Professional Documents
Culture Documents
Storage Tank Hydrotest Procedure
Storage Tank Hydrotest Procedure
SINOPEC INTERNATIONAL
PETROLEUM SERVICE
لواقملا
CONTRACTOR CORPORATION
LOCATION: TITLE:
3 2 5 - Q D 6 0 - F -
SUBCONTRACTOR:
Sheet 1of16
KINGDOM OF SAUDI ARABIA Page: 2 of 16
Saline Water Conversion Corporation
YANBU-MADINAH PHASE 3 WATER TRANSMISSION SYSTEM
HYDROSTATIC TEST PROCEDURE Spec. No. QC10-H-049 M09
Subject:
FOR STORAGE TANK ILF CONSULTING ENGINEERS
IndexRevision
TABLE OFCONTENTS
1 SCOPE ............................................................................................................................................. 3
2 PURPOSE ........................................................................................................................................ 3
3 REFERENCES ................................................................................................................................. 3
4 DEFINITIONS ................................................................................................................................... 3
5 ABBREVIATIONS ............................................................................................................................ 4
6 RESPONSIBILITIES ........................................................................................................................ 4
7 GENERAL ........................................................................................................................................ 5
8 VACUUM TEST................................................................................................................................ 6
9 HYDROSTATIC PRESSURE TEST ................................................................................................ 8
10 AIR TEST ....................................................................................................................................... 12
11 SAFETY PRECAUTIONS .............................................................................................................. 15
1 SCOPE
This Procedure specifies the requirements of Hydrostatic Test, Vacuum Test and Air
Test for Aboveground Water Storage Tank in the PROJECT OF YANBU-MADINAH
PHASE 3 WATER TRANSMISSION SYSTEM for SALINE WATER CONVERSION
CORPORATION (SWCC).
2 PURPOSE
This Procedure describes the equipment and materials to be used and factors to be
considered during the Pressure Test of Storage Tank, and ensure that this procedure
shall be done in accordance with the Project Specifications and related Standards
and Codes.
3 REFERENCES
API Standard 650 Welded Steel Tanks for Oil Storage
QC10-H-049 M09 Steel Tanks - Rev4
ASME Section VIII, Division 1 Boiler and Pressure Vessel Code
EN 10204 Metallic Products – Types of Inspection Documents
4 DEFINITIONS
Employer Saline Water Conversion Corporation (SWCC)
Engineer ILF Consulting Engineers
Contractor Sinopec International Petroleum Service Corporation (SIPSC)
Project YANBU-MADINA PHASE 3 WATER TRANSMISSION SYSTEM
5 ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ANSI American National Standard Institute
ASTM American Society for Testing and Materials
EN European Standards IFC
Issue For Construction QC Manager
Quality Control Manager QC Engineer
Quality Control Engineer
6 RESPONSIBILITIES
6.1 QA/QC Engineer / Inspector
Shall be responsible to witness the test and judge the suitability of work
carried out.
Responsible to make calculations, prepare documents and layout
systems of work.
Assessing the suitability of the method, medium and test pressure
requested given the design of the item submitted for testing.
Produce written instructions for the supervisor and technicians relating to
the procedures, equipment and personnel to be employed in the test.
6.2 Construction Supervisor
Shall be responsible for organizing the test as per this procedure and
approved ITP and shall also be responsible for maintaining the records
duly signed by all concerns.
Responsible to ensure that the technicians working under his supervision
Shall communicate with his management, client and other contractors.
Shall ensure method statements, risk assessments and permit to work
requirements are communicated to the technicians and other personnel.
7 GENERAL
7.1 After the completion of all welding works and non-destructive examinations of
bottom plate welds, shell plate welds, roof plate welds and reinforced plate
welds of the tank
7.2 The tank shall be pressure tested for the identifications of leakage. This
pressure shall be carried out as per the approved drawing, approved ITP and
standard API 650.
7.3 This test will divide into following mentioned stages:
Test preliminaries such as Visual Inspection.
Inspection of Tank Bottom Welds (Vacuum Box Testing).
Testing of the Shell Course and Tank Bottom Settlement (Hydrostatic-
Testing).
Inspection of Roof-Plate and Reinforcing Plates (Air Testing).
7.4 Ensure that all of the mentioned test must perform after controlling all of the
N.D.T. test reports.
7.5 Vacuum test is carried out to find any leakage in the bottom plate by the use
the vacuum box testing equipment.
7.6 Hydrostatic test is conducted to find any leakage in the shell plate weld and to
check the elevation of the tank bottom settlement. Potable water shall be used
to fill the tank.
7.7 Air test is conducted to check the gas tight of roof and reinforced plates of shell
openings of the tank.
8 VACUUM TEST
The Vacuum box test is conducted to check soundness of annular welded joints and
all lap joints of bottom plates (long seam and short seam).
8.1 Equipment and Material
The vacuum box test is performed by using a box with visible window of
fiber glass (i.e. 6’’ Wide by 30’’ long metallic box with a fiber glass). The
open bottom is sealed against the tank surface by a sponge rubber
gasket.
The test scheme shall have suitable connections, such as necessary
valves and calibrated vacuum gauge.
The gauge shall have a range of 21Kpa (6 in. Hg) to 35Kpa (10 in. Hg)
for normal leaks and 56Kpa (16 in. Hg) to 70Kpa (20 in. Hg) shall
be performed for the detection of very small leaks.
The test scheme shall be demonstrated with sample test block by
application bubble solution at site before conduction of the test on the
job.
The bubble forming solution shall produce a film that does not break
away from the area to be tested, and the bubbles formed shall not break
rapidly due to air drying or low surface tension.
A vacuum can be drawn on the box by any convenient method, such as
connection to a diesel motor intake manifold or special vacuum pump.
8.2 Surface Preparation
The surface to be examined and all adjacent areas shall be cleaned
thoroughly and free from all dirt, grease, lint, scale, welding flux, weld
spatters, paint, oil and other extraneous matter that could obstruct
surface openings.
Prior to vacuum testing all joints shall be checked visually.
8.3 Procedure of Vacuum Test
The temperature of the surface of the part to be examined shall not below
0 0 0 0
4 C (40 F) and nor above 52 C (125 F).
The weld seam on the test shall be applied with a bubble solution for
detecting leaks prior to placing vacuum box.
The foaming shall be minimized by means of uniform application of
bubble solution.
A vacuum can be drawn on the box by any convenient method, such as
connection to a gasoline- or diesel motor intake manifold.
The gauge shall register a partial vacuum of at least 21Kpa for inspection
of the joints.
The required partial vacuum shall be maintained for greater or either at
least 5 seconds examination time, stop watch to be used after reaching
the 21Kpa /designation vacuum.
8.4 Evaluation of Defects
Bubbles produced by air sucked through the welded seam can detect the
presence of defect.
The tested areas are accepted only when no continuous bubbles
formation is observed.
A minimum light intensity of 100Lux is required for conducting the
examination.
Upon satisfactory inspection, a report shall be prepared for the further
activities.
8.5 Repair and Retest
Defects in welds shall be repaired by chipping, grinding or melting out the
defects from one side or both sides of the joints as required and
re-welding are done.
Only the cutting out of defective joints that is necessary to correct the
defect is required.
After repairing, retest of vacuum box test of welded joint shall be carried
out.
8.6 Cleaning
After test the area shall be thoroughly cleaned for the further activities
9 HYDROSTATIC TEST
Hydrostatic test is conducted to carry out the leakage in the shell plates and also to
carry out elevation measurement of the bottom foundation of tank by using tank
foundation settlement method.
9.1 General Consideration
The water for hydro test will be provided by SWCC, the initial filling of the
first and second will come from this pipe system source.
After the first tank is tested, the water will be transferred to the second
tank. After the second tank is tested, the water will be transferred to the
third and fourth tank for Testing.
Contractor will furnish the pipe and pumps required to move the water
from tank to tank.
After the completion of the hydro testing operations for the first and fourth
tank, contractor will dispose of the water on site at the designated point.
9.2 Preparation of Hydrostatic Test
After the completion of all welding works and non-destructive
examination of tank and all welded joints shall be signed off by QC
welding inspector prior to commencement of the hydrostatic test.
Temporary test gaskets shall be used for all fittings and manholes.
The hydrostatic test of tank shall be conducted before permanent
external piping is connected to the tank.
Cleaning inside the tank and removal of temporary jigs and tools shall be
completed.
All shell openings shall be closed by block valves or by appropriate cover
plates.
Roof manholes shall be opened while introducing water into the tank or
drawing off water.
Initial tank level readings shall be taken using 16 equally spaced points
marked on the bottom plate projecting out from the bottom shell around
the tank at its base.
Filling shall be done in four stages 25%, 50%, 75% and 100%. After each
stage a load stabilization period shall be observed.
As water rises in the tank, observe the shell fittings for any signs of
leakage around the blind flanges.
Continue filling the tank until the water level reaches the quarter point of
the tank height. At this point discontinue filling while the level readings
are taken on the 16 points as described in above (9.1- Item no.7) and
readings are recorded.
At least 24 hours after the tank has been filled to the maximum test
height. This period may be increased in accordance to the
requirement of the project specification.
10 AIR TEST
Air test is carried out to check the gas tight of the roof plate and reinforced plate of
shell openings of the tank.
10.1 Equipment and Material
Pressure Gauge or Manometer
Blank/Blind Flange with Safety Relief Valve
Soapsuds
Air Supply System
11 SAFETY PRECAUTIONS
11.1 The safety measures shall be implemented during testing activities and the
contractor shall provide the necessary safety equipment, communication
equipment, access barriers etc.
11.2 Contractor shall issue a statement to all persons connected with testing,
warning of the hazards of failure under pressure.
There is a possibility that workers can take remedial action once minor
leakages are noticed before total failure occurs.
11.3 Hydrostatic tests are conducted under the constraints of projects
specifications.
11.4 Air/gas used for Air test is compressible to large extent and has very high
potential energy stored when compressed.
11.5 Ensure that no any worker shall present inside the tank prior to pressure
test.
11.6 Use and storage of any compressed gas under high pressure can be
extremely dangerous if proper gas handling procedures are not observed.
11.7 Where the test system is testing using pressurization above its normal
working level, it follows that the tester should be prepared for the
consequences of failure.
11.8 This means that there may need to be protective barriers or screens, but all
such precautions will be specifically dedicated to the risk involved in the
test.
11.9 The technician must be conscious at all times of the potential for a rise in
temperature to significantly increase pressure.
11.10 Safety officer must be present at site during test.
11.11 Tested & certified Lifting equipment shall be used for lifting and shifting
purpose.
11.12 Safety Precautions shall be followed during fabrication and erection as per
project specification.
11.13 Welding cables and power cables to be laid properly as per Instrumentation
and Electrical rules and local state govt. rules and regulation.
Engineering Subcontractor EPC Contractor Subcontractor