Professional Documents
Culture Documents
Dry Port Planning Analysis and Design at Pling Bhutan
Dry Port Planning Analysis and Design at Pling Bhutan
OF
DRY PORT IN PHUNTSHOLING
Project Report
Submitted in partial fulfillment of the requirements
for the award of the degree of Bachelor of Engineering
in
Civil Engineering
By:
Melody Beattie said “Gratitude unlocks the fullness of life. It turns what we have into
enough, and more. It turns denial into acceptance, chaos to order, confusion to clarity. It can
turn a meal into a feast, a house into a home, a stranger into a friend”. We would like to
express our sincere gratitude to our project guide Dr. P.V. Surya Prakash for his continuous
and timely support. We are highly indebt for his inspirations and hard works for making this
project a successful one, besides his busy teaching schedule in the college.
We express our gratitude to the College of Science and Technology for providing such a
forum where we could utilize our learned knowledge and acquired new knowledge over the
period of project completion.
In addition, we are thankful to our lecturers Dr. Cheki Dorji (HoD, Civil Department),
Mr.Ugyen Tenzey (Head of IIR), Miss. Chimmi Wangmo (Project Coordinator), Mr. Ugyen
Dorji (Construction Manager), and other faculty members who have helped directly or
indirectly in providing the timely feedbacks. Many of these people provided valuable
information that has being incorporated in this project.
We are highly indebt to Mr. Karma Dorji (Architecture, Phuntsholing City cooperation),
Wangchuk Thaye (Joint Commissioner, Custom and Excise), and Bhishal Rai (Revenue and
Accounts section officer) for their supports in providing the necessary information required
for this project.
We are also thankful to Mr. Suzay Giri (Structural Engineer, Tashi Dawa Associates), and to
all those whose names are missing and those who has landed their help by providing the
valuable information, timely criticism and their support in making this project a success.
Yangchen Wangmo
Passang Wangmo
i
ABSTRACT
Phuentsholing is commonly known as the main business hub for Bhutan and it is also the
main entry point to the Kingdom of Bhutan for the transshipment of goods. Year by year, the
number of industries are rising significantly and the business interests for private sectors are
rapidly expanding to meet the Vision Bhutan 2020. As swift development has been taking
place and it was seen as major concern by PCC, RRCO and MTI in managing and handling
the flow of goods as well as other economic activities. As per the master plan of PCC, the
government has proposed a dry port and earmarked the site for the same from the feasibility
studies carried out earlier. The proposed site for dry port has an area of 7.78 acres which
comprises of central workshop, STCBL, Sal forest and some other private lands. Hence, the
same site is selected to carry out present project titled “Planning, Analysis and Design of Dry
Port in Phuentsholing”.
All components required for a dry port studied from the literature review are incorporated in
the present proposed dry port. Based on the data and information collected from PCC, RRCO
& MTI, the spatial requirements were calculated. Incorporating all the requirements of a dry
port and space estimated as above, the planning analysis is carried out and a systematic plan
for the proposed dry port was arrived.
Major components of dry port viz. office building, warehouse and hazardous storage house
with all the facilities necessary for its proper functioning, are only selected for the analysis
and design purpose. The analysis was carried out using STAAD Pro software. A program
using Microsoft Excel was developed for the design of all the building components.
However, sample calculations were made manually for the design for all components of the
building to verify the developed program. The design of pavement and drainage are also
done.
The total built up area for buildings is 2.78 acres and roads and pavement area is 5 acres. The
estimated cost based on plinth area method for this dry port is approximately Nu. 99.16
millions excluding land cost.
ii
Contents
Page no
ABSTRACT i
ACKNOWLEDGEMENT ii
LIST OF FIGURES iii
LIST OF ABBREVIATIONS iv
1. INTRODUCTION 1
2. SCOPE AND OBJECTIVE 2
2.1 Scope 2
2.2 Objectives 2
3. FEASIBILITY STUDY FOR DRY PORT 3
3.1 Need 3
3.2 Background Information 3
3.3 Site Location 4
4. PLANNING ASPECTS 6
4.1 Dry functions, components and requirements 6
4.1.1 Functions 6
4.1.2 Components 7
4.1.3 Requirements 8
4.2 Spatial Planning 9
4.3 System Plan 14
5. STRUCTURAL ANALYSIS OF BUILDING COMPONENTS 17
5.1 Design Loads Considerations 17
5.2 Analysis of Roof Trusses 21
6. DESIGN OF BUILDING COMPONENTS 22
6.1 Design of Main Roof Truss of Office Building 22
6.1.1 Design of Member Sections 22
6.1.2 Design of Purlins 26
6.2 Design of Two Way Slabs of Office Building 27
6.3 Design of Beam of Office Building 30
6.4 Design of Column of Office Building 36
6.5 Design of Stair Case of Office Building 43
6.6 Design of Isolated Footing of Office Building 50
6.7 Design of Combined Footing of Office Building 53
6.8 Design of Slab Beam Type Strip Footing of Office Building 58
6.9 Pavement 63
6.9.1 Design of Flexible Pavement 63
6.9.2 Design of Drainage 65
7. COST ESTIMATION 68
7.1 Specification of Building 68
7.1.1 Two storied RCC framed structure 68
7.1.2 Ware house and Storage (one storey) 69
7.2 Calculations 69
8. CONCLUSION 72
9. REFERENCES 74
BIBLIOGRAPHY 76
APPENDICES 77
List of figures
Page
Figure 4.1 Functional Structure of Dry Port 6
Figure 4.2 Flow of Cargo in Dry Port 7
Figure 4.3 Ariel Photograph of Dry Port 10
Figure 4.4 Spatial Planning 14
Figure 4.5 System Plan of Dry Port 15
Figure 4.6 Flow of Vehicles within the Dry Port entering from India 16
Figure 4.7 Flow of Vehicles within the Dry Port entering from in Country 17
Figure 6.1 Slab Plan of 1st Floor 28
Figure 6.2 Shear force diagram 35
Figure 6.3 Stair case plan 45
Figure 6.4 Loading diagram on stair case 47
Figure 6.5 Loading diagram on landing of stair case 49
Figure 6.6 Footing & column plan of office building 53
Figure 6.7 Diagram of Loading, Shear Force & Bending Moment of
57
Combined Footing
Figure 6.8 Loading Diagram of Footing 61
Figure 6.9 Shear Force & Bending Moment Diagram of Strip Footing 62
Figure 7.0 Drainage outline of dry port 68
iii
List of abbreviations
iv
The width of the passage provided for the trolley movement is 2m. The clearance between
the external wall and the nearest stack for the people movement is 1m. From the available
data which we got from the custom office the yearly increment is about 8.7%. Taking into the
variation in economic activities, the yearly increment as 10% is adopted for planning
purpose. The dry port is planned to meet the next fifteen years. Refer table 3 in the appendix
for the yearly increment detail. With all the consideration the size of the warehouse is coming
to be 66m in length by 40 m in width. For two symmetrical warehouses the total area
required is 5280 m2. For the vehicle movement we require minimum of 20m space available
in front of warehouse for vehicle movement. Considering all these factors we have placed
warehouse in zone 1 with a parking facility.
Zones 2 of having an area of 1.5 acres proposed to have the following components as
mentioned below. The component includes office building, workshop, canteen and car
parking area. Other smaller components like public toilet and waste disposal pit are also
located in this zone2.
The reasons for having the above mentioned components placed in this zone are as follows:
The dimension of the office building was calculated considering the no of staffs that will be
employed and that are likely to increase in future with growth of dry port. The no of staff
required is calculated from the existing staffing pattern of custom office. The oregano gram
is given below for detail.
The dry port will be handling the huge volume of cargo and the vehicular flow and there is
every chance that damages on containers or vehicle break downs might happen. To carry out
11
the repair work the workshop is needed. To avoid the delays in remaining break down
vehicles from dry port, a workshop for emergency repair works is proposed in the dry port
itself. To make the work easier and to save time we have proposed the workshop to be
located within the dry port. Considering the number of vehicle, height and equipment
required the dimension of workshop is coming out to be 20.5m in length by 14.5m in width.
The car parking spaces for office staffs and the daily visitors requires 190 m2. The total
spaces we require for all the components in this zone is about 1010m2 and for detail refer the
table4.2 below. Considering the space required for vehicular movement, setbacks, etc the
available area is enough just to fit all the structures.
Zone 3 as mentioned earlier it consists heavy vehicle parking, goods transition area from
vehicle to vehicle and hazardous storage. At present whatever the hazardous materials are
imported, they directly transported to its destination. For the future use with the available
information we have provided a chemical storage space of 20 m by 15m is provided. As per
the guidelines provided by the Building code of Bhutan, BTS 002-2003, the hazardous
storage should be located in an isolated area. With this view the hazardous storage is placed
in this zone 3 where there are no residents in the nearby area. Also, this area is located, even
if any chemical leakages or fire accidents takes place, there will not be major destruction to
other structures located in this area. The hazardous storage structure will be filled with all
necessary fire safety systems and equipments.
The leakages of chemicals in the storage from the containers have to be taken great
precaution and containers have to be constantly checked for the presence of any
leakages/damage. Apart from the above measures, the chemicals should be stored in cool
12
and dark condition. In order to incorporate the safety, we have considered following points in
our planning, design and analysis part.
Provide suitable fire fighting system like sprinkle system and fire hydrants.
The common practice that is practiced followed at present in Bhutan is the direct transition of
goods from vehicle to vehicle. To have such provision in future we have provided the
separate area for such activity along with the vehicle parking facilities. We have separate
parking area for the other trucks which will park only to get the custom clearance or for
necessary documentation. The details of the site and structure locations are all given in figure
2 below.
13
DRYPORT
The system plan is related to the vehicle movement within the dry port. It is of utmost
importance to have a good traffic flow within the port without any intervention on the other
activities those takes place. In dry port available space, we have fitted all the necessary
structures those are required in the dry port. One of the major components is parking facility.
We have provided three separate parking areas for heavy vehicles and one for light vehicle.
We have two entry and exit points, both located at separate plates. The details are shown in
figure number 6.
14
Figure
4.5 System plan of dry port (source: PCC)
The entry point will lead the vehicle to warehouse where we have provided one separate
parking area only for those vehicles which have to wait for its turn to get unloaded. This
parking will not be used for holding the trucks for carrying out the custom clearance. The
separate parking is provided for these purposes. However those vehicles which will go
directly to the warehouse can hold here. The flows of the vehicles are given below in the
form of flow diagram in figure4.6.
15
Figure 4.6 Flow of vehicles within the dry port entering from India
As mentioned earlier, the dry port is divided into three zones. In zone 3, there are two
parking areas, one for the trucks to hold and other for direct transition of goods from vehicle
to vehicle which is shown in the above diagram. Those trucks waiting for the custom
clearance will park their trucks in parking number three as shown above. The trucks or the
container containing the chemicals will directly go to zone three where the storage house is
provided.
The same pattern can be followed for the vehicles that enter into the dry port from within
country. For those trucks which will get unloaded and loaded back with the export goods
from within country will flow the following path as shown below in figure4.7.
16
Figure 4.7 Flow of vehicles within the dry port entering from in country
The zone two consisting of office and workshop will be responsible for carrying out the
custom clearance, documentation and repair works within the dry port. The basic idea of
having such type of vehicle flow is to avoid the interruption of different activities that takes
place in dry port. To be clearer it is to have different segregated activity at different location.
The advantages that we will gain from the above system of vehicles flow are as mentioned
below.
17
5. STRUCTURAL ANALYSIS OF BUILDING COMPONENTS
As mentioned in the scope of our project that we have mainly focused ourselves in the
planning of the dry port and to gain some experience regarding the design, analysis and
design of the important components within the dry port are included in the project.
The number of components that is actually required is already mentioned. Among those
components, the following components are selected for analysis and design purpose.
1. Office building
2. Hazardous storage building
3. Warehouse
The first step in the design of any structure is the loads to be considered for design includes-
the loads from roof trusses, dead loads from various components, live loads due to various
activities, wind loads and seismic loads. The dead loads and the live loads are considered as
per IS; 875-1987, wind loads are considered as per IS 875-1987 and the seismic loads are
considered as per IS 13920:1993 since Bhutan falls under zone v.
To save our time, we have done the analysis using STAAD Pro, 2006 software. All the
designs are done manually for which the details are give in next chapter. As a check we have
done manual analysis for the storage building and the final answers were compared with the
STAAD Pro analysis. After having found out that the STAAD Pro analyzed value and
manually analyzed value is negligible, we have directly gone for the STAAD Pro analysis for
all the remaining structures.
For the analysis using STAAD Pro, the loads were all taken according to the code IS: 875-
1987. The basic wind speed is taken as 44 m/s as per the Bhutan code.
18
The details of load consideration and analysis of roof trusses are given below:
Slope provided for roof = 15o (as per Bhutan building rule 2002 the angle varies between 12o-
15o) for office and storage building and
Pd = 0.6xVz2
Vz = VbxK1xK2xK3
Where,
K1 = risk coefficient
K2 = terrain, height, and structure size factor
K3 = topography factor
Vb = basic wind pressure in m/s at 10 m height
Therefore the wind pressure up to the height of 10 m is = ‘Pd’ = 0.6x442 =1.1616 kN/m2
For the building with height between 10 to 15m the wind pressure,
Pd=1.1X Pd
=1.1X1.1616
=1.2778 kN/m2
The wind force F acting in a direction normal to the individual structure element is
F = (Cpe-Cpi). A.Pz
Where,
Cpe = external wind pressure
19
Cpi = internal wind pressure
For the building with less than 5% opening its value is taken as = 0.2
For building with opening between 5% to 20% its value is taken as =0.5
A = surface area of the structural element
Load calculation
Dead load from purlin = 90
Live load =0.65kN/m2
Load of truss = (L/3+5) X 10
Where the L is the span of truss
Load from CGI sheet of 0.63 mm =0.056kN/m2
Clear floor height (ceiling height) = 2.6 m (assumption for analysis as depth of beam is not
known)
Note: this load of 15kN is given to building slab where it is place as plate pressure (area load)
20
7. Dead load from brick wall on internal partition wall = 0.15x2.6x19
= 7.41 kN/m
8. Dead load from cornices = 0.7250.52525
= 4.46 kN/m
Building height = 3m
Height of the external wall = 2.6 m (assumption for analysis as depth of beam is not known)
21
Live load are taken as per IS 875:1987
1. Live load = Live load due to storage =2.4kN/m2 per each m of storage with minimum
of 7.5 kN/m2
2. Dead load from brick wall on periphery beams = 0.3x2.6x19
= 14.82 kN/m
3. Dead load from brick wall on internal partition wall = 0.15x2.6x19
= 7.41 kN/m
Note: Inside the storage house we are not allowing the trolley movement. We have taken into
our consideration all the works (both loading and unloading) will be done manually.
A roof truss is basically a framed structure formed by connecting various members at their
ends to form a system of triangles, arranged in pre-decided pattern depending upon the span,
type of loading and functional requirements. The members are connected by riveting,
welding or using gusset plate if required. External loads are applied at joints only to take care
of the direct forces (either compression or tension). The roof trusses are divided as T1, T2,
T3, T4, T5, T6, T7 and analysis was done manually.
There are three methods to analyze the truss (i.e. graphical method, method of joints and
method of sections). Method of joints is used to analyze the trusses of all the components of
Dry Port. In this method, the forces at the joint and reactions are worked out for dead load,
wind load and live load. Then a free body diagram of each joints are applied with equilibrium
conditions ΣV=0 and ΣH=0 to determine the member forces. The truss is assumed to be
simply supported. The grouping was done and the most critical conditions from the groups
are taken for the design. The analysis for the trusses of other components was done in the
similar manner. For grouping of trusses, refer Table no.1 for office building and Table no.9
for warehouse in Appendices.
22
6. DESIGN OF BUILDING COMPONENTS
1. Tie member:
24 .37 × 10 3
= 165 .676 mm
2
Areanet=
147 .1
Area=4.14cm2
l 1.104 × 10 3
λ= = = 68 .57
r 16 .1
When wind loads are considered, the permissible stress (fc) can be increased by %
Therefore fc=1.33x114.03=151.66N/mm2
23
Load capacity=151.66x10-3 x 414 =62.79 kN > 49.953kN. Hence safe
2. Rafter
42.377 × 10 3
= 288 .08 mm
2
Areanet=
147 .1
Area=4.14cm2
l 1.128 × 10 3
λ= = = 70 .06
r 16 .1
24
3. Vertical members
20 .631 × 10 3
= 140 .25 mm
2
Areanet=
147 .1
Area=2.02cm2
l 0.276 × 10 3
λ= = = 32 .09
r 8 .6
4. Inclined members
25
Maximum compressive force = 37.501 kN
20 .631 × 10 3
= 140 .25 mm
2
Areanet=
147 .1
Area=4.00cm2
l 1.14 × 10 3
λ= = = 82 .01
r 13 .9
Design Results are tabulated in Table no.13 for all the Trusses of office building, Table no.18
for hazardous storage building and Table no.23 for warehouse in Appendices.
26
6.1.2 Design of Purlins
Load on Purlins:
112.7 × 1.5
Dead load due to roof covering material= = 0..169 kN/m
1000
Total DL=0.169+0.08=0.249
DL+LL=0.249+1.065=1.314 kN/m
DL+WL=0.249-2.125=-1.879 kN/m
Yst 240,
fb =165N/mm2
wl 2 1.876 × 2.25 2
Maximum B.M= = = 0.949 kNm
10 10
M 0 .949 × 10 6
= 5751 .7 mm 3 ≈ 5 .75 cm
3
Section modulus= =
fb 165
l 2250
Permissible deflection= = = 6.92 mm
325 325
27
Concentrated load on Purlins=1.876x2.25 = 4.221kN
5× w× l 3 5 × ( 4.221 × 10 3 ) × ( 2250 ) 3
Deflection at the centre = = = 6.029 mm < 6.92. Hence safe
384 × E × I 384 × 2.1 × 10 5 × 49 .44 X 10 4
1. Two way slab (P1, P2, P3, P4, P17, P18, 19, P20 and P14)
.
= 1.3<2Hence it is a two way slab.
.
28
Effective length (Le ) = 3.28+0.10=3.38 m
Moment coefficient:
Short span:
Long span:
Moments:
√.
Depth required d= = 47 < 150 therefore safe.
.
=1.2- 1.2
..
= 0.087 < 0.48
29
Z =100(1-0.420.087) =96.346
.!"#$
Ast(s) =
.
.!%&.
Ast(s) = = 175.92mm2
!%.&
'
n= = 2.24~3(Ast=235.62mm 2 )
Spacing = = 300 mm c/c
Torsion reinforcement:
Provide 8mm ∅
.%
'
n= = 2.25~3
*+
%
= 656~600mm
∴Provide 3nos. 8mm ∅ @ 300mm c/c for a distance of 600 mm from face of the column.
%.
Pt= =0.24, Kt=1.44
- .provided =
*
= 33.8
Vu=Wu (0.5lxd)
= 10.5(0.53.28.100) =16.17KN
0v =
.!1
=0.162
τc / τv , Hence it is safe
The summary of the slab design for office building is tabulated in Table no.16 and Table
no.20 for hazardous storage building in the Appendices.
f y = 415 N/mm2
Mu
d=
0.138×f ck × b
6
95.914x10
d= 40.138x300x20 = 340.35mm
Provide d=370mm
Mu Lim = 0.138. f ck bd 2
.%999! 4.6x95.914x10
6
x :1 41 2 ; = 854.95 mm
% 20x300x370
2
Ast, reqd =
%.&%
= 3.35 < 4 nos.
%.!
No. of bars required =
32
=9=
Spacing = = 55.5mm
Mu Lim = 0.138. f ck bd 2
.%999! 6
4.6x39.789x10
x :1 41 2 ; = 316.752 mm
% 20x300x370
2
Ast, reqd =
.!%
= 2.8 < 3nos.
.
No. of bars required =
=9=
Spacing = = 76mm
Check-
.!"> ?@A
."BC D
Xu =
.!9%9&.
.99
Xu = = 56.515 mm
33
Shear reinforcement:-
b) Shear force due to formation of plastic hinges at both ends of the beam plus the factored
gravity load on the span. This is given by:
fy. Ast
AS
Mu Lim = Mu Lim
BS
= 0.87. fy. Ast d −
fck .b
D+ L D+ L 1.2(D + L )
Va = Vb =
2
D+ L
Mu, AS lim + Mu Lim Bh
Vu, a = V a + 1.4
L AB
Mu , AS lim + Mu Lim Bh
Vu , b = VbD + L − 1.4
L AB
Mu?J
GHI = MuGHI = 0.87x415x804.24-370 . = 91.28kNm
KJ %9.
9
Factored load = 27 kN
34
Figure 6.2 Shear force diagram
By interpolating:-
Vu %.9
9!
Normal Shear; τ v = = = 0.587N/mm2
bd
Referring to the Table no: 19, we get the value of τ c = 0.39 N/mm 2 .
Vus = Vu - τ c bd =65.16x1000-0.39x300x370=21870N
.!9"> 9?@O N
PQ@
Sv = = 467mm
R
.!9%9!99 S 9
!
Sv = = 614mm
35
As per IS 13920:1993 for ductile reinforcement; clause 6.3.5
The spacing of hoops over a length of 2d at either end of the beam shall not exceed
(a) d/4 and (b) 8 times the dia of the smallest longitudinal bar ; however, it need not be less
than 100mm. the first hoop shall at a distance not exceeding 50mm from the joint face.
Vertical hoops at same spacing as the above shall also be provided at a length equal to 2d on
either side of the section where flexural yielding may occur under the effect of
(b) The earthquake forces. Elsewhere, the beam shall have vertical hoops at a spacing not
exceeding d/2.
Hence provide 2-legged, 10mm dia. Stirrup @ 100mm c/c at either side portion (i.e. 2d).
l
≤ 26 × MF T ×MFC
d
AstRe quired
fs = 0.58 × fy ×
AstPr ovided
%.&%
!.
fs = 0.58x 415x = 202
MFT =1.17
36
From Figure 5 of IS 456:2000
MFC =1.02
- .basic =26x1.17x1.02=31.03
T
N
- .=
T .!%
N .!
= 11.55 <31.03, hence safe
For design of other beams, refer Table no.14 for office building, Table no.19 for hazardous
storage building and Table no.24 for warehouse in the Appendix II.
For group F2
=1.2 x 3
= 3.6 m
l e ff .
.
= = 9 <12 ⇒ Short column
Dy
l eff .
.
= = 9 <12 ⇒ Short column
Dx
e m in x =19.33
e m in y =19.33
Hence the column is designed as an axially loaded short column with the help of Design Aids
charts of SP-16, IS 456:1978
37
Mx=43.658 kNm
My=71.085 kNm
Pu = 24.882 kN
Since moments due to minimum eccentricity is very small then the applied moment, so it can
be neglected as per IS: 456.
NU
V
= = 0.10
d'
Refer chart 44 from SP (16) for =0.1 and fy =415Mpa
D
Wu .9
f ck VD 99
= = 0.0077
Q &%.&9
f ck DV 99
= = 0.075
W
= 0.041
f ck
P=0.041x20= 0.82 %
.99
Ast = = 1312mm2
38
%!.!&9
P= = 0.982
W
= 0.05
f ck
QZ[
f ck DV
= 0.08
\]
QZ \] Q>
- . +^ _ 1.12 ` 1, which is not safe, hence revise the design
QZ[ Q>[
W
= 0.075
f ck
.%99
Ast = = 2400 mm2
%.%9
P= = 1.51
W
Therefore, = 0.08
f ck
QZ[
f ck DV
= 0.11
39
Therefore Mu = 140.80 kN
WQ .
WQa !.
= = 0.0115 < 0.02
.% !.%
- . +- . = 0.82 ` 1, which is saf
. .
Shear design
eb eZ
Vu = 1.4 ^ Qbcd fQbcd
_
L@A
9Q 9Q
N N
Mubl lim = 0.36x x (1-0.42x ) bd2 xfck
.9.9
Therefore, Vu = = 133.504kN
P= 1.5%
40
9&.%
9
P= = 0.684
From IS 456:2000
τc = 0.54Mpa
As per IS-456:2000, clause 40.2.2, the member subjected to axial compression Pu, the design
strength of concrete, given in table 19, shall be multiplied by following factor.
3Pu
δ = 1+ , but not exceeding 1.5.
Ag f ck
9.
9
δ = 1+ = 1.02<1.5
τ c x δ = 0.54x1.02 = 0.5508
.%91
τv = = 0.83
τv > τc
41
Asv = x2x8 = 100.53 mm2
g
.!9%9.%9
!.9
Sv = = 277.4mm
i. Least dimension=400mm
ii. 163h = 16x 32 =512mm
iii. 483i = 48x8=384mm
iv. Sv = 250mm
v. 300mm
vi. As per clause 7.3.3 of IS 13920
V
Spacing of hoops < half the lateral dimension = = 200 mm
As per IS: 13920, clause 7.2.1 for splice spacing of hoops < 150mm c/c
Pitch reinforcement for confining reinforcement (As per IS: 13920, Clause 7.4.8)
fck Ag
Ash = 0.18Sh − 1 ,
fy Ak
42
A k = Area of concrete core
h= Longer dimension of the rectangular confining hook measured to its outer face and shall
not exceed 300mm
Ak = 72583.36 mm2
=l9m
= 160 < 300mm
h=
%.!9%
[nnnn
.999- =.
Sv = = 30.07 mm
op1.1
As per IS 13920:1993, clause 7.4.6, spacing of the hoops used as spherical confining
reinforcement shall not exceed ¼ of minimum member dimension, but need not be less than
75mm nor more than 100mm.
b.100mm
Adopt 8mmФ stirrup for confining reinforcement @ 100mm c/c.
Special confining reinforcement shall be provided over a length lo from each joint face,
towards mid span, and on either side of any section, where flexural yielding may occur under
the effect of earthquake forces.
43
The length ‘lo’ shall not be less than
(a) Larger lateral dimension of the member at the section where yielding occurs,
(c) 450 mm
Also extend the special confinement at least up to 300mm into footing as per clause 7.4.2
The design summary of columns, refer Table no.15 for office building, Table no.21 for
hazardous storage building and Table no.25 for warehouse in the Appendices.
Data:
Service Load=4kN/m2
f ck =20 N/mm2
f y =415N/mm2
44
Effective Span
The slab thickness in the landing region may be taken as 150mm as the bending moment are
relatively low here.
w R 2 + T2
W= s
T
.!%v√ =%
W= = 3.25 kN/m
1
= × (0.15 × 0.3 × 25)
2
= 0.563 kN
.%v
= = 1.875 kN/m
= = 6.26 kN/m
Calculation of Reaction
A B
RA RB
=49.85kN
R A × 4.2 = 14.60x2.825x2.7875+0.5x6.26x1.3752
∴ R A = 28.78kN
∴ R B = 21.07kN
46
Calculation of maximum factored moment
Now the maximum moment on the span occurs at the minimum shear force i.e. at a distance
of x from the support A (shown in figure above)
.!
.
x= = 1.97m from support A
u
Depth; d = 4
.9D9 f ck
=
.!9
.99
= 101.40 mm <114mm, hence safe
Calculation of reinforcement
D= 150 mm
t=150-30- =114 mm
0.5× f ck × b× d 4.6× M u
Ast = 1- 1-
fy f ck × b× d 2
x 1 1
.%999 .9.!9
% 99
Ast = = 808.63 mm2
R
9 9
S
.
Spacing of the bars = = 139.86mm ≈ 135 mm c/c
47
Provide 12mm3 bar @ 135mm c/c as main reinforcement
Distribution bars
.99
A st = = 252 mm2
R
9 9
S
%
Spacing of the bars = = 199.46 mm ≈ 190 mm c/c
Vu =28.78 kN
Vu .!9
bd 9
Normal Shear; τ v = =
τ v =0.25N/mm 2
Referring to the table no: 19, we get the value of τ c = 0.55 N/mm 2 .
48
Design for landing slab BC
.9.%
RB = RC = =10.173kN
wl 2 .9.%
Bending moment at centre Mu = = = 8.27 kN-m
8
D= 150 mm
d = 150-30- = 115mm
Mu
Depth, d =
0.138×f ck × b
=
.!9
.99
= 54.72mm< 115mm
Calculation of reinforcement
0.5× f ck × b× d 4.6× M u
Ast = 1- 1-
fy f ck × b× d 2
x 1 1 = 207.01 mm2
.%999% .9.!9
% 99%
Ast =
R
9 9
S
!.
Spacing of the bars = = 379.4 mm
49
Therefore, provide 10mm3 bar @ 300mm c/c as main reinforcement
Distribution bars
.9%9
A st = = 180 mm2
R
9 9
S
Spacing of the bars= = 279 mm ≈ 250 mm c/c
Vu =36.23 kN
Vu .9
9%
Normal Shear; τ v = =
bd
τ v =0.32N/mm 2
Referring to the table no: 19, we get the value of τ c = 0.34 N/mm 2 .
Thickness-150mm
For landing:
Thickness=150mm
Data-
The safe bearing capacity of the soil is taken as 150 kN/m 2 , when the earthquake load is
considered the bearing capacity of the soil is increased by 50%. The safe bearing capacity of
the soil becomes 150x1.5=225kN/m2
Let the self weight of the footing and the earth fill be 10% of the factored load on column
!.
%9.%
Footing area = = 2.994m2
51
Adopting a square footing of 1.73mx1.73m
Net soil pressure at ultimate loads with a load factor of 1.5 is given by
W .
= 204.6 N/m2 < 0.205 N/mm2
?srw u" "uuxHqy .!9.!
qu = =
The critical section is at a distance ‘d’ from the column face (shown in figure)
Assuming the percentage of reinforcement in the footing pt =0.25 % for M20 grade concrete
Vu1 ` Vc1
235842.25-354.65d`622.8d
dz241.28mm
52
Two way shear
Assuming the effective depth of slab=d= 241.28 mm and computing the two way shear
resistance at a critical section (d/2) from the face of the column, we have the relation,
τ c = 0.25 ( )
f ck × ks
ks =1
Vu2 ` Vc2
dz197.92mm
D=224.28+60+8=292.28mm
Take D=310mm
Therefore, d=310-60-8=242mm
%
Mu =0.205x1730x 10-6 x = 78.418 kN-m
53
!.9
KN = !9
R= =0.774Mpa
Interpolate the percentage reinforcement as, pt =0.23 which is less than 0.25% assumed for
one-way shear. (From SP (16), Table 2, page 48)
Ast =- .
{x9D9N .%99
= = 605mm2
9 9
S
π
%
Spacing of the bars, S= = 332.3< 300mmc/c
Pu= 612.361 kN
f br,max = 0.45x f ck x
?
?
|
? !
?
= 4.325 limited to 2.0
Hence the column face governs the design and f br,max = 9Mpa
&9
Fbr = = 1440kN>Pu =612.361kN
54
For the design summary of footings, refer Table no.17 for office building, Table no.22 for
hazardous storage building and Table no.26 for warehouse.
For group F3
Pu1 =693.816 kN
Pu2=693.808kN
Mu1=6.04 kN-m
Mu2=6.055 kN-m
For the earthquake load consideration increase the safe bearing capacity by 50%.
∑ P + ∆P + ∑ M × 6 = sbc
LB L2 B
∑
.9!.
GK
6.907L+0.323=LB2 ……………………….(i)
Let X be the CG of the column load from the centre of the column B
&.9.%f.%%f.
&.f&.
= 1.134m
Let A be the distance from the centre of the column to the edge of the footing
L
A+X=
2
55
Assume A=1.0
L
1.0+01.134=
2
L=4.27m………………………………… (ii)
B=2.64 m
∑W !.
GK .!9.
Net upward pressure= = = 123.1 kN/m2
Figure 6.7 Diagram of loading, shear force & bending moment of combined footing
56
Analysis for actions in transverse direction
9 l.=.m
= = 1.12m
.9.
Mu = = 77.21kN-m
Longitudinal reinforcement
Mmax=163.43 kN-m
=
.9
.99
Mu
d= = 149.76mm
0.138×f ck × b
Provide D=310 mm
Dx=310-60-8=242 mm
Dy=310-60-8=242 mm
Bottom steel
0.5× f ck × b× d 4.6× M u
Ast = 1- 1-
fy f ck × b× d 2
x 1 1
.%999 .9.9
% 99
Ast = = 2001.51 mm2
R
9 9
S
.%
Spacing of the bars = = 265 mm ≈ 250 mm c/c
.%
= 9.95< 10 nos.
.
No of bars =
57
Provide 10-16mmØ bar @250mmc/c as bottom reinforcement
Top reinforcement
.%99
%
Minimum steel= = 1308.55mm2
Transverse reinforcement
Mu=77.21kN
x 1 1
.%999 .9!!.9
% 99
Ast = = 963.754 mm2
R
9 9
S
&.!%
Spacing of the bars = = 208mm ≈ 170 mm c/c
.%99
%
Ast(min) = = 495.66mm2
Maximum shear=303.94 kN
Shear at d=242mm
Vu=303.94-0.242x324.984=225.294 kN
Vu %.&9
9
Normal Shear; τ v = = = 0.353 Mpa
bd
Percentage of steel as
58
9? st 9 .
D9N 9
= = 0.315
Referring to the Table no: 19 of IS 456:2000, we get the value of τ c = 0.39 N/mm 2 .
d=242mm
At d/2 from the face of the column, the length of the square
9
=400+ = 642mm
Vu=693.816-0.642x0.642x123.1=644.5 kN
Vu .%9
!9
τv = = = 0.624 Mpa
bd
59
6.8 Design of footing (slab beam type strip footing)
= 2472.604 kN.
= 247.2604 kN
For the Earthquake consideration the bearing capacity of the soil is increased by 50%
!.
%
Area required = = 12.08m2
.
.
Therefore the length of footing is = 9.3m
60
C.G of the load from the centre of CF2
~ =
.&9.!f.!!9%.f.9.f.&
!.
= 4m from CF2
61
Mu
Depth required =
0.138×f ck b
=
!.!9
.99
= 99.585 mm
D= 250mm
!.!9
DN 9
= = 0.808
Pt = 0.2354%
WA 9DN .%99
Ast = = = 433.136mm2
9.&!
.
Spacing = = 261 mm
Minimum reinforcement:
.
A st = x 1000x250 = 300mm2
9%.!
Spacing of the bar = = 167.56mm
62
Shear Check
The critical section for shear occurs at a distance‘d’ from the column face, i.e. d= 184mm
Vu %.9
9
τv = = = 0.296 Mpa
bd
9? st 9.
D9N 9
Pt = = = 0.24%
τ c = 0.352Mpa
τ c > τ v Hence ok
= 47 × 12 = 564mm
Mu
Depth required (d req.) =
0.138×f ck b
=
9
.99
= 661.43 mm
Provide D= 665 mm
63
d = 665 – 60 – 8 = 597 mm
.%DN .%99%&!
"> %
Ast(min) = = = 489.11 mm2
&.
R
9
Number of bars = = 2.43< 3nos.
S
!9
9%&!
Vu
τv = = = 1.75 Mpa
bd
9? st 9&.
D9N 9%&!
Pt = = = 0.205 %
τ c = 0.324Mpa
.!+
+ .!+%++ + + %&!
| S
&.+
Sv = = 105.9 mm
64
6.9 Pavement
The pavement is one of the important components of dry port. The design of pavement
involves lots of considerations like climatic conditions, axle loads, topography of the site,
traffic and subgrade conditions. Flexible pavement and rigid pavement are the two type of
pavement. The selection of the pavement depends on the materials available and on above
mentioned conditions.
The site location of the parking was done according to the need and the space available. The
parking area should have minimum slope of ¼ inch per feet to have good drainage. The
accumulation of the water should be avoided as it will weaken the sub-base course of the
pavement and lead to failure of pavement.
The location being located above the river bed the soil condition was assumed to be sand
and sandy-gravel with moderate amount of sand and clay. Due to limitation on time
availability, the soil tests could not carried out. The CBR value and the design of the
pavement are based on the IRC 37:1984.
65
CBR value of sandy gravel soil= 5%
365xl1 rm 1
N| xAxDxF
Where,
= 2.5
=2.5
=15 years
= 4.4% (determined from no. of vehicles and the yearly increment in cargo volume)
N= The cumulative number of standard axles to be catered for in the design in terms of msa.
365xl1 0.044m 1
N| x150x2.5x0.5 | 1.5510
0.044
= 1.55 msa
From the figure 1 given in IRC 37: 1984, for the above calculated value of N
Base = 225mm
66
Sub-base = 205mm
The subgrade of the pavement should have minimum of 150 mm stone soling and should be
well compacted.
The poor drainage is the major problem which not only leads to the over flooding of the area
but also the pavement failures. The main idea of providing the drainage is to drain out all the
water so that no infiltration and no accumulation of water take place.
The general drainage system layout is shown below. The figure7.0 which is given below
shows the general outline of the main drainage line. The main drainage line was fixed
according to the slope available. During the site visit, it was found that there exists only one
main drainage line and the area remains flooded during the rainy seasons. To have good
drainage the main drainage line is bifurcated into different branches to avoid flooding as
shown in the figure 7.0.
67
Design of drain
Intensity, I=1035mm/month (data collected from rain water harvesting project group)
I=1.4375mm/hr
Provide k=0.825
Runoff, |
Dividing the above calculated runoff into three zones depending on the area, we get
68
By Manning's Formula, we get
1
V| xS
|
P= wetted perimeter
From the above relations we get the dimensions of the drain as follows
d= 500mm
b= 400mm
69
7. COST ESTIMATION
It is very much necessary to have the cost estimate for every project. Therefore to have the
approximate cost estimate for the construction, the plinth area method was adopted. The
estimate is based on the BSR 2005 and to incorporate the rise in the price hick the market
survey was done and the percentage increment is done to total estimate to get final
approximate cost estimate for construction.
PA=plinth area
Knowing the room size room, size factor rsf can be found from the given table.
2. External and internal wall-Brick wall with 300mm external and 200mm internal
3. Flooring-Concrete flooring
3. Flooring-Concrete
7.2 Calculations
Room height=3.32m
Number of rooms=26
Room size factor=1.025 (from the Quick cost Guide) BSR 2005
Adjustable rate=2544
7.2.2 Warehouse
Room height=7m
Number of room=12
=14.39
71
room size factor=0.8161 (from the Quick cost Guide) BSR 2005
Room height=3
Number of room=5
Total cost of the structures =Nu.66, 929,369/-(Ngultrum six crores sixty nine lakhs fifty four
thousand one hundred ten)
Comparing the major increase in the rate of materials and the built up rate for some major
items as per the BSR 2005 and 2007, it is found that rate increases by about 15% annually
Increment cost= x66, 929,369=Nu.20, 078,812/- (twenty crores seventy eight lakhs eight
Therefore by adding all the amount the total cost of construction of the structures by the end
of year 2009 will be Nu.87, 008,181 (Ngultrum eight crores seventy lakhs eight thousand one
hundred eight one) approximately
72
7.2.4 Approximate estimation of the road and pavement
The pavement being the flexible pavement the 80/100 grade bitumen is used. The cost of the
laying and compacting using the rollers provided as per the material gradation and aggregate
quality specified is as follows;
Total Cost=20234.13x435=Nu.8, 801,847 (Ngultrum eighty eight lakhs one thousand eight
hundred forty seven)
73
8. CONCLUSION
This project was undertaken mainly after realizing the growth in commercial and industrial
activities in our country that demands the establishment of dry port. Hence the planning,
design and analysis of dry port was carried out to learn the various principles involved in the
planning, analysis and design of its components. It is seen that only few godowns and
warehousing is not sufficient to cater the smooth flow of goods due to the expansion in the
commercial activities and increase in the number of private entrepreneurs. To meet the
growing demand of economic activities, a dry port was proposed by RGoB in Phuentsholing
master plan 2004.
As per the functions and requirements of the dry port the information required was collected
from the various organizations like PCC, RCCO and MTI. Further the additional information
required was collected through the literature review and interactions. The general
specification and the recommendation for the establishment of dry port were all followed
according to the materials collected and as per the Indian standards Codes. In order to
preserve the traditional Bhutanese architecture recommended in BBR 2002, few traditional
features of buildings were also incorporated wherever it is feasible.
The load calculations were made as per the IS: 875-1987 and the analysis of frames were
carried out using the STAAD Pro 2006 software. A typical frame was selected for its
verification of the software results with the manual calculation using the Kani’s Method of
the frame analysis. The results obtained by manual calculations and results obtained by using
STAAD Pro have good agreement. Hence all other analysis of the components was carried
out using the above software.
Then the design was carried out by a programme which was developed using Microsoft excel
by incorporating all the design aspects as per the IS codes for beams, slabs, columns and
footings. Further the design of the flexible bituminous pavement was carried out as per IRC
37: 1984. The approximate cost of the inbuilt structures like office building, warehouse and
hazardous storage were estimated using the plinth area method given in BSR 2005. However
the cost of roads and pavements were estimated based on the thumb rule provided by DoR of
Bhutan.
74
The total dry port area consist of 7.78 acres (built up area is 2.78 acres and for roads and
pavements is 5 acres). The estimated cost based on plinth area method for this dry port is
approximately Nu. 99.16 millions excluding land cost.
After the successful completion of the project we came to understand the various planning
and design aspects that are needed for the civil engineer in the field. We also learned the
approaches to be taken while collecting the data and the interpretation of the collected data
for the execution of any project in future.
If the project could be implemented by the government it would bring the much changes and
improvement to the commercial and industrial activities, thus raising the economy of the
country and improving the living standard of the people.
75
REFERENCES
1. Asian Development Bank, 2002. “Technical Assistance to Kingdom of Bhutan for Preparing
the Industrial Estate and Dry Port Development Project”. Availability:
http://www.adb.org/Documents/CSPs/BHU/2003/BHU_Appendix2.pdf .
2. Bhavikatti SS, 2005, second edition; “Structural Analysis vol.1 and vol. 2”; Vikas Publishing
House PVT. Limited.
3. Building Code; Structural Design; BST-002-2003(Part I, Section1); Basis of Design; Safety
and Loads.
4. Chhetri, Kushal et al, 2006; “Project Report on Planning, Analysis and Design of
Multipurpose Stadium in Phuntsholing Area”; College of Science and Technology.
5. Department of Defence Personnel property Storage, 2004. “Guidelines for Warehouse
Construction”; 200 Stovall Street, Alexandria Va.22332-5000
6. Design Vehicles, 2004. “American Association of State Highway and Transportation
Officials”.
7. Dorji, Tashi, 2008; “Project Report on Planning, Analysis and Design of hostel building in
CST”; College of Science and Technology.
8. Dr. Punmia, B.C., Ashok Kumar Jain and Arun Kumar Jain 1998; “R.C.C Designs”; Laxmi
Publications (P) limited, New Delhi.
• FDT , CESEF, (9/7/2008);“Feasibility Study on Network Working of Hinterland Hubs to
Improve and Modernize Port Connection to the Hinterland and to Improve Networking”;
Valga County Government; Valka Town Council. Availability:
http://www.inloc.info/internal/wp1/activity_15_feasibility_study_dry_ports.pdf
9. UNCTD, (26/10/2008)“Hand Book on Management and Operation of Dry Ports, 1991”,
Geneva. Availability :http://www.r0.unctad.org/tt/docs-un
10. IS: 13920-1993, fifth revision; Bureau of Indian Standards, New Delhi.
11. IS: 456-200; Bureau of Indian Standards, New Delhi.
12. IS: 875-1987; Bureau of Indian Standards, New Delhi.
13. IS: 1893(part I): 2002; “Indian Standard Criteria for Earthquake Resistant Design of
Structures”; General provisions for buildings, fifth revision; Bureau of Indian Standard, New
Delhi.
14. Krishna, N Raju, 2003; “Design of Reinforced Concrete Structures (IS: 456-2000)”; CBS
Publishers and Distributors, New Delhi.
76
15. Krishna, N Raju 2005; “Advanced Reinforced Concrete Structures”; Satish Kumar Jain for
CBS Publishers and Distributors, New Delhi.
16. Memos, Constantine D; “Port Planning and Designing”; National Technical University of
Athens; Zografos; Greece.
17. Ministry of Trade and Industry, 2003, “TA 4019-BHU: Industrial Estate and Dry Port
Development”.
18. Negi, L.S., Third Edition; “Design of Steel Structures”; Tata McGraw Hill, New Delhi.
19. Officer Association, Essex Planning, 2001; “Vehicle Parking Standards”.
20. Ramamrutham, S., 2002; “Design of Reinforced Concrete Structures”; Dhanpat Rai
Publishing Company (P) Ltd.
21. Reddy, C.S. (Second Edition), 1996. “Basic Structural Analysis”; Tata McGraw Hill
Company Limited.
22. SP-16, “ Design Aids for Reinforced Concrete to IS: 456-2000”; Bureau of Indian Standards,
New Delhi.
23. Thapa, Gautam et al, 2006; “ Project Report on Planning, Analysis and Design of Library
com Administrative Building”; College of Science and Technology.
24. Varghese, P.C., 2003 Second Edition; “Limit State Design of Reinforced Concrete”; Prentice-
Hall of India Pvt. Ltd.
25. Vazirani, V.N. & Ratwani, 2002; “Analysis and design of steel Structures”; Khanna
Publishers, New Delhi.
77
Bibliography
• http://www.adb.org/Documents/CSPs/BHU/2003/BHU_Appendix2.pdf
• http://www.adb.org/Documents/Profiles/PPTA/36256012.ASP#obj_scope
• http://www.ccc.govt.nz/Parks/Publications/ManagementPlans/HalswellQuarryParkM
anagementPlan/p39-41.pdf
• http://www.civil.iitb.ac.in/tvm/1100_LnTse/411_lntse/plain/plain.html
• http:// www.adopted_plan_for_charnwood_-_appendix_1
• http://www.doond.com/forum/forum_posts.asp?TID=4411
• http://www.dur.ac.uk/~des0www4/cal/roads/pavdes/slndes.html
• http://gltrs.grc.nasa.gov/reports/1998/TM-1998-206615.pdf
• http://www.inloc.info/internal/wp1/activity_15_feasibility_study_dry_ports.pdf
• http://www.kennebell.net/techinfo/gm-tech/manifold-injection.pdf
• http://news.nauticexpo.com/press/vertical-yachts-storage-systems-llc/a-whole-new-
concept-in-dry-dock-storage-25856-6929.html
• http://www.ppsez.com/dry_port.html
• http://www.ppsez.com/sitemap.html
• http://www.spatial.baltic.net/_files/NeLoC_Report.pdf
• http://www.sestran.gov.uk/files/A14.Appendix%20Dryport%20appendix4_050308.p
df (25/10/08)
• http://www.standardsforhighways.co.uk/dmrb/vol7/index.htm
• http://www.supplychains.in/en/cev/29
• http://www.transport.vgtu.lt/upload/tif_zur/2007-3-jarzemskis_vasilis-
vasiliauskas.pdf
• http://www.voka.be/west-vlaanderen/infotheek/Pages/DryPortproject.aspx
• http://WSUD guidlines_int_05-06f_hi.pd.PDF
78
Summary of analysis
Truss 1
Load
combination Design Load Type of
members
Dead Live Wind
Member load load load DL+LL DL+WL Compression Tension
1 -2.62 -10.3 8.049 -12.92 5.429 -12.92 5.429
2 -2.62 -10.3 8.049 -12.92 5.429 -12.92 5.429
3 -5.51 22.24 -36.37 16.73 -41.878 -41.878 16.73
4 -3.897 28.268 -46.06 24.371 -49.953 -49.953 24.371
5 -3.694 27.306 -45.92 23.612 -49.615 -49.615 23.612 Tie
6 -3.694 27.306 -45.92 23.612 -49.615 -49.615 23.612 member
7 -3.897 28.268 -46.06 24.371 -49.953 -49.953 24.371
8 -5.51 22.24 -36.37 16.73 -41.878 -41.878 16.73
9 -2.62 -10.3 8.049 -12.92 5.429 -12.92 5.429
10 -2.62 -10.3 8.049 -12.92 5.429 -12.92 5.429
11 2.679 10.533 -7.66 13.212 -4.981 -4.981 13.212
12 -5.63 -22.73 38.899 -28.364 33.269 -28.364 33.269
13 -7.279 -28.9 49.656 -36.176 42.377 -36.176 42.377
14 -7.07 -27.91 50.47 -34.98 43.4 -34.98 43.4
15 -6.058 -23.82 46.029 -29.877 39.971 -29.877 39.971
Rafter
16 -6.058 -23.82 46.029 -29.877 39.971 -29.877 39.971
17 -7.07 -27.91 50.47 -34.98 43.4 -34.98 43.4
18 -7.279 -28.9 49.656 -36.176 42.377 -36.176 42.377
19 -5.63 -22.73 38.899 -28.364 33.269 -28.364 33.269
20 2.679 10.533 -7.66 13.212 -4.981 -4.981 13.212
21 -4.969 -19.05 25.6 -24.019 20.631 -24.019 20.631
22 -2.027 -8.113 11.099 -10.14 9.072 -10.14 9.072
23 -0.752 -2.811 4.471 -3.563 3.719 -3.563 3.719
24 0.137 0.649 -0.091 0.786 0.046 0 0.786
Vertical
25 4.742 1.275 -5.159 6.017 -0.417 -0.417 6.017
member
26 0.137 0.649 -0.091 0.786 0.046 0 0.786
27 -0.752 -2.811 4.471 -3.563 3.719 -3.563 3.719
28 -2.027 -8.113 11.099 -10.14 9.072 -10.14 9.072
29 -4.969 -19.05 25.6 -24.019 20.631 -24.019 20.631
30 8.379 33.537 -45.88 41.916 -37.501 -37.501 41.916
31 1.78 6.651 -10.58 8.431 -8.799 -8.799 8.431
32 -0.245 -1.16 0.163 -1.405 -0.082 -1.405 0
33 -1.312 -5.289 5.442 -6.601 4.13 -6.601 4.13 Inclined
34 -1.312 -5.289 5.442 -6.601 4.13 -6.601 4.13 member
35 -0.245 -1.16 0.163 -1.405 -0.082 -1.405 0
36 1.78 6.651 -10.58 8.431 -8.799 -8.799 8.431
37 8.379 33.537 -45.88 41.916 -37.501 -37.501 41.916
79
Truss 2
Load
combination Design Load Type of
Dead Live Wind members
Member load load load DL+LL DL+WL Compression Tension
Tie
1 -1.524 -6.963 8.7 -8.487 7.176 -8.487 7.176 member
2 1.558 7.118 -8.51 8.676 -6.952 -6.952 8.676 Rafter
Vertical
3 -0.648 -2.96 3.62 -3.608 2.972 -3.608 2.972 member
Truss 3
Load
combination Design Load Type of
Dead Live Wind members
Member load load load DL+LL DL+WL Compression Tension
1 -1.41 -6.318 7.936 -7.728 6.526 -7.728 6.526 Tie
2 -1.41 -6.318 7.936 -7.728 6.526 -7.728 6.526 member
3 1.438 6.459 -7.265 7.897 -5.827 -5.827 7.897
Rafter
4 1.438 6.459 -7.763 7.897 -6.325 -6.325 7.897
5 -0.55 -2.467 3.027 -3.017 2.477 -3.017 2.477 Vertical
6 -0.55 -2.467 2.99 -3.017 2.44 -3.017 2.44 member
Inclined
7 0 0 0.15 0 0.15 0 0.15 member
Truss 4
Load
combination Design Load Type of
Dead Live Wind members
Member load load load DL+LL DL+WL Compression Tension
1 -1.43 -6.304 7.921 -7.734 6.491 -7.734 6.49
2 -1.43 -6.304 7.921 -7.734 6.491 -7.734 6.49 Tie member
3 -0.879 -5.085 5.112 -5.964 4.233 -5.964 4.23
4 1.457 6.432 -6.774 7.889 -5.317 -5.317 7.89
5 0.899 5.199 -4.171 6.098 -3.272 -3.272 6.1 Rafter
6 1.462 6.445 -7.746 7.907 -6.284 -6.284 7.91
7 -0.812 -3.03 4.403 -3.842 3.591 -3.842 3.59
Vertical
8 -0.137 -0.304 0.7 -0.441 0.563 -0.441 0.56
member
9 -0.557 -2.469 2.948 -3.026 2.391 -3.026 2.39
10 0.567 1.256 -2.895 1.823 -2.328 -2.328 1.82 Inclined
11 -0.603 -1.33 3.442 -1.933 2.839 -1.933 2.84 member
80
Truss 5
Load
combination Design Load Type of
Membe Live Wind DL+L DL+W Compressio Tensio members
r Dead load load load L L n n
1 -1.458 -6.318 7.921 -7.78 6.463 -7.776 6.463
2 -1.458 -6.318 7.921 -7.78 6.463 -7.776 6.463 Tie
3 -0.336 -1.453 2.022 -1.79 1.686 -1.789 1.686 member
4 -0.689 -2.976 4.01 -3.67 3.321 -3.665 3.321
5 1.489 6.452 -6.244 7.941 -4.755 -4.755 7.941
6 0.704 3.044 -2.516 3.748 -1.812 -1.812 3.748
Rafter
7 0.344 1.486 -1.074 1.83 -0.73 -0.73 1.83
8 1.491 6.459 -7.748 7.95 -6.257 -6.257 7.95
9 -1.087 -4.714 5.781 -5.8 4.694 -5.801 4.694
10 -0.279 -1.213 1.471 -1.49 1.192 -1.492 1.192 Vertical
11 0.164 0.71 -0.925 0.874 -0.761 -0.761 0.874 member
12 -0.569 -2.466 2.935 -3.04 2.366 -3.035 2.366
13 1.156 5.014 -6.08 6.17 -4.924 -4.924 6.17
Inclined
14 -0.389 -1.68 2.188 -2.07 1.799 -2.069 1.799
member
15 -0.927 -4.02 5.089 -4.95 4.162 -4.947 4.162
Truss 6
Load
combination Design Load Type of
Membe Dead Live Wind Compressio members
r load load load DL+LL DL+WL n Tension
1 -1.487 -6.332 7.936 -7.819 6.449 -7.819 6.449
2 -1.487 -6.332 7.936 -7.819 6.449 -7.819 6.449
Tie
3 0.232 0.982 -0.295 1.214 -0.063 -0.063 1.214
member
4 -0.084 -5.85 0.839 -5.934 0.755 -5.934 0.755
5 -0.759 -11.981 4.282 -12.74 3.523 -12.74 3.523
6 1.534 11.925 -6.55 13.459 -5.016 -5.016 13.459
7 0.604 5.891 -2.274 6.495 -1.67 -1.67 6.495
8 -0.086 -0.377 0.777 -0.463 0.691 -0.463 0.691 Rafter
9 -0.237 -1.003 1.35 -1.24 1.113 -1.24 1.113
10 1.52 6.474 -7.763 7.994 -6.243 -6.243 7.994
11 -1.374 -5.85 7.175 -7.224 5.801 -7.224 5.801
12 -0.429 -1.836 2.052 -2.265 1.623 -2.265 1.623
Vertical
13 0.07 3.186 -0.529 3.256 -0.459 -0.459 3.256
member
14 0.455 4.135 -2.32 4.59 -1.865 -1.865 4.59
15 -0.583 -0.698 3.04 -1.281 2.457 -1.281 2.457
81
16 1.772 7.538 -8.483 9.31 -6.711 -6.711 9.31
17 -0.163 -0.675 1.251 -0.838 1.088 -0.838 1.088 Inclined
18 -0.814 -7.395 4.153 -8.209 3.339 -8.209 3.339 member
19 -1.205 -7.823 6.305 -9.028 5.1 -9.028 5.1
Truss 7
Load
combination Design Load Type of
Dead Live Wind members
Member load load load DL+LL DL+WL Compression Tension
1 -11.212 -36.89 2.494 -48.102 -8.718 -48.102 0
2 -11.212 -36.89 2.494 -48.102 -8.718 -48.102 0
Tie
3 -1.219 -3.34 -6.99 -4.559 -8.209 -8.209 0
member
4 1.345 6.047 -7.323 7.392 -5.978 -5.978 7.392
5 1.384 6.081 -7.726 7.465 -6.342 -6.342 7.465
6 0 0 0 0 0 0 0
7 -1.399 -6.147 7.81 -7.546 6.411 -7.546 6.411
8 -1.359 -6.112 7.402 -7.471 6.043 -7.471 6.043 Rafter
9 1.233 -3.377 -7.07 -2.144 -5.837 -5.837 0
10 11.334 37.294 -2.521 48.628 8.813 0 48.628
11 -6.642 -9.65 12.003 -16.292 5.361 -16.292 5.361
12 -1.762 -5.917 1.672 -7.679 -0.09 -7.679 0
Vertical
13 -0.833 -3.05 4.65 -3.883 3.817 -3.883 3.817
member
14 -0.018 -0.016 0.188 -0.034 0.17 -0.034 0.17
15 -1.375 -5.85 7.175 -7.225 5.8 -7.225 5.8
16 10.147 34.072 -9.63 44.219 0.517 0 44.219
17 2.696 9.87 -15.05 12.566 -12.354 -12.354 12.566 Inclined
18 0.043 0.038 -0.445 0.081 -0.402 -0.402 0.081 member
19 -1.632 -7.171 9.111 -8.803 7.479 -8.803 7.479
Max
Group Roof Beam (+ve) Min (-ve)
A1-A2,A3-A4,B1-B2,B3-B4,C1-C2,C3-C4,D1-D2,D3-D4,E1-
1 E2,E3-E4,F3-F4,F1-F2,G1-G2,G3-G4,J1-J2,J3-J4,H3-H4 39.934 36.062
2 A2-A3,J2-J3,G2-G3 32.987 30.233
3 B2-B3,C2-C3,D2-D3,E2-E3,F2-F3 26.494 23.234
4 1A-1B,1I-1J,2A-2B,2I-2J,3A-3B,3G-3H,4A-4B,4I-4J 35.13 29.825
1B-1C,1C-1D,1D-1E,1E-1F,1F-1G,1G-1I, 2B-2C,2C-2D, 2D-
2E,2E-2F,2F-2G,2G-2I, 3B-3C,3C-3D,3D-3E,3E-3F, 3F-3G,3I-
5 3H, 4B-4C,4C-4D,4D-4E,4E-4F,4F-4G,4G-4I 27.791 26.381
82
Max(-
Group First Floor Beam Max(+ve) ve)
Plinth beam
Moment Range (KN-m)
Group Beams
Max(+ve) Max(-ve)
1 2A-2B,2B-2C,2C-2D,2D-2E,5A-5B,5C-5D,5D-5E 30.944 26.58
2 5B-5C,1C-1D,3C-3D,4C-4D,6C-6D 58.451 23.37
3 1A-1B,1B-1C,1D-1E,3A-3B,3B-3C,3D-3E,4A-4B, 75.592 33.438
4B-4C,4D-4E,6A-6B,6B-6C,6D-6E
Moment Range (KN-m)
Group Beams
Max(+ve) Max(-ve)
B1-B2,B2-B3,B3-B4,B4-B5,B5-B6,D1-D2,D2-D3, D3-
1 D4,D4-D5,D5-D6 32.455 26.524
2 A3-A4,C3-C4,C4-C5,E3-E4 56.708 21.239
3 A1-A2,A4-A5,C1-C2,E1-E2,E4-E5 69.59 29.009
4 A2-A3,A5-A6,E2-E3,E5-E6 79.467 56.708
83
Roof beam
Moment Range (KN-m)
Group Beams
Max(+ve) Max(-ve)
1C-1D,2A-2B,2B-2C,2C-2D,2D-2E,3C-3D,4C-4D,5A-
1 25.981 20.629
5B,5B-5C,5C-5D,5D-5E,6C-6D
1A-1D,1B-1C,1D-1E,3A-3B,3B-3C,3D-3E,4A-4B,4B-4C,4D-
2 38.012 29.217
4E,6A-6B,6B-6C,6D-6E
Grouping of Beams in X-X Direction
Moment Range (KN-m)
Group Beams
Max(+ve) Max(-ve)
A3-A4,A4-A5,B1-B2,B2-B3,B4-B5,B5-B6,C3-C4,C4-C5,D1-
1 25.981 20.629
D2,D2-D3,D4-D5,D5-D6,E3-E4,E4-E5
A1-A2,A2-A3,A5-A6,B3-B4,C1-C2,C2-C3,C5-C6,D3-
2 38.012 29.217
D4,E1-E2,E2-E3,E5-E6
First Floor
PAD2
B1,C1,D1,E1,F1,G1,I1,B4,C4,D4,E4,F4,H4 612.361 -69.477
PAD3
A2,A3,B2,B3,C2,C3,D2,D3,E2,E3,F2,F3,G2,H3,I2,J2,J3 693.816 -6.04
PAD4 F2,G2,I2,J2
PAD5 F3,H3,J3
84
Table No.5: Beam grouping of hazardous storage house
B1-B2,B2-B3,B3-B4,B4-B5,B5-B6,D1-D2,D2-D3,
1 D3-D4,D4-D5,D5-D6 32.455 26.524
2 A3-A4,C3-C4,C4-C5,E3-E4 56.708 21.239
3 A1-A2,A4-A5,C1-C2,E1-E2,E4-E5 69.59 29.009
4 A2-A3,A5-A6,E2-E3,E5-E6 79.467 56.708
85
Table No.7: Footing grouping of hazardous storage house
Max Mx
Groups Footings Pu (kN) (kN-m)
PAD1 1,4,9,12,74,77,81,82,83 9.071
PAD2 75,78,86,90,73,84,79,85,76,89,87,80 612.361 -69.477
PAD3 75,78,86,90,73,84,79,85,76,89,87,80 693.816 -6.04
PAD4 2,10,3,11,5,8
PAD5 6,7
Load
Truss T1 combination Design Load Member
Member DL LL WL DL+LL DL+WL Compression Tension
AO -41.34 -59.56 101.4 -100.9 60.1
OP -37.6 -51.43 81.1 -89.03 43.5
PQ -33.97 -44.83 71.2 -78.8 37.23
-100.9 60.1 RAFTER
QR -30.3 -39.12 60.11 -69.42 29.81
RS -26.51 -33.52 50.99 -60.03 24.48
ST -22.74 -27.99 46.89 -50.73 24.15
AB 40.11 57.79 -98.43 97.9 -58.32
BC 40.11 57.79 -98.43 97.9 -58.32
CD 36.47 55.17 -78.79 91.64 -42.32
-58.32 97.9 TIE
DE 32.94 49.27 -51.81 82.21 -18.87
EF 30.26 43.72 -41.04 73.98 -10.78
FG 26.59 24.84 -32.22 51.43 -5.63
BO 0 0 0 0 0
CP 0.91 0.65 -4.9 1.56 -3.99 -11.95 11.14
DQ 1.8 3.01 -13.75 4.81 -11.95 VERTICAL
ER 2.68 4.18 -8.11 6.86 -5.43 STRUTS
FS 3.67 5.42 -8.82 9.09 -5.15
TG 4.52 6.62 -4.62 11.14 -0.1
OC -3.75 -2.7 20.24 -6.45 16.49
PD -3.96 -6.62 30.28 -10.58 26.32 -26.32 14.34
INCLINED
QE -4.46 -6.95 13.48 -11.41 9.02 STRUTS
RF -5.19 -7.67 12.48 -12.86 7.29
SG -5.82 -8.52 6.35 -14.34 0.53
86
Table No.9: Column grouping of hazardous storage house
Load
Truss T2 combination Design Load Member
Member DL LL WL DL+LL DL+WL Compression Tension
1 -1.716 -5.25 20.71 -6.966 18.994
2 -1.716 -5.25 20.71 -6.966 18.994
Tie
3 -0.756 -2.67 -7.564 -3.426 -8.32 6.966 20.384
member
4 -1.579 -1.818 21.96 -3.397 20.384
5 -2.857 1.23 11.12 -1.627 8.261
6 1.769 5.415 -20.13 7.184 -18.361
7 0.78 -2.75 11.44 -1.97 12.22
8 1.627 -1.876 27.49 -0.249 29.117 18.361 29.117 Rafter
9 2.95 1.276 -18.73 4.226 -15.78
10 4.45 3.29 -18.11 7.74 -13.66
11 -2.675 -6.55 24.35 -9.225 21.675
13 -0.239 -1.976 7.05 -2.215 6.811
Vertical
15 0.419 0.434 6.74 0.853 7.159 9.225 21.675
strut
17 0.963 2.29 8.17 3.253 9.133
19 -5.17 3.416 5.36 -1.754 0.19
12 0.989 8.167 -29.14 9.156 -28.151
14 -0.923 -0.956 -14.84 -1.879 -15.763 Inclined
28.151 9.156
16 -1.6 -3.82 -13.58 -5.42 -15.18 strut
18 -2.06 -6.24 2.47 -8.3 0.41
87
Table No.10: Beam grouping of ware house
88
Group Side roof and central Beams Max(+ve) Max(-ve)
1A-1B,1K-1L,6A-6B,6K-6L,1B-1C,1C-1D,1D-1E,1E-
I 1F,1F-1G,1G-1H,1H-1I,1I-1J,1J-1K,6B-6C,6C-6D,6D- 74.8 55.8
6E,6E-6F,6F-6G,6G-6H,6H-6I,6I-6J,6J-6K
A1-A2,A5-A6,L1-L2,L5-L6,B1-B2,B5-B6,C1-C2,C5-
II C6,D1-D2,D5-D6,E1-E2,E5-E6,F1-F2,F5-F6,G1-G2,G5- 182 142
G6,H1-H2,H5-H6,I1-I2,I5-I6,J1-J2,J5-J6,K1-K2,K5-K6
Maximum value
Group Member
Pu(kN) Mx(kNm) My(kNm)
I 351.977 231.164 97.045
C7,C8,C11,C12,C19,C20,C23,C24
C1,C2,C5,C6,C9,C10,C14,C17,C21,C22,C25,C2
II 371.935 260.417 255.957
6,C29,C30
III 270.557 343.496 304.717
C3,C4,C15,C16,C18,C27,C28
IV 463.771 365.601 325.38
89
Table No.12: Column grouping of ware house
Maximum value
Group Member
Pu(kN) Mx(kNm) My(kNm)
90
Summary of design
Nominal
Outer
Length bore(inner Weight
Sl.no Members diameter Class Thickness(mm)
(m) dia)(mm) (kg/m)
(OD)
NB
Nominal
bore Outer
Length Weight
Sl.no Members (inner diameter Class Thickness(mm)
(m) (kg/m)
dia)(mm) (OD)
NB
91
Truss T3 (3.03m span)
Nominal
bore Outer
Length Weight
Sl.no Members (inner diameter Class Thickness(mm)
(m) (kg/m)
dia)(mm) (OD)
NB
Nominal
bore Outer
Length Weight
Sl.no Members (inner diameter Class Thickness(mm)
(m) (kg/m)
dia)(mm) (OD)
NB
92
Truss T5 (5.79m span)
Nominal
bore Outer
Length Weight
Sl.no Members (inner diameter Class Thickness(mm)
(m) (kg/m)
dia)(mm) (OD)
NB
Nominal
bore Outer
Length Weight
Sl.no Members (inner diameter Class Thickness(mm)
(m) (kg/m)
dia)(mm) (OD)
NB
93
Truss T7 (10.15m span)
Nominal
Outer
Length bore (inner Weight
Sl.no Members diameter Class Thickness(mm)
(m) dia)(mm) (kg/m)
(OD)
NB
94
Office building first floor beam
Top Bottom Beam
Group Reinforcement Reinforcement Dimension(mm2) Shear Reinforcement
8mmФ,2 legged stirrups@100mmc/c at
1 3nos, 12mmФ 4nos, 20mmФ 300 x 400 either side & 8mmФ@135mmc/c at
middle portion
8mmФ,2 legged stirrups@100mmc/c at
2 3nos, 20mmФ 3nos, 20mmФ 300 x 400 either side & 8mmФ@160mmc/c at
middle portion
8mmФ,2 legged stirrups@100mmc/c at
3 3nos, 20mmФ 3nos, 20mmФ 300 x 400 either side & 8mmФ@160mmc/c at
middle portion
8mmФ,2 legged stirrups@100mmc/c at
4 3nos, 12mmФ 4nos, 20mmФ 300 x 400 either side & 8mmФ@185mmc/c at
middle portion
8mmФ,2 legged stirrups@100mmc/c at
5 3nos, 12mmФ 4nos, 20mmФ 300 x 400 either side & 8mmФ@135mmc/c at
middle portion
8mmФ,2 legged stirrups@100mmc/c at
6 3nos, 20mmФ 3nos, 20mmФ 300 x 400 either side & 8mmФ@160mmc/c at
middle portion
96
Table No. 17: Two Way Slab Design Details for the Roof of Office building
Moments Reinforcement
97
First floor slab details
Moments Reinforcement
98
Table No.18: Footing design summary of offg blg
Footing Footing type Dimensions(mm2) Depth, D Reinforcements
groups (mm)
PAD1 Isolated 1570x1570 300 12mmФ @ 180mm c/c in both
footing directions
PAD2 Isolated 1730x1730 300 12mmФ @ 180mm c/c in both
footing directions
PAD3 Combined 4270x2640 310 10-16mmФ @ 250mm c/c in
footing longitudinal direction 16mmФ @
170 c/c in transverse direction
PAD4 Slab beam type 9300x1300 250 12mmФ @ 250mm c/c as main
strip footing reinforcement & 8mmФ @ 160 c/c
as distribution reinforcement
For footing width=400 665 3-16mmФ bar as both top and
beam with bottom reinforcement with 2
clear legged stirrups of 10mmФ @ 95
cover=60mm c/c
PAD5 Slab beam type 9000x1000 250 16mmФ @ 160mm c/c as main
strip footing reinforcement & 8mmФ @ 160 c/c
as distribution reinforcement
For footing width=400 400 3-12mmФ bar as both top and
beam with bottom reinforcement with 2
clear legged stirrups of 10mmФ @
cover=60mm 80mm c/c
100
Table No. 21: Two Way Slab Design Details for the Roof of hazardous storage house
Moments Reinforcement
Mx 8mm dia @
5.69 8mm dia @ 300mm c/c
=4.23 250mm c/c
A,B,C, 8mm dia @ 300mm
D c/c for the length of
8mm dia @
My = 3.7 4.89 8mm dia @ 300mm c/c 600mm from the
300mm c/c
face of column
101
Table No.23: Footing design summary for Storage
Footing Footing type Dimensions(mm) Depth, D Reinforcements
groups (mm)
PAD1 Isolated footing 1350X1350 250 10mmФ @ 150mm c/c in both
directions
PAD2 Isolated footing 1100X1100 250 10mmФ @ 200mm c/c in both
directions
PAD3 Isolated footing 1600X1600 300 16mmФ @170mm c/c in both
direction
PAD4 Isolated footing 1750X1750 300 16mmФ @180mm c/cin both
direction
PAD5 Isolated footing 2000X2000 350 16mmФ @ 1460mm c/c in both
direction
Table No.24: Ware house truss design summary
Load Member
Truss T1 combination Design Load Properties
Member
Membe DL+L DL+W Compressio Tensio
r DL LL WL L L n n
101.4
AO -41.34 -59.56 4 -100.9 60.1
OP -37.6 -51.43 81.1 -89.03 43.5 NB=80,
PQ -33.97 -44.83 71.2 -78.8 37.23 -100.9 60.1 RAFTER OD=88.9
QR -30.3 -39.12 60.11 -69.42 29.81 (L)
RS -26.51 -33.52 50.99 -60.03 24.48
ST -22.74 -27.99 46.89 -50.73 24.15
AB 40.11 57.79 -98.43 97.9 -58.32
BC 40.11 57.79 -98.43 97.9 -58.32
NB=65,
CD 36.47 55.17 -78.79 91.64 -42.32
-58.32 97.9 TIE OD=76.1
DE 32.94 49.27 -51.81 82.21 -18.87 (L)
EF 30.26 43.72 -41.04 73.98 -10.78
FG 26.59 24.84 -32.22 51.43 -5.63
BO 0 0 0 0 0
CP 0.91 0.65 -4.9 1.56 -3.99 -11.95 11.14
VERTICA NB=32,
DQ 1.8 3.01 -13.75 4.81 -11.95
L OD=42.4
ER 2.68 4.18 -8.11 6.86 -5.43 STRUTS (L)
FS 3.67 5.42 -8.82 9.09 -5.15
TG 4.52 6.62 -4.62 11.14 -0.1
OC -3.75 -2.7 20.24 -6.45 16.49
PD -3.96 -6.62 30.28 -10.58 26.32 -26.32 14.34 NB=40,
INCLINED
QE -4.46 -6.95 13.48 -11.41 9.02 OD=40.3
STRUTS
RF -5.19 -7.67 12.48 -12.86 7.29 (L)
SG -5.82 -8.52 6.35 -14.34 0.53
102
Load Member
Truss T2 combination Design Load Membe Properties
Membe DL+L DL+W Compressi Tensio r
r DL LL WL L L on n
1 -1.716 -5.25 20.71 -6.966 18.994
2 -1.716 -5.25 20.71 -6.966 18.994
-
3 -0.756 -2.67 7.564 -3.426 -8.32 Tie NB=25,
- 6.966 20.384 membe OD=33.7(L
1.81 21.96 r )
4 -1.579 8 3 -3.397 20.384
11.11
5 -2.857 1.23 8 -1.627 8.261
5.41 -
6 1.769 5 20.13 7.184 -18.36
7 0.78 -2.75 11.44 -1.97 12.22
- NB=32,
1.87 18.361 29.117 Rafter OD=42.4(
8 1.627 6 27.49 -0.249 29.117 M)
1.27 -
9 2.95 6 18.73 4.226 -15.78
-
10 4.45 3.29 18.11 7.74 -13.66
11 -2.675 -6.55 24.35 -9.225 21.675
-
1.97
13 -0.239 6 7.05 -2.215 6.811 NB=25,
Vertica
0.43 9.225 21.675 OD=33.7(L
l strut
15 0.419 4 6.74 0.853 7.159 )
17 0.963 2.29 8.17 3.253 9.133
3.41
19 -5.17 6 5.36 -1.754 0.19
8.16 -
12 0.989 7 29.14 9.156 -28.15
-
0.95 - NB=32,
Incline
14 -0.923 6 14.84 -1.879 -15.76 28.151 9.156 OD=42.4(
d strut
- M)
16 -1.6 -3.82 13.58 -5.42 -15.18
18 -2.06 -6.24 2.47 -8.3 0.41
103
Table No.25: Ware house beams design summary
Plinth beam
Group Top Bottom Dimension Shear Reinforcement
Reinforcement Reinforcement (mm2)
I 3nos, 16mmФ 4nos, 25mmФ 450X450 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@210mmc/c at middle portion
III 4nos, 16mmФ 4nos, 20mmФ 450X450 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@210mmc/c at middle portion
Middle Beam
Group Top Bottom Reinforcement Dimension Shear Reinforcement
Reinforcement (mm2)
104
IV 3nos, 20mmФ 3nos, 32mmФ 450x500 8mmФ,2 legged stirrups@100mmc/c at
either side & 8mmФ@235mmc/c at
middle portion
Roof Beam
Group Top Bottom Dimensions Shear Reinforcement
Reinforcement Reinforcement (mm2)
I 5nos, 16mmФ 4nos, 20mmФ 400 x 400 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@185mmc/c at middle portion
II 4nos, 16mmФ 3nos, 25mmФ 400 x 400 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@185mmc/c at middle portion
I 5nos, 16mmФ 4nos, 20mmФ 400 x 400 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@185mmc/c at middle portion
II 2nos, 16mmФ 3nos, 20mmФ 400 x 400 8mmФ,2 legged stirrups@100mmc/c at either
side & 8mmФ@185mmc/c at middle portion
105
Table No.26: Design summary of column for warehouse