You are on page 1of 89

Project: ETAP Page: 1

12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Electrical Transient Analyzer Program

Short-Circuit Analysis

IEC 60909 Standard


3-Phase, LG, LL, & LLG Fault Currents

Swing V-Control Load Total


Number of Buses:  2  0  71  73

XFMR2 XFMR3 Reactor Line/Cable Impedance Tie PD Total


Number of Branches:  2  0  0  66  0  3  71

Synchronous Power Synchronous Induction Lumped


Generator Grid Motor Machines Load
Total
Number of Machines:  0  2  0  0  0  2

System Frequency: 60.00 Hz

Unit System: Metric

Project Filename: EP17009 SC AND RC STUDY

Output Filename: D:\PEE APPLICATION\EP17009\MCSET\7 Doc Sub\8 EP17009 SC AND RC STUDY REV03\01
ETAP\sc minimum.SI2
Project: ETAP Page: 2
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

Cable Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: No

Cable Resistance: Yes Global  75


Project: ETAP Page: 3
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Bus Input Data

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

Bus1 SWNG  13.800  13.800  1  100.00  0.00

Bus2 Load  13.800  13.800  1  100.00  0.00

Bus3 SWNG  13.800  13.800  2  100.00  0.00

Bus4 Load  13.800  13.800  2  100.00  0.00

Bus5 Load  13.800  13.800  1  100.00  0.00

Bus6 Load  13.800  13.800  1  100.00  0.00

Bus7 Load  13.800  13.800  1  100.00  0.00

Bus8 Load  13.800  13.800  1  100.00  0.00

Bus9 Load  13.800  13.800  1  100.00  0.00

Bus10 Load  0.400  0.400  1  100.00 -30.00

Bus11 Load  13.800  13.800  2  100.00  0.00

Bus12 Load  0.400  0.400  2  100.00 -30.00

Bus13 Load  13.800  13.800  2  100.00  0.00

Bus14 Load  13.800  13.800  2  100.00  0.00

Bus15 Load  13.800  13.800  2  100.00  0.00

Bus16 Load  13.800  13.800  2  100.00  0.00

Bus21 Load  0.400  0.400  1  100.00 -30.00

Bus22 Load  0.400  0.400  1  100.00 -30.00

Bus24 Load  0.400  0.400  1  100.00 -30.00

Bus25 Load  0.400  0.400  1  100.00 -30.00

Bus26 Load  0.400  0.400  1  100.00 -30.00

Bus27 Load  0.400  0.400  1  100.00 -30.00

Bus29 Load  0.400  0.400  1  100.00 -30.00

Bus30 Load  0.400  0.400  1  100.00 -30.00

Bus31 Load  0.400  0.400  1  100.00 -30.00

Bus32 Load  0.400  0.400  1  100.00 -30.00

Bus33 Load  0.400  0.400  1  100.00 -30.00

Bus34 Load  0.400  0.400  1  100.00 -30.00

Bus35 Load  0.400  0.400  1  100.00 -30.00

Bus36 Load  0.400  0.400  1  100.00 -30.00

Bus37 Load  0.400  0.400  1  100.00 -30.00

Bus38 Load  0.400  0.400  1  100.00 -30.00

Bus39 Load  0.400  0.400  1  100.00 -30.00

Bus40 Load  0.400  0.400  1  100.00 -30.00

Bus41 Load  0.400  0.400  1  100.00 -30.00


Project: ETAP Page: 4
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

Bus42 Load  0.400  0.400  1  100.00 -30.00

Bus43 Load  0.400  0.400  2  100.00 -30.00

Bus45 Load  0.400  0.400  2  100.00 -30.00

Bus46 Load  0.400  0.400  2  100.00 -30.00

Bus47 Load  0.400  0.400  2  100.00 -30.00

Bus48 Load  0.400  0.400  2  100.00 -30.00

Bus49 Load  0.400  0.400  2  100.00 -30.00

Bus50 Load  0.400  0.400  2  100.00 -30.00

Bus51 Load  0.400  0.400  2  100.00 -30.00

Bus53 Load  0.400  0.400  2  100.00 -30.00

Bus54 Load  0.400  0.400  2  100.00 -30.00

Bus55 Load  0.400  0.400  2  100.00 -30.00

Bus56 Load  0.400  0.400  2  100.00 -30.00

Bus57 Load  0.400  0.400  2  100.00 -30.00

Bus58 Load  0.400  0.400  2  100.00 -30.00

Bus59 Load  0.400  0.400  2  100.00 -30.00

Bus60 Load  0.400  0.400  2  100.00 -30.00

Bus61 Load  0.400  0.400  1  100.00 -30.00

Bus63 Load  0.400  0.400  1  100.00 -30.00

Bus64 Load  0.400  0.400  1  100.00 -30.00

Bus65 Load  0.400  0.400  1  100.00 -30.00

Bus66 Load  0.400  0.400  1  100.00 -30.00

Bus67 Load  0.400  0.400  1  100.00 -30.00

Bus68 Load  0.400  0.400  1  100.00 -30.00

Bus69 Load  0.400  0.400  1  100.00 -30.00

Bus70 Load  0.400  0.400  2  100.00 -30.00

Bus72 Load  0.400  0.400  2  100.00 -30.00

Bus73 Load  0.400  0.400  2  100.00 -30.00

Bus74 Load  0.400  0.400  2  100.00 -30.00

Bus75 Load  0.400  0.400  2  100.00 -30.00

Bus76 Load  0.400  0.400  2  100.00 -30.00

Bus77 Load  0.400  0.400  2  100.00 -30.00

Bus78 Load  0.400  0.400  2  100.00 -30.00

Main Bus A1 Load  0.400  0.400  1  1.00 -30.00

Main Bus A2 Load  0.400  0.400  2  1.00 -30.00

Main Bus B1 Load  0.400  0.400  1  1.00 -30.00

Main Bus B2 Load  0.400  0.400  2  1.00 -30.00


Project: ETAP Page: 5
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

Main Bus C Load  0.400  0.400  1  1.00 -30.00

73 Buses Total

All voltages reported by ETAP are in % of bus Nominal kV.


Base kV values of buses are calculated and used internally by ETAP.
Project: ETAP Page: 6
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Line/Cable Input Data

Ohms or Siemens per 1000 m per Conductor (Cable) or per Phase (Line)
Line/Cable Length

ID Library Size Adj. (m) % Tol. #/Phase T (°C) R1 X1 Y1 R0 X0 Y0

Cable A1 1.0MCUN4 120  23.0  0.0  1  75  0.1869399  0.073  0.0001499  0.5888607  0.17958

Cable A2 1.0MCUN4 240  19.0  0.0  1  75  0.0925162  0.072  0.0001565  0.291426  0.17712

Cable A3 1.0MCUN4 50  23.0  0.0  1  75  0.4711649  0.079  0.0001188  1.484169  0.19434

Cable A4 1.0MCUN4 95  26.0  0.0  1  75  0.2355824  0.073  0.0001433  0.7420847  0.17958

Cable A5 1.0MCUN3 70  139.0  0.0  1  75  0.3261911  0.075  0.0001307  1.027502  0.1845

Cable A6 1.0MCUN3 120  138.0  0.0  1  75  0.1869399  0.073  0.0001499  0.5888607  0.17958

Cable A7 1.0MCUN4 35  21.0  0.0  1  75  0.6380755  0.08  0.0001015  2.009985  0.1968

Cable A8 1.0MCUN2 2.5  138.0  0.0  1  75  9.003636  0.1188  0.0000588  28.36145  0.292248

Cable A10 1.0MCUN4 120  19.0  0.0  1  75  0.1869399  0.073  0.0001499  0.5888607  0.17958

Cable A11 1.0MCUN4 240  23.0  0.0  1  75  0.0925162  0.072  0.0001565  0.291426  0.17712

Cable A12 1.0MCUN4 50  27.0  0.0  1  75  0.4711649  0.079  0.0001188  1.484169  0.19434

Cable A13 1.0MCUN4 35  19.0  0.0  1  75  0.6380755  0.08  0.0001015  2.009985  0.1968

Cable A14 1.0MCUN4 95  30.0  0.0  1  75  0.2355824  0.073  0.0001433  0.7420847  0.17958

Cable A15 1.0MCUN3 70  131.0  0.0  1  75  0.3261911  0.075  0.0001307  1.027502  0.1845

Cable A16 1.0MCUN3 120  131.0  0.0  1  75  0.1869399  0.073  0.0001499  0.5888607  0.17958

Cable A18 1.0MCUN2 2.5  131.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B1 1.0MCUN3 2.5  139.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B2 1.0MCUN3 2.5  140.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B3 1.0MCUN3 2.5  141.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B4 1.0MCUN3 2.5  140.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B5 1.0MCUN3 2.5  144.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B6 1.0MCUN3 2.5  145.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B7 1.0MCUN3 2.5  149.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B8 1.0MCUN3 2.5  144.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B9 1.0MCUN3 2.5  145.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B10 1.0MCUN3 2.5  147.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B11 1.0MCUN3 2.5  148.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B12 1.0MCUN3 2.5  99.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B13 1.0MCUN4 10  182.0  0.0  1  75  2.222296  0.084  0.0000807  7.000232  0.20664

Cable B14 1.0MCUN4 16  26.0  0.0  1  75  1.392512  0.08  0.0000971  4.386411  0.1968

Cable B16 1.0MCUN3 35  180.0  0.0  1  75  0.6380755  0.08  0.0001015  2.009938  0.1968

Cable B20 1.0MCUN3 2.5  144.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B21 1.0MCUN3 2.5  146.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354
Project: ETAP Page: 7
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Ohms or Siemens per 1000 m per Conductor (Cable) or per Phase (Line)
Line/Cable Length

ID Library Size Adj. (m) % Tol. #/Phase T (°C) R1 X1 Y1 R0 X0 Y0

Cable B22 1.0MCUN3 2.5  146.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B23 1.0MCUN3 2.5  145.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B24 1.0MCUN3 2.5  147.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B25 1.0MCUN3 2.5  149.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B26 1.0MCUN3 2.5  152.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B27 1.0MCUN3 2.5  148.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B28 1.0MCUN3 2.5  149.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B29 1.0MCUN3 2.5  151.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B30 1.0MCUN3 2.5  152.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B31 1.0MCUN3 2.5  102.0  0.0  1  75  9.003636  0.099  0.000049  28.36145  0.24354

Cable B32 1.0MCUN4 10  185.0  0.0  1  75  2.222296  0.084  0.0000807  7.000232  0.20664

Cable B33 1.0MCUN4 16  29.0  0.0  1  75  1.392512  0.08  0.0000971  4.386411  0.1968

Cable B37 1.0MCUN4 25  185.0  0.0  1  75  0.8841494  0.082  0.0000889  2.785119  0.20172

Cable B38 1.0MCUN4 10  170.0  0.0  1  75  2.222296  0.084  0.0000807  7.000232  0.20664

Cable C1 1.0MCUN4 95  130.0  0.0  1  75  0.2355824  0.073  0.0001433  0.7420847  0.17958

Cable C2 1.0MCUN4 120  159.0  0.0  1  75  0.1869399  0.073  0.0001499  0.5888607  0.17958

Cable C3 1.0MCUN4 10  19.0  0.0  1  75  2.222296  0.084  0.0000807  7.000232  0.20664

Cable C4 1.0MCUN4 70  19.0  0.0  1  75  0.3261911  0.075  0.0001307  1.027502  0.1845

Cable C5 1.0MCUN4 70  19.0  0.0  1  75  0.3261911  0.075  0.0001307  1.027502  0.1845

Cable1-INC CAB 15NCUS1 240  390.0  0.0  1  75  0.09347  0.1356  0.1486172  0.344424

Cable2 15NCUS1 240  415.0  0.0  1  75  0.09347  0.1356  0.1486172  0.344424

Cable3 15NCUS3 120  178.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable4 15NCUS3 120  190.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable5 15NCUS3 120  144.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable6 15NCUS3 120  185.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable7-TRF HV CAB 15NCUS3 120  42.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable8-TRF LV CAB 1.0MCUN1 630  33.0  0.0  1  75  0.0400586  0.1032  0.0002428  0.1261844  0.253872

Cable9 1.0MCUN1 630  29.0  0.0  1  75  0.0400586  0.1032  0.0002428  0.1261844  0.253872

Cable10 15NCUS3 120  32.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable11 15NCUS3 120  178.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable12 15NCUS3 120  125.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable13 15NCUS3 120  186.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Cable14 15NCUS3 120  158.0  0.0  1  75  0.1869399  0.119  0.2972344  0.30226

Line / Cable resistances are listed at the specified temperatures.


Project: ETAP Page: 8
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted Phase Shift


ID MVA Prim. kV Sec. kV %Z X/R + 5% - 5% % Tol. Prim. Sec. %Z Type Angle

T1  1.000  13.800  0.400  6.00  3.50  0    0    0   0     0     6.0000 Dyn  30.000

T2  1.000  13.800  0.400  6.00  3.50  0    0    0   0     0     6.0000 Dyn  30.000

2-Winding Transformer Grounding Input Data

Grounding

Transformer Rating Conn. Primary Secondary


ID MVA Prim. kV Sec. kV Type Type kV Amp Ohm Type kV Amp Ohm

T1  1.000  13.800  0.400 D/Y Solid

T2  1.000  13.800  0.400 D/Y Solid


Project: ETAP Page: 9
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVAb


ID Type From Bus To Bus R X Z Y

T1 2W XFMR Bus9 Bus10  158.92  556.22  578.48

T2 2W XFMR Bus11 Bus12  158.92  556.22  578.48

Cable3 Cable Bus2 Bus5  1.75  1.11  2.07

Cable4 Cable Bus2 Bus6  1.87  1.19  2.21

Cable5 Cable Bus2 Bus7  1.41  0.90  1.68

Cable6 Cable Bus2 Bus8  1.82  1.16  2.15

Cable7-TRF HV CAB Cable Bus2 Bus9  0.41  0.26  0.49

Cable8-TRF LV CAB Cable Bus10 Main Bus A1  82.62  212.85  228.32  0.0000013

Cable9 Cable Bus12 Main Bus A2  72.61  187.05  200.65  0.0000011

Cable10 Cable Bus4 Bus11  0.31  0.20  0.37

Cable11 Cable Bus4 Bus13  1.75  1.11  2.07

Cable12 Cable Bus4 Bus14  1.23  0.78  1.45

Cable13 Cable Bus4 Bus15  1.83  1.16  2.16

Cable14 Cable Bus4 Bus16  1.55  0.99  1.84

Cable A1 Cable Main Bus A1 Bus61  268.73  104.94  288.49  0.0000006

Cable A2 Cable Main Bus A1 Bus63  109.86  85.50  139.21  0.0000005

Cable A3 Cable Main Bus A1 Bus64  677.30  113.56  686.75  0.0000004

Cable A4 Cable Main Bus A1 Bus65  382.82  118.63  400.78  0.0000006

Cable A5 Cable Main Bus A1 Bus66  2833.79  651.56  2907.73  0.0000029

Cable A6 Cable Main Bus A1 Bus67  1612.36  629.63  1730.93  0.0000033

Cable A7 Cable Main Bus A1 Bus68  837.47  105.00  844.03  0.0000003

Cable A8 Cable Main Bus A1 Bus69  77656.36  1024.65  77663.12  0.0000013

Cable A10 Cable Main Bus A2 Bus77  221.99  86.69  238.32  0.0000005

Cable A11 Cable Main Bus A2 Bus78  132.99  103.50  168.52  0.0000006

Cable A12 Cable Main Bus A2 Bus70  795.09  133.31  806.19  0.0000005

Cable A13 Cable Main Bus A2 Bus72  757.71  95.00  763.65  0.0000003

Cable A14 Cable Main Bus A2 Bus73  441.72  136.88  462.44  0.0000007

Cable A15 Cable Main Bus A2 Bus74  2670.69  614.06  2740.38  0.0000027

Cable A16 Cable Main Bus A2 Bus75  1530.57  597.69  1643.13  0.0000031

Cable A18 Cable Main Bus A2 Bus76  73717.27  810.56  73721.73  0.0000010

Cable B1 Cable Main Bus B1 Bus27  78219.09  860.06  78223.82  0.0000011

Cable B2 Cable Main Bus B1 Bus29  78781.81  866.25  78786.58  0.0000011

Cable B3 Cable Main Bus B1 Bus30  79344.55  872.44  79349.34  0.0000011

Cable B4 Cable Main Bus B1 Bus31  78781.81  866.25  78786.58  0.0000011

Cable B5 Cable Main Bus B1 Bus32  81032.73  891.00  81037.63  0.0000011

Cable B6 Cable Main Bus B1 Bus33  81595.45  897.19  81600.38  0.0000011

Cable B7 Cable Main Bus B1 Bus34  83846.36  921.94  83851.43  0.0000012


Project: ETAP Page: 10
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVAb


ID Type From Bus To Bus R X Z Y

Cable B8 Cable Main Bus B1 Bus35  81032.73  891.00  81037.63  0.0000011

Cable B9 Cable Main Bus B1 Bus36  81595.45  897.19  81600.38  0.0000011

Cable B10 Cable Main Bus B1 Bus37  82720.91  909.56  82725.91  0.0000012

Cable B11 Cable Main Bus B1 Bus38  83283.63  915.75  83288.67  0.0000012

Cable B12 Cable Main Bus B1 Bus39  55710.00  612.56  55713.37  0.0000008
Cable B13 Cable Main Bus B1 Bus40  25278.61  955.50  25296.67  0.0000023

Cable B14 Cable Main Bus B1 Bus41  2262.83  130.00  2266.56  0.0000004

Cable B16 Cable Main Bus B1 Bus42  7178.35  900.00  7234.55  0.0000029

Cable B20 Cable Main Bus B2 Bus43  81032.73  891.00  81037.63  0.0000011

Cable B21 Cable Main Bus B2 Bus45  82158.18  903.37  82163.15  0.0000011

Cable B22 Cable Main Bus B2 Bus46  82158.18  903.37  82163.15  0.0000011

Cable B23 Cable Main Bus B2 Bus47  81595.45  897.19  81600.38  0.0000011

Cable B24 Cable Main Bus B2 Bus48  82720.91  909.56  82725.91  0.0000012

Cable B25 Cable Main Bus B2 Bus49  83846.36  921.94  83851.43  0.0000012

Cable B26 Cable Main Bus B2 Bus50  85534.54  940.50  85539.71  0.0000012

Cable B27 Cable Main Bus B2 Bus51  83283.63  915.75  83288.67  0.0000012

Cable B28 Cable Main Bus B2 Bus53  83846.36  921.94  83851.43  0.0000012

Cable B29 Cable Main Bus B2 Bus54  84971.81  934.31  84976.95  0.0000012

Cable B30 Cable Main Bus B2 Bus55  85534.54  940.50  85539.71  0.0000012

Cable B31 Cable Main Bus B2 Bus56  57398.18  631.13  57401.65  0.0000008

Cable B32 Cable Main Bus B2 Bus57  25695.29  971.25  25713.64  0.0000024

Cable B33 Cable Main Bus B2 Bus58  2523.93  145.00  2528.09  0.0000005

Cable B37 Cable Main Bus B2 Bus59  10222.98  948.13  10266.85  0.0000026

Cable B38 Cable Main Bus B2 Bus60  23611.89  892.50  23628.75  0.0000022

Cable C1 Cable Main Bus C Bus21  1914.11  593.13  2003.90  0.0000030

Cable C2 Cable Main Bus C Bus22  1857.72  725.44  1994.33  0.0000038

Cable C3 Cable Main Bus C Bus24  2638.98  99.75  2640.86  0.0000002

Cable C4 Cable Main Bus C Bus25  387.35  89.06  397.46  0.0000004

Cable C5 Cable Main Bus C Bus26  387.35  89.06  397.46  0.0000004

Cable1-INC CAB Cable Bus1 Bus2  1.91  2.78  3.37

Cable2 Cable Bus3 Bus4  2.04  2.95  3.59

QM2A - MED MCC INCOMER-1 Tie Breakr Bus61 Main Bus B1

QM2B Tie Breakr Bus77 Main Bus B2

QM3A - GEN DB INCOMER Tie Breakr Bus63 Main Bus C


Project: ETAP Page: 11
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Power Grid Input Data

% Impedance
Power Grid Connected Bus Rating 100 MVA Base Grounding
ID ID MVASC kV R X" R/X" Type

U1 Bus1  500.000  13.800  0.66630  19.98890  0.03 Wye - Solid


U2 Bus3  500.000  13.800  0.66630  19.98890  0.03 Wye - Solid

Total Connected Power Grids ( = 2 ): 1000.000 MVA


Project: ETAP Page: 12
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

SHORT- CIRCUIT REPORT

Fault at bus: Bus1


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus1 Total  0.00  20.918  0.00  100.00  100.00  20.918  20.918 6.66E-001 2.00E+001 6.66E-001 2.00E+001

Bus2 Bus1  0.00  0.000  0.00  100.00  100.00  0.000  0.000

U1 Bus1  100.00  20.918  100.00  100.00  100.00  20.918  20.918 6.66E-001 2.00E+001 6.66E-001 2.00E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  20.918  20.918  18.116  20.918
Peak Current (kA), Method C :  56.408  56.408  48.850  56.408
Breaking Current (kA, rms, symm) :  20.918  18.116  20.918
Steady State Current (kA, rms) :  20.918  20.918  18.116  20.918

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 13
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus2


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus2 Total  0.00  18.260  0.00  102.44  103.82  17.166  17.166 2.58E+000 2.28E+001 3.71E+000 2.70E+001

Bus1 Bus2  14.72  18.260  19.64  100.00  100.00  17.166  17.166 2.58E+000 2.28E+001 3.71E+000 2.70E+001

Bus5 Bus2  0.00  0.000  0.00  102.44  103.82  0.000  0.000

Bus6 Bus2  0.00  0.000  0.00  102.44  103.82  0.000  0.000

Bus7 Bus2  0.00  0.000  0.00  102.44  103.82  0.000  0.000

Bus8 Bus2  0.00  0.000  0.00  102.44  103.82  0.000  0.000

Bus9 Bus2  0.00  0.000  0.00  102.44  103.82  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  18.260  17.166  15.814  17.885
Peak Current (kA), Method C :  44.352  41.696  38.410  43.442
Breaking Current (kA, rms, symm) :  17.166  15.814  17.885
Steady State Current (kA, rms) :  18.260  17.166  15.814  17.885

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 14
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus3


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus3 Total  0.00  20.918  0.00  100.00  100.00  20.918  20.918 6.66E-001 2.00E+001 6.66E-001 2.00E+001

Bus4 Bus3  0.00  0.000  0.00  100.00  100.00  0.000  0.000

U2 Bus3  100.00  20.918  100.00  100.00  100.00  20.918  20.918 6.66E-001 2.00E+001 6.66E-001 2.00E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  20.918  20.918  18.116  20.918
Peak Current (kA), Method C :  56.408  56.408  48.850  56.408
Breaking Current (kA, rms, symm) :  20.918  18.116  20.918
Steady State Current (kA, rms) :  20.918  20.918  18.116  20.918

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 15
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus4


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus4 Total  0.00  18.109  0.00  102.60  104.00  16.968  16.968 2.70E+000 2.29E+001 3.90E+000 2.75E+001

Bus3 Bus4  15.53  18.109  20.66  100.00  100.00  16.968  16.968 2.70E+000 2.29E+001 3.90E+000 2.75E+001

Bus11 Bus4  0.00  0.000  0.00  102.60  104.00  0.000  0.000

Bus13 Bus4  0.00  0.000  0.00  102.60  104.00  0.000  0.000

Bus14 Bus4  0.00  0.000  0.00  102.60  104.00  0.000  0.000

Bus15 Bus4  0.00  0.000  0.00  102.60  104.00  0.000  0.000

Bus16 Bus4  0.00  0.000  0.00  102.60  104.00  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  18.109  16.968  15.683  17.716
Peak Current (kA), Method C :  43.748  40.990  37.887  42.798
Breaking Current (kA, rms, symm) :  16.968  15.683  17.716
Steady State Current (kA, rms) :  18.109  16.968  15.683  17.716

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 16
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus5


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus5 Total  0.00  17.240  0.00  103.19  105.23  15.870  15.870 4.33E+000 2.39E+001 6.49E+000 2.99E+001

Bus2 Bus5  8.54  17.240  10.18  102.60  103.21  15.870  15.870 4.33E+000 2.39E+001 6.49E+000 2.99E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.240  15.870  14.930  16.804
Peak Current (kA), Method C :  38.741  35.662  33.551  37.761
Breaking Current (kA, rms, symm) :  15.870  14.930  16.804
Steady State Current (kA, rms) :  17.240  15.870  14.930  16.804

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 17
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus6


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus6 Total  0.00  17.173  0.00  103.24  105.31  15.787  15.787 4.45E+000 2.40E+001 6.68E+000 3.01E+001

Bus2 Bus6  9.08  17.173  10.81  102.60  103.18  15.787  15.787 4.45E+000 2.40E+001 6.68E+000 3.01E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.173  15.787  14.872  16.732
Peak Current (kA), Method C :  38.411  35.311  33.265  37.425
Breaking Current (kA, rms, symm) :  15.787  14.872  16.732
Steady State Current (kA, rms) :  17.173  15.787  14.872  16.732

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 18
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus7


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus7 Total  0.00  17.432  0.00  103.03  104.99  16.108  16.108 3.99E+000 2.37E+001 5.96E+000 2.93E+001

Bus2 Bus7  6.98  17.432  8.36  102.57  103.32  16.108  16.108 3.99E+000 2.37E+001 5.96E+000 2.93E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.432  16.108  15.096  17.008
Peak Current (kA), Method C :  39.707  36.692  34.387  38.742
Breaking Current (kA, rms, symm) :  16.108  15.096  17.008
Steady State Current (kA, rms) :  17.432  16.108  15.096  17.008

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 19
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus8


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus8 Total  0.00  17.201  0.00  103.22  105.28  15.821  15.821 4.40E+000 2.39E+001 6.60E+000 3.00E+001

Bus2 Bus8  8.85  17.201  10.55  102.60  103.19  15.821  15.821 4.40E+000 2.39E+001 6.60E+000 3.00E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.201  15.821  14.896  16.762
Peak Current (kA), Method C :  38.548  35.456  33.383  37.564
Breaking Current (kA, rms, symm) :  15.821  14.896  16.762
Steady State Current (kA, rms) :  17.201  15.821  14.896  16.762

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 20
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus9


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus9 Total  0.00  18.016  0.00  102.60  104.19  16.850  16.850 2.99E+000 2.30E+001 4.37E+000 2.77E+001

Bus2 Bus9  2.10  18.016  2.55  102.48  103.67  16.850  16.850 2.99E+000 2.30E+001 4.37E+000 2.77E+001

Bus10 Bus9  0.00  0.000  60.15  59.23  100.00  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  18.016  16.850  15.602  17.628
Peak Current (kA), Method C :  42.896  40.119  37.149  41.972
Breaking Current (kA, rms, symm) :  16.850  15.602  17.628
Steady State Current (kA, rms) :  18.016  16.850  15.602  17.628

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 21
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus10


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus10 Total  0.00  22.798  0.00  99.20  99.53  23.092  23.092 1.62E+002 5.79E+002 1.59E+002 5.56E+002

Main Bus A1 Bus10  0.00  0.000  0.00  99.20  99.53  0.000  0.000

Bus9 Bus10  96.18  22.798  97.91  100.00  98.24  23.092  23.092 * 1.62E+002 5.79E+002 1.59E+002 5.56E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  22.798  23.092  19.744  22.987
Peak Current (kA), Method C :  46.547  47.147  40.311  46.931
Breaking Current (kA, rms, symm) :  23.092  19.744  22.987
Steady State Current (kA, rms) :  22.798  23.092  19.744  22.987

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 22
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus11


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus11 Total  0.00  17.925  0.00  102.72  104.28  16.730  16.730 3.02E+000 2.31E+001 4.40E+000 2.80E+001

Bus4 Bus11  1.60  17.925  1.93  102.63  103.88  16.730  16.730 3.02E+000 2.31E+001 4.40E+000 2.80E+001

Bus12 Bus11  0.00  0.000  60.20  59.31  100.00  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.925  16.730  15.524  17.522
Peak Current (kA), Method C :  42.659  39.815  36.944  41.699
Breaking Current (kA, rms, symm) :  16.730  15.524  17.522
Steady State Current (kA, rms) :  17.925  16.730  15.524  17.522

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 23
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus12


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus12 Total  0.00  22.794  0.00  99.19  99.52  23.089  23.089 1.62E+002 5.79E+002 1.59E+002 5.56E+002

Main Bus A2 Bus12  0.00  0.000  0.00  99.19  99.52  0.000  0.000

Bus11 Bus12  96.16  22.794  97.90  100.00  98.23  23.089  23.089 * 1.62E+002 5.79E+002 1.59E+002 5.56E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  22.794  23.089  19.740  22.983
Peak Current (kA), Method C :  46.538  47.142  40.303  46.924
Breaking Current (kA, rms, symm) :  23.089  19.740  22.983
Steady State Current (kA, rms) :  22.794  23.089  19.740  22.983

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 24
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus13


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus13 Total  0.00  17.101  0.00  103.35  105.36  15.696  15.696 4.45E+000 2.41E+001 6.68E+000 3.03E+001

Bus4 Bus13  8.47  17.101  10.07  102.76  103.37  15.696  15.696 4.45E+000 2.41E+001 6.68E+000 3.03E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.101  15.696  14.810  16.648
Peak Current (kA), Method C :  38.274  35.129  33.147  37.260
Breaking Current (kA, rms, symm) :  15.696  14.810  16.648
Steady State Current (kA, rms) :  17.101  15.696  14.810  16.648

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 25
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus14


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus14 Total  0.00  17.397  0.00  103.11  105.00  16.062  16.062 3.93E+000 2.37E+001 5.86E+000 2.95E+001

Bus4 Bus14  6.05  17.397  7.24  102.72  103.55  16.062  16.062 3.93E+000 2.37E+001 5.86E+000 2.95E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.397  16.062  15.066  16.963
Peak Current (kA), Method C :  39.764  36.712  34.436  38.771
Breaking Current (kA, rms, symm) :  16.062  15.066  16.963
Steady State Current (kA, rms) :  17.397  16.062  15.066  16.963

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 26
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus15


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus15 Total  0.00  17.057  0.00  103.39  105.42  15.641  15.641 4.53E+000 2.41E+001 6.81E+000 3.04E+001

Bus4 Bus15  8.82  17.057  10.49  102.76  103.34  15.641  15.641 4.53E+000 2.41E+001 6.81E+000 3.04E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.057  15.641  14.772  16.601
Peak Current (kA), Method C :  38.059  34.900  32.960  37.041
Breaking Current (kA, rms, symm) :  15.641  14.772  16.601
Steady State Current (kA, rms) :  17.057  15.641  14.772  16.601

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 27
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus16


Nominal kV =  13.800
Voltage c Factor = 1.00 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus16 Total  0.00  17.212  0.00  103.26  105.23  15.833  15.833 4.25E+000 2.39E+001 6.37E+000 3.00E+001

Bus4 Bus16  7.56  17.212  9.02  102.74  103.44  15.833  15.833 4.25E+000 2.39E+001 6.37E+000 3.00E+001

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.212  15.833  14.906  16.766
Peak Current (kA), Method C :  38.824  35.712  33.622  37.818
Breaking Current (kA, rms, symm) :  15.833  14.906  16.766
Steady State Current (kA, rms) :  17.212  15.833  14.906  16.766

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 28
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus21


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus21 Total  0.00  5.072  0.00  117.49  127.40  3.244  3.244 2.27E+003 1.47E+003 6.79E+003 2.75E+003

Main Bus C Bus21  74.12  5.072  80.49  103.48  101.02  3.244  3.244 2.27E+003 1.47E+003 6.79E+003 2.75E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  5.072  3.244  4.392  4.730
Peak Current (kA), Method C :  7.385  4.724  6.396  6.888
Breaking Current (kA, rms, symm) :  3.244  4.392  4.730
Steady State Current (kA, rms) :  5.072  3.244  4.392  4.730

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 29
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus22


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus22 Total  0.00  5.019  0.00  117.04  127.08  3.238  3.238 2.21E+003 1.60E+003 6.62E+003 3.07E+003

Main Bus C Bus22  73.00  5.019  79.51  103.32  101.25  3.238  3.238 2.21E+003 1.60E+003 6.62E+003 3.07E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  5.019  3.238  4.347  4.688
Peak Current (kA), Method C :  7.351  4.743  6.366  6.866
Breaking Current (kA, rms, symm) :  3.238  4.347  4.688
Steady State Current (kA, rms) :  5.019  3.238  4.347  4.688

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 30
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus24


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus24 Total  0.00  4.355  0.00  120.61  128.08  2.660  2.660 2.99E+003 9.77E+002 9.08E+003 1.54E+003

Main Bus C Bus24  83.87  4.355  87.93  103.34  99.93  2.660  2.660 2.99E+003 9.77E+002 9.08E+003 1.54E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  4.355  2.660  3.771  4.005
Peak Current (kA), Method C :  6.282  3.838  5.440  5.778
Breaking Current (kA, rms, symm) :  2.660  3.771  4.005
Steady State Current (kA, rms) :  4.355  2.660  3.771  4.005

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 31
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus25


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus25 Total  0.00  11.254  0.00  107.79  122.88  8.417  8.417 7.42E+002 9.67E+002 1.99E+003 1.51E+003

Main Bus C Bus25  32.62  11.254  41.62  106.51  106.40  8.417  8.417 7.42E+002 9.67E+002 1.99E+003 1.51E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  11.254  8.417  9.746  10.950
Peak Current (kA), Method C :  17.794  13.309  15.410  17.314
Breaking Current (kA, rms, symm) :  8.417  9.746  10.950
Steady State Current (kA, rms) :  11.254  8.417  9.746  10.950

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 32
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus26


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus26 Total  0.00  11.254  0.00  107.79  122.88  8.417  8.417 7.42E+002 9.67E+002 1.99E+003 1.51E+003

Main Bus C Bus26  32.62  11.254  41.62  106.51  106.40  8.417  8.417 7.42E+002 9.67E+002 1.99E+003 1.51E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  11.254  8.417  9.746  10.950
Peak Current (kA), Method C :  17.794  13.309  15.410  17.314
Breaking Current (kA, rms, symm) :  8.417  9.746  10.950
Steady State Current (kA, rms) :  11.254  8.417  9.746  10.950

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 33
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus27


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus27 Total  0.00  0.174  0.00  125.92  126.33  0.102  0.102 7.87E+004 1.76E+003 2.48E+005 3.45E+003

Main Bus B1 Bus27  99.33  0.174  99.42  100.19  100.00  0.102  0.102 7.87E+004 1.76E+003 2.48E+005 3.45E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.174  0.102  0.151  0.155
Peak Current (kA), Method C :  0.251  0.146  0.218  0.224
Breaking Current (kA, rms, symm) :  0.102  0.151  0.155
Steady State Current (kA, rms) :  0.174  0.102  0.151  0.155

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 34
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus29


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus29 Total  0.00  0.173  0.00  125.92  126.33  0.101  0.101 7.93E+004 1.76E+003 2.49E+005 3.47E+003

Main Bus B1 Bus29  99.33  0.173  99.43  100.18  100.00  0.101  0.101 7.93E+004 1.76E+003 2.49E+005 3.47E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.173  0.101  0.150  0.154
Peak Current (kA), Method C :  0.249  0.145  0.216  0.222
Breaking Current (kA, rms, symm) :  0.101  0.150  0.154
Steady State Current (kA, rms) :  0.173  0.101  0.150  0.154

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 35
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus30


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus30 Total  0.00  0.172  0.00  125.92  126.33  0.100  0.100 7.99E+004 1.77E+003 2.51E+005 3.48E+003

Main Bus B1 Bus30  99.34  0.172  99.43  100.18  100.00  0.100  0.100 7.99E+004 1.77E+003 2.51E+005 3.48E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.172  0.100  0.149  0.153
Peak Current (kA), Method C :  0.248  0.144  0.214  0.221
Breaking Current (kA, rms, symm) :  0.100  0.149  0.153
Steady State Current (kA, rms) :  0.172  0.100  0.149  0.153

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 36
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus31


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus31 Total  0.00  0.173  0.00  125.92  126.33  0.101  0.101 7.93E+004 1.76E+003 2.49E+005 3.47E+003

Main Bus B1 Bus31  99.33  0.173  99.43  100.18  100.00  0.101  0.101 7.93E+004 1.76E+003 2.49E+005 3.47E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.173  0.101  0.150  0.154
Peak Current (kA), Method C :  0.249  0.145  0.216  0.222
Breaking Current (kA, rms, symm) :  0.101  0.150  0.154
Steady State Current (kA, rms) :  0.173  0.101  0.150  0.154

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 37
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus32


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus32 Total  0.00  0.168  0.00  125.93  126.33  0.098  0.098 8.15E+004 1.79E+003 2.57E+005 3.53E+003

Main Bus B1 Bus32  99.35  0.168  99.44  100.18  100.00  0.098  0.098 8.15E+004 1.79E+003 2.57E+005 3.53E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.168  0.098  0.146  0.150
Peak Current (kA), Method C :  0.242  0.141  0.210  0.216
Breaking Current (kA, rms, symm) :  0.098  0.146  0.150
Steady State Current (kA, rms) :  0.168  0.098  0.146  0.150

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 38
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus33


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus33 Total  0.00  0.167  0.00  125.93  126.33  0.097  0.097 8.21E+004 1.79E+003 2.58E+005 3.55E+003

Main Bus B1 Bus33  99.36  0.167  99.45  100.18  100.00  0.097  0.097 8.21E+004 1.79E+003 2.58E+005 3.55E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.167  0.097  0.145  0.149
Peak Current (kA), Method C :  0.241  0.140  0.209  0.215
Breaking Current (kA, rms, symm) :  0.097  0.145  0.149
Steady State Current (kA, rms) :  0.167  0.097  0.145  0.149

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 39
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus34


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus34 Total  0.00  0.163  0.00  125.93  126.32  0.095  0.095 8.44E+004 1.82E+003 2.65E+005 3.61E+003

Main Bus B1 Bus34  99.37  0.163  99.46  100.17  100.00  0.095  0.095 8.44E+004 1.82E+003 2.65E+005 3.61E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.163  0.095  0.141  0.145
Peak Current (kA), Method C :  0.234  0.137  0.203  0.209
Breaking Current (kA, rms, symm) :  0.095  0.141  0.145
Steady State Current (kA, rms) :  0.163  0.095  0.141  0.145

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 40
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus35


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus35 Total  0.00  0.168  0.00  125.93  126.33  0.098  0.098 8.15E+004 1.79E+003 2.57E+005 3.53E+003

Main Bus B1 Bus35  99.35  0.168  99.44  100.18  100.00  0.098  0.098 8.15E+004 1.79E+003 2.57E+005 3.53E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.168  0.098  0.146  0.150
Peak Current (kA), Method C :  0.242  0.141  0.210  0.216
Breaking Current (kA, rms, symm) :  0.098  0.146  0.150
Steady State Current (kA, rms) :  0.168  0.098  0.146  0.150

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 41
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus36


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus36 Total  0.00  0.167  0.00  125.93  126.33  0.097  0.097 8.21E+004 1.79E+003 2.58E+005 3.55E+003

Main Bus B1 Bus36  99.36  0.167  99.45  100.18  100.00  0.097  0.097 8.21E+004 1.79E+003 2.58E+005 3.55E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.167  0.097  0.145  0.149
Peak Current (kA), Method C :  0.241  0.140  0.209  0.215
Breaking Current (kA, rms, symm) :  0.097  0.145  0.149
Steady State Current (kA, rms) :  0.167  0.097  0.145  0.149

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 42
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus37


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus37 Total  0.00  0.165  0.00  125.93  126.32  0.096  0.096 8.32E+004 1.81E+003 2.62E+005 3.58E+003

Main Bus B1 Bus37  99.37  0.165  99.46  100.18  100.00  0.096  0.096 8.32E+004 1.81E+003 2.62E+005 3.58E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.165  0.096  0.143  0.147
Peak Current (kA), Method C :  0.238  0.139  0.206  0.212
Breaking Current (kA, rms, symm) :  0.096  0.143  0.147
Steady State Current (kA, rms) :  0.165  0.096  0.143  0.147

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 43
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus38


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus38 Total  0.00  0.164  0.00  125.93  126.32  0.095  0.095 8.38E+004 1.81E+003 2.64E+005 3.59E+003

Main Bus B1 Bus38  99.37  0.164  99.46  100.17  100.00  0.095  0.095 8.38E+004 1.81E+003 2.64E+005 3.59E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.164  0.095  0.142  0.146
Peak Current (kA), Method C :  0.236  0.138  0.204  0.210
Breaking Current (kA, rms, symm) :  0.095  0.142  0.146
Steady State Current (kA, rms) :  0.164  0.095  0.142  0.146

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 44
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus39


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus39 Total  0.00  0.244  0.00  125.85  126.37  0.142  0.142 5.62E+004 1.51E+003 1.77E+005 2.84E+003

Main Bus B1 Bus39  99.06  0.244  99.19  100.26  100.00  0.142  0.142 5.62E+004 1.51E+003 1.77E+005 2.84E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.244  0.142  0.211  0.217
Peak Current (kA), Method C :  0.352  0.205  0.305  0.314
Breaking Current (kA, rms, symm) :  0.142  0.211  0.217
Steady State Current (kA, rms) :  0.244  0.142  0.211  0.217

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 45
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus40


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus40 Total  0.00  0.530  0.00  125.38  126.66  0.310  0.310 2.58E+004 1.85E+003 8.09E+004 3.69E+003

Main Bus B1 Bus40  97.83  0.530  98.17  100.55  100.03  0.310  0.310 2.58E+004 1.85E+003 8.09E+004 3.69E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.530  0.310  0.459  0.475
Peak Current (kA), Method C :  0.765  0.447  0.662  0.684
Breaking Current (kA, rms, symm) :  0.310  0.459  0.475
Steady State Current (kA, rms) :  0.530  0.310  0.459  0.475

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 46
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus41


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus41 Total  0.00  4.632  0.00  120.02  128.11  2.850  2.850 2.78E+003 1.03E+003 8.39E+003 1.66E+003

Main Bus B1 Bus41  76.57  4.632  80.85  104.39  101.68  2.850  2.850 2.78E+003 1.03E+003 8.39E+003 1.66E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  4.632  2.850  4.012  4.274
Peak Current (kA), Method C :  6.684  4.113  5.789  6.167
Breaking Current (kA, rms, symm) :  2.850  4.012  4.274
Steady State Current (kA, rms) :  4.632  2.850  4.012  4.274

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 47
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus42


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus42 Total  0.00  1.736  0.00  123.39  127.45  1.031  1.031 7.69E+003 1.80E+003 2.39E+004 3.55E+003

Main Bus B1 Bus42  91.59  1.736  93.18  101.69  100.40  1.031  1.031 7.69E+003 1.80E+003 2.39E+004 3.55E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  1.736  1.031  1.503  1.572
Peak Current (kA), Method C :  2.504  1.487  2.169  2.268
Breaking Current (kA, rms, symm) :  1.031  1.503  1.572
Steady State Current (kA, rms) :  1.736  1.031  1.503  1.572

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 48
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus43


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus43 Total  0.00  0.168  0.00  125.93  126.32  0.098  0.098 8.15E+004 1.74E+003 2.56E+005 3.42E+003

Main Bus B2 Bus43  99.42  0.168  99.51  100.15  100.00  0.098  0.098 8.15E+004 1.74E+003 2.56E+005 3.42E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.168  0.098  0.146  0.150
Peak Current (kA), Method C :  0.243  0.141  0.210  0.216
Breaking Current (kA, rms, symm) :  0.098  0.146  0.150
Steady State Current (kA, rms) :  0.168  0.098  0.146  0.150

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 49
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus45


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus45 Total  0.00  0.166  0.00  125.93  126.32  0.097  0.097 8.26E+004 1.76E+003 2.60E+005 3.45E+003

Main Bus B2 Bus45  99.43  0.166  99.52  100.15  100.00  0.097  0.097 8.26E+004 1.76E+003 2.60E+005 3.45E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.166  0.097  0.144  0.148
Peak Current (kA), Method C :  0.239  0.140  0.207  0.213
Breaking Current (kA, rms, symm) :  0.097  0.144  0.148
Steady State Current (kA, rms) :  0.166  0.097  0.144  0.148

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 50
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus46


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus46 Total  0.00  0.166  0.00  125.93  126.32  0.097  0.097 8.26E+004 1.76E+003 2.60E+005 3.45E+003

Main Bus B2 Bus46  99.43  0.166  99.52  100.15  100.00  0.097  0.097 8.26E+004 1.76E+003 2.60E+005 3.45E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.166  0.097  0.144  0.148
Peak Current (kA), Method C :  0.239  0.140  0.207  0.213
Breaking Current (kA, rms, symm) :  0.097  0.144  0.148
Steady State Current (kA, rms) :  0.166  0.097  0.144  0.148

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 51
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus47


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus47 Total  0.00  0.167  0.00  125.93  126.32  0.097  0.097 8.21E+004 1.75E+003 2.58E+005 3.44E+003

Main Bus B2 Bus47  99.43  0.167  99.52  100.15  100.00  0.097  0.097 8.21E+004 1.75E+003 2.58E+005 3.44E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.167  0.097  0.145  0.149
Peak Current (kA), Method C :  0.241  0.141  0.209  0.215
Breaking Current (kA, rms, symm) :  0.097  0.145  0.149
Steady State Current (kA, rms) :  0.167  0.097  0.145  0.149

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 52
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus48


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus48 Total  0.00  0.165  0.00  125.93  126.32  0.096  0.096 8.32E+004 1.76E+003 2.62E+005 3.47E+003

Main Bus B2 Bus48  99.43  0.165  99.52  100.15  100.00  0.096  0.096 8.32E+004 1.76E+003 2.62E+005 3.47E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.165  0.096  0.143  0.147
Peak Current (kA), Method C :  0.238  0.139  0.206  0.212
Breaking Current (kA, rms, symm) :  0.096  0.143  0.147
Steady State Current (kA, rms) :  0.165  0.096  0.143  0.147

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 53
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus49


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus49 Total  0.00  0.163  0.00  125.94  126.32  0.095  0.095 8.43E+004 1.78E+003 2.65E+005 3.50E+003

Main Bus B2 Bus49  99.44  0.163  99.53  100.15  100.00  0.095  0.095 8.43E+004 1.78E+003 2.65E+005 3.50E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.163  0.095  0.141  0.145
Peak Current (kA), Method C :  0.235  0.137  0.203  0.209
Breaking Current (kA, rms, symm) :  0.095  0.141  0.145
Steady State Current (kA, rms) :  0.163  0.095  0.141  0.145

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 54
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus50


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus50 Total  0.00  0.159  0.00  125.94  126.32  0.093  0.093 8.60E+004 1.79E+003 2.71E+005 3.54E+003

Main Bus B2 Bus50  99.45  0.159  99.54  100.14  100.00  0.093  0.093 8.60E+004 1.79E+003 2.71E+005 3.54E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.159  0.093  0.138  0.142
Peak Current (kA), Method C :  0.230  0.134  0.199  0.205
Breaking Current (kA, rms, symm) :  0.093  0.138  0.142
Steady State Current (kA, rms) :  0.159  0.093  0.138  0.142

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 55
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus51


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus51 Total  0.00  0.164  0.00  125.93  126.32  0.095  0.095 8.37E+004 1.77E+003 2.63E+005 3.48E+003

Main Bus B2 Bus51  99.44  0.164  99.53  100.15  100.00  0.095  0.095 8.37E+004 1.77E+003 2.63E+005 3.48E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.164  0.095  0.142  0.146
Peak Current (kA), Method C :  0.236  0.138  0.205  0.211
Breaking Current (kA, rms, symm) :  0.095  0.142  0.146
Steady State Current (kA, rms) :  0.164  0.095  0.142  0.146

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 56
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus53


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus53 Total  0.00  0.163  0.00  125.94  126.32  0.095  0.095 8.43E+004 1.78E+003 2.65E+005 3.50E+003

Main Bus B2 Bus53  99.44  0.163  99.53  100.15  100.00  0.095  0.095 8.43E+004 1.78E+003 2.65E+005 3.50E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.163  0.095  0.141  0.145
Peak Current (kA), Method C :  0.235  0.137  0.203  0.209
Breaking Current (kA, rms, symm) :  0.095  0.141  0.145
Steady State Current (kA, rms) :  0.163  0.095  0.141  0.145

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 57
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus54


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus54 Total  0.00  0.160  0.00  125.94  126.32  0.094  0.094 8.54E+004 1.79E+003 2.69E+005 3.53E+003

Main Bus B2 Bus54  99.45  0.160  99.54  100.14  100.00  0.094  0.094 8.54E+004 1.79E+003 2.69E+005 3.53E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.160  0.094  0.139  0.143
Peak Current (kA), Method C :  0.231  0.135  0.200  0.206
Breaking Current (kA, rms, symm) :  0.094  0.139  0.143
Steady State Current (kA, rms) :  0.160  0.094  0.139  0.143

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 58
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus55


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus55 Total  0.00  0.159  0.00  125.94  126.32  0.093  0.093 8.60E+004 1.79E+003 2.71E+005 3.54E+003

Main Bus B2 Bus55  99.45  0.159  99.54  100.14  100.00  0.093  0.093 8.60E+004 1.79E+003 2.71E+005 3.54E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.159  0.093  0.138  0.142
Peak Current (kA), Method C :  0.230  0.134  0.199  0.205
Breaking Current (kA, rms, symm) :  0.093  0.138  0.142
Steady State Current (kA, rms) :  0.159  0.093  0.138  0.142

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 59
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus56


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus56 Total  0.00  0.237  0.00  125.86  126.36  0.138  0.138 5.79E+004 1.48E+003 1.82E+005 2.78E+003

Main Bus B2 Bus56  99.18  0.237  99.31  100.21  100.00  0.138  0.138 5.79E+004 1.48E+003 1.82E+005 2.78E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.237  0.138  0.205  0.211
Peak Current (kA), Method C :  0.342  0.199  0.296  0.305
Breaking Current (kA, rms, symm) :  0.138  0.205  0.211
Steady State Current (kA, rms) :  0.237  0.138  0.205  0.211

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 60
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus57


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus57 Total  0.00  0.523  0.00  125.39  126.65  0.306  0.306 2.62E+004 1.82E+003 8.20E+004 3.62E+003

Main Bus B2 Bus57  98.09  0.523  98.42  100.46  100.02  0.306  0.306 2.62E+004 1.82E+003 8.20E+004 3.62E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.523  0.306  0.453  0.468
Peak Current (kA), Method C :  0.755  0.441  0.653  0.675
Breaking Current (kA, rms, symm) :  0.306  0.453  0.468
Steady State Current (kA, rms) :  0.523  0.306  0.453  0.468

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 61
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus58


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus58 Total  0.00  4.363  0.00  120.53  128.08  2.668  2.668 2.98E+003 9.98E+002 9.04E+003 1.59E+003

Main Bus B2 Bus58  80.43  4.363  84.40  103.56  101.14  2.668  2.668 2.98E+003 9.98E+002 9.04E+003 1.59E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  4.363  2.668  3.778  4.014
Peak Current (kA), Method C :  6.294  3.849  5.451  5.791
Breaking Current (kA, rms, symm) :  2.668  3.778  4.014
Steady State Current (kA, rms) :  4.363  2.668  3.778  4.014

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 62
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus59


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus59 Total  0.00  1.266  0.00  124.21  127.19  0.746  0.746 1.07E+004 1.80E+003 3.33E+004 3.56E+003

Main Bus B2 Bus59  94.80  1.266  95.83  101.07  100.16  0.746  0.746 1.07E+004 1.80E+003 3.33E+004 3.56E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  1.266  0.746  1.096  1.141
Peak Current (kA), Method C :  1.826  1.077  1.582  1.646
Breaking Current (kA, rms, symm) :  0.746  1.096  1.141
Steady State Current (kA, rms) :  1.266  0.746  1.096  1.141

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 63
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus60


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus60 Total  0.00  0.568  0.00  125.34  126.67  0.332  0.332 2.41E+004 1.75E+003 7.55E+004 3.43E+003

Main Bus B2 Bus60  97.92  0.568  98.28  100.50  100.03  0.332  0.332 2.41E+004 1.75E+003 7.55E+004 3.43E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.568  0.332  0.492  0.509
Peak Current (kA), Method C :  0.820  0.479  0.710  0.734
Breaking Current (kA, rms, symm) :  0.332  0.492  0.509
Steady State Current (kA, rms) :  0.568  0.332  0.492  0.509

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 64
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus61


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus61 Total  0.00  13.268  0.00  104.97  118.80  10.599  10.599 5.13E+002 8.97E+002 1.27E+003 1.34E+003

Main Bus A1 Bus61  27.91  13.268  37.64  105.21  103.97  10.599  10.599 5.13E+002 8.97E+002 1.27E+003 1.34E+003

Bus27 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus29 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus30 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus31 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus32 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus33 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus34 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus35 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus36 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus37 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus38 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus39 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus40 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus41 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus42 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  13.268  10.599  11.490  13.032
Peak Current (kA), Method C :  22.443  17.928  19.436  22.045
Breaking Current (kA, rms, symm) :  10.599  11.490  13.032
Steady State Current (kA, rms) :  13.268  10.599  11.490  13.032

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 65
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus63


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus63 Total  0.00  14.488  0.00  104.64  113.56  12.158  12.158 3.54E+002 8.78E+002 7.65E+002 1.29E+003

Main Bus A1 Bus63  14.71  14.488  20.17  104.53  106.08  12.158  12.158 3.54E+002 8.78E+002 7.65E+002 1.29E+003

Bus21 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus22 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus24 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus25 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus26 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  14.488  12.158  12.547  14.134
Peak Current (kA), Method C :  26.877  22.556  23.277  26.221
Breaking Current (kA, rms, symm) :  12.158  12.547  14.134
Steady State Current (kA, rms) :  14.488  12.158  12.547  14.134

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 66
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus64


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus64 Total  0.00  10.611  0.00  109.69  125.61  7.589  7.589 9.22E+002 9.06E+002 2.55E+003 1.36E+003

Main Bus A1 Bus64  53.14  10.611  65.03  105.02  100.95  7.589  7.589 9.22E+002 9.06E+002 2.55E+003 1.36E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  10.611  7.589  9.189  10.272
Peak Current (kA), Method C :  16.000  11.444  13.856  15.490
Breaking Current (kA, rms, symm) :  7.589  9.189  10.272
Steady State Current (kA, rms) :  10.611  7.589  9.189  10.272

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 67
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus65


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus65 Total  0.00  12.399  0.00  106.12  121.43  9.567  9.567 6.27E+002 9.11E+002 1.63E+003 1.37E+003

Main Bus A1 Bus65  36.24  12.399  47.47  105.28  102.84  9.567  9.567 6.27E+002 9.11E+002 1.63E+003 1.37E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  12.399  9.567  10.738  12.151
Peak Current (kA), Method C :  20.062  15.479  17.374  19.660
Breaking Current (kA, rms, symm) :  9.567  10.738  12.151
Steady State Current (kA, rms) :  12.399  9.567  10.738  12.151

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 68
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus66


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus66 Total  0.00  4.033  0.00  119.74  127.83  2.497  2.497 3.08E+003 1.44E+003 9.35E+003 2.68E+003

Main Bus A1 Bus66  85.52  4.033  90.34  101.91  99.70  2.497  2.497 3.08E+003 1.44E+003 9.35E+003 2.68E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  4.033  2.497  3.493  3.723
Peak Current (kA), Method C :  5.827  3.608  5.046  5.379
Breaking Current (kA, rms, symm) :  2.497  3.493  3.723
Steady State Current (kA, rms) :  4.033  2.497  3.493  3.723

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 69
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus67


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus67 Total  0.00  5.863  0.00  115.97  126.92  3.839  3.839 1.86E+003 1.42E+003 5.50E+003 2.63E+003

Main Bus A1 Bus67  74.01  5.863  81.81  102.68  100.16  3.839  3.839 1.86E+003 1.42E+003 5.50E+003 2.63E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  5.863  3.839  5.078  5.504
Peak Current (kA), Method C :  8.619  5.644  7.464  8.092
Breaking Current (kA, rms, symm) :  3.839  5.078  5.504
Steady State Current (kA, rms) :  5.863  3.839  5.078  5.504

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 70
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus68


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus68 Total  0.00  9.756  0.00  111.56  126.78  6.756  6.756 1.08E+003 8.97E+002 3.06E+003 1.34E+003

Main Bus A1 Bus68  60.05  9.756  71.25  104.72  100.37  6.756  6.756 1.08E+003 8.97E+002 3.06E+003 1.34E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  9.756  6.756  8.449  9.373
Peak Current (kA), Method C :  14.435  9.997  12.501  13.869
Breaking Current (kA, rms, symm) :  6.756  8.449  9.373
Steady State Current (kA, rms) :  9.756  6.756  8.449  9.373

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 71
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus69


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus69 Total  0.00  0.176  0.00  125.91  126.34  0.103  0.103 7.79E+004 1.82E+003 2.45E+005 3.60E+003

Main Bus A1 Bus69  99.67  0.176  99.76  100.08  99.96  0.103  0.103 7.79E+004 1.82E+003 2.45E+005 3.60E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.176  0.103  0.152  0.157
Peak Current (kA), Method C :  0.254  0.148  0.220  0.226
Breaking Current (kA, rms, symm) :  0.103  0.152  0.157
Steady State Current (kA, rms) :  0.176  0.103  0.152  0.157

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 72
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus70


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus70 Total  0.00  10.028  0.00  110.97  126.46  7.014  7.014 1.03E+003 9.00E+002 2.89E+003 1.34E+003

Main Bus A2 Bus70  58.96  10.028  70.55  104.19  100.46  7.014  7.014 1.03E+003 9.00E+002 2.89E+003 1.34E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  10.028  7.014  8.685  9.659
Peak Current (kA), Method C :  14.914  10.431  12.916  14.365
Breaking Current (kA, rms, symm) :  7.014  8.685  9.659
Steady State Current (kA, rms) :  10.028  7.014  8.685  9.659

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 73
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus72


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus72 Total  0.00  10.435  0.00  110.55  126.55  7.331  7.331 9.92E+002 8.61E+002 2.77E+003 1.25E+003

Main Bus A2 Bus72  58.12  10.435  69.95  104.40  100.45  7.331  7.331 9.92E+002 8.61E+002 2.77E+003 1.25E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  10.435  7.331  9.037  10.076
Peak Current (kA), Method C :  15.509  10.896  13.432  14.975
Breaking Current (kA, rms, symm) :  7.331  9.037  10.076
Steady State Current (kA, rms) :  10.435  7.331  9.037  10.076

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 74
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus73


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus73 Total  0.00  12.152  0.00  106.60  122.46  9.247  9.247 6.76E+002 9.03E+002 1.78E+003 1.35E+003

Main Bus A2 Bus73  40.98  12.152  52.95  104.63  102.09  9.247  9.247 6.76E+002 9.03E+002 1.78E+003 1.35E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  12.152  9.247  10.524  11.898
Peak Current (kA), Method C :  19.311  14.695  16.724  18.908
Breaking Current (kA, rms, symm) :  9.247  10.524  11.898
Steady State Current (kA, rms) :  12.152  9.247  10.524  11.898

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 75
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus74


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus74 Total  0.00  4.263  0.00  119.49  127.86  2.647  2.647 2.91E+003 1.38E+003 8.80E+003 2.53E+003

Main Bus A2 Bus74  85.20  4.263  90.26  101.76  99.73  2.647  2.647 2.91E+003 1.38E+003 8.80E+003 2.53E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  4.263  2.647  3.692  3.941
Peak Current (kA), Method C :  6.160  3.826  5.335  5.694
Breaking Current (kA, rms, symm) :  2.647  3.692  3.941
Steady State Current (kA, rms) :  4.263  2.647  3.692  3.941

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 76
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus75


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus75 Total  0.00  6.147  0.00  115.65  126.89  4.042  4.042 1.77E+003 1.36E+003 5.21E+003 2.49E+003

Main Bus A2 Bus75  73.66  6.147  81.76  102.45  100.16  4.042  4.042 1.77E+003 1.36E+003 5.21E+003 2.49E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  6.147  4.042  5.323  5.780
Peak Current (kA), Method C :  9.042  5.946  7.831  8.503
Breaking Current (kA, rms, symm) :  4.042  5.323  5.780
Steady State Current (kA, rms) :  6.147  4.042  5.323  5.780

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 77
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus76


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus76 Total  0.00  0.185  0.00  125.92  126.33  0.108  0.108 7.40E+004 1.58E+003 2.33E+005 3.01E+003

Main Bus A2 Bus76  99.67  0.185  99.77  100.08  99.96  0.108  0.108 7.40E+004 1.58E+003 2.33E+005 3.01E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  0.185  0.108  0.161  0.165
Peak Current (kA), Method C :  0.267  0.156  0.232  0.238
Breaking Current (kA, rms, symm) :  0.108  0.161  0.165
Steady State Current (kA, rms) :  0.185  0.108  0.161  0.165

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 78
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus77


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus77 Total  0.00  14.172  0.00  103.90  117.51  11.580  11.580 4.57E+002 8.53E+002 1.09E+003 1.23E+003

Main Bus A2 Bus77  24.63  14.172  33.97  104.70  104.03  11.580  11.580 4.57E+002 8.53E+002 1.09E+003 1.23E+003

Bus43 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus45 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus46 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus47 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus48 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus49 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus50 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus51 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus53 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus54 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus55 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus56 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus57 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus58 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus59 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus60 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  14.172  11.580  12.273  13.986
Peak Current (kA), Method C :  24.386  19.927  21.119  24.067
Breaking Current (kA, rms, symm) :  11.580  12.273  13.986
Steady State Current (kA, rms) :  14.172  11.580  12.273  13.986

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 79
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Bus78


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus78 Total  0.00  14.520  0.00  104.36  114.11  12.161  12.161 3.68E+002 8.70E+002 8.07E+002 1.27E+003

Main Bus A2 Bus78  17.84  14.520  24.42  104.04  105.14  12.161  12.161 3.68E+002 8.70E+002 8.07E+002 1.27E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  14.520  12.161  12.575  14.206
Peak Current (kA), Method C :  26.610  22.288  23.045  26.035
Breaking Current (kA, rms, symm) :  12.161  12.575  14.206
Steady State Current (kA, rms) :  14.520  12.161  12.575  14.206

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 80
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Main Bus A1


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Main Bus A1 Total  0.00  16.541  0.00  104.24  108.43  14.615  14.615 2.45E+002 7.92E+002 4.19E+002 1.08E+003

Bus61 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus63 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus64 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus65 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus66 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus67 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus68 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus69 Main Bus A1  0.00  0.000  0.00  104.24  108.43  0.000  0.000

Bus10 Main Bus A1  27.54  16.541  36.96  99.46  99.74  14.615  14.615 2.45E+002 7.92E+002 4.19E+002 1.08E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  16.541  14.615  14.325  16.055
Peak Current (kA), Method C :  32.940  29.105  28.527  31.973
Breaking Current (kA, rms, symm) :  14.615  14.325  16.055
Steady State Current (kA, rms) :  16.541  14.615  14.325  16.055

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 81
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Main Bus A2


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Main Bus A2 Total  0.00  17.108  0.00  103.73  107.72  15.296  15.296 2.35E+002 7.66E+002 3.88E+002 1.02E+003

Bus77 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus78 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus70 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus72 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus73 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus74 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus75 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus76 Main Bus A2  0.00  0.000  0.00  103.73  107.72  0.000  0.000

Bus12 Main Bus A2  25.03  17.108  33.99  99.43  99.72  15.296  15.296 2.35E+002 7.66E+002 3.88E+002 1.02E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  17.108  15.296  14.816  16.655
Peak Current (kA), Method C :  34.146  30.529  29.571  33.240
Breaking Current (kA, rms, symm) :  15.296  14.816  16.655
Steady State Current (kA, rms) :  17.108  15.296  14.816  16.655

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 82
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Main Bus B1


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Main Bus B1 Total  0.00  13.268  0.00  104.97  118.80  10.599  10.599 5.13E+002 8.97E+002 1.27E+003 1.34E+003

Bus27 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus29 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus30 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus31 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus32 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus33 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus34 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus35 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus36 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus37 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus38 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus39 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus40 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus41 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Bus42 Main Bus B1  0.00  0.000  0.00  104.97  118.80  0.000  0.000

Main Bus A1 Bus61  27.91  13.268  37.64  105.21  103.97  10.599  10.599 5.13E+002 8.97E+002 1.27E+003 1.34E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  13.268  10.599  11.490  13.032
Peak Current (kA), Method C :  22.443  17.928  19.436  22.045
Breaking Current (kA, rms, symm) :  10.599  11.490  13.032
Steady State Current (kA, rms) :  13.268  10.599  11.490  13.032

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 83
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Main Bus B2


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Main Bus B2 Total  0.00  14.172  0.00  103.90  117.51  11.580  11.580 4.57E+002 8.53E+002 1.09E+003 1.23E+003

Bus43 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus45 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus46 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus47 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus48 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus49 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus50 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus51 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus53 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus54 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus55 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus56 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus57 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus58 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus59 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Bus60 Main Bus B2  0.00  0.000  0.00  103.90  117.51  0.000  0.000

Main Bus A2 Bus77  24.63  14.172  33.97  104.70  104.03  11.580  11.580 4.57E+002 8.53E+002 1.09E+003 1.23E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  14.172  11.580  12.273  13.986
Peak Current (kA), Method C :  24.386  19.927  21.119  24.067
Breaking Current (kA, rms, symm) :  11.580  12.273  13.986
Steady State Current (kA, rms) :  14.172  11.580  12.273  13.986

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 84
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Fault at bus: Main Bus C


Nominal kV =  0.400
Voltage c Factor = 0.95 (Minimum If)
Positive & Zero Sequence Impedances
Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"
From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Main Bus C Total  0.00  14.488  0.00  104.64  113.56  12.158  12.158 3.54E+002 8.78E+002 7.65E+002 1.29E+003

Bus21 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus22 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus24 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus25 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Bus26 Main Bus C  0.00  0.000  0.00  104.64  113.56  0.000  0.000

Main Bus A1 Bus63  14.71  14.488  20.17  104.53  106.08  12.158  12.158 3.54E+002 8.78E+002 7.65E+002 1.29E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) :  14.488  12.158  12.547  14.134
Peak Current (kA), Method C :  26.877  22.556  23.277  26.221
Breaking Current (kA, rms, symm) :  12.158  12.547  14.134
Steady State Current (kA, rms) :  14.488  12.158  12.547  14.134

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta-Y transformer
Project: ETAP Page: 85
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Short-Circuit Summary Report

3-Phase, LG, LL, LLG Fault Currents

Bus 3-Phase Fault Line-to-Ground Fault Line-to-Line Fault *Line-to-Line-to-Ground


ID kV I"k ip Ik I"k ip Ib Ik I"k ip Ib Ik I"k ip Ib Ik

Bus1  13.800  20.918  56.408  20.918  20.918  56.408  20.918  20.918  18.116  48.850  18.116  18.116  20.918  56.408  20.918  20.918
Bus2  13.800  18.260  44.352  18.260  17.166  41.696  17.166  17.166  15.814  38.410  15.814  15.814  17.885  43.442  17.885  17.885
Bus3  13.800  20.918  56.408  20.918  20.918  56.408  20.918  20.918  18.116  48.850  18.116  18.116  20.918  56.408  20.918  20.918
Bus4  13.800  18.109  43.748  18.109  16.968  40.990  16.968  16.968  15.683  37.887  15.683  15.683  17.716  42.798  17.716  17.716
Bus5  13.800  17.240  38.741  17.240  15.870  35.662  15.870  15.870  14.930  33.551  14.930  14.930  16.804  37.761  16.804  16.804
Bus6  13.800  17.173  38.411  17.173  15.787  35.311  15.787  15.787  14.872  33.265  14.872  14.872  16.732  37.425  16.732  16.732
Bus7  13.800  17.432  39.707  17.432  16.108  36.692  16.108  16.108  15.096  34.387  15.096  15.096  17.008  38.742  17.008  17.008
Bus8  13.800  17.201  38.548  17.201  15.821  35.456  15.821  15.821  14.896  33.383  14.896  14.896  16.762  37.564  16.762  16.762
Bus9  13.800  18.016  42.896  18.016  16.850  40.119  16.850  16.850  15.602  37.149  15.602  15.602  17.628  41.972  17.628  17.628
Bus10  0.400  22.798  46.547  22.798  23.092  47.147  23.092  23.092  19.744  40.311  19.744  19.744  22.987  46.931  22.987  22.987
Bus11  13.800  17.925  42.659  17.925  16.730  39.815  16.730  16.730  15.524  36.944  15.524  15.524  17.522  41.699  17.522  17.522
Bus12  0.400  22.794  46.538  22.794  23.089  47.142  23.089  23.089  19.740  40.303  19.740  19.740  22.983  46.924  22.983  22.983
Bus13  13.800  17.101  38.274  17.101  15.696  35.129  15.696  15.696  14.810  33.147  14.810  14.810  16.648  37.260  16.648  16.648
Bus14  13.800  17.397  39.764  17.397  16.062  36.712  16.062  16.062  15.066  34.436  15.066  15.066  16.963  38.771  16.963  16.963
Bus15  13.800  17.057  38.059  17.057  15.641  34.900  15.641  15.641  14.772  32.960  14.772  14.772  16.601  37.041  16.601  16.601
Bus16  13.800  17.212  38.824  17.212  15.833  35.712  15.833  15.833  14.906  33.622  14.906  14.906  16.766  37.818  16.766  16.766
Bus21  0.400  5.072  7.385  5.072  3.244  4.724  3.244  3.244  4.392  6.396  4.392  4.392  4.730  6.888  4.730  4.730
Bus22  0.400  5.019  7.351  5.019  3.238  4.743  3.238  3.238  4.347  6.366  4.347  4.347  4.688  6.866  4.688  4.688
Bus24  0.400  4.355  6.282  4.355  2.660  3.838  2.660  2.660  3.771  5.440  3.771  3.771  4.005  5.778  4.005  4.005
Bus25  0.400  11.254  17.794  11.254  8.417  13.309  8.417  8.417  9.746  15.410  9.746  9.746  10.950  17.314  10.950  10.950
Bus26  0.400  11.254  17.794  11.254  8.417  13.309  8.417  8.417  9.746  15.410  9.746  9.746  10.950  17.314  10.950  10.950
Bus27  0.400  0.174  0.251  0.174  0.102  0.146  0.102  0.102  0.151  0.218  0.151  0.151  0.155  0.224  0.155  0.155
Bus29  0.400  0.173  0.249  0.173  0.101  0.145  0.101  0.101  0.150  0.216  0.150  0.150  0.154  0.222  0.154  0.154
Bus30  0.400  0.172  0.248  0.172  0.100  0.144  0.100  0.100  0.149  0.214  0.149  0.149  0.153  0.221  0.153  0.153
Bus31  0.400  0.173  0.249  0.173  0.101  0.145  0.101  0.101  0.150  0.216  0.150  0.150  0.154  0.222  0.154  0.154
Bus32  0.400  0.168  0.242  0.168  0.098  0.141  0.098  0.098  0.146  0.210  0.146  0.146  0.150  0.216  0.150  0.150
Bus33  0.400  0.167  0.241  0.167  0.097  0.140  0.097  0.097  0.145  0.209  0.145  0.145  0.149  0.215  0.149  0.149
Bus34  0.400  0.163  0.234  0.163  0.095  0.137  0.095  0.095  0.141  0.203  0.141  0.141  0.145  0.209  0.145  0.145
Bus35  0.400  0.168  0.242  0.168  0.098  0.141  0.098  0.098  0.146  0.210  0.146  0.146  0.150  0.216  0.150  0.150
Bus36  0.400  0.167  0.241  0.167  0.097  0.140  0.097  0.097  0.145  0.209  0.145  0.145  0.149  0.215  0.149  0.149
Bus37  0.400  0.165  0.238  0.165  0.096  0.139  0.096  0.096  0.143  0.206  0.143  0.143  0.147  0.212  0.147  0.147
Bus38  0.400  0.164  0.236  0.164  0.095  0.138  0.095  0.095  0.142  0.204  0.142  0.142  0.146  0.210  0.146  0.146
Bus39  0.400  0.244  0.352  0.244  0.142  0.205  0.142  0.142  0.211  0.305  0.211  0.211  0.217  0.314  0.217  0.217
Bus40  0.400  0.530  0.765  0.530  0.310  0.447  0.310  0.310  0.459  0.662  0.459  0.459  0.475  0.684  0.475  0.475
Bus41  0.400  4.632  6.684  4.632  2.850  4.113  2.850  2.850  4.012  5.789  4.012  4.012  4.274  6.167  4.274  4.274
Bus42  0.400  1.736  2.504  1.736  1.031  1.487  1.031  1.031  1.503  2.169  1.503  1.503  1.572  2.268  1.572  1.572
Bus43  0.400  0.168  0.243  0.168  0.098  0.141  0.098  0.098  0.146  0.210  0.146  0.146  0.150  0.216  0.150  0.150
Project: ETAP Page: 86
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

3-Phase, LG, LL, LLG Fault Currents

Bus 3-Phase Fault Line-to-Ground Fault Line-to-Line Fault *Line-to-Line-to-Ground


ID kV I"k ip Ik I"k ip Ib Ik I"k ip Ib Ik I"k ip Ib Ik

Bus45  0.400  0.166  0.239  0.166  0.097  0.140  0.097  0.097  0.144  0.207  0.144  0.144  0.148  0.213  0.148  0.148
Bus46  0.400  0.166  0.239  0.166  0.097  0.140  0.097  0.097  0.144  0.207  0.144  0.144  0.148  0.213  0.148  0.148
Bus47  0.400  0.167  0.241  0.167  0.097  0.141  0.097  0.097  0.145  0.209  0.145  0.145  0.149  0.215  0.149  0.149
Bus48  0.400  0.165  0.238  0.165  0.096  0.139  0.096  0.096  0.143  0.206  0.143  0.143  0.147  0.212  0.147  0.147
Bus49  0.400  0.163  0.235  0.163  0.095  0.137  0.095  0.095  0.141  0.203  0.141  0.141  0.145  0.209  0.145  0.145
Bus50  0.400  0.159  0.230  0.159  0.093  0.134  0.093  0.093  0.138  0.199  0.138  0.138  0.142  0.205  0.142  0.142
Bus51  0.400  0.164  0.236  0.164  0.095  0.138  0.095  0.095  0.142  0.205  0.142  0.142  0.146  0.211  0.146  0.146
Bus53  0.400  0.163  0.235  0.163  0.095  0.137  0.095  0.095  0.141  0.203  0.141  0.141  0.145  0.209  0.145  0.145
Bus54  0.400  0.160  0.231  0.160  0.094  0.135  0.094  0.094  0.139  0.200  0.139  0.139  0.143  0.206  0.143  0.143
Bus55  0.400  0.159  0.230  0.159  0.093  0.134  0.093  0.093  0.138  0.199  0.138  0.138  0.142  0.205  0.142  0.142
Bus56  0.400  0.237  0.342  0.237  0.138  0.199  0.138  0.138  0.205  0.296  0.205  0.205  0.211  0.305  0.211  0.211
Bus57  0.400  0.523  0.755  0.523  0.306  0.441  0.306  0.306  0.453  0.653  0.453  0.453  0.468  0.675  0.468  0.468
Bus58  0.400  4.363  6.294  4.363  2.668  3.849  2.668  2.668  3.778  5.451  3.778  3.778  4.014  5.791  4.014  4.014
Bus59  0.400  1.266  1.826  1.266  0.746  1.077  0.746  0.746  1.096  1.582  1.096  1.096  1.141  1.646  1.141  1.141
Bus60  0.400  0.568  0.820  0.568  0.332  0.479  0.332  0.332  0.492  0.710  0.492  0.492  0.509  0.734  0.509  0.509
Bus61  0.400  13.268  22.443  13.268  10.599  17.928  10.599  10.599  11.490  19.436  11.490  11.490  13.032  22.045  13.032  13.032
Bus63  0.400  14.488  26.877  14.488  12.158  22.556  12.158  12.158  12.547  23.277  12.547  12.547  14.134  26.221  14.134  14.134
Bus64  0.400  10.611  16.000  10.611  7.589  11.444  7.589  7.589  9.189  13.856  9.189  9.189  10.272  15.490  10.272  10.272
Bus65  0.400  12.399  20.062  12.399  9.567  15.479  9.567  9.567  10.738  17.374  10.738  10.738  12.151  19.660  12.151  12.151
Bus66  0.400  4.033  5.827  4.033  2.497  3.608  2.497  2.497  3.493  5.046  3.493  3.493  3.723  5.379  3.723  3.723
Bus67  0.400  5.863  8.619  5.863  3.839  5.644  3.839  3.839  5.078  7.464  5.078  5.078  5.504  8.092  5.504  5.504
Bus68  0.400  9.756  14.435  9.756  6.756  9.997  6.756  6.756  8.449  12.501  8.449  8.449  9.373  13.869  9.373  9.373
Bus69  0.400  0.176  0.254  0.176  0.103  0.148  0.103  0.103  0.152  0.220  0.152  0.152  0.157  0.226  0.157  0.157
Bus70  0.400  10.028  14.914  10.028  7.014  10.431  7.014  7.014  8.685  12.916  8.685  8.685  9.659  14.365  9.659  9.659
Bus72  0.400  10.435  15.509  10.435  7.331  10.896  7.331  7.331  9.037  13.432  9.037  9.037  10.076  14.975  10.076  10.076
Bus73  0.400  12.152  19.311  12.152  9.247  14.695  9.247  9.247  10.524  16.724  10.524  10.524  11.898  18.908  11.898  11.898
Bus74  0.400  4.263  6.160  4.263  2.647  3.826  2.647  2.647  3.692  5.335  3.692  3.692  3.941  5.694  3.941  3.941
Bus75  0.400  6.147  9.042  6.147  4.042  5.946  4.042  4.042  5.323  7.831  5.323  5.323  5.780  8.503  5.780  5.780
Bus76  0.400  0.185  0.267  0.185  0.108  0.156  0.108  0.108  0.161  0.232  0.161  0.161  0.165  0.238  0.165  0.165
Bus77  0.400  14.172  24.386  14.172  11.580  19.927  11.580  11.580  12.273  21.119  12.273  12.273  13.986  24.067  13.986  13.986
Bus78  0.400  14.520  26.610  14.520  12.161  22.288  12.161  12.161  12.575  23.045  12.575  12.575  14.206  26.035  14.206  14.206
Main Bus A1  0.400  16.541  32.940  16.541  14.615  29.105  14.615  14.615  14.325  28.527  14.325  14.325  16.055  31.973  16.055  16.055
Main Bus A2  0.400  17.108  34.146  17.108  15.296  30.529  15.296  15.296  14.816  29.571  14.816  14.816  16.655  33.240  16.655  16.655
Main Bus B1  0.400  13.268  22.443  13.268  10.599  17.928  10.599  10.599  11.490  19.436  11.490  11.490  13.032  22.045  13.032  13.032
Main Bus B2  0.400  14.172  24.386  14.172  11.580  19.927  11.580  11.580  12.273  21.119  12.273  12.273  13.986  24.067  13.986  13.986
Main Bus C  0.400  14.488  26.877  14.488  12.158  22.556  12.158  12.158  12.547  23.277  12.547  12.547  14.134  26.221  14.134  14.134

All fault currents are in rms kA. Current ip is calculated using Method C.

* LLG fault current is the larger of the two faulted line currents.
Project: ETAP Page: 87
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Sequence Impedance Summary Report

Bus Positive Seq. Imp. (ohm) Negative Seq. Imp. (ohm) Zero Seq. Imp. (ohm) Fault Zf (ohm)
ID kV Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance

Bus1  13.800  0.01269  0.38067  0.38088  0.01269  0.38067  0.38088  0.01269  0.38067  0.38088  0.00000  0.00000  0.00000

Bus2  13.800  0.04914  0.43355  0.43633  0.04914  0.43355  0.43633  0.07065  0.51499  0.51982  0.00000  0.00000  0.00000

Bus3  13.800  0.01269  0.38067  0.38088  0.01269  0.38067  0.38088  0.01269  0.38067  0.38088  0.00000  0.00000  0.00000

Bus4  13.800  0.05148  0.43694  0.43996  0.05148  0.43694  0.43996  0.07437  0.52360  0.52886  0.00000  0.00000  0.00000

Bus5  13.800  0.08242  0.45473  0.46214  0.08242  0.45473  0.46214  0.12356  0.56880  0.58206  0.00000  0.00000  0.00000

Bus6  13.800  0.08466  0.45616  0.46395  0.08466  0.45616  0.46395  0.12712  0.57242  0.58637  0.00000  0.00000  0.00000

Bus7  13.800  0.07606  0.45069  0.45706  0.07606  0.45069  0.45706  0.11345  0.55852  0.56993  0.00000  0.00000  0.00000

Bus8  13.800  0.08373  0.45557  0.46320  0.08373  0.45557  0.46320  0.12564  0.57091  0.58457  0.00000  0.00000  0.00000

Bus9  13.800  0.05699  0.43855  0.44224  0.05699  0.43855  0.44224  0.08313  0.52769  0.53420  0.00000  0.00000  0.00000

Bus10  0.400  0.00259  0.00927  0.00962  0.00259  0.00927  0.00962  0.00254  0.00890  0.00926  0.00000  0.00000  0.00000

Bus11  13.800  0.05746  0.44075  0.44448  0.05746  0.44075  0.44448  0.08388  0.53328  0.53983  0.00000  0.00000  0.00000

Bus12  0.400  0.00259  0.00927  0.00963  0.00259  0.00927  0.00963  0.00254  0.00890  0.00926  0.00000  0.00000  0.00000

Bus13  13.800  0.08475  0.45812  0.46590  0.08475  0.45812  0.46590  0.12727  0.57741  0.59127  0.00000  0.00000  0.00000

Bus14  13.800  0.07485  0.45182  0.45797  0.07485  0.45182  0.45797  0.11152  0.56139  0.57236  0.00000  0.00000  0.00000

Bus15  13.800  0.08625  0.45908  0.46711  0.08625  0.45908  0.46711  0.12965  0.57982  0.59414  0.00000  0.00000  0.00000

Bus16  13.800  0.08102  0.45574  0.46289  0.08102  0.45574  0.46289  0.12133  0.57136  0.58410  0.00000  0.00000  0.00000

Bus21  0.400  0.03630  0.02353  0.04326  0.03630  0.02353  0.04326  0.10871  0.04399  0.11728  0.00000  0.00000  0.00000

Bus22  0.400  0.03539  0.02565  0.04371  0.03539  0.02565  0.04371  0.10587  0.04920  0.11674  0.00000  0.00000  0.00000

Bus24  0.400  0.04789  0.01564  0.05038  0.04789  0.01564  0.05038  0.14525  0.02457  0.14731  0.00000  0.00000  0.00000

Bus25  0.400  0.01187  0.01547  0.01950  0.01187  0.01547  0.01950  0.03177  0.02415  0.03990  0.00000  0.00000  0.00000

Bus26  0.400  0.01187  0.01547  0.01950  0.01187  0.01547  0.01950  0.03177  0.02415  0.03990  0.00000  0.00000  0.00000

Bus27  0.400  1.25972  0.02811  1.26003  1.25972  0.02811  1.26003  3.96249  0.05526  3.96288  0.00000  0.00000  0.00000

Bus29  0.400  1.26872  0.02821  1.26903  1.26872  0.02821  1.26903  3.99085  0.05550  3.99124  0.00000  0.00000  0.00000

Bus30  0.400  1.27772  0.02831  1.27804  1.27772  0.02831  1.27804  4.01922  0.05575  4.01960  0.00000  0.00000  0.00000

Bus31  0.400  1.26872  0.02821  1.26903  1.26872  0.02821  1.26903  3.99085  0.05550  3.99124  0.00000  0.00000  0.00000

Bus32  0.400  1.30474  0.02861  1.30505  1.30474  0.02861  1.30505  4.10430  0.05648  4.10469  0.00000  0.00000  0.00000

Bus33  0.400  1.31374  0.02871  1.31405  1.31374  0.02871  1.31405  4.13266  0.05672  4.13305  0.00000  0.00000  0.00000

Bus34  0.400  1.34975  0.02910  1.35007  1.34975  0.02910  1.35007  4.24611  0.05770  4.24650  0.00000  0.00000  0.00000

Bus35  0.400  1.30474  0.02861  1.30505  1.30474  0.02861  1.30505  4.10430  0.05648  4.10469  0.00000  0.00000  0.00000

Bus36  0.400  1.31374  0.02871  1.31405  1.31374  0.02871  1.31405  4.13266  0.05672  4.13305  0.00000  0.00000  0.00000

Bus37  0.400  1.33175  0.02891  1.33206  1.33175  0.02891  1.33206  4.18938  0.05721  4.18978  0.00000  0.00000  0.00000

Bus38  0.400  1.34075  0.02900  1.34106  1.34075  0.02900  1.34106  4.21775  0.05745  4.21814  0.00000  0.00000  0.00000

Bus39  0.400  0.89957  0.02415  0.89990  0.89957  0.02415  0.89990  2.82803  0.04552  2.82840  0.00000  0.00000  0.00000

Bus40  0.400  0.41267  0.02964  0.41373  0.41267  0.02964  0.41373  1.29429  0.05902  1.29564  0.00000  0.00000  0.00000

Bus41  0.400  0.04442  0.01643  0.04736  0.04442  0.01643  0.04736  0.13430  0.02652  0.13689  0.00000  0.00000  0.00000
Project: ETAP Page: 88
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Bus Positive Seq. Imp. (ohm) Negative Seq. Imp. (ohm) Zero Seq. Imp. (ohm) Fault Zf (ohm)
ID kV Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance

Bus42  0.400  0.12307  0.02875  0.12638  0.12307  0.02875  0.12638  0.38204  0.05683  0.38624  0.00000  0.00000  0.00000

Bus43  0.400  1.30383  0.02791  1.30413  1.30383  0.02791  1.30413  4.10144  0.05474  4.10180  0.00000  0.00000  0.00000

Bus45  0.400  1.32184  0.02810  1.32213  1.32184  0.02810  1.32213  4.15816  0.05523  4.15853  0.00000  0.00000  0.00000

Bus46  0.400  1.32184  0.02810  1.32213  1.32184  0.02810  1.32213  4.15816  0.05523  4.15853  0.00000  0.00000  0.00000

Bus47  0.400  1.31283  0.02800  1.31313  1.31283  0.02800  1.31313  4.12980  0.05499  4.13017  0.00000  0.00000  0.00000

Bus48  0.400  1.33084  0.02820  1.33114  1.33084  0.02820  1.33114  4.18652  0.05547  4.18689  0.00000  0.00000  0.00000

Bus49  0.400  1.34885  0.02840  1.34915  1.34885  0.02840  1.34915  4.24325  0.05596  4.24362  0.00000  0.00000  0.00000

Bus50  0.400  1.37586  0.02870  1.37616  1.37586  0.02870  1.37616  4.32833  0.05669  4.32870  0.00000  0.00000  0.00000

Bus51  0.400  1.33984  0.02830  1.34014  1.33984  0.02830  1.34014  4.21489  0.05572  4.21525  0.00000  0.00000  0.00000

Bus53  0.400  1.34885  0.02840  1.34915  1.34885  0.02840  1.34915  4.24325  0.05596  4.24362  0.00000  0.00000  0.00000

Bus54  0.400  1.36685  0.02860  1.36715  1.36685  0.02860  1.36715  4.29997  0.05645  4.30034  0.00000  0.00000  0.00000

Bus55  0.400  1.37586  0.02870  1.37616  1.37586  0.02870  1.37616  4.32833  0.05669  4.32870  0.00000  0.00000  0.00000

Bus56  0.400  0.92568  0.02375  0.92598  0.92568  0.02375  0.92598  2.91026  0.04451  2.91060  0.00000  0.00000  0.00000

Bus57  0.400  0.41843  0.02919  0.41945  0.41843  0.02919  0.41945  1.31243  0.05790  1.31371  0.00000  0.00000  0.00000

Bus58  0.400  0.04769  0.01597  0.05029  0.04769  0.01597  0.05029  0.14460  0.02538  0.14681  0.00000  0.00000  0.00000

Bus59  0.400  0.17087  0.02882  0.17329  0.17087  0.02882  0.17329  0.53264  0.05699  0.53568  0.00000  0.00000  0.00000

Bus60  0.400  0.38509  0.02793  0.38611  0.38509  0.02793  0.38611  1.20743  0.05480  1.20867  0.00000  0.00000  0.00000

Bus61  0.400  0.00821  0.01435  0.01654  0.00821  0.01435  0.01654  0.02025  0.02141  0.02947  0.00000  0.00000  0.00000

Bus63  0.400  0.00567  0.01404  0.01514  0.00567  0.01404  0.01514  0.01224  0.02064  0.02400  0.00000  0.00000  0.00000

Bus64  0.400  0.01475  0.01449  0.02068  0.01475  0.01449  0.02068  0.04084  0.02175  0.04627  0.00000  0.00000  0.00000

Bus65  0.400  0.01004  0.01457  0.01769  0.01004  0.01457  0.01769  0.02600  0.02195  0.03402  0.00000  0.00000  0.00000

Bus66  0.400  0.04925  0.02310  0.05440  0.04925  0.02310  0.05440  0.14953  0.04292  0.15557  0.00000  0.00000  0.00000

Bus67  0.400  0.02971  0.02275  0.03742  0.02971  0.02275  0.03742  0.08797  0.04206  0.09751  0.00000  0.00000  0.00000

Bus68  0.400  0.01731  0.01435  0.02249  0.01731  0.01435  0.02249  0.04892  0.02141  0.05340  0.00000  0.00000  0.00000

Bus69  0.400  1.24641  0.02907  1.24675  1.24641  0.02907  1.24675  3.92059  0.05761  3.92101  0.00000  0.00000  0.00000

Bus70  0.400  0.01647  0.01440  0.02188  0.01647  0.01440  0.02188  0.04627  0.02151  0.05103  0.00000  0.00000  0.00000

Bus72  0.400  0.01588  0.01378  0.02102  0.01588  0.01378  0.02102  0.04439  0.02000  0.04869  0.00000  0.00000  0.00000

Bus73  0.400  0.01082  0.01445  0.01805  0.01082  0.01445  0.01805  0.02846  0.02165  0.03576  0.00000  0.00000  0.00000

Bus74  0.400  0.04648  0.02209  0.05146  0.04648  0.02209  0.05146  0.14080  0.04043  0.14649  0.00000  0.00000  0.00000

Bus75  0.400  0.02824  0.02183  0.03569  0.02824  0.02183  0.03569  0.08334  0.03979  0.09235  0.00000  0.00000  0.00000

Bus76  0.400  1.18323  0.02523  1.18350  1.18323  0.02523  1.18350  3.72155  0.04817  3.72186  0.00000  0.00000  0.00000

Bus77  0.400  0.00730  0.01365  0.01548  0.00730  0.01365  0.01548  0.01739  0.01967  0.02626  0.00000  0.00000  0.00000

Bus78  0.400  0.00588  0.01392  0.01511  0.00588  0.01392  0.01511  0.01290  0.02034  0.02408  0.00000  0.00000  0.00000

Main Bus A1  0.400  0.00391  0.01267  0.01326  0.00391  0.01267  0.01326  0.00671  0.01728  0.01853  0.00000  0.00000  0.00000

Main Bus A2  0.400  0.00375  0.01226  0.01282  0.00375  0.01226  0.01282  0.00620  0.01626  0.01740  0.00000  0.00000  0.00000

Main Bus B1  0.400  0.00821  0.01435  0.01654  0.00821  0.01435  0.01654  0.02025  0.02141  0.02947  0.00000  0.00000  0.00000

Main Bus B2  0.400  0.00730  0.01365  0.01548  0.00730  0.01365  0.01548  0.01739  0.01967  0.02626  0.00000  0.00000  0.00000
Project: ETAP Page: 89
12.6.5C
Location: Date: 12-06-2018
Contract: SN: SCHNEDR-EL
Engineer: Revision: Base
Study Case: SC minimum
Filename: EP17009 SC AND RC STUDY Config.: Normal

Bus Positive Seq. Imp. (ohm) Negative Seq. Imp. (ohm) Zero Seq. Imp. (ohm) Fault Zf (ohm)
ID kV Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance

Main Bus C  0.400  0.00567  0.01404  0.01514  0.00567  0.01404  0.01514  0.01224  0.02064  0.02400  0.00000  0.00000  0.00000

You might also like