Estimate for concrete work of M15 (1:2:4)

L
(i) Estimating Work Volume
Length, L = 0.8 m B
Width, B = 0.8 m
Height, H = 0.8 m
H

Volume of Work, V = 0.512 m3

(ii) Estimation of Materials

Dry Work Volume = 0.768 m3

Cement = 157.99 Kg
= 3.16 Bag

Sand = 0.15 m3
= 5.17 cft

Aggregate = 0.29 m3
= 10.33 cft

(iii) Cost of Materials (with stone chips)

Item Quantity Unit Unit Rate Total (tk.)


Cement 3.16 Bag 490 1548.29
Sand 5.17 cft 45 232.47
Stone 10.33 cft 160 1653.13
Total = 3433.89

(iv) Cost of Materials (with brick chips)

Item Quantity Unit Unit Rate Total (tk.)


Cement 3.16 Bag 490 1548.29
Sand 5.17 cft 45 232.47
Stone 10.33 cft 85 878.23
Total = 2658.99

(v) Total Cost Calculation


with stone with brick
1. Material Cost = 3433.89 2658.99
2. Labor Cost (1 Mason, 2 Helper) = 1700.00 1700.00
3. Overhead Cost (3%) = 154.02 130.77
4. Equipment and tools (2%) = 102.68 87.18
5. Profit (10%) = 513.39 435.90
Unit Rate/Item = 5903.97 5012.83