Ms-General-Qap 001rev. For Epc
Ms-General-Qap 001rev. For Epc
Ms-General-Qap 001rev. For Epc
A 12-09-2020
A 12-09-2020 Approval
Page 1 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
1.1. SERVICE 4
1.2. QUALITY 4
1.3. QUALITY ASSURANCE 4
1.4. QA PLAN 4
1.5. QA SYSTEM 4
1.6. QUALITY CONTROL 4
1.7. INSPECTION LEVEL 4
V. WORK ASSIGNMENT 6
VI WORKING PROCEDURE 7
7.1 GENERAL 8
7.2 TESTING IN THE CONTRACTOR'S FIELD LABORATORY 8
7.3 INSTRUMENT / EQUIPMENT CALIBRATION AND FREQUENCY 8
7.4 ADITIONAL TEST 8
VIII NONCONFORMANCE 9
Page 2 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
9.3 REVISION 10
9.4 DOCUMENT APPROVAL 10
9.5 DISTRIBUTION 10
X RECORD CONTROL 10
XI FILLING SYSTEM 11
XV RECORD 12
16.1 INSPECTOR 12
16.2 INSPECTION AND TEST EXECUTION CONTROL 12
XVII LOGISTIC 13
XIX AUDIT 13
Page 3 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
I. GENERAL
Scope
This Quality Assurance and Quality Plan is to establish control procedures that to be executed
properly and effectively in order to assure the reliability in procurement, inspection, and
construction in compliance with the requirements specified in the contract documents. If there
is any conflict between this plan and contract documents, the last revision of the contract
documents shall be favour.
1.1 SERVICE
1.2 QUALITY
Fitness for use; means intended purpose, performs satisfactory in service for a special time.
1.4 QA PLAN
A detailed scheme is developed and documented, for achieving the desired level of quality in
completion facilities.
1.5 QA SYSTEM
The procedures, equipment, activities, organization and personnel use implement quality
assurance plan
It Is the overall system of routine technical activities whose purpose is to measure and control
the quality of a product or service so that it meets the needs of the user or standards.
The specified amount of inspection is deemed necessary to ensure that the product of service
conform to specification.
2.1 In “Anwesha Engineering & Projects Limited” quality assurance policy shall be
formulated to achieve procurement, construction, and test which are defined as time schedule,
project cost, safely execution. A part of the quality assurance is to satisfy the contractor at all
stage of the project. Executive management “Anwesha Engineering & Projects Limited” shall
be required to confirm their commitments to implement this plan by signing the Quality
Assurance Policy Statement.
2.2 Project Manager and each relevant manager are responsible for assure that all phases
of the program which is his responsible are operate strictly in accordance to the quality
assurance. The QA/QC Manager has authority to delegate the inspection, identify quality
problems and problem solving to all inspectors in every discipline.
Page 5 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
The organization and its authority and responsibility in activity performance which is affecting
the quality to satisfy the requirements. The level of the responsibility and assigned authority of
these personnel shall be clearly indicated.
Project Manager has overall authority and responsibility to execute the project regarding
contractual condition, establishment of project organization and coordination, implementation
and maintenance of QA Plan, monitoring the job quality, effective cost and schedule, and the
entire project management.
In order to ensure the implementation of the QA Plan, QA/QC manager will be assigned in the
project organization. He will report directly to the project manager.
4.3. ENGINEER
Engineer is responsible to report to construction Manager for all engineering aspects of the
project and assure that the work is compliance with the applicable documents.
PC is responsible to report to Project Manager for the control of cost, Schedule, documents,
materials and loss prevention control on the planning.
Page 6 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
Construction Manager is assist Project Manager in handling the construction activities and
ensure that the activities are in accordance with the requirements of this plan.
4.6. PROCUREMENT
Procurement is responsible for all aspect of the procurement of equipment, materials and
service, including purchasing, expediting and shipping. He shall establish the procurement
policy including the activities specified by the QA plan.
Safety Manager / Health and Environment Officer shall assist to the Construction Manager in
conducting the safety, health and environment program under the direction of the project
manager. HES Officer shall check the concept of each work plan or procedure and report his
conclusion to the construction manager.
7.8. LOGISTIC
Logistic shall responsible to the construction manager for overall control materials, including
receiving, checking, inspection, storing, issuing, and handling over and disposal materials.
Document Control shall responsible to Identify and Control of Document affecting quality to
assure that documents are processed properly, and that the latest applicable documents are
available to the personnel or organization concerned on schedule.
V. WORK ASSIGNMENT
This Work assignment describes a QA/QC contribution from Planning Stage until
Project have finished.
5.1 When Contract Awarded, QA/QC Manager held a Contract Review Meeting with all of
project Management Team. Reviewing project requirement, ensuring that contract have not
noncompliance, job sharing to develop a planning.
5.2 When Engineering personnel submit constructability review from drawing and
execution method then QA/QC inspector have to follow Inspection and Testing Plan and as
per project requirement.( Subcontractor will follow Contractor Inspection and Test Plan)
5.3 When Procurement want to procure material, QA/QC Manager have to review the
compliance before submission Purchase Order to Vendor and ensuring that appropriate
document such as mill certificate, MSDS, Inspection Manual, Heat Number have described on
Purchase Order.
5.4 At Material Receiving, QA/QC Inspector have to make inspection material compliance,
and ask for a Material Verification from Contractor‘s Inspector.
5.5 All of Material must have identification, in order traceability more easy. QA/QC Officer
and Logistic have to make identification for all material.
Page 7 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
4.6 QA/QC inspector have to ensure that storage process satisfy with work order,
Maintained, placed on safe area in warehouse.
5.7 Material will not be damaged then process handling and delivery satisfy with
procedure. QA/QC Manager have to give explanation to Logistic the essential of
implementation correct delivery and handling method.
5.8. All of non-conformance since material receiving until final inspection must be corrected
and prevented to increase performance of Work. Non conformance control system have to be
applied by QA/QC Manager and will get Corrective and Preventive Action by personnel whose
responsible for Corrective and preventive action.
5.9 All Correction and preventive action have to be monitored in order the cause of non
conformance have eliminated and can be prevented for next time.
5.10 When QA/QC wants to conduct Audit, then Audit prepared by QA/QC Manager. The
implementation of audit is responsible QA/QC Manager. All of Non-conformances have to be
eliminated by auditor. The result of audit has to be reported to Project Manager and then all
PMT will involve the management review to make plan of system improvement.
7.1 GENERAL
To ensure that all required testing is properly identified, planned, documented and performed
under controlled and suitable environmental conditions, including cleanliness.
6.1.1 “Anwesha Engineering & Projects Limited” will perform all required testing and
will provide all the necessary labour, materials and testing equipment as per project
requirements and scope of work.
6.1.3 Sub contractor will produce and submit fabrication and construction / errection
procedure, WPS, PQR, Qualified Personnel List, Inspection Test Records (Mill Test
Certificate), QA/QC Plan, Special Process Records Technical Documents, and MSDS
etc to Contractor.
Page 8 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
6.1.4 As early as possible Subcontractor will submit all test report to Contractor
which will carried out at site. All tests will be recorded on standard tests reports format
agreed with or supplied by contractor
Sub-Contractor shall established material testing laboratory at site, equipped and adequately
staffed to carry out the field laboratory tests as per requirements defined in the Contract.
This Field Laboratory established by the sub-contractor and supervised by the Contractors
Quality Control / Assurance staff will carry out the required tests and maintain a systematic
and retrievable record.
The Sub-Contractor will be responsible for providing and transporting the test specimens to
the laboratory under the guidance and supervision of the Contractors representative.
Instruments and equipment shall be calibrated prior to each use or on a scheduled, periodic
basis. The calibrations performed and the standards used will be recorded. Calibration
certificate will be available at work site.
Additional tests, not covered on this specification may be required for projects. These tests in
general shall be in accordance with the equipment manufacturer’s recommendation or
Contractors recommendation. Such field tests that are necessary for this equipment shall be
performed by the Contractor Engineer, Manufacturer’s test engineer, or Third-party Inspectors
with agreement between Sub-Contractor and Contractor and results shall be submitted to the
Contractor.
VIII. NONCONFORMANCE
7.2.1 Work that was not built as indicated in the approved Issued for Construction
drawings
7.2.2 Work that fails to meet specified tolerances as established in the project
specifications
7.2.3 Work that is being performed using non-approved methods or standards
7.2.4 Failure to follow the approved testing and inspection plan
7.2.5 Testing results demonstrate that the product does not meet established and
approved standards
7.2.6 Material used that has not been approved as a substitute (equal or similar)
Documents controller controls all documents affecting quality to assure that documents are
processed properly, and that the latest applicable documents are available to the personnel or
organization concerned on schedule.
Each documents prepare by the relevant discipline shall assigned a unique number in
accordance with the document numbering system established for the project numbering
system shall be approve by Contractor.
Document controller shall list up the document, and shall be updated for issuance, receipt and
approval to identify the current document status.
Page 10 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
9.3 Revision
Each document conduct to revise have to be marked with number revise. And Document old
ones pulled from circulation to be kept or annihilate.
All documents to be submitted to Contractor for Approval and issue to use. If document have
got approval from contractor hence can be distributed to field.
9.6 Distribution
All Documents have to be distributed according to request. Document control has to record all
of document distribution. Document that distributed have to be marked CONTROLLED
DOCUMENT, UNCONTROLLED DOCUMENT, CONFIDENTIAL, RECEIVED, OBSELENCE.
XI RECORD CONTROL
10.2 All of record from field operation or execution process must be maintained by
Construction Manager.
10.3 Company Record for process business have to be maintained under responsibility of
manager.
11.3 All of Superintendent have to maintain document through filling system assisted
document control.
Basis of the engineering data received from Contractor applicable documents following as
deemed necessary:
12.1 Scope of work, delivery date, location, applicable project code, and standard,
specification, and design and QA/QC document.
12.2 Requirement for personnel qualification, inspection and test and shipping preparation
and reporting.
Page 11 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
12.4 Vendor document required, such as Inspection Test Records (Mill and Test
Certificate), QA/QC Plan, Special Process Records Technical Documents, MSDS etc.
For identification control, documents controller provides vendor as mill certificate and test
certificate of goods and specification for mayor items, marking for packing and shipping
instruction, in which the marking method, marking location, marking items and colour coding
are specified.
Where physical identification on the item is impractical, physical separation procedure control
such as by tags, labels, and records shall be employed.
A transfer of marking shall be controlled and identification during storage shall be controlled,
separated, and labelled by tags etc.
Non-conforming items shall be identified and separated based on inspection status (accepted,
rejected, not yet inspected) shall be identify.
Marking shall be applied in a manner and at a location that would leave detrimental effect on
the items.
For material from vendor there must be stamp from fabricator of like material spec, logo
fabricator, tugs number, etc.
XV. RECORD
The record shall be traceability to the items and shall be checked by Inspector.
Inspector shall submit document inspection “as built sketch of material” allocation in
which the marking location including weld number.
Inspection and testing to verify the conformance of products and service to the specified
requirements of the contract, applicable codes and standard for the procurements phase.
Sub contractor will follow Contractors ITP with related inspection format.
16.1 INSPECTOR
Page 12 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
Inspector Coordinator select inspector on the basis of prior experiences and qualification. The
nominated inspection classification:
*Pre-inspection meeting will be held for mayor items or when deemed necessary by inspector
coordinator with contractor for mutual understanding prior to the fabricating.
*Witnesses’ inspection will be conducted at shop or field by inspection Representative for the
Hold Point items.
*Final inspection shall include a record review of the result and resolution of non-
conformances identified by prior inspections. Inspector coordinator shall check the inspection
record and when the record is found to meet purchase order requirements.
XVII LOGISTIC
All materials will identify on handling, storage, and shipping on the basis of legal restrictions,
and specification on the procurements documents.
*The methods and means of handling that the prevent damages or deterioration.
*All material handling shall be clearly identified by marking, tags, labels, location, etc to
prevent abuse, misuse and loss.
*Handling of heavy components specials handling by operator and lifting equipment, the
equipment checked periodically at appropriate intervals.
Page 13 of 14
RURAL WATER SUPPLY PROJECT AT
KUARMUNDA AND NUAGAON
DISTT. SUNDERGARH ODISHA
17.2 QAQC manager / QAQC engineer have to obey the filling system and prepare quality
record index to identify all the records to be collected and filled with the cooperation of
relevant design engineering.
17.3 The size of record, format of record, contents of file shall also be defined.
17.4 Record shall be legible with approved signs and the identification
17.5 Record shall be made available with subcontractor and submit to contractor upon
request within the retention period.
XIX. AUDIT
18.1 QA/QC Officer establish audit plant for internal and external, consideration to the
importance of items and service for which the received orders and to their past performance.
18.2 Audit is performed in accordance with the appropriate procedure, Scheduling and
check list by auditor.
18.3 Audit is performed in accordance with the predetermined schedule, which includes
audits for the site work at appropriate stages.
18.4 In the event that QA/QC Officer deems necessary through routine monitoring of
QA/QC activities as required by the contact, additional internal audits are to be selected.
18.5 Audit will be performed by QA/QC Officer or personnel designated by him on the
particular areas.
Audit result shall be recorder in audit check list and reported to Construction Manager
together with audit summary report. These shall be reviewed by Construction Manager and
sent to the Project Manager, with recommended for the corrective actions.
Page 14 of 14