layout.
The next stage of work is to introduce pile eccentricity into the 3-D model and
analyse the impact to
jetty and the piles system.
6 CLARIFICATION
7 CONCLUSION
The next updated interim report will present the outcome on the study after the
completion of the 3-D
modelling design taking into consideration of the pile eccentricities.
8| Page