CENTERING RATE CALCULATIONS

1 Steel entering for sides and softs including supports and


strutting upto 3.00m height for plan surface such as RCC slab,
rectangular beams, T or L beams lintels bedblocks, staircase
waist and landing slab landing beams, canopy etc., with all cross
bracings using mild steel sheets of size 90cm x 60cm x 10 guage
stiffened withwelded mild steel angles of size 25mm x 25mm x
6mm for boarding laid over silver oak (country wood) joist of
size 10cm x 6.50cm spaced at about 90 cms c/c and supported
by causrina props of 10 cms to 13 cms dia spaced at 75cm c/c
etc., complete

Sub Data 1
Cost of MS Sheets and angles for each et Weights of MS sheet
90cmx60cmx10guage
3.175 x 7850/1000 = 24.92 Kg/Sqm
0.90 x 0.60 x 24.92 = 13.46 Kg/No

Weight of MS angle of size 25 x 25 x 3mm


3.60m x 1.11 Kg/m = 4.00 Kg/No

13.46 Kg Cost of MS Sheets , 90cm x 60cm x 10 gauge = 41.20 /Kg 554.55


4.00 Kg Cost of MS angles , 25cm x 25cm x 3mm = 41.20 /Kg 164.80
17.46 Kg Cutting, bending and welding charges = 36.20 /Kg 632.05
Sundries 0.78
1352.18

Sub Data 2
19 Nos Cost of MS angle and sheet = 1352.18 Each 25691.42
(Assuming for 40 users) Total 25691.42
Cost for Single use 25691.42 /40 642.29

0.12 Cum Silver Oak country wood joist, 1cm x 6.5cm at about 90cm 15500.00 cum 1860.00
C/C etc.,
For 1 use = 372
Steel props, 40*11.10*60/40 For 1 use = 666.00
Cost for Single use 1038.00

Main Data
1.00 Use Cost of M.S Sheets and angles 642.29 40 users 642.29
1.00 Use Cost of Silver oak joists and steel props 1038.00 5 users 1038.00
3.80 Nos Carpenter I Class 638.00 Each 2424.40
5.40 Nos Mazdoor catogory I 426.00 Each 2300.40
1.00 Nos Fitter II class 560.00 Each 560.00
LS Add for Welding grills nails etc., LS 10.00
LS Add for Oiling for MS Sheets and edges etc., LS 50.00
Sundries 0.91
7026.00
Rate per 1 sqm = 702.60 /Sqm

1 Centering for Foundation, Pile cap etc., (Below Sill)

1.00 Sqm Centering rate 702.60 Sqm 702.60


Deduct for Strutting charges -103.80
Sundries 0.20
599.00
Rate per 1 sqm = 599.00 /Sqm

2 Centering for Coloumn footing Plinth beam

10.00 Sqm Centering rate 702.60 Sqm 7026.00


19.70 Nos Causrina props 25.50 Each 502.35
0.30 Nos Carpenter I class 638.00 Each 191.40
0.30 Nos Mazdoor I class 426.00 Each 127.80
Sundries 0.45
7848.00
Rate per 1 sqm = 785.00 /Sqm

3 Centering for Vertical surfaces (Abutment and Piers)

1.00 Sqm Centering rate 702.60 Sqm 702.60


1.00 Sqm Add 10% extra for Vertical surfaces 70.26 Sqm 70.26
Sundries 0.14
773.00
Rate per 1 sqm = 773.00 /Sqm

4 Centering for Coloumns piers, rectangular piers

1.00 Sqm Centering rate 702.60 Sqm 702.60


1.00 Sqm Add 100% extra for Vertical surfaces 702.60 Sqm 702.60
Sundries 0.80
1406.00
Rate per 1 sqm = 1406.00 /Sqm

5 Centering for Caping beam, Parapet, Crash barrier

1.00 Sqm Centering rate 702.60 Sqm 702.60


1.00 Sqm Add 50% extra for Vertical surfaces 351.30 Sqm 351.30
Sundries 0.10
1054.00
Rate per 1 sqm = 1054.00 /Sqm

6 Centering for T - Beam cum Deck slab

1.00 Sqm Centering rate 702.60 Sqm 702.60


1.00 Sqm Add 30% extra for Vertical surfaces 210.78 Sqm 210.78
Sundries 0.62
914.00
Rate per 1 sqm = 914.00 /Sqm