You are on page 1of 9

STEEL STRUCTURE CERTIFICATE

PROJECT NAME : MARTABE MILLING CAPACITY EXPANTION PROJECT


PROJECT NO. : 104036-03
CLIENT : PT Agincourt Resources
TEST PACKAGE NO. : EMK - A1 - WFI - TP001
LOCATION : VERT MILL AREA

STEEL STUCTURE G/A NO. : 1929 - 0220 - G - 101 - B

DRAWING NO. : 104036 - 0220 - S - 100

ASSEMBLY DRAWING NO. : 220 - PRB - E01 220 - PRS - E01 220 - PRS - E011

220 - PRB - E02 220 - PRS - E02 220 - PRS - E012

220 - PRB - E03 220 - PRS - E03 220 - PRS - E013

220 - PRB - E04 220 - PRS - E04 220 - PRS - E014

220 - PRS - E05 220 - PRS - E015

220 - PRS - E06 220 - PRS - E016

220 - PRS - E07 220 - PRS - E017

220 - PRS - E08 220 - PRS - E018

220 - PRS - E09 220 - PRS - E019

220 - PRS - E010 220 - PRS - E020

220 - PRS - E021

ALL INSTALLATION OF THE ABOVE STEEL STRUCTURE " PRIMARY REGIND AREA BUILDING AREA " HAS BEEN
COMPLETED INSTALLED SATISFACTORY IN ACCORDANCE WITH THE CLIENT SPECIFICATION

PREPARED BY, CHECKED BY REVIEWED BY,


PT. EMK PT. EMK PTAR

Name : Name : Name :


Date : Date : Date :
WELDING INSPECTION REPORT

Client : PT Agincourt Resources Report No. :

Contract : PT.EMK Date :

Ptoject No : MILLING CAPACITY EXPANSION PROJECT Sheet :

Material Desciption Consumable Welder Stamp Inspection NDT Requirement


Joint
No. Line No. SHT REV Spool First Item Second Item Joint WPS No. Welding Remarks
No. Type Proses Fill/ Fill/ Fit up Welding Visual
Root Root RT UT MT/PT
Dia Cap Cap Date Date Result
Type Heat No. SCH Type Heat No. Dia SCH
(mm) (mm)

10

Prepared By : Witnessed/Examination By : Reviewd By :


LEDENDS : FW = Field Weld EMK EMK PTAR
SW = Shop Weld
THD = Threaded

Name : Name : Name :


Date : Date : Date :
STEEL STRUCTURE FINAL CHECKLIST

PROJECT NAME : MARTABE MILLING CAPACITY EXPANTION PROJECT


PROJECT NO. : 104036-03
CLIENT : PT Agincourt Resources
CONTRACTOR : PT.EMK
INSTALL PACKAGE NO. : PRIMARY REGRIND AREA BUILDING STRUCTURE
LOCATION : VERT MILL AREA

No. In Process Inspection / Activity YES N/A

1 Base plates at correct elevation

2 Base plates at correct NS & EW location

3 Coloum hold down nuts and washer in place and toque

4 Coloumns plumb in all directiobs

5 Horizontal steel framing at correct elevation

6 Bolted connections properly torqued using correct material

7 Plate washers provided to cover long slotted holes as required

8 weld completed weldment acceptable

9 Post weld heat treatment complete and acceptable

10 Nondestructive examination complete and acceptable

11 Vertical and horizontal bracing complete and properly bolted

12 Exterior siding supports instaaled correcly

13 Temporary supports and bracket rermove from structure

14 Miscellaneous steel ( Ladder, Platform,etc ) properly installed

15 Grouting Completed

16 Coatings touched up as required

STEEL STRUCTURE PRIMARY REGRIND AREA HAS BEEN COMPLETED INSTALLATION SATISFACTORY IN
ACCORDANCE WITH, ISOMETRIC DRAWING AND THE CLIENT SPECIFICATION

PREPARED BY, CHECKED BY REVIEWED BY,


PT. EMK PT. EMK PTAR

Name : Name : Name :


Date : Date : Date :
Punch List
PROJECT : MARTABE MILLING CAPACITY EXPANTION PROJECT Area : PRIMARY REGRIND AREA BUILDING STRUCTURE
Client : PT.Agincourt Resources Sheet :
Contractor : PT.EMK
Date :

Sign Off
Item Punch List Before After Discipline Action By Category Priority Close Date Remark
Conractor Client

Discipline Category Priority


C : Civil A : Prior to discipline handover 1 : Effect for Hidrotest
Legends :

S : Structure B : Prior to practical completion 2 : Not Effect for Hidrotest


M : Mechanical C : Prior to C1 Pre-commissioning
P : Piping D1 : Prior to C2 Dry Commissioning
E : Electrical D2 : Prior to C3 Dry Commissioning
D3 : Prior to C4 Dry Commissioning

Prepared Perfomed By Witnesed/Inspected By Approved By


PT.EMK PT.EMK PT.AR

Name : Name : Name :


Date : Date : Date :
EMK
PT. EPITERMA MAS KONSTRUKSI

DYE PENETRANT TESTING REPORT

Client : Report No. :


Contract No : Sheet : of
Location : Date of INSP :

Subject : Surface Preparation


Item No. : As Welded As Cast
Line/Dwg No. : As Rolled Grinding
Material : As Forged Machining
Temp :
Stage of Examination
Criteria : Before/After PWHT
After Hydrotest

Technique : Color Contrast Fluerescent


Solvent Removel Other/

Product Manufacturer Dwel Time


Penetrant : Minutes
Developer : Minutes
Cleaner :

Penetrant Application
Spraying Black light intensity : µw/cm2
Brushing Light Intensity : Lux
Other/ Light meter S/N :

Part Of IND. Size (mm) Result Welder IND. Size (mm) Result
Weld Welder Stamp No Part Of Weld Stamp No
Liner Rounded ACC REJ Liner Rounded ACC REJ

PT EMK PTAR

Name : Name :
Date : Date :
MILLING CAPACITY EXPANSION PROJECT

EMK Client
Contract
:
:
Report No.
Date
:
:
Ptoject : Sheet :

Material Desciption Welder Stamp Consumable Inspection NDT Requirement


Joint
First Item Second Item Welding
No. Line No. SHT REV Spool Joint Type WPS No. Fit up Welding Visual Remarks
No. Proses Root Fill/Cap Root Fill/Cap RT UT MT/PT
Type Heat No. Dia (mm) SCH Type Heat No. Dia (mm) SCH Date Date Result

2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31

LEDENDS : BW = Butt Weld FW = Fillet Weld THD = Threaded SW = Shop Weld

Prepared By : Witnessed/Examination By : Reviewd By :


LEDENDS : BW = Butt Weld FW = Fillet Weld
EMK EMK PTAR

Name : Name : Name :


Date : Date : Date :

You might also like