You are on page 1of 14

Project: ihsan manarul ETAP Page: 1

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Electrical Transient Analyzer Program

Load Flow Analysis

Loading Category (1): Design

Generation Category (1): Design

Load Diversity Factor: None

Swing V-Control Load Total


Number of Buses: 1 2 11 14

Line/Cable/
XFMR2 XFMR3 Reactor Busway Impedance Tie PD Total
Number of Branches: 4 2 1 7 0 0 14

Method of Solution: Adaptive Newton-Raphson Method

Maximum No. of Iteration: 99

Precision of Solution: 0.0001000

System Frequency: 60.00 Hz

Unit System: English

Project Filename: TUGAS 5

Output Filename: D:\TUGAS 5 ihsan\Untitled.lfr


Project: ihsan manarul ETAP Page: 2

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

Cable / Busway Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable / Busway Resistance: Yes Individual


Project: ihsan manarul ETAP Page: 3

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Bus Input Data

Load

Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bus1 34.500 1 100.0 0.0

Bus2 34.500 1 100.0 0.0

Bus3 34.500 1 100.0 0.0

Bus4 13.800 1 100.0 0.0

Bus5 13.800 1 100.0 0.0

Bus6 13.800 1 100.0 0.0

Bus7 13.800 1 100.0 0.0

Bus8 2.400 1 100.0 0.0 4.003 1.577

Bus9 13.800 1 100.0 0.0

Bus10 13.800 1 100.0 0.0

Bus11 2.400 1 100.0 0.0 4.003 1.577

Bus12 2.400 1 100.0 0.0 8.000 0.000

Bus13 13.800 1 100.0 0.0

Bus14 2.400 1 100.0 0.0 42.772 26.508 15.028 9.314

Total Number of Buses: 14 50.777 29.661 23.028 9.314 0.000 0.000 0.000 0.000

Generation Bus Voltage Generation Mvar Limits

ID kV Type Sub-sys % Mag. Angle MW Mvar % PF Max Min

Bus1 34.500 Swing 1 100.0 0.0

Bus4 13.800 Voltage Control 1 100.0 0.0 0.000 0.000 0.000

Bus6 13.800 Voltage Control 1 100.0 0.0 0.000 0.000 0.000

0.000 0.000
Project: ihsan manarul ETAP Page: 4

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Line/Cable/Busway Input Data

ohms or siemens/1000 ft per Conductor (Cable) or per Phase (Line/Busway)

Line/Cable/Busway Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y

Cable1 0,6MCUN3 500 400.0 0.0 1 75 0.029400 0.034896

Cable2 0,6MCUN1 500 400.0 0.0 1 75 0.029400 0.046596

Cable3 0,6MCUN3 250 100.0 0.0 1 75 0.055200 0.051600

Cable4 0,6MCUN3 250 100.0 0.0 1 75 0.055200 0.051600

Cable5 0,6MCUN3 250 100.0 0.0 1 75 0.055200 0.037896

Cable6 0,6MCUN3 250 100.0 0.0 1 75 0.055200 0.037896

Cable7 0,6MCUN3 250 1300.0 0.0 1 75 0.055200 0.037896

Line / Cable / Busway resistances are listed at the specified temperatures.


Project: ihsan manarul ETAP Page: 5

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted Phase Shift

ID Phase MVA Prim. kV Sec. kV % Z1 X1/R1 + 5% - 5% % Tol. Prim. Sec. %Z Type Angle

T11 3-Phase 68.000 13.800 2.400 6.50 34.10 0 0 0 0 0 6.5000 Dyn 0.000
T12 3-Phase 68.000 13.800 2.400 6.50 34.10 0 0 0 0 0 6.5000 Dyn 0.000

T13 3-Phase 68.000 13.800 2.400 6.50 34.10 0 0 0 0 0 6.5000 Dyn 0.000

T14 3-Phase 68.000 13.800 2.400 6.50 34.10 0 0 0 0 0 6.5000 Dyn 0.000

3-Winding Transformer Input Data

Transformer Rating Tap Impedance Z Variation Phase Shift


ID Winding MVA kV % % Z1 X1/R1 MVAb % Tol. + 5% - 5% Type Angle

T9 Primary: 68.000 34.500 0 Zps = 7.50 34.50 68.000 0 0 0

Secondary: 68.000 13.800 0 Zpt = 7.50 13.80 68.000 0 Std Pos. Seq. 0.000

Tertiary: 68.000 13.800 0 Zst = 14.50 13.80 68.000 0 Std Pos. Seq. 0.000

T10 Primary: 68.000 34.500 0 Zps = 7.50 34.50 68.000 0 0 0

Secondary: 68.000 13.800 0 Zpt = 7.50 13.80 68.000 0 Std Pos. Seq. 0.000

Tertiary: 68.000 13.800 0 Zst = 14.50 13.80 68.000 0 Std Pos. Seq. 0.000
Project: ihsan manarul ETAP Page: 6

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Reactor Input Data

Reactor Connected Buses Rated Impedance

ID Phase From Bus To Bus kV X (ohm) X/R % Tol.

X1 3-Phase Bus8 Bus11 13.800 73.90289 19.50 0.00


Project: ihsan manarul ETAP Page: 7

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVA Base


ID Type From Bus To Bus R X Z Y

T11 2W XFMR Bus7 Bus8 0.28 9.55 9.56

T12 2W XFMR Bus9 Bus11 0.28 9.55 9.56

T13 2W XFMR Bus10 Bus12 0.28 9.55 9.56

T14 2W XFMR Bus13 Bus14 0.28 9.55 9.56

T9 3W Xfmr Bus3 Bus4 0.09 11.39 11.39

3W Xfmr Bus3 Bus5 0.60 11.39 11.40

3W Xfmr Bus4 Bus5 161.17 228.94 279.98

T10 3W Xfmr Bus2 Bus5 0.09 11.39 11.39

3W Xfmr Bus2 Bus6 0.60 11.39 11.40

3W Xfmr Bus5 Bus6 161.17 228.94 279.98

Cable1 Cable Bus1 Bus3 0.10 0.12 0.15

Cable2 Cable Bus1 Bus2 0.10 0.16 0.19

Cable3 Cable Bus4 Bus7 0.29 0.27 0.40

Cable4 Cable Bus5 Bus9 0.29 0.27 0.40

Cable5 Cable Bus5 Bus10 0.29 0.20 0.35

Cable6 Cable Bus6 Bus13 0.29 0.20 0.35

Cable7 Cable Bus12 Bus14 124.58 85.53 151.12

X1 Reactor Bus8 Bus11 6579.67 128303.60 128472.20


Project: ihsan manarul ETAP Page: 8

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

LOAD FLOW REPORT

Bus Voltage Generation Load Load Flow XFMR


ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

* Bus1 34.500 100.000 0.0 72.464 47.417 0.000 0.000 Bus3 15.241 2.996 259.9 98.1

Bus2 57.223 44.422 1212.3 79.0

Bus2 34.500 99.874 0.0 0.000 0.000 0.000 0.000 Bus1 -57.171 -44.340 1212.3 79.0

Bus5 57.171 44.340 1212.3 79.0

&Bus6

Bus3 34.500 99.981 0.0 0.000 0.000 0.000 0.000 Bus1 -15.238 -2.993 259.9 98.1

Bus4 15.238 2.993 259.9 98.1

&Bus5

Bus4 13.800 99.810 -0.3 0.000 0.000 0.000 0.000 Bus7 4.004 1.595 180.7 92.9

Bus5 -4.004 -1.595 180.7 92.9

&Bus3

Bus5 13.800 99.751 -0.7 0.000 0.000 0.000 0.000 Bus9 4.003 1.595 180.7 92.9

Bus10 15.695 -0.102 658.3 100.0

Bus3 -11.225 -1.232 473.6 99.4

&Bus4

Bus6 -8.473 -0.261 355.5 100.0

&Bus2

Bus6 13.800 94.793 -3.1 0.000 0.000 0.000 0.000 Bus13 48.370 39.219 2748.4 77.7

Bus2 -48.370 -39.219 2748.4 77.7

&Bus5

Bus7 13.800 99.794 -0.3 0.000 0.000 0.000 0.000 Bus4 -4.004 -1.595 180.7 92.9

Bus8 4.004 1.595 180.7 92.9

Bus8 2.400 99.631 -0.5 0.000 0.000 4.003 1.577 Bus7 -4.003 -1.577 1038.9 93.0

Bus11 0.001 0.000 0.1 100.0

Bus9 13.800 99.735 -0.7 0.000 0.000 0.000 0.000 Bus5 -4.002 -1.595 180.7 92.9

Bus11 4.002 1.595 180.7 92.9

Bus10 13.800 99.705 -0.7 0.000 0.000 0.000 0.000 Bus5 -15.688 0.107 658.3 100.0

Bus12 15.688 -0.107 658.3 100.0

Bus11 2.400 99.571 -0.9 0.000 0.000 4.003 1.577 Bus9 -4.002 -1.577 1039.2 93.0

Bus8 -0.001 0.000 0.1 100.0

Bus12 2.400 99.683 -1.6 0.000 0.000 7.949 0.000 Bus14 7.732 -0.343 1867.7 -99.9
Project: ihsan manarul ETAP Page: 9

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Bus Voltage Generation Load Load Flow XFMR


ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bus10 -15.681 0.343 3785.1 -100.0

Bus13 13.800 94.562 -3.1 0.000 0.000 0.000 0.000 Bus6 -48.245 -39.133 2748.4 77.7

Bus14 48.245 39.133 2748.4 77.7

Bus14 2.400 90.590 -6.1 0.000 0.000 55.105 34.151 Bus12 -6.981 0.859 1867.7 -99.3

Bus13 -48.124 -35.010 15803.3 80.9


* Indicates a voltage regulated bus ( voltage controlled or swing type machine connected to it)
# Indicates a bus with a load mismatch of more than 0.1 MVA
Project: ihsan manarul ETAP Page: 10

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Bus Loading Summary Report

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bus1 34.500 86.599 83.7 1449.2


Bus2 34.500 72.350 79.0 1212.3
Bus3 34.500 15.529 98.1 259.9
Bus4 13.800 4.310 92.9 180.7
Bus5 13.800 19.762 99.7 828.9
Bus6 13.800 62.272 77.7 2748.4
Bus7 13.800 4.310 92.9 180.7
Bus8 2.400 4.003 1.577 4.303 93.0 1038.9
Bus9 13.800 4.308 92.9 180.7
Bus10 13.800 15.688 100.0 658.3
Bus11 2.400 4.003 1.577 4.302 93.0 1039.3
Bus12 2.400 7.949 15.685 100.0 3785.1
Bus13 13.800 62.121 77.7 2748.4
Bus14 2.400 42.772 26.508 12.333 7.643 65.286 84.4 17336.7

* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).
# Indicates operating load of a bus exceeds the bus marginal limit (95.0% of the Continuous Ampere rating).
Project: ihsan manarul ETAP Page: 11

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Branch Loading Summary Report

Transformer
CKT / Branch Busway / Cable & Reactor
Loading (input) Loading (output)
Ampacity Loading Capability
ID Type (Amp) Amp % (MVA) MVA % MVA %

Cable1 Cable 363.66 259.93 71.48

* Cable2 Cable 376.64 1212.29 321.87

Cable3 Cable 245.67 180.67 73.54

Cable4 Cable 245.67 180.73 73.57

* Cable5 Cable 245.67 658.28 267.96

* Cable6 Cable 245.67 2748.41 1118.76

* Cable7 Cable 245.67 1867.67 760.25

T11 Transformer 68.000 4.310 6.3 4.303 6.3

T12 Transformer 68.000 4.308 6.3 4.301 6.3

T13 Transformer 68.000 15.688 23.1 15.685 23.1

T14 Transformer 68.000 62.121 91.4 59.512 87.5

T9 3W XFMR p 68.000 15.529 22.8

3W XFMR s 68.000 4.310 6.3

3W XFMR t 68.000 11.293 16.6

* T10 3W XFMR p 68.000 72.350 106.4

3W XFMR s 68.000 8.477 12.5

3W XFMR t 68.000 62.272 91.6

* Indicates a branch with operating load exceeding the branch capability.


Project: ihsan manarul ETAP Page: 12

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Branch Losses Summary Report

Vd
From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop

Branch ID MW Mvar MW Mvar kW kvar From To in Vmag

Cable1 15.241 2.996 -15.238 -2.993 2.4 2.8 100.0 100.0 0.02

Cable2 57.223 44.422 -57.171 -44.340 51.8 82.2 100.0 99.9 0.13

Cable3 4.004 1.595 -4.004 -1.595 0.5 0.5 99.8 99.8 0.02

Cable4 4.003 1.595 -4.002 -1.595 0.5 0.5 99.8 99.7 0.02

Cable5 15.695 -0.102 -15.688 0.107 7.2 4.9 99.8 99.7 0.05

Cable6 48.370 39.219 -48.245 -39.133 125.1 85.9 94.8 94.6 0.23

Cable7 7.732 -0.343 -6.981 0.859 750.9 515.5 99.7 90.6 9.09

T10 57.171 44.340 -8.473 -0.261 328.1 4859.6 99.9 99.8 0.12

0.000 0.000 -48.370 -39.219 99.9 94.8 5.08

T11 4.004 1.595 -4.003 -1.577 0.5 17.8 99.8 99.6 0.16

T12 4.002 1.595 -4.002 -1.577 0.5 17.8 99.7 99.6 0.16

T13 15.688 -0.107 -15.681 0.343 6.9 236.6 99.7 99.7 0.02

T14 48.245 39.133 -48.124 -35.010 120.9 4123.4 94.6 90.6 3.97

T9 15.238 2.993 -4.004 -1.595 8.8 165.1 100.0 99.8 0.17

0.000 0.000 -11.225 -1.232 100.0 99.8 0.23

X1 0.001 0.000 -0.001 0.000 0.0 0.0 99.6 99.6 0.06

1404.3 10112.7

* This Transmission Line includes Series Capacitor.


Project: ihsan manarul ETAP Page: 13

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

Alert Summary Report

% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0

Cable / Busway 100.0 95.0

Reactor 100.0 95.0

Line 100.0 95.0

Transformer 100.0 95.0

Panel 100.0 95.0

Protective Device 100.0 95.0

Generator 100.0 95.0

Inverter/Charger 100.0 95.0

Bus Voltage
OverVoltage 105.0 102.0

UnderVoltage 95.0 98.0

Generator Excitation
OverExcited (Q Max.) 100.0 95.0

UnderExcited (Q Min.) 100.0

Critical Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Bus13 Bus Under Voltage 13.800 kV 13.050 94.6 3-Phase

Bus14 Bus Under Voltage 2.400 kV 2.174 90.6 3-Phase

Bus6 Bus Under Voltage 13.800 kV 13.081 94.8 3-Phase

Cable2 Cable Overload 376.643 Amp 1212.294 321.9 3-Phase

Cable5 Cable Overload 245.666 Amp 658.284 268.0 3-Phase

Cable6 Cable Overload 245.666 Amp 2748.407 1118.8 3-Phase

Cable7 Cable Overload 245.666 Amp 1867.671 760.2 3-Phase

Gen3 Generator Under Excited 0.000 Mvar 0.000 0.0 3-Phase

Gen3 Generator Under Power 0.000 MW 0.000 0.0 3-Phase

Gen4 Generator Under Excited 0.000 Mvar 0.000 0.0 3-Phase

Gen4 Generator Under Power 0.000 MW 0.000 0.0 3-Phase

T10 Transformer Overload 68.000 MVA 72.350 106.4 3-Phase


Project: ihsan manarul ETAP Page: 14

Location: TSM 19.0.1C Date: 06-30-2021

Contract: SN:

Engineer: Revision: Base


Study Case: LF
Filename: TUGAS 5 Config.: Normal

SUMMARY OF TOTAL GENERATION , LOADING & DEMAND

MW Mvar MVA % PF

Source (Swing Buses): 72.464 47.417 86.599 83.68 Lagging

Source (Non-Swing Buses): 0.000 0.000 0.000

Total Demand: 72.464 47.417 86.599 83.68 Lagging

Total Motor Load: 50.777 29.661 58.806 86.35 Lagging

Total Static Load: 20.282 7.643 21.675 93.58 Lagging

Total Constant I Load: 0.000 0.000 0.000

Total Generic Load: 0.000 0.000 0.000

Apparent Losses: 1.404 10.113

System Mismatch: 0.000 0.000

Number of Iterations: 3

You might also like