ENGINEERING DIVISION

PUBLIC INFRASTRUCTURE AND DEVELOPMENT HANDBOOK

Table of Contents
Section Title Page

I. Design Standards and Material Specifications


A. Watermain I-2
B. Sanitary Sewer I-8
C. Storm Sewer and Stormwater Management Systems I-13
D. Roadways, Sidewalks and Pathways I-16
E. Grading I-18
F. Erosion Control I-19
II. Drafting Standards
A. General II-2
B. Watermain II-3
C. Sanitary Sewer II-4
D. Storm Sewer and Stormwater Management Systems II-5
E. Roadways II-6
F. Grading & Erosion Control II-7
III. As-Built Standards
A. Public Infrastructure III-2
B. Grading & Drainage III-3
IV. Appendix
Standard Details (30 sheets, 29 details)
Stormwater Management Application Packet (10 sheets)
Example Design Sheets-Sanitary Sewer & Water Main (2 sheets)
Example As-builts-Sanitary Sewer, Water Main, & Storm Sewer (3 sheets)
Example As-builts- Commercial & Residential Grading (2 sheets)
Example Easement Exhibit (1 sheet)

Note: Technical changes to the Public Infrastructure and Development Handbook shall be provided to the Board of
Public Works and/or the Water and Sewer Board on a quarterly basis. Material changes affecting policy shall not be
made to the Handbook without concurrence from the appropriate Board in advance.
Last Revised: June 5, 2007

ENGINEERING DIVISION 2000 N. CALHOUN ROAD BROOKFIELD, WI 53005-5095


PHONE: 262-787-3919 FAX: 262-782-1323
Section I - Design Standards and Material Specifications

Title Page
A. Watermain I-2
B. Sanitary Sewer I-8
C. Storm Sewer and Stormwater Management Systems I-13
D. Roadways, Sidewalks, and Pathways I-16
E. Grading I-18
F. Erosion Control I-19

Note: The City of Brookfield Design Standards and Material Specifications have been
provided in an effort to assist with public and private infrastructure design. This section was
intended to provide general guidance to the design engineer. The Engineer must also follow
all applicable State of Wisconsin & Federal guidelines. The City of Brookfield Engineering
Division reserves the right to alter or add requirements through the review process. Specific
design questions not detailed in the following sections should be directed to the City
Engineering Division (262-787-3919).

I-1
SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

A. WATERMAIN_____________________________________________________

Design Standards

1. Water Mains shall typically be located 12 feet off the north and east right-of-way (R.O.W.)
lines, or as otherwise approved by the City Engineer. Where watermains are located outside
the R.O.W. but contiguous to it, an easement will be required a distance of 15 feet on both
sides of the centerline of the watermain, or to the right-of-way line, whichever is less. Where
watermains are located on private property, not contiguous to R.O.W., a 30 foot easement
will be required. All hydrants must be included in the right-of-way or in an easement and
service valves must be placed at the edge of the right-of-way or at the easement line.
2. Minimum depth for watermains shall be 6 feet to the top of pipe from finished grade.
3. Water appurtenance locations shall be as follows:
1. Hydrants
a. 5 feet off water main (Refer to Appendix- Standard Detail No. BRK.009,
BRK.009A)
b. One at each intersection (5.0 feet from right-of-way line, away from
intersection)
c. At far end of cul-de-sac
d. Mid-block locations at lot line extended
e. Maximum spacing shall be 500 feet in all cases (measured along the
watermain)
f. All high points in water main installation shall be placed at hydrant locations
2. Valves
a. At intersections adjoining street line extended toward intersection
b. 5’ from hydrant tees (on the high side)
c. On hydrant branches 30 inches from hydrant
d. Maximum spacing shall be 800 feet in all cases
e. Three valves shall be installed at all main crosses and two valves shall be
installed on all main tees, unless otherwise approved by the City Engineer.
3. Air Vents
a. At high points in line when no hydrant is present, minimum 2 inches in
diameter. (Engineering approval required)
b. At ends of water laterals 4 inches in diameter and larger
4. Flushing Hydrants
a. At temporary ends of watermain, minimum 2 inches in diameter.
4. Elevations of water main shall refer to flowline or invert of pipe.
5. Minimum water main size shall be 8 inch diameter, 6 inch diameter for hydrant leads.
6. Installation of tracer wire - #10 gauge direct bury copper wire (coated) shall be taped to the
top of all PVC and HDPE water main. The copper wire shall be wrapped around the pipe at
the beginning and at the end of the water main installation. The copper wire shall extend
along the entire length of the pipe in a continuous fashion. Splices must be made using
connectors approved by the Engineer, or by twisting the wires together a minimum of ten
(10) turns. At all crosses and tees, the tracing wires running both directions shall be
interconnected. The contractor shall properly tape all splices/inter-connects to provide
proper water proof insulation. The wire shall extend along each hydrant lead to a tracer wire

CITY OF BROOKFIELD I-2 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

access box located immediately behind each hydrant and shall run up into the tracer wire
access box and connect to a stainless steel terminal bolt on the underside of the lid. The next
run of tracer wire will connect to the second stainless steel terminal bolt on the underside of
the lid, run down into the tracer wire access box, back along the hydrant lead and continue
along the water main. Both wires in the access box shall have enough slack to allow for
settlement, easy removal of the lid and future maintenance (restripping of the wire ends).
Provide tracer wire access box by Valvco, inc. or equal. Tracer wire access box shall also
include 2 inch diameter schedule 40 PVC pipe from a depth equal to the hydrant lead and
extending halfway into the access box. Access box shall be set flush with final grade with 2
inch of adjustment available up and down. Any bare wire shall be covered with water proof
insulation protector. The Contractor shall test all tracer wire for continuity in the presence of
a City Inspector. All costs for the tracer wire along the water main shall be included in the
unit bid prices for water main. All costs for the tracer wire access box and tracer wire along
the hydrant leads shall be included in the unit bid price for hydrant assembly.
7. Single family residential services shall, at a minimum, be 1-1/4 inch HDPE pipe (larger sizes
may be approved with Engineering Division approval).
8. Crushed stone backfill (as specified by the Wisconsin Standard Specifications for Sewer and
Water Construction) is required under or within 5’ of pavement; otherwise approved spoil
backfill.
9. Maintain a 6 inch minimum vertical separation with all sanitary and storm sewers when
crossing over. Maintain an 18 inch minimum vertical separation with all sanitary and storm
sewers when crossing under.
10. Permitting and Approvals- All public water main extensions must also be approved by the
Wisconsin Department of Natural Resources. All submittals must be completed by the
developer’s design engineer. (Please contact the City Engineering Division for fire flow tests,
the minimum residential fire flow must be designed to be 1500 GPM at a calculated residual
pressure of 20 PSI, the required flows for other uses must follow the current ISO fire flows
and be approved by the Engineering Division). These submittals must first be transmitted to
the City Engineering Division for review and approval; the City will then transmit the
appropriate materials to the permitting agency.

Material Specifications - Watermain


1. Watermain Pipe
PVC shall be C-900, Class 150 (DR18) for 4 inch through 12 inch sizes.
PVC shall be C-905, Class 150 (DR18) for sizes larger than 12 inch.

HDPE shall be AWWA C-906, DR 11, ductile iron pipe size (DIPS), high-density
polyethylene (HDPE) water pipe for use as a fluid pressure conduit. HDPE pipe shall be
made from virgin resins exhibiting a cell classification of PE 345444C as defined in ASTM
D3350 with an established hydrostatic-design-basis of 1,600 psi for water at 73 degrees
Fahrenheit. The resin shall be listed by the Plastic Pipe Institute (PPI) in its pipe-grade
registry Technical Report (TR) 4, “Listing of Plastic Pipe Compounds.” Pipe shall be NSF
listed by the manufacturer with the pipe bearing the “NSF” logo or mark. Pipe shall be
marked as prescribed by AWWA C-906 and NSF. Pipe markings shall include nominal size,
OD base (i.e. 12 inch ductile iron pipe sizing, DIPS) dimension ratio, pressure class, WPR,
AWWA C-906, manufacturer’s name, manufacturer’s production code including day, month,

CITY OF BROOKFIELD I-3 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

year extruded, and manufacturer’s plant and extrusion line. Pipe manufacturer shall have an
approved in-house QA/QC program providing compliance to the testing specifications and
requirements of AWWA C-906 and ISO 9001 certification.

Ductile Iron shall be Class 350 (cement lined), AWWA C-151 slip joint pipe with
compression type push-on rubber gaskets conforming to AWWA C-111 (unless an alternate
joint is approved by the City Engineer).

2. Joints
PVC pipe shall have push-on bell joints with rubber gasket.

HDPE pipe shall be joined by means of a zero leak-rate heat fusion or electrofusion butt joint
and approved mechanical joints, meeting the specifications and requirements of AWWA C-
906.

Ductile Iron shall be slip joint pipe with compression type push-on rubber gaskets
conforming to AWWA C-111 (unless an alternate joint is approved by the City Engineer).

3. Fittings
Shall be Ductile Iron with mechanical joints conforming to Chapter 6.22.0 of the Standard
Specifications, A.W.W.A. C-110 and C-111 with the exception of the manufacturer's design
dimensions and thicknesses. Compact Ductile Iron fittings are allowed in accordance with
Chapter 6.22.2 of the Standard Specifications.

HDPE mechanical joint adapters shall conform to AWWA C-906 for connections to
dissimilar materials (PVC or ductile iron). A butt fused HDPE mechanical joint adapter with
a stainless steel internal stiffener shall be used. The DR for any polyethylene fitting shall be
9 (unless otherwise approved by the City Engineer).

4. Services
Shall be 1-1/4 inch to 2 inch CTS C-901 SDR-9 HDPE Water Tube.
On HDPE services, solid stainless steel insert sleeves should be included with the curb stop
and corporation stop. Joints shall be with pack joint compression fittings as manufactured by
Mueller, McDonald and Ford.

5. Corporation Stops For HDPE Water Tube


1” x 1-1/4”, 1-1/2”, 1-1/2” x 2” & 2”
Shall be: Mueller H-15008
McDonald 4701BQ
Ford F1000

6. Ground Key Stop Valve (Curb Stops)


1 ¼” x 1” x 1 ¼”
Shall be: Mueller P-15155
McDonald 6104Q
Ford B44-455M

CITY OF BROOKFIELD I-4 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

1 ½” and 2”
Shall be: McDonald 6104Q
Ford B44-666M (1 ½”)
Ford B44-777M (2”)

All with 2" Minneapolis thread.

7. Service Box (Curb Boxes)


For 1”
Shall be: Mueller H-10300
McDonald 5614

For 1-1/2” and 2" Ball Valve


Shall be: McDonald 5615 or equal

8. Service Saddles
Stainless steel clamp with rubber gasket and integral service outlet.
Cascade Waterworks (CSC2 for 4"-10", CS22 for 12" & 16"), Smith-Blair (372 for 4”-12”),
Power Seal or equal.

Service saddle required for all services 1-1/4” and larger (except saddle not required for 1-
1/4” service if 1” x 1-1/4” corporation stop is used).

9. Gate Valves - A.W.W.A. Spec. C509


Shall be resilient wedge type for 4", 6", 8" or 10"
American Flow Control, Series 2500, SS Bolts
Clow F-6100, SS Bolts
Mueller 2360-20, SS Bolts
Kennedy Ken-seal, SS Bolts
M&H, SS Bolts

All gate valves shall be furnished with a gate valve adaptor with gasket as manufactured by
Adaptor, Inc. A valve extension stem is only required if the operating nut is 8 feet or more
below finished grade. If a valve extension stem is required, the length shall be such that the
top of the extension is within 8 feet of finished grade.

NOTE: Any R.W.G. valve used for cutting in must use a cutting tool that will develop a hole
not less 1/2" smaller than the valve. (Any test plugs included on valves shall be replaced
with stainless steel plugs.)

10. Butterfly Valves - A.W.W.A. Spec. C504


Shall be for 12" and larger, Clow , Pratt Groundhog, M&H 450 or Mueller Lineseal III. All
butterfly valves shall have SS nuts and bolts.

CITY OF BROOKFIELD I-5 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

All butterfly valves shall be furnished with a butterfly valve adaptor with gasket as
manufactured by Adaptor, Inc. A valve extension stem is only required if the operating nut is
8 feet or more below finished grade. If a valve extension stem is required, the length shall be
such that the top of the extension is within 8 feet of finished grade.

11. Valve Boxes and Lids


Shall be: Tyler 6860
Star Pipe Products two-piece cast iron valve box with lid

12. Flush Valve Assembly


The following shall be required only if specifically included on the plans:

Plug & Air Vent for ends of mains and laterals - see File #43 Standard Specifications

Flushing Hydrant for ends of mains – Eclipse No. 2 Post Hydrant with stainless steel shaft by
Kupferle or equal.

13. Air Release Assembly


For high points in mains, see File #42 Standard Specifications.

14. Hydrants
Shall have: bronze on bronze seat
bronze upper valve plate
break away flange
oil or grease reservoir
coated elbow
meets or exceeds A.W.W.A. C502 with a 5-1/2" valve, two 2-1/2" hose nozzles and one
pumper nozzle with stainless steel bolts underground, and shall be: Clow Medallion, Mueller
Centurian and Kennedy Guardian (with reservoir).

All parts used to modify hydrant must be from the original equipment manufacturer.
The bars on all hydrants shall be 3/4" diameter.

15. Check Valve


Valmatic 1800 series globe style, 125 lb. class, with cast iron body, bronze plug and stainless
steel spring.

16. Pressure Switch


Mercoid DA-31, 5-150 PSIG

17. Pressure Gauges


Marshalltown Series 44K, 3-1/2" with phosphor bronze Bourdon tube, Gauge scales to be 0-
150 PSI.

CITY OF BROOKFIELD I-6 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

18. Ball Valves


Nibco 590 Series ball valves, except for 1/4" valves which shall be Nibco 580 Series ball
valves.

19. Meter Yoke


Ford Meter Box Co. Straight Line Yoke. Yoke to match owner's 5/8, 5/8 x 3/4 or 3/4 inch
meter. Verify meter size.

20. Sampling Faucets


Chicago Faucet No. 4, chrome plated brass, 1/2 inch smooth end.

21. Tracer Wire Access Box


Shall be Valvco, Inc. Access Box or equal

22. Tapping Sleeves


Tapping sleeves shall have a stainless steel body with removable bolts. The outlet, body,
flange, bolts and nuts shall be 18-8 type 304 stainless steel. All welds are fully passivated to
restore stainless characteristics. Flange shall conform to AWWA Standard C207, "Steel Pipe
Flanges for Waterworks Service-Sizes 4 In. Through 144 In.", Class D ANSI 150 lb. with
drilling recessed to accept standard tapping valves per MSS-SP 60. Bolt holes straddle pipe
centerline. Shell gasket must seal the full circumference of the pipe. Flanged gasket shall
be full faced, cut from 1/8 inch thick cloth inserted rubber sheet, boltholes prepunched,
conforming to the requirements of ANSI B16.21.

Approved stainless steel tapping sleeve manufacturers/models:


Ford FTSS
JCM 432
Power Seal 3490
Smith-Blair

CITY OF BROOKFIELD I-7 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

B. SANITARY SEWER________________________________________________

Design Standards

1. Location & Depth


a. Sanitary sewers shall typically be located at the centerline of the street or easement
b. Sewers in curved streets shall typically not be more than 10 feet from centerline
c. Manholes shall be located at the centerline of street/easement
d. Sewer depth shall be designed to accommodate gravity flow from the lowest part of all
buildings. Residential basements shall have an assumed minimum depth of 10 ft from
finished floor elevation to the basement floor elevation. Also, 1.8 ft. should be used for
the depth from the basement floor to the sewer lateral to accommodate for clearing the
footing depth

2. Design Flow
a. Average residential sewer flows shall be 125 gallons per capita per day. Peak residential
sewer flows shall include a peaking factor of 5, and an additional 85 gallons per capita
per day for inflow and 85 gallons per day for infiltration (Total = 795 gal./capita/day).
b. The City of Brookfield maintains a standard loading for residential design flows.
• 2.86 people per house
• 2.5 people per unit
c. The capacity and velocity of sanitary sewers shall be determined using Manning’s
Formula using a frictional coefficient of 0.013 for sanitary sewers
d. Sanitary sewer calculations must be submitted with proposed sanitary sewer plans

3. Sanitary Sewer Sizes and Slopes


a. Residential: 8 in. (minimum)
b. Sanitary sewers shall be sized to provide a minimum velocity of 2 ft/sec at 50 % full
c. All sewers must be sized adequately to accommodate future tributary areas as directed by
City Engineer
d. Public mains located within private property must be placed within an easement. See #8
below for requirements.
e. Minimum Slopes:
• 8” = 0.40 % (dead end reach = 0.60 %)
• 10” = 0.28 % (dead end reach = 0.40 %)
• 12” = 0.22 %
• 15” = 0.15 %
• 18” = 0.12 %
• 21” = 0.10 %
• 24” = 0.08 %
• Other sizes - Per Engineering Division

4. Sanitary Manholes
a. Sanitary manhole rims must be placed 2.0 ft. above the 100-yr floodplain elevation
(FPE). When practicable, grade earth around manhole at 4H:1V slope.

CITY OF BROOKFIELD I-8 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

b. Public manholes located within private property must be placed within an easement. See
#8 below for requirements.
c. Elevations of sewer inverts shall refer to the flowline or invert of pipe in MH.
d. Maximum distance between manholes shall be 400 ft. unless approved otherwise
e. Drops in manhole (Angle measured between incoming and outgoing sewer pipe)
• Angle of 0 to 10 degrees = 0.10 ft drop
• Angle of 10 to 30 degrees = 0.15 ft. drop
• Angle greater than 30 degrees = 0.25 ft. drop
• Maximum allowable drop in MH shall be 24 in.
• Where drops exceed 24 inches an outside drop manhole shall be used (detail can be
found in the appendix)
• Where different sized pipes meet in MH, 80 % flowlines shall match
f. Frames, Lids and Seals:
• All sanitary sewer manholes shall have a heavy duty frame with solid, gasketed self-
sealing lid with concealed pick holes (see standard details and material specifications)
• Sealed bolted-down lids/frames shall be required in floodplain areas
• All sanitary sewer manholes shall utilize an external seal (see standard details and
material specifications)
g. Chimney Height:
• Minimum Height = 6 Inches
• Maximum Height = 22 Inches

5. Sanitary Sewer Laterals


a. A minimum 6 inch diameter sewer lateral shall be installed for residential use, larger
sizes for different uses must be approved by the Engineering Division
b. Laterals shall be installed to the lot line/street right-of-way or the edge of the easement
the sewer resides in
c. Laterals may not be connected to manholes except in cul-de-sac where necessary and
approved by the City Engineer. Where laterals connect to manholes, the lateral shall
extend to the flow line of the pipe or the bench shall be modified to include the lateral as
a pipe.
d. A minimum slope of 2 % shall be used. Under special approval, City Engineer may
authorize the use of 1 %
e. Existing laterals not used in development or redevelopment shall be abandoned at the
main. Slurry or grout filling of laterals will be required where open cutting existing
roadway is not practical. Existing laterals used in new developments or redevelopments
must be televised and reviewed by Public Work Inspection prior to reconnection. Should
defects or infiltration or inflow (I&I) exist, the City will require appropriate measures be
taken which may include relay, lining, or grouting of the lateral.
f. Vertical risers shall be used where excessive drop occurs from the property line to the
mainline. In general, the sanitary lateral should be placed at a depth between 10 to 13’
below finished grade at the property line or at a depth adequate to serve the lowest point
of the building to be served. (see standard details and material specifications)

6. Force Main
a. Valve spacing shall be placed every 800 ft.

CITY OF BROOKFIELD I-9 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

b. Minimum Design depth: 6 ft. from top of pipe to finished grade


c. Tracer wire is required to be secured to the force main
d. Minimum design velocity is 2 ft./sec., while maximum shall not exceed 10 ft./sec.
e. Air release/vacuum valves and cleanouts must be incorporated into design layout

7. Lift Stations
a. Lift Stations are to be avoided.
b. Coordinate with Engineering Division for specific design requirements regarding sanitary
lift stations.

8. Easements
a. The City’s standard width for sanitary sewer easements is 30 ft. for a single utility, plus
10 ft. for each additional utility within the easement.
b. No structures or trees will be permitted to be placed in Municipal utility easements.
Unless avoidable: shrubs, plantings, and shallow berms will be permitted in easement
but not within a 5 foot radius of appurtenances. A written explanation of why
landscaping or berming must be placed within easements needs to be submitted along
with a signed encroachment agreement.
c. Grade changes within utility easements is not allowed without prior Engineering
approval.
d. Written easement documents shall be executed & recorded for all easements depicted on
CSM’s, plats and plans. The developer/owner shall provide the exhibit and legal
description of the easement (see appendix); the City will prepare the actual easement
document for signatures and recording.
e. Manholes located within private property should be placed within a paved surface where
it is practical for easy inspection and cleaning.

9. Permitting and Approvals


a. All public sanitary sewer extensions must also be approved by the Wisconsin Department
of Natural Resources, and in some cases other permitting agencies such as the Milwaukee
Metropolitan Sewerage District. All submittals must be completed by the developer’s
design engineer. These submittals must first be transmitted to the City Engineering
Division for review and owner approval, the City will then transmit the appropriate
materials to the permitting agency for their approval.

Any variation of the above standards must be approved by the City of Brookfield Engineering
Division

Material Specifications – Sanitary Sewer

1. Sanitary Sewer Main


All pipe used for public and private sanitary sewer shall be:
PVC, ASTM D-3034, SDR 35 meeting the requirements of Section 8.10.0 of the Standard
Specifications for Sewer and Water Construction in Wisconsin (Standard Specifications)

CITY OF BROOKFIELD I-10 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

2. Sanitary Sewer Laterals


All pipe used for sanitary sewer laterals shall be:
PVC, ASTM D-3034, SDR 35 meeting the requirements of Section 8.10.0 of the Standard
Specifications. Sanitary laterals shall be 6” in diameter.

3. Sanitary Force Main


All pipe used for sanitary force mains shall be:
AWWA C-900 meeting the requirements of section 8.51.2 or
HDPE, ASTM F-714, SDR 11 meeting the requirements of section 8.51.3

4. Sanitary Manholes

Sanitary manholes shall conform to the following:


All manholes shall be precast reinforced concrete and have a minimum inside diameter of 48
inches. Minimum wall thickness shall be per Table No. 1 in File No. 12 of the Standard
Specifications. Precast concrete manhole base, barrel risers, cone section and adjusting rings
shall meet the requirements of ASTM C-478. Manhole external seals shall be provided for
each manhole and shall be manufactured by Adaptor, Inc. Manholes shall be constructed per
drawing BRk 11, 11A and 11B and vacuum tested in accordance with Section 3.7.6 of the
Standard Specifications.

5. Bedding, Cover and Backfill Materials

Bedding, cover and backfill materials shall be as follows:

Bedding and cover material shall conform to Table 32 of the Standard Specifications and
shall be 3/8” crushed limestone with a minimum of 6 inches of bedding to a cover 12 inches
above the crown of the pipe.

Granular backfill shall conform to Section 8.43.4 of the Standard Specifications.

Spoil backfill (may be used in locations settlement is not critical and approved by the City)
shall conform to Section 8.43.5 of the Standard Specifications.

Slurry backfill (where required by the City Engineer) shall conform to Section 8.43.9 of the
Standard Specifications.

6. Fittings

All fittings used for sanitary pipe and laterals shall be as follows:

Fittings for sewer laterals shall be PVC, ASTM D-3034, SDR 35 and meet the requirements
of Section 8.10.0 of the Standard Specifications.

Couplings for connecting dissimilar pipe materials shall be non-shear coupling as


manufactured by DFW/HPI or shall be made with a flexible mechanical compression joint
coupling conforming to ASTM C-594 Type B with stainless steel bands and shear ring

CITY OF BROOKFIELD I-11 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

conforming to ASTM A-167 as manufactured by Joints, Inc. (Calder) of Gardena, CA;


Fernco Joint Sealer Co. of Ferndale, MI; or equal and in addition, using a transitional bushing
conforming to ASTM C-594 Type B when pipe with different outside diameters are to be
connected.

Flexible saddles for connecting laterals to an existing sanitary sewer shall be as manufactured
by NDS or approved equal.

CITY OF BROOKFIELD I-12 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

C. Storm Sewer and Stormwater Management Systems___________________

Design Standards
1. Storm sewers shall be typically located 10 ft. to 12 ft. off the south or west right-of-way line
with sufficient manholes set behind the curb to allow connection of inlets to same.
2. Inlets shall not substitute as manholes.
3. Storm sewers to have a minimum cover of 18 inches.
4. Storm sewer elevations shall refer to the flowline or invert of the pipe.
5. Inlets at intersections shall be 1 ft. from the end of curb and gutter radius.
6. Inlet spacing – maximum of 300 feet from crest of hill or previous inlet structure so as to
limit the maximum travel distance to 300 feet.
7. Inlets shall be located on the upstream side of the radii, upstream of sidewalks/bikepaths, and
low points of an intersection.
8. Manhole spacing shall not exceed 400 feet.
9. Manholes located within private property should be placed within a paved surface where it is
practical for easy inspection and cleaning.
10. Storm sewer pipe shall be reinforced concrete pipe (RCP) Class III with a minimum diameter
of 12 inches.
11. The minimum design storm for all conduits shall be Southeastern Wisconsin Regional
Planning Commission (SEWRPC) 10-year, 24-hour event. Storm Sewer sizing calculations
must be submitted with the Civil Design Plan set. (Note: Dead-low points may require dual
inlets and/or grate capacity analysis.)
12. Site design must provide an emergency overland flow path capable of handling SEWRPC’s
100-year, 24-hour storm event or greater.
13. The City of Brookfield Engineering Division requires designs for both minor and major
storm events and requires all new developments to meet the following minimum standards:
A. Minor Storms (10-yr, 24-hr recurrence interval storm event)
1. Stormwater systems managing this storm event shall be designed to provide an
acceptable level of access to property and of traffic service.
• Designed to provide two clear 10-foot lanes for moving traffic on existing
arterial streets, and one clear 10-foot lane for moving traffic on existing
collector and land access streets.
• Flow of stormwater along and across the full pavement width of collector
and land access streets shall be acceptable during storm events greater than
the 10-year storm event. (When the street is an integral part of the system)
B. Major Storms (100-yr, 24-hr recurrence interval storm event)
1. Development of a stormwater system (pipe and/or overland flow) that manage
this storm are designed in order to prevent significant property damage and
safety hazards.

14. All new and replacement bridges and culverts over waterways shall be designed according to
the following:
1. SEWRPC’s 10-year, 24-hr storm event for minor and collector streets.
2. SEWRPC’s 50-year, 24-hr storm event for arterial streets and highways, other than
freeways and expressways.
3. SEWRPC’s 100-year, 24-hr storm event for freeways, expressways, and railways

CITY OF BROOKFIELD I-13 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

15. Stormwater Management Designs should all follow City of Brookfield Title 14 requirements
and all applicable state requirements. MMSD requirements also apply to all areas within the
MMSD sanitary sewer service boundary. A stormwater management application packet is
included in the appendix. The application is required for most projects.
16. Where applicable, Designer shall submit to the City one copy of a Preliminary Stormwater
Management Plan (SWMP). This report shall include the following items:
a. Project overview / Executive Summary
b. Name of the Owner/Developer
c. Pre-development watershed description
d. Post-development watershed description
e. Method of Analysis
f. Soil Type
g. Curve Numbers
h. Stormwater runoff quality with SLAMM analysis
• Sediment reduction of at least 80% must be demonstrated
i. Construction Site Erosion & Sediment Controls (BMP’s)
j. Summary table of Stormwater Calculations
 Pre-development (2, 10 & 100-yr, 24-hr events)
 Post-development (2, 10 & 100-yr, 24-hr events)
k. Existing hydrology conditions map showing:
 Existing topography contours (minimum 2’ interval)
 Existing site
 Drainage basins
 Time of concentration paths
 Curve numbers
 Runoff volumes (Q) in cfs for the 2, 10 & 100-yr, 24-hr events
l. Proposed hydrology conditions map showing:
 Proposed topography contours (minimum 2’ intervals) overlaid on existing
 Proposed site plan/design
 Drainage basins/subcatchments
 Time of concentration paths
 Curve numbers
 Runoff volumes (Q) in cfs for the 2, 10 & 100-yr, 24-hr events
m. Stormwater Facility Maintenance Plan. Maintenance Plan shall include:
i. Contact name
ii. Telephone number
iii. Signature of Owner
iv. Cleaning/maintenance methods
v. Cleaning/maintenance schedule
n. Stormwater basin design
o. Outlet control structure design
17. Upon City approval of the civil site design and SWMP, Designer shall provide the City with
two (2) signed and sealed (by a P.E.) copies of the SWMP (seal to be affixed to cover/title
page of report and Item 12 of SWMP Application).

CITY OF BROOKFIELD I-14 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

18. Wet detention basins and infiltration devices shall not be located:
a. Within the boundary of a recharge area to a wellhead identified in a wellhead area
protection plan
b. Within 100 feet of a private well
c. Within 100 feet of a transient, noncommunity public water system
d. Within 1,200 feet of a well serving a public water system other than a transient
noncommunity system

17. Wet detention basins, where contamination of the groundwater is possible, should be lined
with an impermeable liner.

18. Permitting and Approvals- Most stormwater management systems must also be approved by
the Wisconsin Department of Natural Resources, and in some cases other permitting agencies
such as the Milwaukee Metropolitan Sewerage District. For MMSD (and occasionally other
agencies) submittals, forms and plans must be completed by the developer’s design engineer.
These submittals must first be transmitted to the City Engineering Division for review and
owner approval, the City will then transmit the appropriate materials to the MMSD
(occasionally other agencies) for their approval.

CITY OF BROOKFIELD I-15 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

D. ROADWAYS, SIDEWALKS AND PATHWAYS

Design Standards
1. Typical road section shall be as shown on the City Standard Cross-Section (City Standard
Plate Detail No. BRK.001)
2. Elevations shall refer to finished grade (minimum grade of all streets shall be 0.500%)
3. Centerline radius shall be not less than 200 ft. A smaller radius may be considered by the
City Engineer if traffic calming efforts are deemed necessary to the project.
4. Minimum radius (measured at back of curb) shall be 25 ft., curb shall be placed from PC to
PT at all new or redeveloped intersections.
5. Longitudinal grades of City owned roadways shall not exceed 10% on local roads and 6% on
secondary and major streets. Longitudinal grades shall not be less that 0.5%.
6. Cross slope shall be 2% for traveled lanes, and shall not exceed 4% for shoulders and parking
lanes.
7. Tapers shall be designed in accordance with latest version of the MUTCD based on design
speeds.
8. Major streets shall have a right-of way width of not less than 120 feet, a 48 ft. pavement
width, separated by a 24 ft. median strip, and a pavement consisting of a minimum of 8 in.
crushed stone base course and 8 in. Portland cement concrete surface or 6 inches of asphalt
concrete pavement over a 10 in. stone base subject to paragraph 15.
9. Secondary streets shall have a right-of-way width of not less than 90 ft., a pavement width of
52 ft. and a pavement consisting of a minimum of 8 in. crushed stone base course and a 6 in.
bituminous concrete surface or an 8 in. Portland cement concrete surface with 6 in. stone
base course subject to paragraph 15.
10. Local streets shall have a right-of-way width of not less than 60 ft. and a pavement consisting
of a minimum of 8 in. stone base and a 5-1/2 in. asphaltic concrete pavement or a 6 in. stone
base with a 7 in. non-reinforced concrete pavement subject to paragraph 15. The pavement
shall be 34 ft. for collector streets and 22 ft. for minor streets, except that minor streets in
industrial subdivisions shall be a minimum of 30 ft. wide and shall be constructed in
accordance with secondary street specifications.
11. Cul-de-sacs shall meet the requirements for a minor street and shall provide a turnaround of
120 ft. in diameter right-of-way, of which 80 ft. in diameter shall be paved.
12. Pathways shall be 6 feet or 8 feet wide 5 inch thick concrete cross-section. Configuration
will vary for each development, but the preferred design will have a 2% cross-slope on the
pathway draining to a 4% cross-slope with an eight foot terrace area draining off the back of
curb.
13. Pathways may need to be within an easement from time to time. The easement required will
contain a minimum of one foot on both sides of the pathway. An easement exhibit with legal
description must be prepared by the developer and submitted to the City for review and
preparation of easement documents.
14. Cross sections may be required in some instances.
15. Perform and submit an engineering analysis on the pavement cross-section that is suitable for
the soil and loading conditions for which the pavement will be used.
16. Horizontal Curves. A minimum sight distance with clear visibility, measured along the
centerline, shall be provided of at least three hundred feet (300) on major streets, two

CITY OF BROOKFIELD I-16 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

hundred feet (200) on secondary streets and one hundred twenty feet (120) on all other
streets.
17. Vertical Curves. All changes in street grades shall be connected by vertical curves of a
minimum length equivalent to thirty (30) times the algebraic difference in the rate of grade
for major streets and secondary streets and twenty (20) times this minimum length for all
other streets.
18. Tangents. A tangent of at least one hundred (100) feet long shall be introduced between
reverse curves on major and collector streets.

Material Specifications- Roadways & Pathways

Contact the City’s Engineering Division Roadway Engineer for Current Specifications.
262-787-3919

CITY OF BROOKFIELD I-17 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

E. GRADING ________________________________________________________

Design Standards

1. Use existing drainage channels wherever possible.


2. Grades shall be established to avoid erosion, flooding of structures or public infrastructure,
and nuisance ponding of water.
3. Plan View (The information under this heading shall be shown within the
boundaries of the development and a minimum of 200’ adjacent where necessitated by the
development.)- NOTE: A draft grading plan is required prior to Plan Commission
approvals for most projects (this requirement may be waived by the City Engineer on a
case by case basis). Items d, f, & g are not required for most draft grading plans.
a. Existing contour lines shall be shown in light or dashed lines with elevation shown in
light numbers.
b. Proposed contour lines where different from existing shall be shown in bold solid
lines with bold elevation numbers.
c. Proposed building elevations (yard grade at front entrance) shall be indicated at the
building setback line. For exposed or partially exposed basements – yard grade at
rear shall also be indicated on plans.
d. Proposed finished elevations to 0.1 of a foot at all lot corners, at setback line plus
twenty feet along lot lines, and other points deemed necessary should be shown.
e. Spot grades on pavement areas, walks, ditchlines, swales, berms, property corner
elevations.
f. Finished street centerline elevations shall be indicated at 100’ stations, all
intersections, cul-de-sacs and other changes in slope. (Stationing should match the
centerline stationing of the utility plans.)
g. Channel or swale flow-lines shall be indicated every 50’ within public land or
easement.
h. Existing and proposed storm sewer utilities, rims, inverts and sizes
i. Ponds, spillways and outlet elevations
j. Top and bottom of retaining wall elevations shown
k. Other information pertinent to grading shall be shown and labeled.
l. Drainage & other pertinent easements shall be shown on plans.
m. Any other information pertinent to grading, such as wetland limits, 100-year surface
water elevations, two foot above 100 yr floodplain within area shown or within 200’
adjacent shall be indicated on plans.
4. An as-built grading plan is required for all commercial and residential site development.
Refer to Section III for requirements.

CITY OF BROOKFIELD I-18 ENGINEERING DIVISION


SECTION I - DESIGN STANDARDS AND MATERIAL SPECIFICATIONS

F. EROSION CONTROL_______________________________________________

Design Standards

1. Provide best management practices for erosion control using Wisconsing Department of
Natural Resources (WDNR) Construction Site Erosion and Sediment Control Standards and
all other applicable WDNR requirements.
2. Plan shall represent adjacent site conditions for a minimum of 200’.
3. Erosion control plan should be overlaid on the site grading plan on a separate sheet.
4. A safe overland flow path is to be provided from all areas of the site to be captured in
accordance with the stormwater management plan during all phases of construction.
5. Plan View
a. Existing contour lines should be shown in light or dashed lines with elevation labels
(2’ max interval)
b. Proposed contour lines should be shown where different from existing in bold lines
with elevation labels (2’ max interval)
c. Topsoil stockpiles to be shown and circled with silt fence
d. Plan should include a construction phasing schedule
e. Plan should include the following note on the construction phasing schedule: All
exposed soil areas not disturbed for up to seven days must be immediately restored
with seed and mulch.
f. Temporary Erosion Control devices shown and labeled
 Inlet baskets
 Silt Fence
 Erosion bales
 Temporary ditch checks (straw bales, rolls, or silt fence)
 Temporary seeding and mulching
 Temporary settling basin
 Dewatering basin
 Gravel construction entrance / Stone tracking mat
g. Permanent Erosion Control devices shown and labeled
 Sod
 Rip Rap
 Permanent seeding and mulching
 Permanent sediment basin

CITY OF BROOKFIELD I-19 ENGINEERING DIVISION


Section II - Drafting Standards

Title Page
A. General II-2
B. Watermain II-3
C. Sanitary Sewer II-4
D. Storm Sewer and Stormwater Management Systems II-5
E. Roadways II-6
E. Grading & Erosion Control II-7_

Note: The City of Brookfield Plan Standards have been provided in an effort to assist with
public and private infrastructure design. This section was intended to provide general
guidance to the design engineer. The City of Brookfield Engineering Division reserves the
right to alter or add requirements through the review process. Specific questions not detailed
in the following sections should be directed to the City Engineering Division (262-787-3919).
II-1
SECTION II – DRAFTING STANDARDS

A. GENERAL_____________________________________________________
1. Plans shall be prepared on sheets measuring 34 inches across and 22 inches high, unless otherwise
specified under plan preparation standards.
2. Title blocks conforming to the City Standard shall be located in the lower right hand corner of the
plan view and readable from the 34 inch side of the sheet. Location of limits of improvement shall be
given by distance and direction from the centerline of the nearest cross street. (Title Block – City
Standard Plate No. BRK.019)
3. Seal and signature of the registered Professional Engineer who prepared the plans shall be affixed
immediately to the left of the title block.
4. Profile view shall be located below the plan view on plan-profile drawings, and the two views should
be in alignment vertically.
5. North direction shall be at the top or to the right of the sheet and indicated by an arrow and the letter
“N”.
6. Stationing shall be at 100’ intervals from South to North or West to East and shall be indicated on plan and
profile. The stationing will start at an even station and at a centerline intersection of two streets. Every
100’ station shall be noted.
7. Date of drawing and dates of all revisions shall be shown.
8. All plans shall read from the bottom (34 inch side) and the right side of the plan, unless the streets
shown enter the main street of the plan at an angle that dictates it to be read from the left.
9. All existing and proposed right-of-way and lot lines to be shown with a solid line; only future right-
of-way and lot lines to be shown dashed.
10. All proposed improvements shall be drawn with bold lines.
11. Plans shall be drafted with AutoCAD (most current version or as approved by City Engineer).
12. Plan View
a. Lot, block, street, property or subdivision, ¼ section and easement lines shall be shown.
b. Lot and block numbers, subdivision name and addresses, property owner name, tax key
numbers, shall be shown, if known.
c. If the plan is in an existing subdivision or in a street or easement through or adjacent to
unplatted lands, the property owners’ name, address, and tax key are to be shown. The
names, addresses, and tax keys can be obtained at the City Assessor’s office.
d. Lot or property frontage, street width and easement dimensions shall be indicated (existing
and proposed).
e. Street names shall be shown.
f. Street centerline shall be indicated.
13. Profile View
a. Elevations shall be based on the UGVD29 datum and given to the nearest 0.01 feet.
b. The benchmarks used shall be indicated on the plans.
c. To convert to UGVD29 datum from old City datum use 580.50.

II-2
SECTION II – DRAFTING STANDARDS

B. WATERMAIN____________________________________________________

1. Scale of plans shall be 1” = 50’ horizontal and 1” = 5’ vertical.


2. Water main system plan to be 200 scale only (drawing size not to exceed 22” x 34”).
3. Plan View
a. Pipe diameter, fitting center-to-center length, and lateral spacing shall be dimensioned.
b. Elevations of the center of hydrant nozzle shall be indicated.
c. Existing underground improvements shall be indicated and the size labeled.
d. Existing surface improvements shall be indicated with solid light lines and labeled.
e. Proposed underground improvements shall be indicated and the size labeled.
f. Existing and proposed pavement shall be shown and the name labeled.
4. Profile View
a. Draw pipe as two solid lines, indicating crown and flowline of pipe.
b. Flowline elevations shall be shown at fittings and breaks in grade.
c. Grades shall be indicated in percent slope, to the nearest 0.001%.
d. Pipe diameter and fitting center-to-center length shall be dimensioned.
e. Pipe type and class shown.
f. Fitting elevations must be labeled.
g. Crushed stone and spoil backfill limits shall be dimensioned and labeled.
h. Existing or proposed grade above water main shall be drawn and labeled.
i. Crossings with existing or proposed underground improvements shall be drawn with the name,
diameter, elevation, and station indicated.
j. Concrete cradles shall be drawn where storm sewer crosses above.

II-3
SECTION II – DRAFTING STANDARDS

C. SANITARY SEWER________________________________________________

1. Scale of plans shall be 1” = 50’ horizontal and 1’ = 5’ vertical.


2. Stationing shall begin at downstream manhole (when sanitary is the only utility on the plan and when
sanitary is in an easement.)
3. Sanitary system plan to be 100 scale or larger. Consultant must use the City system plans for
approval submittal (drawing size not to exceed 22” x 34”).
4. Plan View
a. Pipe diameter, manhole center-to-center length, and lateral spacing shall be dimensioned.
b. Existing underground improvements shall be indicated and the size labeled.
c. Existing surface improvements shall be indicated with solid light lines and labeled.
d. Proposed underground improvements shall be indicated and the size labeled.
e. Existing and proposed pavement shall be shown and the name labeled.
5. Profile View
a. Draw pipe as two solid lines, indicating crown and flowline of pipe.
b. Flowline elevations shall be shown at manholes.
c. Grades shall be indicated in percent slope, to the nearest 0.001%.
d. Pipe diameter, manhole center-to-center length and riser length shall be dimensioned.
e. Sewer pipe strength shall be labeled.
f. Elevations of manhole rim shall be indicated.
g. Crushed stone and spoil backfill limits shall be dimensioned and labeled.
h. Existing or proposed grade above sewer shall be drawn and labeled.
i. Crossings with existing or proposed underground improvements shall be drawn with the name,
diameter, elevation, and station indicated.

II-4
SECTION II – DRAFTING STANDARDS

D. STORM SEWER/STORMWATER MANAGEMENT____________________


1. Scale of plans shall be 1” = 40’ horizontal and 1” = 4’ vertical.
2. Storm system plan to be 200 scale or larger. (Drawing size not to exceed 22” x 34”)
3. Plan View
a. Pipe diameter, lengths, center-to-center of manholes, and/or inlets shall be dimensioned.
b. Existing underground improvements shall be indicated and the size labeled.
c. Existing surface improvements shall be indicated with solid light lines and labeled.
d. Proposed underground improvements shall be indicated and the size labeled.
e. Existing and proposed pavement shall be shown and the name labeled.
4. Profile View
a. Draw pipe as two solid lines, indicating crown and flowline of pipe.
b. Flowline elevations shall be shown at manholes and inlets.
c. Slope shall be indicated in percent slope, to the nearest 0.001%.
d. Pipe diameter and manhole center-to-center length shall be dimensioned.
e. Sewer pipe strength shall be labeled.
f. Elevations of manhole rim and inlet gutter shall be indicated.
g. Granular material backfill shall be dimensioned and labeled. Unlabeled sections shall require
excavated material.
h. Concrete cradles shall be required where other proposed utilities cross under storm sewers, when
minimum clearance can’t be maintained or when soil conditions dictate usage.
i. Crossings with existing or proposed underground improvements shall be drawn with the name,
diameter, elevations and station indicated.
j. Grade profiles shall be shown at proposed/existing centerlines and the proposed/existing grade
above the proposed utility.

II-5
SECTION II – DRAFTING STANDARDS

E. ROADWAYS____________________________________________________
1. Scale of plans shall be 1” = 40’ horizontal and 1” = 4’ vertical.
2. Plan View
a. Stations shall be indicated by tick marks along the centerline and every 100’ station shall be
labeled. Elevations shall also be given at intersections, PT, & PC.
b. Curb radii shall be dimensioned to the face of the curb – 25’ radius minimum. (Back of curb
radius 24.50’)
c. Flange lines and back-of-curb lines shall be drawn. (When proposed on the plan, these lines shall
be drawn bold. Proposed, future, and existing curbs shall be labeled as such.)
d. Flange elevations shall be indicated at all curved curb and gutter sections, cul-de-sacs and warped
pavement sections from beginning to end and not farther apart than 25’.
e. Grades shall be given in plus or minus to the nearest 0.001%.
f. Vertical curves must meet or exceed K values.
g. Existing underground improvements shall be indicated and the size labeled.
h. Proposed underground improvements shall be indicated and the size labeled.
3. Profile View
a. All stations shall coincide with accented vertical lines.
b. Proposed finished centerline grade shall be drawn as a heavy line, when built on plan.
c. Existing centerline grade.
d. Proposed elevations and stationing shall be given at each station, at intersections, street lines
extended and at ¼ points along vertical and horizontal curves (and the P.C., P.T. & P.I’s)
e. Grades shall be specified in plus or minus percent to the nearest 0.001%.

II-6
SECTION II – DRAFTING STANDARDS

F. GRADING & EROSION CONTROL__________________________________


1. The name of the landscape architect and/or professional engineer who prepared the plans shall be
shown.
2. Scale of the plans shall be 1” = 100’ for master plan and 1” = 50’ for individual plan sheets.
3. Plan View (The information under this heading shall be shown within the boundaries of the development and
a minimum of 200’ adjacent where necessitated by the development.)
a. Existing contour lines shall be shown in light or dashed lines with elevation shown in light
numbers.
b. Proposed contour lines where different from existing shall be shown in bold solid lines with bold
elevation numbers.
c. Proposed building elevations (yard grade at front entrance) shall be indicated at the building
setback line. For exposed or partially exposed basements – yard grade at rear shall also be
indicated on plans.
d. Finished street centerline elevations shall be indicated at 100’ stations, all intersections, cul-de-
sacs and other changes in slope. (Stationing should match the centerline stationing of the utility
plans.)
e. Channel or swale flow-lines shall be indicated every 50’ within public land or easement.
f. Other information pertinent to grading shall be shown and labeled.
g. Drainage easements shall be shown on plans.
h. 100-year surface water elevations within area shown shall be indicated on plans.

II-7
Section III – As-Built Standards

Title Page
A. Public Infrastructure III-2
B. Grading & Drainage III-3

Note: The City of Brookfield As-Built Plan Standards have been provided in an effort to assist
with As-built Preparation. This section was intended to provide general guidance to the design
engineer. The City of Brookfield Engineering Division reserves the right to alter or add
requirements through the review process. Specific questions not detailed in the following
sections should be directed to the City Engineering Division (262-787-3919).
III-1
SECTION III – AS-BUILT PLAN STANDARDS

A. PUBLIC INFRASTRUCTURE _______________________________________

1. Developer to supply City of Brookfield with as-builts complying with the City of Brookfield
Municipal Code.
2. Provide in draft form for review. Upon approval, paper copies and digital format (Current version of
AutoCAD or as approved by the City Engineering Division) shall be submitted.
3. Valve cards shall also be provided for all main line and hydrant valves. See example in index. Blank
cards may be obtained from the Engineering Division.
4. For the City of Brookfield as-builts, the consultant may use the construction plan but only as-built the
plan view. The following must be shown in addition to what is shown on the construction plan:
a. In title block: date as-built, contractor’s name, inspector’s name, as-built by _________, and year
installed.
b. For sanitary: rim and inverts for every manhole, distances between manholes and laterals, laterals
to laterals, plus overall distance manhole to manhole with slope.
c. For sanitary: Size of sewers shown bold. Lateral lengths with elevation or depths – measured or
calculated and stated so, at property line or end of lateral. In large bold letters and numbers in the
upper left-hand corner of drawing, list size of sewer, material used and note showing laterals have
inspection tees (ref: as-built of ___ PVC, ASTM, DR sanitary sewer)
d. For water main: distances between all fittings, all fittings called out, size of watermain shown
bold. Ties from fixed points (i.e.: manholes, building corners, etc.) to lateral connection at main
line should be shown and easy to find. In upper left-hand corner in large bold letters and numbers,
list size of water main, and material used. (ref: as-built of ___ PVC, AWWA, C-900, DR 18)
e. For storm sewer: rim and inverts for every manhole, distances between manholes and laterals,
laterals to laterals, plus overall distance manhole to manhole with slope. Size of sewers shown
bold. Lateral lengths with elevation or depths – measured or calculated and stated so, at property
line or end of lateral. In large bold letters and numbers in the upper left-hand corner of drawing,
list size of sewer, material used (ref: as-built of ___ RCP, storm sewer)
5. For sanitary as-builts for the Milwaukee Metropolitan Sewerage District – As-built plans must
comply with MMSD Standards.
6. As-built quantity boxes should be updated from the plan quantities to reflect the final quantities.
7. All references to “proposed” on as-builts shall be removed.
8. Private mains shall be inspected, documented and as-built drawings provided to the City in
accordance with the requirements listed above.

III-2
SECTION III – AS-BUILT PLAN STANDARDS

B. GRADING & DRAINAGE _______________________________________

1. Developer may use the construction plan. The following must be shown in addition to what is shown
on the construction plan.
a. Must be stamped by an R.L.S. or P.E. and signed.
b. As-built spot grades and 1 foot or 2 foot contours shall be shown in bold.
c. Date of survey data collection should be given.
d. Proposed spot grades and 1 foot or 2 foot contours shall be shown in light or dashed lines.
e. As-built building and pavement elevations.
f. For storm sewer and stormwater management structures: as-built rim and invert grades (including
outlet control structures), pipe lengths, sizes, etc.
g. All retention, detention, and swales shall be shown in detail.
h. All other features deemed pertinent such as modified floodplain or sensitive grading required per
the plans shall be shown.
i. City may require more information if spot grades do not allow for proper review or field visit
shows potential issues.

III-3
Section IV - Appendix

Title ________
Standard Details (30 sheets, 29 details)
Stormwater Management Application Packet (10 sheets)
Example Design Sheets-Sanitary Sewer & Water Main (2 sheets)
Example As-builts-Sanitary Sewer, Water Main, & Storm Sewer (3 sheets)
Example As-builts- Commercial & Residential Grading (2 sheets)
Example Easement Exhibit (1 sheet)____________________

Note: The City of Brookfield Engineering Division reserves the right to alter standards or add
requirements through the review process. Specific questions not detailed in the following
sections should be directed to the City Engineering Division (262-782-9650).
IV-1