ETAP

Project: GERD HYDRO POWER PROJECT Page: 1


12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Electrical Transient Analyzer Program

Load Flow Analysis

Loading Category (1): Design

Generation Category (1): Design

Load Diversity Factor: None

Swing V-Control Load Total


Number of Buses: 1 2 57 60

XFMR2 XFMR3 Reactor Line/Cable Impedance Tie PD Total


Number of Branches: 18 0 0 37 0 5 60

Method of Solution: Adaptive Newton-Raphson Method

Maximum No. of Iteration: 99

Precision of Solution: 0.0001000

System Frequency: 50.00 Hz

Unit System: English

Project Filename: GRANDRENAISSANCE1

Output Filename: D:\Technical\GRAND RENAISSANCE\Electrical\GERD ETAP\Load flow analysis\AC


Auxiliary load flow analysis Master file\Untitled.lfr
ETAP
Project: GERD HYDRO POWER PROJECT Page: 2
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

Cable Length: Yes Individual

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable Resistance: Yes Individual


ETAP
Project: GERD HYDRO POWER PROJECT Page: 3
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Bus Input Data

Load
Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bottom Out bus A 0.400 1 100.0 0.0 0.070 0.037 0.016 0.000

Bottom Out BusB 0.400 1 100.0 0.0 0.072 0.037 0.020 0.000

Bus bar A 15.000 1 100.0 0.0

Bus bar B 15.000 1 100.0 0.0

Bus-3-1 0.400 1 100.0 0.0

Bus-3-1-1 0.400 1 100.0 0.0

Bus7-8-1 0.400 1 100.0 0.0

Bus7-8-1-1 0.400 1 100.0 0.0

Bus22 18.000 1 100.0 0.0

Bus35 15.000 1 100.0 0.0

Bus253 18.000 1 100.0 0.0

Bus256 15.000 1 100.0 0.0

Bus589 0.400 1 100.0 0.0

Bus608-1-1 0.400 1 100.0 0.0 1.143 0.503 0.087 0.041

Bus608-3-1 0.400 1 100.0 0.0 1.143 0.503 0.085 0.041

Bus620-8-1 0.400 1 100.0 0.0 0.007 0.000 0.010 0.000

Bus620-8-1-1 0.400 1 100.0 0.0 0.013 0.000 0.019 0.000

Bus631-1 15.000 1 100.0 0.0

Bus636-1 15.000 1 100.0 0.0

Bus637-1 0.400 1 100.0 0.0

Bus643-1 0.400 1 100.0 0.0

Bus646-1 15.000 1 100.0 0.0

Bus647-1 0.400 1 100.0 0.0

Bus687 0.400 1 100.0 0.0 0.250 0.000

Bus690 15.000 1 100.0 0.0

Bus691 15.000 1 100.0 0.0

Bus692 0.400 1 100.0 0.0

Bus696 0.400 1 100.0 0.0 0.250 0.000

Bus704 500.000 1 100.0 0.0

Bus708 15.000 1 100.0 0.0

Bus709 0.400 1 100.0 0.0

Bus724 15.000 1 100.0 0.0

Bus736 15.000 1 100.0 0.0


ETAP
Project: GERD HYDRO POWER PROJECT Page: 4
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Load
Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bus739 0.400 1 100.0 0.0

Bus742 0.400 1 100.0 0.0 0.450 0.000

Bus743 0.400 1 100.0 0.0 0.450 0.000

Bus749 0.400 1 100.0 0.0 0.175 0.000

Bus752 0.400 1 100.0 0.0

Bus754 0.400 1 100.0 0.0 0.175 0.000

Bus798 15.000 1 100.0 0.0

Bus800 15.000 1 100.0 0.0

Bus801 0.400 1 100.0 0.0

Bus809 15.000 1 100.0 0.0

Bus813-1 15.000 1 100.0 0.0

Bus814 15.000 1 100.0 0.0

Bus815 15.000 1 100.0 0.0

Bus817 15.000 1 100.0 0.0

Bus818 0.400 1 100.0 0.0

Bus819 0.400 1 100.0 0.0

Bus821 0.400 1 100.0 0.0

Bus822 15.000 1 100.0 0.0

MDBR1 BUS A 0.400 1 100.0 0.0 0.206 0.075 0.121 0.050

MDBR1 BUS B 0.400 1 100.0 0.0 0.165 0.076 0.178 0.053

MDBR2 BUS A 0.400 1 100.0 0.0 0.552 0.232 0.440 0.213

MDBR2 BUS B 0.400 1 100.0 0.0 0.302 0.135 0.301 0.128

RIGHT INTAKE BUS BAR A 15.000 1 100.0 0.0

RIGHT INTAKE BUS BAR B 15.000 1 100.0 0.0

Swy Bus bar A 15.000 1 100.0 0.0

Swy Bus bar B 15.000 1 100.0 0.0

Cable177~ 15.000 100.0 0.0

Total Number of Buses: 60 3.672 1.598 3.027 0.525 0.000 0.000 0.000 0.000

Generation Bus Voltage Generation Mvar Limits


ID kV Type Sub-sys % Mag. Angle MW Mvar % PF Max Min

Bus22 18.000 Voltage Control 1 100.0 0.0 0.000 317.288 0.000

Bus253 18.000 Voltage Control 1 100.0 0.0 0.000 181.813 0.000

Bus704 500.000 Swing 1 100.0 0.0


ETAP
Project: GERD HYDRO POWER PROJECT Page: 5
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Generation Bus Voltage Generation Mvar Limits


ID kV Type Sub-sys % Mag. Angle MW Mvar % PF Max Min

0.000 0.000
ETAP
Project: GERD HYDRO POWER PROJECT Page: 6
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Line/Cable Input Data

Ohms or Siemens/1000 ft per Conductor (Cable) or per Phase (Line)

Line/Cable Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y

Cable 3 11NCUS1 400 164.0 0.0 10 75 0.018605 0.030785 0.0000537

Cable-8-1 11NCUS1 150 65.6 0.0 10 75 0.046223 0.035662 0.0000364

Cable-8-1- 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable-8-1-1 11NCUS1 150 65.6 0.0 5 75 0.046223 0.035662 0.0000364

Cable-8-1--1 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable12 3.3MCUN3 95 98.4 0.0 3 75 0.071806 0.024384 0.0000316

Cable511-3-1 11NCUS3 300 164.0 0.0 7 75 0.023257 0.026640 0.0000502

Cable532-1 11NCUS1 95 164.0 0.0 3 75 0.072096 0.037490 0.0000309

Cable533-1 11NCUS1 240 49.2 0.0 10 75 0.028490 0.033223 0.0000529

Cable536-1 11NCUS1 95 49.2 0.0 3 75 0.072096 0.037490 0.0000309

Cable537-1 11NCUS1 240 164.0 0.0 3 75 0.028490 0.033223 0.0000440

Cable540-1 11NCUS3 300 164.0 0.0 3 75 0.023257 0.026640 0.0000502

Cable541-1 1.0NCUN1 500 49.2 0.0 12 75 0.014826 0.026822 0.0000579

Cable544-1 11NCUS3 300 164.0 0.0 3 75 0.023257 0.026640 0.0000502

Cable545-1 1.0NCUN1 400 32.8 0.0 15 75 0.018605 0.027127 0.0000554

Cable581 11NCUS3 50 65.6 0.0 1 75 0.143611 0.035052 0.0000249

Cable582 11NCUS1 120 65.6 0.0 6 75 0.056979 0.035966 0.0000338

Cable588 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable593 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable601 11NCUS1 95 9842.5 0.0 3 75 0.072096 0.037490 0.0000309

Cable605 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable609 11NCUS1 50 49.2 0.0 3 75 0.143611 0.042062 0.0000241

Cable610 11NCUS1 50 49.2 0.0 3 75 0.143611 0.042062 0.0000241

Cable611 11NCUS1 95 49.2 0.0 3 75 0.072096 0.037490 0.0000309

Cable612 11NCUS1 95 49.2 0.0 3 75 0.072096 0.037490 0.0000309

Cable618 11NCUS3 50 65.6 0.0 3 75 0.143611 0.035052 0.0000299

Cable619 11NCUS1 95 65.6 0.0 3 75 0.072096 0.037490 0.0000309

Cable622 11NCUS1 50 65.6 0.0 3 75 0.143611 0.042062 0.0000241

Cable623 11NCUS3 95 65.6 0.0 3 75 0.072096 0.031090 0.0000384

Cable663 0.6NCUS3 120 65.6 0.0 3 75 0.061631 0.020320

Cable665 0.6NCUS1 50 65.6 0.0 3 75 0.144774 0.030480

Cable667 0.6NCUS3 120 65.6 0.0 3 75 0.061631 0.020320

Cable668 0.6NCUS1 50 65.6 0.0 3 75 0.144774 0.030480

Cable669 0.6NCUS1 70 65.6 0.0 3 75 0.100877 0.027940


ETAP
Project: GERD HYDRO POWER PROJECT Page: 7
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Ohms or Siemens/1000 ft per Conductor (Cable) or per Phase (Line)

Line/Cable Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y

Cable670 0.6NCUS1 50 65.6 0.0 3 75 0.144774 0.030480

Cable675 15NCUS1 240 9842.5 0.0 3 75 0.028490 0.034442

Cable177 11NCUS3 95 984.3 0.0 3 75 0.072096 0.031090 0.0000320

Line / Cable resistances are listed at the specified temperatures.


ETAP
Project: GERD HYDRO POWER PROJECT Page: 8
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted Phase Shift

ID Phase MVA Prim. kV Sec. kV % Z1 X1/R1 + 5% - 5% % Tol. Prim. Sec. %Z Type Angle

MAIN TRANSFORMER 08 3-Phase 417.000 500.000 18.000 12.50 45.00 0 0 0 0 0 12.5000 YNd 0.000

MAIN TRANSFORMER10 3-Phase 417.000 500.000 18.000 12.50 45.00 0 0 0 0 0 12.5000 YNd 0.000

MDBR1-TR1 3-Phase 3.150 15.000 0.400 6.25 6.00 0 0 0 0 0 6.2500 Dyn 0.000

MDBR1-TR2 3-Phase 3.150 15.000 0.400 6.25 6.00 0 0 0 0 0 6.2500 Dyn 0.000

MDBR2-TR1 3-Phase 4.000 15.000 0.400 7.15 8.50 0 0 0 0 0 7.1500 Dyn 0.000

MDBR2-TR2 3-Phase 4.000 15.000 0.400 7.15 8.50 0 0 0 0 0 7.1500 Dyn 0.000

OFF-TR1 3-Phase 0.600 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

OFF-TR2 3-Phase 0.535 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T25-8-1 3-Phase 0.040 0.400 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T25-8-1-1 3-Phase 0.040 0.400 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T40 3-Phase 1.000 15.000 0.400 5.00 3.50 0 0 0 0 0 5.0000 Dyn 0.000

T41 3-Phase 1.000 15.000 0.400 5.00 3.50 0 0 0 0 0 5.0000 Dyn 0.000

T42 3-Phase 0.400 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T43 3-Phase 0.400 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T44 3-Phase 0.225 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

T45 3-Phase 0.225 15.000 0.400 4.00 1.50 0 0 0 0 0 4.0000 Dyn 0.000

TR-T1 3-Phase 9.000 18.000 15.000 7.15 8.50 0 0 0 0 0 7.1500 Dyn 0.000

TR-T2 3-Phase 9.000 18.000 15.000 7.15 8.50 0 0 0 0 0 7.1500 Dyn 0.000
ETAP
Project: GERD HYDRO POWER PROJECT Page: 9
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVA Base


ID Type From Bus To Bus R X Z Y

MAIN TRANSFORMER 08 2W XFMR Bus704 Bus253 0.07 3.00 3.00

MAIN TRANSFORMER10 2W XFMR Bus704 Bus22 0.07 3.00 3.00

MDBR1-TR1 2W XFMR Bus631-1 Bus589 32.62 195.71 198.41

MDBR1-TR2 2W XFMR Bus636-1 Bus637-1 32.62 195.71 198.41

MDBR2-TR1 2W XFMR Bus813-1 Bus643-1 20.89 177.53 178.75

MDBR2-TR2 2W XFMR Bus646-1 Bus647-1 20.89 177.53 178.75

OFF-TR1 2W XFMR Bus691 Bus692 369.80 554.70 666.67

OFF-TR2 2W XFMR Bus708 Bus709 414.73 622.09 747.66

T25-8-1 2W XFMR Bus7-8-1 Bus-3-1 5547.00 8320.50 10000.00

T25-8-1-1 2W XFMR Bus7-8-1-1 Bus-3-1-1 5547.00 8320.50 10000.00

T40 2W XFMR Bus822 Bus821 137.36 480.76 500.00

T41 2W XFMR Bus736 Bus739 137.36 480.76 500.00

T42 2W XFMR Bus817 Bus818 554.70 832.05 1000.00

T43 2W XFMR Bus814 Bus752 554.70 832.05 1000.00

T44 2W XFMR Bus798 Bus801 986.13 1479.20 1777.78

T45 2W XFMR Bus809 Bus819 986.13 1479.20 1777.78

TR-T1 2W XFMR Bus22 Bus35 9.28 78.90 79.44

TR-T2 2W XFMR Bus253 Bus256 9.28 78.90 79.44

Cable 3 Cable MDBR1 BUS A Bus608-1-1 19.08 31.56 36.88 0.0000141

Cable-8-1 Cable Bus-3-1 Bus620-8-1 18.96 14.63 23.94 0.0000038

Cable-8-1- Cable Bus608-1-1 Bus7-8-1 98.56 51.25 111.09 0.0000010

Cable-8-1-1 Cable Bus-3-1-1 Bus620-8-1-1 37.91 29.25 47.88 0.0000019

Cable-8-1--1 Cable Bus608-3-1 Bus7-8-1-1 98.56 51.25 111.09 0.0000010

Cable12 Cable Bus35 Bus bar A 0.10 0.04 0.11 0.0020999

Cable511-3-1 Cable MDBR2 BUS B Bus608-3-1 34.06 39.02 51.79 0.0000092

Cable532-1 Cable Bus bar A Bus631-1 0.18 0.09 0.20 0.0034256

Cable533-1 Cable Bus589 MDBR1 BUS A 8.76 10.22 13.46 0.0000042

Cable536-1 Cable Bus bar B Bus636-1 0.05 0.03 0.06 0.0010277

Cable537-1 Cable Bus637-1 MDBR1 BUS B 97.36 113.54 149.57 0.0000035

Cable540-1 Cable Bus bar A Bus813-1 0.06 0.06 0.09 0.0055552

Cable541-1 Cable Bus643-1 MDBR2 BUS A 3.80 6.88 7.86 0.0000055

Cable544-1 Cable Bus bar B Bus646-1 0.06 0.06 0.09 0.0055552

Cable545-1 Cable Bus647-1 MDBR2 BUS B 2.54 3.71 4.50 0.0000044

Cable581 Cable Bus690 Bus691 0.42 0.10 0.43 0.0003676

Cable582 Cable Bus692 Bus696 38.95 24.58 46.06 0.0000021

Cable588 Cable Bus709 Bus687 98.56 51.25 111.09 0.0000010

Cable593 Cable Bus bar A Swy Bus bar A 0.07 0.04 0.08 0.0013703
ETAP
Project: GERD HYDRO POWER PROJECT Page: 10
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVA Base


ID Type From Bus To Bus R X Z Y

Cable601 Cable Bus724 Swy Bus bar B 10.51 5.47 11.85 0.2055375

Cable605 Cable Bus bar A RIGHT INTAKE BUS BAR A 0.07 0.04 0.08 0.0013703

Cable609 Cable Swy Bus bar A Bus822 0.10 0.03 0.11 0.0008019

Cable610 Cable Swy Bus bar B Bus736 0.10 0.03 0.11 0.0008019

Cable611 Cable Bus821 Bus742 73.92 38.44 83.31 0.0000007

Cable612 Cable Bus739 Bus743 73.92 38.44 83.31 0.0000007

Cable618 Cable RIGHT INTAKE BUS BAR B Bus817 0.14 0.03 0.14 0.0013230

Cable619 Cable Bus818 Bus749 98.56 51.25 111.09 0.0000010

Cable622 Cable RIGHT INTAKE BUS BAR A Bus814 0.14 0.04 0.15 0.0010692

Cable623 Cable Bus752 Bus754 98.56 42.50 107.33 0.0000012

Cable663 Cable RIGHT INTAKE BUS BAR A Bus800 0.06 0.02 0.06

Cable665 Cable RIGHT INTAKE BUS BAR B Bus815 0.14 0.03 0.14

Cable667 Cable Bus800 Bus798 0.06 0.02 0.06

Cable668 Cable Bus815 Bus809 0.14 0.03 0.14

Cable669 Cable Bus801 Bottom Out bus A 137.90 38.19 143.09

Cable670 Cable Bus819 Bottom Out BusB 197.91 41.67 202.25

Cable675 Cable Bus bar B RIGHT INTAKE BUS BAR B 4.15 5.02 6.52

Cable177 Cable Bus256 Cable177~ 1.05 0.45 1.14 0.0212423

CB17 Tie Breakr Bus bar B Bus bar A

CB464 Tie Breakr Bus bar A Bus690

CB508 Tie Breakr Bus bar B Bus708

CB516 Tie Breakr Bus bar B Bus724

CB530 Tie Breakr Bus749 Bus754


ETAP
Project: GERD HYDRO POWER PROJECT Page: 11
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

LOAD FLOW REPORT

Bus Voltage Generation Load Load Flow XFMR

ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bottom Out bus A 0.400 95.976 -3.6 0 0 0.084 0.037 Bus801 -0.084 -0.037 138.6 91.5

Bottom Out BusB 0.400 95.836 -3.6 0 0 0.090 0.037 Bus819 -0.090 -0.037 146.6 92.4

Bus bar A 15.000 97.556 -3.0 0 0 0 0 Bus35 -6.536 -2.085 270.7 95.3

Bus631-1 1.569 0.728 68.2 90.7

Bus813-1 0.964 0.448 41.9 90.7

Swy Bus bar A 0.424 0.008 16.7 100.0

RIGHT INTAKE BUS BAR A 0.251 0.039 10.0 98.8

Bus bar B 3.091 0.861 126.6 96.3

Bus690 0.235 0.003 9.3 100.0

Bus bar B 15.000 97.556 -3.0 0 0 0 0 Bus636-1 0.334 0.129 14.1 93.3

Bus646-1 1.844 0.874 80.5 90.4

RIGHT INTAKE BUS BAR B 0.255 0.040 10.2 98.8

Bus bar A -3.091 -0.861 126.6 96.3

Bus708 0.235 0.004 9.3 100.0

Bus724 0.424 -0.186 18.3 -91.5

Bus-3-1 0.400 94.056 -5.8 0 0 0 0 Bus620-8-1 0.015 0.000 23.0 100.0

Bus7-8-1 -0.015 0.000 23.0 100.0

Bus-3-1-1 0.400 93.054 -6.7 0 0 0 0 Bus620-8-1-1 0.029 0.000 45.3 100.0

Bus7-8-1-1 -0.029 0.000 45.3 100.0

Bus7-8-1 0.400 94.947 -5.0 0 0 0 0 Bus608-1-1 -0.015 0.000 23.0 100.0

Bus-3-1 0.015 0.000 23.0 100.0

Bus7-8-1-1 0.400 94.829 -5.2 0 0 0 0 Bus608-3-1 -0.030 -0.001 45.3 100.0

Bus-3-1-1 0.030 0.001 45.3 100.0

* Bus22 18.000 100.000 -0.1 0.000 2.626 0 0 Bus704 -6.582 0.153 211.2 -100.0

Bus35 6.582 2.474 225.5 93.6

Bus35 15.000 97.564 -3.0 0 0 0 0 Bus bar A 6.536 2.083 270.6 95.3

Bus22 -6.536 -2.083 270.6 95.3

Bus253 18.000 100.001 0.0 0 0 0 0 Bus704 0.000 0.021 0.7 0.0

Bus256 0.000 -0.021 0.7 0.0

Bus256 15.000 100.017 0.0 0 0 0 0 Cable177~ 0.000 -0.021 0.8 0.0

Bus253 0.000 0.021 0.8 0.0

Bus589 0.400 95.605 -4.8 0 0 0 0 MDBR1 BUS A 1.559 0.669 2561.4 91.9

Bus631-1 -1.559 -0.669 2561.4 91.9

Bus608-1-1 0.400 94.963 -5.0 0 0 1.221 0.539 MDBR1 BUS A -1.236 -0.540 2050.5 91.7

Bus7-8-1 0.015 0.000 23.0 100.0

Bus608-3-1 0.400 94.860 -5.2 0 0 1.220 0.539 Bus7-8-1-1 0.030 0.001 45.3 100.0
ETAP
Project: GERD HYDRO POWER PROJECT Page: 12
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Bus Voltage Generation Load Load Flow XFMR

ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

MDBR2 BUS B -1.250 -0.540 2071.3 91.8

Bus620-8-1 0.400 94.053 -5.8 0 0 0.015 0.000 Bus-3-1 -0.015 0.000 23.0 100.0

Bus620-8-1-1 0.400 93.042 -6.7 0 0 0.029 0.000 Bus-3-1-1 -0.029 0.000 45.3 100.0

Bus631-1 15.000 97.552 -3.0 0 0 0 0 Bus bar A -1.569 -0.731 68.3 90.6

Bus589 1.569 0.731 68.3 90.6

Bus636-1 15.000 97.556 -3.0 0 0 0 0 Bus bar B -0.334 -0.130 14.1 93.2

Bus637-1 0.334 0.130 14.1 93.2

Bus637-1 0.400 97.186 -3.4 0 0 0 0 MDBR1 BUS B 0.334 0.127 530.0 93.5

Bus636-1 -0.334 -0.127 530.0 93.5

Bus643-1 0.400 96.539 -4.0 0 0 0 0 MDBR2 BUS A 0.962 0.432 1576.2 91.2

Bus813-1 -0.962 -0.432 1576.2 91.2

Bus646-1 15.000 97.554 -3.0 0 0 0 0 Bus bar B -1.844 -0.879 80.6 90.3

Bus647-1 1.844 0.879 80.6 90.3

Bus647-1 0.400 95.612 -4.9 0 0 0 0 MDBR2 BUS B 1.835 0.802 3023.0 91.6

Bus646-1 -1.835 -0.802 3023.0 91.6

Bus687 0.400 96.307 -4.0 0 0 0.232 0.000 Bus709 -0.232 0.000 347.5 100.0

Bus690 15.000 97.556 -3.0 0 0 0 0 Bus691 0.235 0.003 9.3 100.0

Bus bar A -0.235 -0.003 9.3 100.0

Bus691 15.000 97.555 -3.0 0 0 0 0 Bus690 -0.235 -0.003 9.3 100.0

Bus692 0.235 0.003 9.3 100.0

Bus692 0.400 96.652 -3.8 0 0 0 0 Bus696 0.233 0.000 348.4 100.0

Bus691 -0.233 0.000 348.4 100.0

Bus696 0.400 96.558 -3.9 0 0 0.233 0.000 Bus692 -0.233 0.000 348.4 100.0

* Bus704 500.000 100.000 0.0 6.582 -0.161 0 0 Bus253 0.000 -0.021 0.0 0.0

Bus22 6.582 -0.140 7.6 -100.0

Bus708 15.000 97.556 -3.0 0 0 0 0 Bus709 0.235 0.004 9.3 100.0

Bus bar B -0.235 -0.004 9.3 100.0

Bus709 0.400 96.544 -3.9 0 0 0 0 Bus687 0.232 0.000 347.5 100.0

Bus708 -0.232 0.000 347.5 100.0

Bus724 15.000 97.556 -3.0 0 0 0 0 Swy Bus bar B 0.424 -0.186 18.3 -91.5

Bus bar B -0.424 0.186 18.3 -91.5

Bus736 15.000 97.515 -3.0 0 0 0 0 Swy Bus bar B -0.424 -0.010 16.7 100.0

Bus739 0.424 0.010 16.7 100.0

Bus739 0.400 96.892 -4.3 0 0 0 0 Bus743 0.421 0.001 627.2 100.0

Bus736 -0.421 -0.001 627.2 100.0

Bus742 0.400 96.611 -4.4 0 0 0.420 0.000 Bus821 -0.420 0.000 627.5 100.0

Bus743 0.400 96.571 -4.4 0 0 0.420 0.000 Bus739 -0.420 0.000 627.2 100.0

Bus749 0.400 96.435 -3.9 0 0 0.163 0.000 Bus818 -0.161 0.000 241.7 100.0

Bus754 -0.001 0.000 1.9 -98.1


ETAP
Project: GERD HYDRO POWER PROJECT Page: 13
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Bus Voltage Generation Load Load Flow XFMR

ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bus752 0.400 96.603 -3.9 0 0 0 0 Bus754 0.164 0.000 245.5 100.0

Bus814 -0.164 0.000 245.5 100.0

Bus754 0.400 96.435 -3.9 0 0 0.163 0.000 Bus752 -0.164 0.000 245.5 100.0

Bus749 0.001 0.000 1.9 -98.1

Bus798 15.000 97.556 -3.0 0 0 0 0 Bus800 -0.085 -0.039 3.7 91.1

Bus801 0.085 0.039 3.7 91.1

Bus800 15.000 97.556 -3.0 0 0 0 0 RIGHT INTAKE BUS BAR A -0.085 -0.039 3.7 91.1

Bus798 0.085 0.039 3.7 91.1

Bus801 0.400 96.112 -3.6 0 0 0 0 Bottom Out bus A 0.084 0.037 138.6 91.5

Bus798 -0.084 -0.037 138.6 91.5

Bus809 15.000 97.543 -3.0 0 0 0 0 Bus815 -0.091 -0.039 3.9 92.0

Bus819 0.091 0.039 3.9 92.0

Bus813-1 15.000 97.555 -3.0 0 0 0 0 Bus bar A -0.964 -0.453 42.0 90.5

Bus643-1 0.964 0.453 42.0 90.5

Bus814 15.000 97.556 -3.0 0 0 0 0 RIGHT INTAKE BUS BAR A -0.166 -0.002 6.5 100.0

Bus752 0.166 0.002 6.5 100.0

Bus815 15.000 97.543 -3.0 0 0 0 0 RIGHT INTAKE BUS BAR B -0.091 -0.039 3.9 92.0

Bus809 0.091 0.039 3.9 92.0

Bus817 15.000 97.543 -3.0 0 0 0 0 RIGHT INTAKE BUS BAR B -0.163 -0.003 6.4 100.0

Bus818 0.163 0.003 6.4 100.0

Bus818 0.400 96.601 -3.9 0 0 0 0 Bus749 0.162 0.000 241.7 100.0

Bus817 -0.162 0.000 241.7 100.0

Bus819 0.400 96.038 -3.6 0 0 0 0 Bottom Out BusB 0.090 0.037 146.6 92.4

Bus809 -0.090 -0.037 146.6 92.4

Bus821 0.400 96.932 -4.3 0 0 0 0 Bus742 0.421 0.001 627.5 100.0

Bus822 -0.421 -0.001 627.5 100.0

Bus822 15.000 97.555 -3.0 0 0 0 0 Swy Bus bar A -0.424 -0.010 16.7 100.0

Bus821 0.424 0.010 16.7 100.0

MDBR1 BUS A 0.400 95.391 -4.8 0 0 0.316 0.120 Bus608-1-1 1.240 0.546 2050.5 91.5

Bus589 -1.556 -0.666 2561.4 91.9

MDBR1 BUS B 0.400 96.704 -3.6 0 0 0.332 0.125 Bus637-1 -0.332 -0.125 530.0 93.5

MDBR2 BUS A 0.400 96.470 -4.0 0 0 0.961 0.431 Bus643-1 -0.961 -0.431 1576.2 91.3

MDBR2 BUS B 0.400 95.532 -5.0 0 0 0.577 0.252 Bus608-3-1 1.257 0.548 2071.3 91.7

Bus647-1 -1.834 -0.800 3023.0 91.7

RIGHT INTAKE BUS BAR 15.000 97.556 -3.0 0 0 0 0 Bus bar A -0.251 -0.040 10.0 98.8
A
Bus814 0.166 0.001 6.5 100.0

Bus800 0.085 0.039 3.7 91.1

RIGHT INTAKE BUS BAR 15.000 97.543 -3.0 0 0 0 0 Bus817 0.163 0.001 6.4 100.0
B
ETAP
Project: GERD HYDRO POWER PROJECT Page: 14
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Bus Voltage Generation Load Load Flow XFMR

ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bus815 0.091 0.039 3.9 92.0

Bus bar B -0.255 -0.040 10.2 98.8

Swy Bus bar A 15.000 97.556 -3.0 0 0 0 0 Bus bar A -0.424 -0.009 16.7 100.0

Bus822 0.424 0.009 16.7 100.0

Swy Bus bar B 15.000 97.515 -3.0 0 0 0 0 Bus724 -0.424 -0.009 16.7 100.0

Bus736 0.424 0.009 16.7 100.0

Cable177~ 15.000 100.017 0.0 0 0 0 0 Bus256 0.000 0.000 0.0 0.0

* Indicates a voltage regulated bus (voltage controlled or swing type machine connected to it)
# Indicates a bus with a load mismatch of more than 0.1 MVA
ETAP
Project: GERD HYDRO POWER PROJECT Page: 15
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Bus Loading Summary Report

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bottom Out bus A 0.400 0.070 0.037 0.015 0 0 0 0 0 0.092 91.5 138.6

Bottom Out BusB 0.400 0.072 0.037 0.018 0 0 0 0 0 0.097 92.4 146.6

Bus bar A 15.000 0 0 0 0 0 0 0 0 6.860 95.3 270.7

Bus bar B 15.000 0 0 0 0 0 0 0 0 3.264 94.7 128.8

Bus-3-1 0.400 0 0 0 0 0 0 0 0 0.015 100.0 23.0

Bus-3-1-1 0.400 0 0 0 0 0 0 0 0 0.029 100.0 45.3

Bus7-8-1 0.400 0 0 0 0 0 0 0 0 0.015 100.0 23.0

Bus7-8-1-1 0.400 0 0 0 0 0 0 0 0 0.030 100.0 45.3

Bus22 18.000 0 0 0 0 0 0 0 0 7.087 92.9 227.3

Bus35 15.000 0 0 0 0 0 0 0 0 6.860 95.3 270.6

Bus253 18.000 0 0 0 0 0 0 0 0 0.021 0.0 0.7

Bus256 15.000 0 0 0 0 0 0 0 0 0.021 0.0 0.8

Bus589 0.400 0 0 0 0 0 0 0 0 1.697 91.9 2561.4

Bus608-1-1 0.400 1.143 0.503 0.078 0.037 0 0 0 0 1.349 91.7 2050.5

Bus608-3-1 0.400 1.143 0.503 0.077 0.036 0 0 0 0 1.361 91.8 2071.3

Bus620-8-1 0.400 0.007 0 0.008 0 0 0 0 0 0.015 100.0 23.0

Bus620-8-1-1 0.400 0.013 0 0.016 0 0 0 0 0 0.029 100.0 45.3

Bus631-1 15.000 0 0 0 0 0 0 0 0 1.731 90.6 68.3

Bus636-1 15.000 0 0 0 0 0 0 0 0 0.358 93.2 14.1

Bus637-1 0.400 0 0 0 0 0 0 0 0 0.357 93.5 530.0

Bus643-1 0.400 0 0 0 0 0 0 0 0 1.054 91.2 1576.2

Bus646-1 15.000 0 0 0 0 0 0 0 0 2.043 90.3 80.6

Bus647-1 0.400 0 0 0 0 0 0 0 0 2.002 91.6 3023.0

Bus687 0.400 0 0 0.232 0 0 0 0 0 0.232 100.0 347.5

Bus690 15.000 0 0 0 0 0 0 0 0 0.235 100.0 9.3

Bus691 15.000 0 0 0 0 0 0 0 0 0.235 100.0 9.3

Bus692 0.400 0 0 0 0 0 0 0 0 0.233 100.0 348.4

Bus696 0.400 0 0 0.233 0 0 0 0 0 0.233 100.0 348.4

Bus704 500.000 0 0 0 0 0 0 0 0 6.584 100.0 7.6

Bus708 15.000 0 0 0 0 0 0 0 0 0.235 100.0 9.3

Bus709 0.400 0 0 0 0 0 0 0 0 0.232 100.0 347.5

Bus724 15.000 0 0 0 0 0 0 0 0 0.463 91.5 18.3

Bus736 15.000 0 0 0 0 0 0 0 0 0.424 100.0 16.7

Bus739 0.400 0 0 0 0 0 0 0 0 0.421 100.0 627.2

Bus742 0.400 0 0 0.420 0 0 0 0 0 0.420 100.0 627.5

Bus743 0.400 0 0 0.420 0 0 0 0 0 0.420 100.0 627.2


ETAP
Project: GERD HYDRO POWER PROJECT Page: 16
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bus749 0.400 0 0 0.163 0 0 0 0 0 0.163 100.0 243.6

Bus752 0.400 0 0 0 0 0 0 0 0 0.164 100.0 245.5

Bus754 0.400 0 0 0.163 0 0 0 0 0 0.164 100.0 245.5

Bus798 15.000 0 0 0 0 0 0 0 0 0.094 91.1 3.7

Bus800 15.000 0 0 0 0 0 0 0 0 0.094 91.1 3.7

Bus801 0.400 0 0 0 0 0 0 0 0 0.092 91.5 138.6

Bus809 15.000 0 0 0 0 0 0 0 0 0.099 92.0 3.9

Bus813-1 15.000 0 0 0 0 0 0 0 0 1.065 90.5 42.0

Bus814 15.000 0 0 0 0 0 0 0 0 0.166 100.0 6.5

Bus815 15.000 0 0 0 0 0 0 0 0 0.099 92.0 3.9

Bus817 15.000 0 0 0 0 0 0 0 0 0.163 100.0 6.4

Bus818 0.400 0 0 0 0 0 0 0 0 0.162 100.0 241.7

Bus819 0.400 0 0 0 0 0 0 0 0 0.098 92.4 146.6

Bus821 0.400 0 0 0 0 0 0 0 0 0.421 100.0 627.5

Bus822 15.000 0 0 0 0 0 0 0 0 0.424 100.0 16.7

MDBR1 BUS A 0.400 0.206 0.075 0.110 0.046 0 0 0 0 1.693 91.9 2561.4

MDBR1 BUS B 0.400 0.165 0.076 0.167 0.050 0 0 0 0 0.355 93.5 530.0

MDBR2 BUS A 0.400 0.552 0.232 0.410 0.199 0 0 0 0 1.053 91.3 1576.2

MDBR2 BUS B 0.400 0.302 0.135 0.275 0.116 0 0 0 0 2.001 91.7 3023.0

RIGHT INTAKE BUS BAR A 15.000 0 0 0 0 0 0 0 0 0.254 98.8 10.0

RIGHT INTAKE BUS BAR B 15.000 0 0 0 0 0 0 0 0 0.258 98.8 10.2

Swy Bus bar A 15.000 0 0 0 0 0 0 0 0 0.424 100.0 16.7

Swy Bus bar B 15.000 0 0 0 0 0 0 0 0 0.424 100.0 16.7

* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).

# Indicates operating load of a bus exceeds the bus marginal limit ( 95.0% of the Continuous Ampere rating).
ETAP
Project: GERD HYDRO POWER PROJECT Page: 17
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Branch Loading Summary Report

Transformer
CKT / Branch Cable & Reactor
Ampacity Loading Capability Loading (input) Loading (output)

ID Type (Amp) Amp % (MVA) MVA % MVA %

Cable 3 Cable 7086.11 2050.49 28.94

Cable-8-1 Cable 3520.98 22.96 0.65

Cable-8-1- Cable 750.21 22.96 3.06

Cable-8-1-1 Cable 1760.49 45.25 2.57

Cable-8-1--1 Cable 750.21 45.25 6.03

Cable12 Cable 586.05 270.67 46.19

Cable511-3-1 Cable 3110.75 2071.32 66.59

Cable532-1 Cable 750.21 68.30 9.10

Cable533-1 Cable 5042.31 2561.39 50.80

Cable536-1 Cable 750.21 14.13 1.88

Cable537-1 Cable 1512.69 530.02 35.04

Cable540-1 Cable 1333.18 42.03 3.15

Cable541-1 Cable 8661.58 1576.18 18.20

Cable544-1 Cable 1333.18 80.61 6.05

Cable545-1 Cable 8888.99 3023.01 34.01

Cable581 Cable 156.32 9.29 5.94

Cable582 Cable 1779.14 348.42 19.58

Cable588 Cable 750.21 347.52 46.32

Cable593 Cable 750.21 16.73 2.23

Cable601 Cable 750.21 18.27 2.44

Cable605 Cable 750.21 10.04 1.34

Cable609 Cable 468.92 16.73 3.57

Cable610 Cable 468.92 16.73 3.57

Cable611 Cable 750.21 627.50 83.64

Cable612 Cable 750.21 627.24 83.61

Cable618 Cable 468.95 6.45 1.37

Cable619 Cable 750.21 241.70 32.22

Cable622 Cable 468.92 6.55 1.40

Cable623 Cable 691.37 245.47 35.50

Cable663 Cable 590.81 3.70 0.63

Cable665 Cable 266.39 3.91 1.47

Cable667 Cable 590.81 3.70 0.63

Cable668 Cable 266.39 3.91 1.47


ETAP
Project: GERD HYDRO POWER PROJECT Page: 18
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Transformer
CKT / Branch Cable & Reactor
Ampacity Loading Capability Loading (input) Loading (output)

ID Type (Amp) Amp % (MVA) MVA % MVA %

Cable669 Cable 359.53 138.60 38.55

Cable670 Cable 266.39 146.65 55.05

Cable675 Cable 1611.51 10.17 0.63

Cable177 Cable 691.37 0.82 0.12

MAIN TRANSFORMER 08 Transformer 417.000 0.021 0.0 0.021 0.0

MAIN TRANSFORMER10 Transformer 417.000 6.584 1.6 6.584 1.6

MDBR1-TR1 Transformer 3.150 1.731 55.0 1.697 53.9

MDBR1-TR2 Transformer 1.765 0.358 20.3 0.357 20.2

MDBR2-TR1 Transformer 4.000 1.065 26.6 1.054 26.4

MDBR2-TR2 Transformer 3.483 2.043 58.7 2.002 57.5

OFF-TR1 Transformer 0.600 0.235 39.2 0.233 38.9

OFF-TR2 Transformer 0.535 0.235 43.9 0.232 43.4

T25-8-1 Transformer 0.040 0.015 37.8 0.015 37.4

T25-8-1-1 Transformer 0.040 0.030 74.3 0.029 72.9

T40 Transformer 1.000 0.424 42.4 0.421 42.1

T41 Transformer 1.000 0.424 42.4 0.421 42.1

T42 Transformer 0.400 0.163 40.8 0.162 40.4

T43 Transformer 0.400 0.166 41.5 0.164 41.1

T44 Transformer 0.225 0.094 41.6 0.092 41.0

T45 Transformer 0.120 0.099 82.6 0.098 81.3

TR-T1 Transformer 9.000 7.032 78.1 6.860 76.2

TR-T2 Transformer 9.000 0.021 0.2 0.021 0.2

* Indicates a branch with operating load exceeding the branch capability.


ETAP
Project: GERD HYDRO POWER PROJECT Page: 19
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Branch Losses Summary Report

Vd
CKT / Branch From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
ID MW Mvar MW Mvar kW kvar From To in Vmag

Cable669 -0.084 -0.037 0.084 0.037 0.1 0.0 96.0 96.1 0.14

Cable670 -0.090 -0.037 0.090 0.037 0.2 0.0 95.8 96.0 0.20

Cable12 -6.536 -2.085 6.536 2.083 0.5 -1.8 97.6 97.6 0.01

Cable532-1 1.569 0.728 -1.569 -0.731 0.1 -3.2 97.6 97.6 0.00

Cable540-1 0.964 0.448 -0.964 -0.453 0.0 -5.3 97.6 97.6 0.00

Cable593 0.424 0.008 -0.424 -0.009 0.0 -1.3 97.6 97.6 0.00

Cable605 0.251 0.039 -0.251 -0.040 0.0 -1.3 97.6 97.6 0.00

Cable536-1 0.334 0.129 -0.334 -0.130 0.0 -1.0 97.6 97.6 0.00

Cable544-1 1.844 0.874 -1.844 -0.879 0.0 -5.3 97.6 97.6 0.00

Cable675 0.255 0.040 -0.255 -0.040 0.0 0.0 97.6 97.5 0.01

Cable-8-1 0.015 0.000 -0.015 0.000 0.0 0.0 94.1 94.1 0.00

T25-8-1 -0.015 0.000 0.015 0.000 0.1 0.2 94.1 94.9 0.89

Cable-8-1-1 0.029 0.000 -0.029 0.000 0.0 0.0 93.1 93.0 0.01

T25-8-1-1 -0.029 0.000 0.030 0.001 0.5 0.8 93.1 94.8 1.78

Cable-8-1- -0.015 0.000 0.015 0.000 0.0 0.0 94.9 95.0 0.02

Cable-8-1--1 -0.030 -0.001 0.030 0.001 0.0 0.0 94.8 94.9 0.03

MAIN TRANSFORMER10 -6.582 0.153 6.582 -0.140 0.3 13.0 100.0 100.0 0.00

TR-T1 6.582 2.474 -6.536 -2.083 45.9 390.1 100.0 97.6 2.44

MAIN TRANSFORMER 08 0.000 0.021 0.000 -0.021 0.0 0.0 100.0 100.0 0.00

TR-T2 0.000 -0.021 0.000 0.021 0.0 0.0 100.0 100.0 0.02

Cable177 0.000 -0.021 0.000 0.000 0.0 -21.2 100.0 100.0 0.00

Cable533-1 1.559 0.669 -1.556 -0.666 2.8 3.2 95.6 95.4 0.21

MDBR1-TR1 -1.559 -0.669 1.569 0.731 10.3 61.6 95.6 97.6 1.95

Cable 3 -1.236 -0.540 1.240 0.546 3.8 6.4 95.0 95.4 0.43

Cable511-3-1 -1.250 -0.540 1.257 0.548 7.0 8.0 94.9 95.5 0.67

MDBR1-TR2 0.334 0.130 -0.334 -0.127 0.4 2.6 97.6 97.2 0.37

Cable537-1 0.334 0.127 -0.332 -0.125 1.3 1.5 97.2 96.7 0.48

Cable541-1 0.962 0.432 -0.961 -0.431 0.5 0.8 96.5 96.5 0.07

MDBR2-TR1 -0.962 -0.432 0.964 0.453 2.5 21.2 96.5 97.6 1.02

MDBR2-TR2 1.844 0.879 -1.835 -0.802 9.2 77.9 97.6 95.6 1.94

Cable545-1 1.835 0.802 -1.834 -0.800 1.1 1.6 95.6 95.5 0.08

Cable588 -0.232 0.000 0.232 0.000 0.6 0.3 96.3 96.5 0.24

Cable581 0.235 0.003 -0.235 -0.003 0.0 -0.3 97.6 97.6 0.00

OFF-TR1 0.235 0.003 -0.233 0.000 2.2 3.2 97.6 96.7 0.90

Cable582 0.233 0.000 -0.233 0.000 0.2 0.1 96.7 96.6 0.09
ETAP
Project: GERD HYDRO POWER PROJECT Page: 20
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Vd
CKT / Branch From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
ID MW Mvar MW Mvar kW kvar From To in Vmag

OFF-TR2 0.235 0.004 -0.232 0.000 2.4 3.6 97.6 96.5 1.01

Cable601 0.424 -0.186 -0.424 -0.009 0.2 -195.4 97.6 97.5 0.04

Cable610 -0.424 -0.010 0.424 0.009 0.0 -0.8 97.5 97.5 0.00

T41 0.424 0.010 -0.421 -0.001 2.6 9.1 97.5 96.9 0.62

Cable612 0.421 0.001 -0.420 0.000 1.4 0.7 96.9 96.6 0.32

Cable611 -0.420 0.000 0.421 0.001 1.4 0.7 96.6 96.9 0.32

Cable619 -0.161 0.000 0.162 0.000 0.3 0.1 96.4 96.6 0.17

Cable623 0.164 0.000 -0.164 0.000 0.3 0.1 96.6 96.4 0.17

T43 -0.164 0.000 0.166 0.002 1.6 2.4 96.6 97.6 0.95

Cable667 -0.085 -0.039 0.085 0.039 0.0 0.0 97.6 97.6 0.00

T44 0.085 0.039 -0.084 -0.037 0.9 1.4 97.6 96.1 1.44

Cable663 -0.085 -0.039 0.085 0.039 0.0 0.0 97.6 97.6 0.00

Cable668 -0.091 -0.039 0.091 0.039 0.0 0.0 97.5 97.5 0.00

T45 0.091 0.039 -0.090 -0.037 1.0 1.5 97.5 96.0 1.50

Cable622 -0.166 -0.002 0.166 0.001 0.0 -1.0 97.6 97.6 0.00

Cable665 -0.091 -0.039 0.091 0.039 0.0 0.0 97.5 97.5 0.00

Cable618 -0.163 -0.003 0.163 0.001 0.0 -1.3 97.5 97.5 0.00

T42 0.163 0.003 -0.162 0.000 1.6 2.3 97.5 96.6 0.94

T40 -0.421 -0.001 0.424 0.010 2.6 9.1 96.9 97.6 0.62

Cable609 -0.424 -0.010 0.424 0.009 0.0 -0.8 97.6 97.6 0.00

105.9 383.9
ETAP
Project: GERD HYDRO POWER PROJECT Page: 21
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

Alert Summary Report

% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0

Cable 100.0 95.0

Reactor 100.0 95.0

Line 100.0 95.0

Transformer 100.0 95.0

Panel 100.0 95.0

Protective Device 100.0 95.0

Generator 100.0 95.0

Inverter/Charger 100.0 95.0

Bus Voltage
OverVoltage 105.0 105.0

UnderVoltage 95.0 95.0

Generator Excitation
OverExcited (Q Max.) 100.0 95.0

UnderExcited (Q Min.)

Critical Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Bus-3-1 Bus Under Voltage 0.40 kV 0.38 94.1 3-Phase

Bus-3-1-1 Bus Under Voltage 0.40 kV 0.37 93.1 3-Phase

Bus608-1-1 Bus Under Voltage 0.40 kV 0.38 95.0 3-Phase

Bus608-3-1 Bus Under Voltage 0.40 kV 0.38 94.9 3-Phase

Bus620-8-1 Bus Under Voltage 0.40 kV 0.38 94.1 3-Phase

Bus620-8-1-1 Bus Under Voltage 0.40 kV 0.37 93.0 3-Phase

Bus7-8-1 Bus Under Voltage 0.40 kV 0.38 94.9 3-Phase

Bus7-8-1-1 Bus Under Voltage 0.40 kV 0.38 94.8 3-Phase

Gen 10 Generator Under Power 0.00 MW 0.00 0.0 3-Phase

Gen8 Generator Under Power 0.00 MW 0.00 0.0 3-Phase


ETAP
Project: GERD HYDRO POWER PROJECT Page: 22
12.6.0H
Location: Date: 10-12-2016
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: GRANDRENAISSANCE1 Config.: Normal

SUMMARY OF TOTAL GENERATION , LOADING & DEMAND

MW Mvar MVA % PF

Source (Swing Buses): 6.582 -0.161 6.584 99.97 Leading

Source (Non-Swing Buses): 0.000 2.626 2.626 0.00 Leading

Total Demand: 6.582 2.465 7.029 93.65 Lagging

Total Motor Load: 3.672 1.598 4.005 91.69 Lagging

Total Static Load: 2.805 0.483 2.846 98.55 Lagging

Total Constant I Load: 0.000 0.000 0.000

Total Generic Load: 0.000 0.000 0.000

Apparent Losses: 0.106 0.384

System Mismatch: 0.000 0.000

Number of Iterations: 1