Professional Documents
Culture Documents
Field: AAB
Vessel/Rig:
I hereby confirm that the assurance checks in my area of responsibility are complete. The vessel
may safely approach the above noted facility and perform the designated works, subject to Sign Date
implementation of mandatory actions noted below.
Vessel: Drilling consultant/ Field GM
Emergency Equipment:
Field General Manger
Risers & Topsides Piping:
Production ass. Manager
Wells: Offshore production ass. General Manager
Compliance With Assurance
HSE General Manager
Process:
The following actions must be completed before the vessel may safely approach the facility. Offshore Production GM to
confirm these actions are complete, before submitting this certificate to Field GM for final approval.
ACTIONS COMPLETE
Items to be Actioned Prior To Approach
Sign (By O/P GM) Date
Validation
In accordance with the assurances provided above, approach certificate approved for the following period:
Valid From: To: Signed: Engineering GM
Revalidation From: To: Signed: Engineering GM
(Note: Certificate to be revalidated by Engineering GM after 3-months).
Vessel/Rig Approach Assurance Page 2 of 3
Field AAB
Vessel/Rig
Estimated No of Day's On
Installation Planned Approach Date
Location
Known Red Anomalies Affecting Approach Action required to permit approach Signed
Vessel/Rig Approach Assurance Page 3 of 3
Field AAB
Vessel/Rig
WI Piping Inspected
Known Red Anomalies Affecting Approach Action required to permit approach Signed
Yes/No Yes/No
Do any wells have significant B annulus pressure (80 % of surface
All free flowing wells have a valid communication test.
casing collapse pressure psi) or direct communication with A annulus.
Do all wells have valid Tree checks, SSSV Tests, Do any wells have tree integrity issues that fall below Amapetco
communication tests. minimum acceptance guidelines.
Do any Wells have conductor vibration Does any Well have Production Or Test Header Valves Passing.
Outstanding actions required to establish well integrity and develop associated pre-approach mandatory actions.
All wells not meeting the minimum well integrity requirments for rig mobilisation and SIMOPS must be killed and/or isolated before approach
certificate will be issued.