1. EXCVATION WORK
1.01. Site clearing, grubing and removing trees,
bushes and so on… 1 12.50
around demessie site 4.10
1 29.50 7.10
3.50 363.88 m3
103.25 m2
around asheber site
1 19.00 1 10.00
4.10 3.50
77.90 m2 4.87
170.45 m3
181.15 m2 Total

1.02. Excavation of ordinary earth materials 1 19.00


irrespective of depth and soil type. 4.10
around demessie site 5.10
397.29 m3
1 15.00
3.50 1,281.27 m3
5.97
313.43 m3
around asheber site

1 12.50
4.10 2 27.50
7.10 2.30
363.88 m3 126.50 m2

677.30 m3 Total
Ditto but soft rock or soft material not classified
as hard material or ordinary soil irrespective of 2 15.00
depth 2.30
around demessie site 0.225
L = 11.5m 15.53 m3
1 14.50 W = 4.10m
4.10 Davg. = 5.97m 2 15.00
5.97 0.35
354.92 m3 0.10
around asheber site 1.05 m3
L = 6.5m
1 6.50 W = 3.50m 2 15.00
3.50 Davg. = 7.10m 0.60
7.10 0.04
161.53 m3 0.72 m3

516.44 m3 Total 1.0 15.00


1.35
1.05. Cart away the excavated unsuitable 0.10
materials as per engineer order 2.03 m3
From site clearing
around demessie site 1.0 15.00
0.60
1 29.50 0.06
3.50 0.54 m3
0.20
20.65 m3
around asheber site
1 15.00
1 19.00 0.225
4.10 3.675
0.20 12.40 m3
15.58 m3
0.5 15.00
From Ordinary excavation 0.125
around demessie site 3.675
3.45 m3
1 15.00
3.50 35.71 m3
5.97
313.43 m3
PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................
Page 2 of 8

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................


Page 3 of 8

For retaining wall


around demessie site 1 15.00
0.23
2 15.00 3.38 m2
3.70
111.00 m2 1 15.00
0.27
2 0.28 3.98 m2
3.70
2.07 m2 4 2.30
0.27
122.92 m2 Total 2.50 m2

5. REINFORCEMENT
5.01. STEEL BAR required for
Total Steel reinforcement
structure.
a. High yield steel reinforcement bar
2,991.62 kg

2.99 ton Total

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................


Page 4 of 8

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................


Page 5 of 8

around asheber site

Around demessie site due to land slide


noted on site book

Around asheber site due to land slide


noted on site book

Total

2. CONCRETE WORK
2.01. C-5 lean concrete under retaining wall
around demessie site

Total

2.02. C-30 Reinforced Concrete.


For footing pad

For retaining wall


around demessie site
L = 12m
W1 = (0.35+0.225) = 0.29m
Davg. = 3.7m

L = 24m
W3 = 0.6m
Davg. = (0.265+0.325)/2 = 0.3m

Total

2.03. Form work for concrete casting


PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................
Page 6 of 8
For footing pad

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................


Page 7 of 8
around demessie site

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................


Page 8 of 8

PRPERED BY.......................... CHECKED BY....................... APPROVED BY...................