Professional Documents
Culture Documents
CONSTRUCTION
AN INTERNSHIP REPORT
Submitted to
Visvesvaraya Technological University
BELAGAVI - 590 018
By
HARSHITH Y
USN: 4SU16CV016
Bachelor of Engineering
[Type here]
SDM INSTITUTE OF TECHNOLOGY
(Affiliated to Visvesvaraya Technological University, Belagavi)
UJIRE – 574 240
CERTIFICATE
External Viva
Name of the Examiners: Signature with
Date
1.
2.
Acknowledgement
_______________________________________________
I express my deepest gratitude to my guide Mr. Naveen Kumar, Site Engineer of RAL
CONSTRUCTIONS, for his valuable guidance and encouragement while doing my internship. I also
extend my heartfelt thanks to Mr. Vijay Kumar, Project Manager for having given me the opportunity
of carrying out internship at RAL CONSTRUCTIONS.
We are indebted to Dr. Krishna Prasad P A, Head of the Department, Internship Co-ordinator Mr.
Vinaya Shyam D , Asst. Prof. for their advice and suggestions at various stages of the work.
I am also grateful to the co-operation and help rendered by the teaching and non-teaching
staff of the department.
Harshith Y
4SU16CV016
i
Table of Contents
Page No.
Acknowledgement i
Table of Contents ii
1 Executive summary 1
2 Company profile 2
3 Introduction 3
8 Bibliography 28
ii
PG Accommodation Building Construction
CHAPTER 1
EXECUTIVE SUMMARY
This report refers to work completed during my internship with Ral Constructions in
Bangalore from 08/07/2019 to 03/08/2013.
This report provides a summary to my internship practice outcome which I gained during
my internship period stay in the site of construction. Actually, I was assigned in the
construction of Residential building as well as where different types of civil construction
activities were going on.
Introduction and some of the departmental works that mainly required for the
construction and execution of the project.
The project details with location in which I did my internship work.
The project execution, how the actual work goes on in the site.
Details of foundation, types of foundation and steps followed in constructing the
foundation.
Raft foundation, with some calculations.
Schedule of columns and retaining wall.
Tests conducted on the bricks, cement, soil, aggregates before taking the materials
into site.
CHAPTER 2
COMPANY PROFILE
OUR VISION
To be known as the creator of unprecedented superior lifestyles
OUR MISSION
We deliver exceptional quality homes, offices and hotels to enhance customer lifestyle and
happiness that sustains for generations.
Customer satisfaction is the cornerstone of all efforts as the company endeavors to craft
homes for lifelong happiness.
Quality
This is a pivotal philosophy that defines every R A L home with quality standards that
define industry benchmarks.
Consistency
Every home built is a product of meticulous planning and fine attention to detail to meet
customer expectations.
CHAPTER 3
INTRODUCTION
The basics need of human existences are food, clothing’s & shelter. From times immemorial
man has been making efforts in improving their standard of living. The point of his efforts has
been to provide an economic and efficient shelter. The possession of shelter besides being a
basic, used, gives a feeling of security, responsibility and shown the social status of man.
Every human being has an inherent liking for a peaceful environment needed for his pleasant
living, this object is achieved by having a place of living situated at the safe and convenient
location, such a place for comfortable and pleasant living requires considered and kept in view.
• A Peaceful environment.
RESIDENTIAL BUILDINGS:
These building include any building in which sleeping accommodation provide for normal
residential purposes, with or without cooking and dining facilities. It includes single or multi-
family dwellings, apartment houses, lodgings or rooming houses, restaurants, hostels,
dormitories and residential hostels.
Villa can be very similar to a house in that it can closely resemble a standard, single family
home, but villas are also known for being luxurious,
larger homes with their own gardens, vineyards or courtyards, hotel-like services and water
fixtures, like pools and fountains.
For successful completion of any construction project following aspects has to be followed:
1. Planning.
2. Execution.
3. Quality.
4. Safety.
Planning:
Construction planning is a fundamental and challenging activity in the management
and execution of construction projects. For example, the extent to which sub-contractors will
be used on a project is often determined during construction planning.
Execution:
Project execution (or implementation) is the phase in which the plan designed in the prior
phases of the project life is put into action. The purpose of project execution is to deliver the
project expected results
(deliverable and other direct outputs).
Quality:
Quality control (QC) is the part of quality management that ensures products and service
comply with requirements. Technical specifications define the type of controls that must be
carried out to ensure the construction works are carried out correctly.
Safety:
Construction work is a hazardous land-based job. Some construction site jobs include: building
houses, roads, tree forts, workplaces and repair and maintain infrastructures. This work
includes many hazardous task and conditions such as working with height, excavation, noise,
dust, power tools and equipment. The most common fatalities are caused by the fatal four: falls,
being struck by an object, electrocutions, and being caught in between two objects.
Construction work has been increasing in developing and undeveloped countries over the past
few years. With an increase in this type of work occupational fatalities have increased.
Occupational fatalities are individuals who die while on the job or en forming work related
tasks. Within the field of construction, it is important to have safe construction sites.
Fig. Safety Components
CHAPTER 4
10/07/2019 Wed Stair case (from first floor to second floor) concreting is
completed today.
11/07/2019 Thu Bar bending works for second floor roof slab is going on
today.
12/07/2019 Fri Chejja construction within the Room is under progress.
24/07/2019 Wed Chejja construction within the room in first floor is going
on.
25/07/2019 Thu Third floor roof slab is laid this day, RMC concrete is used
for slab concreting.
26/07/2019 Fri 7 days cube test is carried out in this week on 25/07/2019.
27/07/2019 Sat Cubes also casted while slab concreting for testing
compressive strength.
31/07/2019 Wed Plastering works are going on in the ground floor and first
floor.
01/08/2019 Thu Centering works are started for third floor roof slab.
02/08/2019 Fri I visited RAL constructions office today and interact with
company H R.
03/08/2019 Sat I Collected my internship certificate.
CHAPTER 5
South – 5 ft.
West – 10 ft from RTL.
East – 10 ft.
• Site Clearance
• Surveying And Layout
• Base Line Marking
• Excavation
• Grid line marking (master plan,column and footing marking)
• Foundation
• Beams And Columns
• Slabs
• Wall Construction
5.2.2 PLAN
Construction planning is a fundamental and challenging activity in the management and
execution of construction projects. It involves the choice of technology, the definition of
work tasks, the estimation of the required resources and durations for individual tasks,
and the identification of any interactions among the different work tasks. A good
construction plan is the basis for developing the budget and the schedule for work.
Developing the construction plan is a critical task in the management of construction, even
if the plan is not written or otherwise formally recorded. In addition to these technical
aspects of construction planning, it may also be necessary to make organizational decisions
about the relationships between project participants and even which organizations to include
in a project. For example, the extent to which sub-contractors will be used on a project
is often determined during construction planning.
The trees are cut to leave tall stumps that are easier to remove. We remove the stumps using
machinery, then focus on removing the roots. It’s especially important to remove stumps and
roots, as the decaying woody material can cause cracks in concrete structures built on the
site. We also remove large stones and dig out animal burrows and fill them with clay.
Auto level is an optical instrument used to establish or verify points in the same horizontal
plane in a process known as leveling and is used in conjunction with a leveling staff to
establish the relative heights levels of objects or marks.
It operates on the principle of establishing a visual level relationship between two or more
points, for which an inbuilt telescope and a highly accurate bubble level are used to achieve
the necessary accuracy.
5.2.7 EXCAVATION:
Excavation work on the site was done by JCB Machines and excavated soil was
transferred using dumpers and bob cat.
Fig. Excavation
5.2.8 COMPACTION
Compaction is a process that brings about an increase in soil density or unit weight,
accompanied by a decrease in air volume. There is usually no change in water content. The
degree of compaction is measured by dry unit weight and depends on the water content and
compactive effort. For a given compactive effort, the maximum dry unit weight occurs at an
optimum water content.
Fig. Compaction
Gridlines are the identification marks of a floor plan, grid lines are often found in
construction drawings
These are usually letters from A to Z, etc, along the vertical direction; and letters 1 to 2, etc
along the horizontal direction; that determines the identity of one particular position of a
structural member on the floor plan.
Baseline
Typically the first layout task is establishing a baseline to which all the setting out can be
related. The baseline is a straight reference line in respect to which the building’s corners are
located on the ground. It often coincides with the ‘building line’, which is the boundary of
the area, or the outer boundary of a road or curb, often demarcated by the local authority.
Horizontal controls
These are the points that have known coordinates with respect to a specific point. Other points
such as layout corners can then be located. Plenty of control points should be used so that
each point of the plan can be precisely located on the ground
5.3 Foundation:
Foundation is one of the most important parts of the structure. Foundation is defined as that
part of the structure that transfers the load from the structure as well as its own weight over a
large area of soil in such a way that the load does not exceed the ultimate bearing capacity of
the soil and the settlement of the total structure remains within a tolerable limit. Foundation
is the part of a structure on which the building stands. The solid ground on which the
foundation rests is called the foundation bed.
Foundation is provided to fulfill certain objectives
They are
• Distribute the weight of the structure over a large area of soil.
• Avoid unequal settlement.
• Prevent the lateral movement of the structure.
• Increase structural stability.
• Pile foundation
The soil has a low bearing capacity, so the weight of the building needs to be spread out over
a large area to create a stable foundation.
5.4 CONCRETING
Concrete, usually Portland cement concrete, is a composite material composed of fine and
coarse aggregate bonded together with a fluid cement that hardens over time.
• There are different types of concrete mixes, according to the structural element and load
considerations required types of concrete mix is used.
• In a concrete mix M20, M stands for mix and 20 for characteristic compressive strength
In N/mm2.
• The required type of concrete mix prepared in RMC plant.
• For every use of carmix to the site 6 cubes of 150 mm dimension is casted and kept
under water for 7 days and 28 days.
• Compressive strength testing of casted cubes is done, cubes should achieve 67% of
required strength should be achieved and the complete strength within 28 days.
(After curing void space is back filled and is compacted by earth rammer)
PCC
After compaction of soil a 4” Plain cement concrete (PCC) is poured by dumping
Grade of concrete used is M 7.5
CHAPTER 6
TESTS
CHAPTER 7
CONCLUSION
As an undergraduate of the SDMIT. I would like to say that this training program is an
excellent opportunity for us to the ground level and experience the things that we would have
never gained through going straight into a job.