SHAYBAH RESIDENTIAL AND INDUSTRIAL COMPLEX EXPANSION PROJECT

Contract No.6600026594 BI No. 10-00774-001

METHOD STATEMENT
DATE UPDATED : Friday, April 01, 2016
RESPONSE OPEN TO
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

1 Method statement for relocation of security fence NO. 01 EW&ID/RIC/L-062/11 30-May-11 CLOSED CLOSED APPROVED
May 29, 2011 023-RIC-005/11
Method of Statement of New Majles Foundation, Excavation,
2
June 28, 2011 023-RIC-033/11 Backfilling & Compaction NO. 02

3 Method of Statement for Dewatering Excavation NO. 03 EW&ID/RIC/L-0133/11 11-Jul-11 CLOSED CLOSED APPROVED
July 5, 2011 023-RIC-049/11

4 METHOD STATEMENT NO.03 REV.01 - FOR DEWATERING OF EW&ID/RIC/T-0820/12 19-Jun-12 CLOSED CLOSED APPROVED
JUNE 16.2012 023-RIC-T-612/12 AN EXCAVATION
Method of Statement / Contingency Plan for Chilled Water Line N0.
5 EW&ID/RIC/L-0169/11 26-Jul-11 CLOSED CLOSED APPROVED
July 25, 2011 023-RIC-077/11 04
Method of Statement for Con. Pouring, Conc. Defects & Conc. Curing
6 EW&ID/RIC/L-0190/11 21-Aug-11 CLOSED CLOSED APPROVED
August 14, 2011 023-RIC-0116/11 NO. 05

CONTRACTOR SUBMITTED REV.


7 EW&ID/RIC/T-0406/11 16-Oct-11 CLOSED CLOSED
DATED OCTOBER 24
October 3, 2011 023-RIC-0206/11 Method Statement - Concrete Defects NO. 06

8 22-Apr-12 CLOSED CLOSED


October 12, 2011 023-RIC-0229/11 Method of Statement - Main feeder of temporary majles
9 CLOSED CLOSED REVISED
October 24, 2011 023-RIC-0255/11 Method of Statement - Concrete Defects NO. 06 EW&ID/RIC/T-512/11 14-Nov-11

COMPLY WITH THE ATTACHED


10 Method Statement - Concrete Defects - Response NO. 06 EW&ID/RIC/T-0162/12 4-Feb-12 CLOSED CLOSED
PID COMMENTS
January 22.2012 023-RIC-0255A/12

11 Method statement of adhesive Bonded joint (final approval for all EW&ID/RIC/T-766/11 1-Jan-12 CLOSED CLOSED APPROVED WITH COMMENTS
December 23,2011 023-RIC-0432/11 RTR)
Method of Statement for Concrete Chipping( Grade Beam Rebar ) OTHERS SPECIFY/
12 CLOSED CLOSED
January 01.2012 023-RIC-0452/12 NO. 07 WCOMMENTS
Method of Statement for Preparation for Sand Bedding & backfilling
13 EW&ID/RIC/T-0215/12 9-Feb-12 CLOSED CLOSED APPROVED WITH COMMENTS
January 03.2012 023-RIC-0464/12 at Dune Sand Area NO. 08
PLESE FIND THE ATTACHED
14 EW&ID/RIC/T-057/12 15-Jan-12 CLOSED CLOSED
January 10.2012 023-RIC-0479/12 Method of Statement - Shaded Car Parking for Airport Terminal REFERENCE DOCUMENT
Method Statement for Hydro statistic test of 6'' RTR Portable Water
15 EW&ID/RIC/T-0109/12 24-Jan-12 CLOSED CLOSED APPROVED WITH COMMENTS
January 16.2012 023-RIC-0497/12 line NO. 09
16 EW&ID/RIC/T-0288/12 20-Feb-12 CLOSED CLOSED APPROVED AS NOTED
January 19.2012 023-RIC-0501/12 Method Statement 0f Pipe Trench Excavation NO. 010

Prepared by: Jailo A. Bantiyan


Page 1 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

CONTRACTOR HAS TO PROVIDE


THE PROCEE APPLICATION &
17 EW&ID/RIC/L-0126/12 13-Feb-12 CLOSED CLOSED
APPLICATION SCOPE OF
January 31.2012 023-RIC-529/12 Method Statement of Brazing Control NO.011 WORKS

REJECTED CONTRACTOR TO
18 EW&ID/RIC/T-0346/12 4-Mar-12 CLOSED CLOSED COMPLY W/ SAPMT COMMENTS
PER EW & ID/RIC/L-126/12
Mar.01.2012 023-RIC-T-244/12 Method Statement of Brazing Control - NO. 011 REV.1

AS PER SIGNED GENERAL


19 Method Statement of Brazing Control - NO. 011 REV.2 CLOSED CLOSED
APPROVAL DATED ON 7/14/12
Mar.21.2012 023-RIC-T-308/12 FROM (PMT-ARAMCO)

20 Method Statement - Road crossing Installation of' 6'' RTR Pipe NO. EW&ID/RIC/T-0181/12 5-Feb-12 CLOSED CLOSED REVISED
January 31.2012 023-RIC-532/12 012
21 REVISED - Method Statement - Road crossing Installation of' 6'' RTR EW&ID/RIC/L-0117/12 13-Feb-12 CLOSED CLOSED APPROVED AS NOTED
February 09.2012 023-RIC-532A/12 Pipe NO. 012
22 EW&ID/RIC/T-0180/12 5-Feb-12 CLOSED CLOSED REVISED
January 31.2012 023-RIC-533/12 Method Statement - Relocation Fire Hydrant NO. 014
23 EW&ID/RIC/T-0269/12 19-Feb-12 CLOSED CLOSED APPROVED AS NOTED
February 08.2012 023-RIC-533A/12 Method Statement - Relocation Fire Hydrant NO. 014
24 EW&ID/RIC/T-0182/12 5-Feb-12 CLOSED CLOSED REVISED
February 02.2012 023-RIC-536/12 Method Statement of Electrical Cable Duct Bank
25 EW&ID/RIC/T-0211/12 8-Feb-12 CLOSED CLOSED APPROVED AS NOTED
February 06.2012 023-RIC-536A/12 Method Statement of Electrical Cable Duct Bank - REVISED
26 EW&ID/RIC/T-0268/12 19-Feb-12 CLOSED CLOSED APPROVED AS NOTED
February 02.2012 023-RIC-539/12 Method Statement of Pipe Layout Along Hills NO. 015
27 EW&ID/RIC/T-0284/12 20-Feb-12 CLOSED CLOSED APPROVED AS NOTED
February 20.2012 023-RIC-575/12 Method Statement - Relocation Of Lighting Pole

EW&ID/RIC/T-319/12 2/27/2012
28 Method Statement - MECH'L Works Dining & Kitchen Commissary EW&ID/RIC/L-136-12 CLOSED CLOSED REVISE AND RESUBMIT
FEB-29-12
February 20.2012 023-RIC-576/12
EW&ID/RIC/T-0282/12 2/21/2012
29 EW&ID/RIC/L-135-12 CLOSED CLOSED REVISED
29-FEB-12
February 21.2012 023-RIC-579/12 Method Statement - ELEct'L. Works Dining & Kitchen Commissary

30 METHOD STATEMENT-DINING HALL EXPANSION - ( RESPONSE EW&ID/RIC/T-0369/12 10-Mar-12 CLOSED CLOSED APPROVED AS NOTED
Mar.06.2012 023-RIC-255/12 TO REF.EW&ID/RIC/L-135-12)
Method Statement - Form Stripping & Re- Shoring of concreted
31 EW&ID/RIC/T-0313/12 28-Feb-12 OPEN REVISE AND RESUBMIT
Elevated Girder / Beams/ Slabs NO. 016
February 23.2012 023-RIC-T-206/12
MS-SDMEP-17 - Method Statement - Shoring & Dewatering of
32 EW&ID/RIC/T-0314/12 27-Feb-12 REVISED
February 23.2012 023-RIC-T-211/12 Manhole Excavation & Installation for MEP Services CLOSED CLOSED
MS-SDMEP-17 ( REV.01 ) Method Statement - Shoring &
33 EW&ID/RIC/T-0359/12 6-Mar-12 CLOSED CLOSED APPROVED AS NOTED
Mar.01.2012 023-RIC-T-245/12 Dewatering of Manhole Excavation & Installation for MEP Services
34 EW&ID/RIC/T-0318/12 27-Feb-12 CLOSED CLOSED 023-RIC-L-700/12
February 24.2012 023-RIC-T-214/12 MS - PO - 018 - Method Statement - Piling Operation
35 EW&ID/RIC/T-0364/12 10-Mar-12 CLOSED CLOSED 023-RIC-L-700/12
Mar.05.2012 023-RIC-T-250/12 MS - PO - 017 rev.1 - Method Statement - Piling Operation
36 EW&ID/RIC/T-0471/12 2-Apr-12 CLOSED CLOSED 023-RIC-L-700/12
Mar.31.2012 023-RIC-T-337/12 MS - PO - 017 rev.2 - Method Statement - Piling Operation
37 EW&ID/RIC/T-0566/12 23-Apr-12 CLOSED CLOSED APPROVED AS NOTED
APRIL 17 2012 023-RIC-T-700 /12 Piling Operation - Response rev.03

Prepared by: Jailo A. Bantiyan


Page 2 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

38 EW&ID/RIC/T-0383/12 14-Mar-12 CLOSED CLOSED REVISED


Mar.05.2012 023-RIC-T-265/12 MS-RCD-018 - Method Statement - Repairing of Concrete Voids
MS-RCD-018 REV.1 - Method Statement - Repairing of Concrete
39 EW&ID/RIC/T-0462/12 9-Apr-12 CLOSED CLOSED APPROVED
Mar.28.2012 023-RIC-T-330/12 Voids
APPROVED AS NOTED FOR
40 EW&ID/RIC/T-0431/12 27-Mar-12 CLOSED CLOSED
Mar.21.2012 023-RIC-T-305/12 METHOD STATEMENT - TERMINAL BLDG EXPANSION PHASE 1 & 2 ONLY
METHOD STATEMENT - Repair of Damaged Pre-Stressed precast
41 EW&ID/RIC/T-0480/12 8-Apr-12 CLOSED CLOSED APPROVED AS SUBMITTED
APRIL 1.2012 023-RIC-T-335/12 Hollow Core Slab ( Ranco & Zamil )
42 EW&ID/RIC/T-0531/12 18-Apr-12 CLOSED CLOSED ACCEPTED W/ COMMENTS
APRIL 9.2012 023-RIC-T-370/12 METHOD STATEMENT - Tank for Cathodic Protection System
43 EW&ID/RIC/T-696/12 23-May-12 CLOSED CLOSED NO OBJECTION AS NOTED
MAY 05.2012 023-RIC-T-465/12 LCC SIPOREX ERECTION PROCEDURE AT RESD'L BLDG.

EW&ID/RIC/T-619/13 PROVIDE JOB SAFETY


44 METHOD STATEMENT NO. 019 STRUCTURAL & EW&ID/RIC/T-914/13 23-Jul-13 CLOSED CLOSED
ANALYSIS
MAY 12.2012 023-RIC-T-496/12 MISCELLANEOUS STEEL ERECTION
METHOD STATEMENT NO. 019 STRUCTURAL &
45 MISCELLANEOUS STEEL ERECTION (ATTACHED JSA PRIOR TO CLOSED CLOSED FOR INFO
NOVEMBER 17 2013 023-RIC-T-496A/12 CLOSED)

46 MOS-CONCRETE CHIPPING FOR THE CASTED CORBEL EW&ID/RIC/T-0677/12 19-May-12 CLOSED CLOSED APPROVED AS NOTED
MAY 17.2012 023-RIC-T-512/12

47 METHOD STATEMENT NO. 019 - CONCRETE CORING FOR EW&ID/RIC/T-0693/12 21-May-12 CLOSED CLOSED APPROVED AS NOTED
MAY 19.2012 023-RIC-T-517/12 MECHANICAL AND ELECTRICAL

48 METHOD STATEMENT NO. 020 - CONCRETE CORING FOR EW&ID/RIC/T-0744/12 12-Jun-12 CLOSED CLOSED APPROVED AS NOTED
MAY 30.2012 023-RIC-T-552/12 TELECOM

49 METHOD STATEMENT NO. 021 - HYDROSTATIC TEST FOR EW&ID/RIC/T-0808/12 18-Jun-12 CLOSED CLOSED REJECTED
JUNE 9.2012 023-RIC-T-590/12 UNDERGROUND UTILITIES

50 METHOD STATEMENT NO. 021 REV.01 - HYDROSTATIC EW&ID/RIC/T-0817/12 18-Jun-12 CLOSED CLOSED APPROVED WITH COMMENTS
JUNE 18.2012 023-RIC-T-625/12 (HYDROTEST RTR) FOR UNDERGROUND UTILITIES

51 JUNE 10.2012 023-RIC-T-593/12 plastering using vetinit premix plaster ms-pp-c-022 EW&ID/RIC/T-0831/12 20-Jun-12 CLOSED CLOSED REVIEWED WITH COMMENTS

52 METHOD STATEMENT WORK FOR TANK CONSTRUCTION (AL- EW&ID/RIC/T-0832/12 23-Jun-12 CLOSED CLOSED REVIEWED WITH COMMENTS
JUNE 11.2012 023-RIC-T-596/12 KHODARI HEAVY EQUIPMENT)

53 REVISED METHOD STATEMENT WORK FOR TANK EW&ID/RIC/T-0927/12 17-Jul-12 CLOSED CLOSED APPROVED AS NOTED
JULY 5.2012 023-RIC-T-596A/12 CONSTRUCTION (AL-KHODARI HEAVY EQUIPMENT)
METHOD STATEMENT NO. 023 - UNDERGROUND UTILITIES REVISED BY REF. 023-RIC-SITE-
54 EW&ID/RIC/T-0866/12 1-Jul-12 CLOSED CLOSED
JUNE 23.2012 023-RIC-T-637/12 PIPE JACKETING-CASING 905-12

55 REVISED METHOD STATEMENT NO. 023 - UNDERGROUND EW&ID/RIC/T-0894/12 11-Jul-12 CLOSED CLOSED APPROVED AS NOTED
JULY 5.2012 023-RIC-L-905/12 UTILITIES PIPE JACKETING-CASING

METHOD STATEMENT NO. 024 - CHIPPING AND EDGING OF


56 ESTABLISHED CMU WALLS FOR CIVIL,MECHANICAL AND EW&ID/RIC/T-0925/12 17-Jul-12 CLOSED CLOSED APPROVED AS SUBMITTED
JULY 10.2012 023-RIC-T-673/12 ELECTRICAL WALL OPENINGS
REJECTED / RESPONSE
57 METHOD STATEMENT NO.025 - CHIPPING OF ESTABLISHED EW&ID/RIC/T-0926/12 17-Jul-12 OPEN
REQUIRED
JULY 11.2012 023-RIC-T-677/12 CONCRETE FOR ANCHOR BOLT POCKETS
CONFIRMED FROM PMT
58 METHOD STATEMENT FOR THE CATHODIC PROTECTION EW&ID/RIC/T-0994/12 9-Aug-12 CLOSED CLOSED
DOC/CON DEC.08, 2013
AUGUST 01.2012 023-RIC-L-969/12 INSTALLATION FOR THE WATER TANK

Prepared by: Jailo A. Bantiyan


Page 3 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

59 METHOD STATEMENT NO.26 CUTTING & CHIPPING OF EW&ID/RIC/T-1012/12 14-Aug-12 CLOSED CLOSED APPROVED AS NOTED
AUGUST 09.2012 023-RIC-T-756/12 EXISTING LINTEL BEAMS & DECORATIVE PANELS

60 EW&ID/RIC/T-1099/12 10-Sep-12 CLOSED CLOSED REJECTED


AUGUST 12.2012 023-RIC-T-763/12 METHOD STATEMENT NO.027 HVAC LIGHT TEST PROCEDURE

61 METHOD STATEMENT NO.027 REV.01 HVAC LIGHT TEST EW&ID/RIC/T-1221/12 3-Oct-12 CLOSED CLOSED APPROVED WITH COMMENTS
SEPT 12.2012 023-RIC-T-838/12 PROCEDURE
METHOD STATEMENT NO.028 COATING APPLICATION
62 PROCEDURE FOR COPPER AND CARBON STEEL PIPING EW&ID/RIC/T-1236/12 7-Oct-12 CLOSED CLOSED APPROVED AS NOTED
AUGUST 29.2012 023-RIC-T-800/12 (UNDERGROUND PIPING) APCS 113A

CONFIRMED FROM PMT


63 WQMM ITEM # 3.5.68 METHOD STATEMENT OF HOLLOW CORE EW&ID/RIC/T-1174/12 25-Sep-12 CLOSED CLOSED
DOC/CON DEC.27, 2012
SEPT 12.2012 023-RIC-T-837/12 CUTTING AT SITE

PLEASE FIND REF.DOCUMENT


64 METHOD STATEMENT NO.029 FOR INSTALLATION OF PRECAST EW&ID/RIC/T-1159/12 19-Sep-12 CLOSED CLOSED
REVIEWED WITH COMMENTS
SEPT 15.2012 023-RIC-T-844/12 FIBERGLASS MANHOLE WITH REINFORCED CONCRETE BASE
METHOD STATEMENT NO.029rev.01 FOR INSTALLATION OF
65 PRECAST FIBERGLASS MANHOLE WITH REINFORCED EW&ID/RIC/T-1222/12 3-Oct-12 CLOSED CLOSED APPROVED WITH COMMENTS
SEPT 27.2012 023-RIC-T-888/12 CONCRETE BASE

66 METHOD STATEMENT NO.030 HYDROTEST FOR COPPER EW&ID/RIC/T-1255/12 9-Oct-12 CLOSED CLOSED APPROVED WITH COMMENTS
SEPT 15.2012 023-RIC-T-845/12 PIPING (AG/UG PIPING)

67 METHOD STATEMENT NO.031 FLUSHING/CLEANING OF EW&ID/RIC/T-1232/12 6-Oct-12 CLOSED CLOSED APPROVED AS NOTED
SEPT 16.2012 023-RIC-T-849/12 UNDERGROUND UTILITIES PIPE WORK

68 METHOD STATEMENT NO.032 EXCAVATION OF SUMP PIT AT EW&ID/RIC/T-1196/12 30-Sep-12 OPEN COMMENTS FOR YOUR ACTION
SEPT 17.2012 023-RIC-T-854/12 SUB-STATION

69 METHOD STATEMENT NO.033 REPAIRING OF CRACKS ON EW&ID/RIC/T-1230/12 6-Oct-12 CLOSED CLOSED APPROVED AS NOTED
SEPT 18.2012 023-RIC-T-856/12 FLOOR SCREED AT RESD'L BLDGS

70 METHOD STATEMENT NO.034 HVAC AND UTILITY PIPING EW&ID/RIC/T-1216/12 3-Oct-12 OPEN REVISE AND RESUBMIT
SEPT 27.2012 023-RIC-T-887/12 HANGERS AND SUPPORTS

71 EW&ID/RIC/T-1359/12 8-Nov-12 CLOSED CLOSED APPROVED AS NOTED


METHOD STATEMENT NO.035 RELOCATION OF WALL
NOV 06.2012 023-RIC-T-982/12 OPENINGS@MECHANICAL ROOM WALL

72 EW&ID/RIC/T-1419/12 21-Nov-12 CLOSED CLOSED APPROVED AS NOTED


METHOD STATEMENT NO.036 INSTALLATION OF REBAR FOR
NOV 20.2012 023-RIC-T-1039/12 THE EXTENDED PORTION OF FIRE WALL@RESD'L BLDGS.

73 EW&ID/RIC/T-1458/12 2-Dec-12 CLOSED CLOSED REVISED


METHOD STATEMENT NO.037 INSTALLATION OF HOLLOW
NOV 27.2012 023-RIC-T-1056/12 CORE SLAB BEARING PAD@GRID 7 AND 11

74 METHOD STATEMENT NO.037 REV.01 INSTALLATION OF EW&ID/RIC/T-003/13 2-Jan-13 CLOSED CLOSED ACCEPTED WITH COMMENTS
DEC 27.2012 023-RIC-T-1127/12 HOLLOW CORE SLAB BEARING PAD@GRID 7 AND 11
AS PER ENGR. JONEL
75 REFER TO TSQ C- METHOD STATEMENT NO.038 - GROUTING,CHIPPING OF MANUEL JAN.02,2013 REFER TO TSQ C-129B
10:00 A.M
129B ESTABLISHED CONCRETE FOR ANCHOR BOLT POCKETS

Prepared by: Jailo A. Bantiyan


Page 4 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

76 METHOD STATEMENT NO.039 EXCAVATION CABLE PULLING EW&ID/RIC/T-016/13 12-Jan-13 CLOSED CLOSED REVISED
JAN 02.2013 023-RIC-T-1147/13 UNDER EXISTING SUBSTATION # 40
CONTRACTOR TO COMBINED
THIS MOS TO MOS NO.041 BOTH
77 EW&ID/RIC/T-095/13 27-Jan-13 CLOSED CLOSED
METHOD STATEMENT NO.039 REV.01 EXCAVATION CABLE SHOULD BE PART OF THE
JAN 21.2013 023-RIC-T-1224/13 PULLING UNDER EXISTING SUBSTATION # 40 PROCEDURE

78 EW&ID/RIC/T-078/13 22-Jan-13 CLOSED CLOSED APPROVED AS NOTED


JAN 14.2013 023-RIC-T-1180/13 METHOD STATEMENT NO.040 ASPHALT CONCRETE PAVING

79 METHOD STATEMENT NO.041 CUT-OVER AND SWITCH-OVER EW&ID/RIC/T-094/13 27-Jan-13 CLOSED CLOSED REVISED
JAN 21.2013 023-RIC-T-1225/13 PLAN/PROCEDURE FOR EXISTING SUBSTATION # 40
METHOD STATEMENT NO.041 REV.01 - CUT-OVER AND
80 SWITCH-OVER PLAN/PROCEDURE FOR EXISTING SWITCH EW&ID/RIC/T-686/14 27-Jan-13 CLOSED CLOSED APPROVED
SEPTEMBER 30 2013 023-RIC-T-2438/13 GEAR S-301 AT SUBSTATION # 40

81 METHOD STATEMENT NO.042 - DEWATERING EXCAVATED EW&ID/RIC/T-119/13 30-Jan-13 CLOSED CLOSED REVISED
JAN 27.2013 023-RIC-T-1254/13 AREAS AROUND RESD'L BLDG. PREMISES

82 METHOD STATEMENT NO.042 REV.01 - DEWATERING EW&ID/RIC/T-164/13 10-Feb-13 CLOSED CLOSED APPROVED AS NOTED
FEB 7.2013 023-RIC-T-1318/13 EXCAVATED AREAS AROUND RESD'L BLDG. PREMISES

83 METHOD STATEMENT NO.043 - REPAIRING OF PLASTERED EW&ID/RIC/T-201/13 17-Feb-13 CLOSED CLOSED APPROVED AS NOTED
FEB 14.2013 023-RIC-T-1356/13 WALLS WITH VOIDS AND CRACKS

84 METHOD STATEMENT FOR INSTALLATION OF HOLLOW CORE EW&ID/RIC/T-322/13 10-Mar-13 CLOSED CLOSED REVISED
FEB 27.2013 023-RIC-T-1444/13 STEEL HANGER (L.B.E. 6704)

85 METHOD STATEMENT FOR INSTALLATION OF HOLLOW CORE EW&ID/RIC/T-382/13 24-Mar-13 CLOSED CLOSED APPROVED AS NOTED
MAR 17.2013 023-RIC-T-1538/13 STEEL HANGER REV.01 (L.B.E. 6704)
METHOD STATEMENT NO.044 - PROCEDURE AND PLAN FOR
86 REPAIRING NON UNIFORMITY OF COLUMNS AND BEAMS IN EW&ID/RIC/T-324/13 11-Mar-13 CLOSED CLOSED REVISED
MAR 09.2013 023-RIC-T-1497/13 LINE AND PLUMBNESS
METHOD STATEMENT NO.044 REV.01 - PROCEDURE AND PLAN
87 FOR REPAIRING NON UNIFORMITY OF COLUMNS AND BEAMS EW&ID/RIC/T-383/13 24-Mar-13 CLOSED CLOSED REVISED
MAR 20.2013 023-RIC-T-1557/13 IN LINE AND PLUMBNESS
METHOD STATEMENT NO.044 REV.02 - PROCEDURE AND PLAN
88 FOR REPAIRING NON UNIFORMITY OF COLUMNS AND BEAMS EW&ID/RIC/T-409/13 27-Mar-13 CLOSED CLOSED APPROVED AS SUBMITTED
MAR 26.2013 023-RIC-T-1587/13 IN LINE AND PLUMBNESS

89 METHOD STATEMENT NO.045 - INSTALLATION AND EW&ID/RIC/T-413/13 16-Apr-13 CLOSED CLOSED BY REF.023-RIC-T-1766/13
MAR 17.2013 023-RIC-T-1541/13 CONNECTION OF FLANGES AND BOLT TIGHTENING

90 METHOD STATEMENT NO.046 - NEOPRENE WRAPPING FOR EW&ID/RIC/T-414/13 31-Mar-13 CLOSED CLOSED APPROVED AS NOTED
MAR 20.2013 023-RIC-T-1559/13 RTR PIPE LINE
METHOD STATEMENT NO.047 - EXCAVATION AND SHORING
91 INSTALLATION FOR THE SANITARY SEWER LINE AT EW&ID/RIC/T-431/13 2-Apr-13 CLOSED CLOSED REVISED
APRIL 01.2013 023-RIC-T-1610/13 NORTH,SOUTH AND WEST SIDE OF BLDG.221

Prepared by: Jailo A. Bantiyan


Page 5 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

METHOD STATEMENT NO.047 REV.01 - EXCAVATION AND


92 SHORING INSTALLATION FOR THE SANITARY SEWER LINE AT EW&ID/RIC/T-454/13 13-Apr-13 CLOSED CLOSED APPROVED AS NOTED
APRIL 08.2013 023-RIC-T-1632/13 NORTH,SOUTH AND WEST SIDE OF BLDG.221

93 METHOD STATEMENT NO.048 - APPLICATION OF WATER EW&ID/RIC/T-453/13 13-Apr-13 CLOSED CLOSED REVISED
APRIL 06.2013 023-RIC-T-1624/13 PROOFING ON WET AREAS

94 METHOD STATEMENT NO.048 REV.01 - APPLICATION OF EW&ID/RIC/T-572/13 6-May-13 CLOSED CLOSED REVISED
APRIL 30.2013 023-RIC-T-1724/13 WATER PROOFING ON WET AREAS

CONFIRMED FROM PMT


95 METHOD STATEMENT NO.048 REV.02 - APPLICATION OF EW&ID/RIC/T-654/13 26-May-13 CLOSED CLOSED
DOC/CON AUG.06 2013
MAY 21 2013 023-RIC-T-1835/13 WATER PROOFING ON WET AREAS

96 METHOD STATEMENT NO.049 - AIR HANDLING UNIT FOR EW&ID/RIC/T-457/13 15-Apr-13 CLOSED CLOSED NO OBJECTION AS NOTED
APRIL 06.2013 023-RIC-T-1628/13 RESIDENTIAL BUILDING

EW&ID/RIC/T-576/13 5/6/2013
97 METHOD STATEMENT NO.050 - TEMPORARY CHILLED WATER EW&ID/RIC/T-566/13 CLOSED CLOSED APPROVED AS NOTED
5/5/2013
MAY 4.2013 023-RIC-T-1760/13 LINE PIPE SUPPORT PUMP HOUSE

EW&ID/RIC/T-620/13
98 METHOD STATEMENT NO.051 - REPAIRING OF CRACKS ON EW&ID/RIC/T-658/13 19-May-13 CLOSED CLOSED APPROVED AS NOTED
MAY 12.2013 023-RIC-T-1782/13 REINFORCED CONCRETE SLAB AT SUBSTATION
METHOD STATEMENT NO.052 - FIELD CHECKING OF METAL
99 CURTAIN WALL,WINDOWS AND SKYLIGHT FOR WATER EW&ID/RIC/T-763/13 19-Jun-13 CLOSED CLOSED APPROVED AS NOTED
JUNE 15 2013 023-RIC-T-1940/13 LEAKAGE

100 METHOD STATEMENT NO.053 - THIS MOS ATTACHED TO


JUNE 23 2013 023-RIC-L-1511/13 REF.023-RIC-L-1511/13 NO OFFICIAL TRANSMITTAL FOR MOS

101 METHOD STATEMENT NO.054 - FOR THREADED ENGAGEMENT EW&ID/RIC/T-890/13 21-Jul-13 CLOSED CLOSED CONDITIONALLY APPROVED
JUNE 25 2013 023-RIC-T-1995/13 PROCEDURE

102 METHOD STATEMENT NO.055 - RELOCATION OF FLOOR EW&ID/RIC/T-903/13 22-Jul-13 CLOSED CLOSED APPROVED AS NOTED
JULY 14 2013 023-RIC-T-2088/13 OPENINGS @ MECH'L ROOM

103 METHOD STATEMENT NO.056 - METALLIC PIPING EW&ID/RIC/T-902/13 22-Jul-13 CLOSED CLOSED REVISED
JULY 15 2013 023-RIC-T-2091/13 FABRICATION,ERECTION,INSPECTION AND TESTING

104 METHOD STATEMENT NO.056 REV.01 - METALLIC PIPING EW&ID/RIC/T-995/13 14-Aug-13 CLOSED CLOSED APPROVED AS NOTED
AUG. 04 2013 023-RIC-T-2169/13 FABRICATION,ERECTION,INSPECTION AND TESTING

105 METHOD STATEMENT NO.057 - DEMOLITION AND EW&ID/RIC/T-1027/13 21-Aug-13 OPEN REVISE AND RESUBMIT
AUG. 13 2013 023-RIC-T-2211/13 RECONSTRUCTION OF T-7 VALVE CHAMBER WALL

106 METHOD STATEMENT NO.058 - UNDERGROUND FW LINE TIE-IN EW&ID/RIC/T-1041/13 22-Aug-13 CLOSED CLOSED REVISED
AUG. 13 2013 023-RIC-T-2212/13 CONNECTIONS

107 METHOD STATEMENT NO.058 REV.01 - UNDERGROUND FW EW&ID/RIC/T-1127/13 11-Sep-13 CLOSED CLOSED APPROVED AS NOTED
SEPTEMBER 09 2013 023-RIC-T-2329/13 LINE TIE-IN CONNECTIONS

108 METHOD STATEMENT NO.059 - INSTALLATION OF PUMPS EW&ID/RIC/T-1502/13 23-Nov-13 CLOSED CLOSED REJECTED
OCT. 23 2013 023-RIC-T-2553/13 (SPECIAL PROCESS PER SCHEDULE)

109 METHOD STATEMENT NO.060 - NEW SEWER LINE TIE-IN TO EW&ID/RIC/T-1430/13 18-Nov-13 CLOSED CLOSED REVISED
NOV. 05 2013 023-RIC-T-2637/13 EXISTING LIFT STATION # 05

Prepared by: Jailo A. Bantiyan


Page 6 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

110 METHOD STATEMENT NO.060 REV.01 - NEW SEWER LINE TIE- EW&ID/RIC/T-1651/13 9-Dec-13 CLOSED CLOSED APPROVED
NOV. 26 2013 023-RIC-T-2777/13 IN TO EXISTING LIFT STATION # 05
METHOD STATEMENT NO.061 -
111 FLUSHING/CLEANING,HYDROTESTING AND LAY-UP OF ABOVE EW&ID/RIC/T-1628/13 4-Dec-13 CLOSED CLOSED REVISED
NOV. 12 2013 023-RIC-T-2671/13 GROUND,UTILITIES PIPE WORK
METHOD STATEMENT NO.061 REV.01 -
112 FLUSHING/CLEANING,HYDROTESTING AND LAY-UP OF ABOVE EW&ID/RIC/T-1753/13 24-Dec-13 CLOSED CLOSED APPROVED WITH COMMENTS
DEC. 15 2013 023-RIC-T-2894/13 GROUND,UTILITIES PIPE WORK

113 METHOD STATEMENT NO.062 - LEAK TESTING FOR EPDM @ EW&ID/RIC/T-017/14 5-Jan-14 CLOSED CLOSED ACCEPTED
JAN. 01 2014 023-RIC-T-2996/13 ROOF SLABS WATER PROOFING MEMBRANE FOR ALL BLDGS.
METHOD STATEMENT NO.063 - REPAIR WORK OF OPEN
114 TEXTURE FOR LAID ASPHALT PAVEMENT AROUND EW&ID/RIC/T-501/14 26-Mar-14 CLOSED CLOSED APPROVED AS NOTED
MARCH 04 2014 023-RIC-T-3400/14 TRANSFORMER FOUNDATION

METHOD STATEMENT NO.064 - INSTALLATION OF HOLLOW BY REF.023-RIC-T-3492/14


115 EW&ID/RIC/T-426/14 13-Mar-14 CLOSED CLOSED
MARCH 09 2014 023-RIC-T-3428/14 CORE CONNECTING BRIDGE FOR RESD'L BLDGS. TSQ-C-300 EW&ID/RIC/T-473/14

116 METHOD STATEMENT NO.065 - TIE-IN EXIT MANHOLE (MH-12) EW&ID/RIC/T-655/14 22-Apr-14 OPEN RESPONSE REQUIRED
APRIL 02 2014 023-RIC-T-3563/13 FROM NEW MANHOLE (MH-12A) OF NEW WAREHOUSE
METHOD STATEMENT NO.066 - REPAIR OF RUSTED STEEL
117 ANGLE FRAMES OF CHILLED WATER PUMPS IN PUMPHOUSE EW&ID/RIC/T-780/14 13-May-14 CLOSED CLOSED REVISED
MAY 05.2014 023-RIC-T-3749/14 AND RESD'L BLDGS.
METHOD STATEMENT NO.066 REV.01 - REPAIR OF RUSTED
118 STEEL ANGLE FRAMES OF CHILLED WATER PUMPS IN EW&ID/RIC/T-853/14 25-May-14 CLOSED CLOSED ACCEPTED
MAY 13.2014 023-RIC-T-3786/14 PUMPHOUSE AND RESD'L BLDGS.

119 METHOD STATEMENT NO.067 - UNDERGROUND LINE REPAIR EW&ID/RIC/T-845/14 22-May-14 CLOSED CLOSED ACCEPTED WITH COMMENTS
MAY 19.2014 023-RIC-T-3819/14 IN BATTERY ROOM
METHOD STATEMENT NO.068 - FABRICATION,INSTALLATION
120 OF TEMPORARY WYE STRAINERS AT BLDG.222 AND 221 FOR EW&ID/RIC/T-930/14 11-Jun-14 CLOSED CLOSED REFER TO SAPMT COMMENT
JUNE 02 2014 023-RIC-T-3869/14 CHILLED WATER LINES
METHOD STATEMENT NO.069 - WATER FLUSHING AND
121 CHEMICAL TREATMENT OF CHILLED WATER LINE FOR EW&ID/RIC/T-908/14 10-Jun-14 CLOSED CLOSED APPROVED
JUNE 03 2014 023-RIC-T-3877/14 BLDG.222 AND 221
METHOD STATEMENT NO.070 - PRIMER COATING OF RUSTED
122 WELDED JOINT OF Z STEEL DOOR FRAMES AT NEW CLOSED CLOSED BY REF.023-RIC-T-3905/14
JUNE 08 2014 023-RIC-T-3894/14 WAREHOUSE BUILDING (PURLINS)

123 METHOD STATEMENT NO.070 REV.01 - PRIMER COATING OF EW&ID/RIC/T-947/14 17-Jun-14 CLOSED CLOSED APPROVED AS NOTED
RUSTED WELDED JOINT OF Z STEEL DOOR FRAMES AT NEW
JUNE 10 2014 023-RIC-T-3905/14 WAREHOUSE BUILDING (PURLINS) HEMPEL GALVOCOAT
METHOD STATEMENT NO.071 - REPLACEMENT OF DAMAGED
124 CHILLED WATER PIPE INSULATION AND DUCTWORK EW&ID/RIC/T-961/14 28-Jun-14 CLOSED CLOSED APPROVED AS NOTED
JUNE 17 2014 023-RIC-T-3934/14 INSULATION

125 METHOD STATEMENT NO.072 - BORING OF HOLES FOR DINING EW&ID/RIC/T-1128/14 7-Sep-14 CLOSED CLOSED APPROVED AS NOTED
AUGUST 12 2014 023-RIC-T-4077/14 STEEL COLUMNS C1052 AND C1053

126 METHOD STATEMENT NO.073 - FLUSHING AND CHLORINATION EW&ID/RIC/T-1204/14 16-Oct-14 CLOSED CLOSED APPROVED WITH COMMENTS
OCTOBER 06 2014 023-RIC-T-4214/14 OF FIRE WATER SPRINKLER SYSTEM AT BLDG.222 AND 221

Prepared by: Jailo A. Bantiyan


Page 7 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT
METHOD STATEMENT NO.074 - CUTTING AND CHIPPING OF
127 EXISTING LINTEL BEAM AND FOOTING AT DINING EXPANSION EW&ID/RIC/T-1208/14 20-Oct-14 CLOSED CLOSED APPROVED AS NOTED
OCTOBER 11 2014 023-RIC-T-4226/14 BLDG.

128 METHOD STATEMENT NO.075 - REPAIRING OF ELEVATOR PIT EW&ID/RIC/T-1332/14 1-Dec-14 CLOSED CLOSED REVISED
NOVEMBER 26 2014 023-RIC-T-4368/14 FOR WATER TIGHTNESS (RENDEROC PLUG)

129 METHOD STATEMENT NO.075 REV.01 - REPAIRING OF EW&ID/RIC/T-1411/14 18-Dec-14 CLOSED CLOSED APPROVED WITH COMMENTS
DECEMBER 16 2014 023-RIC-T-4454/14 ELEVATOR PIT FOR WATER TIGHTNESS (ABSAR)

130 METHOD STATEMENT NO.076 - INSTALLATION OF PRE-CASTED EW&ID/RIC/T-1355/14 8-Dec-14 CLOSED CLOSED APPROVED AS NOTED
DECEMBER 01 2014 023-RIC-T-4391/14 CAR PARKING SHED CONCRETE FOUNDATION

131 METHOD STATEMENT NO.077 - EXCAVATION FOR TANKS EW&ID/RIC/T-0006/15 5-Jan-15 CLOSED CLOSED APPROVED WITH COMMENTS
DECEMBER 31 2014 023-RIC-T-4519/14 FOUNDATIONAT MBR PLANTS

132 METHOD STATEMENT NO.078 - FIRE POTABLE WATER EW&ID/RIC/T-257/15 14-Apr-15 CLOSED CLOSED APPROVED AS NOTED
APRIL 12,2015 023-RIC-T-4820/15 STORAGE TANK CHLORINATION

133 METHOD STATEMENT NO.079 - CUT AND SPLICE FOR MV EW&ID/RIC/T-353/15 24-May-15 CLOSED CLOSED APPROVED
APRIL 21,2015 023-RIC-T-4849/15 CABLE AT MBR
METHOD STATEMENT NO.080 - REPAIRING OF CRACKS ON
134 REINFORCED CONCRETE GRADE SLAB AT TAXIWAY (SHRINK EW&ID/RIC/T-768/15 18-Nov-15 CLOSED CLOSED REJECTED
NOVEMBER 15 2015 023-RIC-T-5494/15 GROUT)

135 METHOD STATEMENT NO.081 - REPAIRING OF CRACKS ON EW&ID/RIC/T-789/15 1-Dec-15 CLOSED CLOSED APPROVED
NOVEMBER 16 2015 023-RIC-T-5504/15 REINFORCED CONCRETE GRADE SLAB AT TAXIWAY (EPOXY)

METHOD STATEMENT NO.082 - RECTIFICATION OF INSTALLED


136 1 NO.STATIC GROUNDING WELL ON CONCRETE GRADE SLAB EW&ID/RIC/T-775/15 25-Nov-15 CLOSED CLOSED APPROVED
NOVEMBER 23 2015 023-RIC-T-5513/15 AT TAXIWAY

137 METHOD STATEMENT NO.083 - EXISTING AERATION TANK EW&ID/RIC/T-804/15 8-Dec-15 CLOSED CLOSED APPROVED AS NOTED
NOVEMBER 23 2015 023-RIC-T-5514/15 CONNECTIONS FOR MBR REQUIREMENTS

138 METHOD STATEMENT NO.084 - WATER LEAK REPAIR ON MBR EW&ID/RIC/T-774/15 24-Nov-15 CLOSED CLOSED APPROVED AS NOTED
NOVEMBER 23 2015 023-RIC-T-5520/15 TANK (RENDEROC PLUG)
METHOD STATEMENT FOR FIRE STOP APPLICATION (MEP
139 PENETRATION AND CONSTRUCTION JOINTS) HILTI (RISE AND EW&ID/RIC/T-601/13 12-May-13 CLOSED CLOSED APPROVED AS NOTED
MAY 05.2013 023-RIC-T-1768/13 SHINE)

REVOKED BY REF.023-RIC-L-
140 ADDITIONAL FIRE STOPPING ASSEMBLY FROM HILTI (IN CLOSED CLOSED
1496/13
JUNE 04 2013 023-RIC-T-1891/13 ADDITION TO MOS REF.023-RIC-T-1768/13)

141 METHOD STATEMENT OF DISINFECTION OF WATER EW&ID/RIC/T-885/13 17-Jul-13 CLOSED CLOSED REVISED
JULY 02 2013 023-RIC-T-2025/13 DISTRIBUTION SYSTEM FOR NGL PIPING (WATER PROJECT)

142 REVISED METHOD STATEMENT OF DISINFECTION OF WATER EW&ID/RIC/T-1026/13 19-Aug-13 CLOSED CLOSED APPROVED WITH COMMENTS
AUG. 15 2013 023-RIC-T-2223/13 DISTRIBUTION SYSTEM FOR NGL PIPING (WATER PROJECT)

143 METHOD STATEMENT OF FIELD LAMINATION OVER THE EW&ID/RIC/T-998/13 14-Aug-13 CLOSED CLOSED APPROVED AS NOTED
AUG. 04 2013 023-RIC-T-2180/13 ADHESIVE JOINT (FPI)

144 METHOD STATEMENT SCHUCO STICK CURTAIN WALL EW&D/RIC/T-1224/13 3-Oct-13 CLOSED CLOSED APPROVED AS NOTED
SEPTEMBER 04 2013 023-RIC-T-2314/13 DETAILED INSTALLATION

Prepared by: Jailo A. Bantiyan


Page 8 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

145 ELECTRICAL METHOD STATEMENT (MV CABLE SPLICING AND EW&ID/RIC/T-1252/13 9-Oct-13 CLOSED CLOSED REVISED
OCTOBER 02 2013 023-RIC-T-2452/13 TERMINATION,MEGGER)

146 REVISED 01 ELECTRICAL METHOD STATEMENT (MV CABLE EW&ID/RIC/T-1397/13 5-Nov-13 CLOSED CLOSED ACCEPTED WITH COMMENTS
OCTOBER 22 2013 023-RIC-T-2545/13 SPLICING AND TERMINATION,MEGGER)

147 METHOD STATEMENT TIE-IN PACKAGE NO.01 NEW RESD'L EW&ID/RIC/T-1307/13 23-Oct-13 CLOSED CLOSED APPROVED AS NOTED
OCTOBER 13 2013 023-RIC-T-2474/13 BLDG.

METHOD STATEMENT TIE-IN PACKAGE NO.01 REV.01 NEW EW&ID/RIC/T-1555/13


148 EW&ID/RIC/T-1618/13 4-Dec-13 OPEN REVISE AND RESUBMIT
NOVEMBER 19 2013 023-RIC-T-2474A/13 RESD'L BLDG.

149 METHOD STATEMENT TIE-IN PACKAGE NO.02 NEW RESD'L EW&ID/RIC/T-1556/13 28-Nov-13 OPEN REVISE AND RESUBMIT
NOVEMBER 20 2013 023-RIC-T-2737/13 BLDG.

150 METHOD STATEMENT TIE-IN PACKAGE NO.03 SUBSTATION EW&ID/RIC/T-1558/13 28-Nov-13 OPEN REVISE AND RESUBMIT
NOVEMBER 20 2013 023-RIC-T-2738/13 AND CHILLYARD

151 METHOD STATEMENT TIE-IN PACKAGE NO.04 SUBSTATION EW&ID/RIC/T-1560/13 28-Nov-13 OPEN REVISE AND RESUBMIT
NOVEMBER 20 2013 023-RIC-T-2739/13 AND CHILLYARD

152 EW&ID/RIC/T-1562/13 28-Nov-13 OPEN REVISE AND RESUBMIT


NOVEMBER 20 2013 023-RIC-T-2740/13 METHOD STATEMENT TIE-IN PACKAGE NO.05 NEW CHILLERS

153 METHOD STATEMENT APPLICATION OF INTERNAL CEMENT EW&ID/RIC/T-357/14 27-Feb-14 CLOSED CLOSED APPROVED WITH COMMENTS
FEBRUARY 23 2014 023-RIC-T-3338/14 MORTAR FOR FIRE HYDRANT RISER (PAN GULF)

154 METHOD STATEMENT FOR CHEMICAL CLEANING OF CHILLED EW&ID/RIC/T-679/14 27-Apr-14 CLOSED CLOSED APPROVED
FEBRUARY 24 2014 023-RIC-L-1716/14 WATER PIPING
METHOD STATEMENT OF WORK SCHEDULE FOR
155 RECTIFICATION OF WRONGLY TERMINATED CABLES AT MV EW&ID/RIC/T-495/14 27-Mar-14 CLOSED CLOSED ACCEPTED
MARCH 09 2014 023-RIC-T-3459/14 SWITCHGEAR

156 AL-MARAE METHOD STATEMENT FOR FIBER OPTIC CABLE 276 EW&ID/RIC/T-1065/14 14-Aug-14 CLOSED CLOSED APPROVED AS NOTED
AUGUST 11 2014 023-RIC-T-4070/14 37-60 SPLICING/TERMINATION AND TESTING (CUT-OVER)
CONFIRMED FROM PMT
157 METHOD STATEMENT FOR LOAD TESTING PROCEDURE OF CLOSED CLOSED DOC/CON APRIL 26,2015 AS PER
DECEMBER 24 2014 023-RIC-T-4494/14 ELEVATORS AT RESIDENTIAL BUILDING 221,222,223 MR. BHANDER
METHOD STATEMENT FOR ROAD MARKING (DASCO DAFER
158 OPEN UNDER REVIEW
NOVEMBER 08 2015 023-RIC-T-5477/15 SUPPLY AND CONTRACTING)

Prepared by: Jailo A. Bantiyan


Page 9 of 10
Document Controller
SR No. DATE TRANSMITTED REFERENCE N0. SUBJECT REMARKS
TRANSMITTAL DATE MMG PMT

Prepared by: Jailo A. Bantiyan


Page 10 of 10