Professional Documents
Culture Documents
50106118083
JULY 2020
POWER HAMMER
50106118083
JULY 2020
DECLARATION
I declare that this report is my original work and all references have been
cited adequately as required by the University.
We have examined this report and verify that it meets the programmed and
university, requirement for the Diploma of Engineering Technology in Welding.
We thank all of those who gave us the opportunity to complete this report for our
gratitude and appreciation. Special thanks to our project coordinator for the final year,
Mr. Abdul Aziz Bin Dawam, who helped us to organize our project, particularly when
writing this project, by encouraging suggestions and encouragement.
We would also like to acknowledge with much gratitude the crucial role played by Mr.
Mazlan, Technical and Operational Advisor of the Welding Workshop, who gave us
permission to use all the necessary machines and materials to complete the Handrail
project.
Last but not least, many thanks go to the members of the team, who have made every
attempt to accomplish the aims of successfully completing this mission, despite the
ups and downs together. We need to express our appreciation, who have helped us a
lot to successfully complete the project within a short timeline. We are working on this
project not only for marks, but also to increase our expertise. Thanks again to those
of you who helped us out.
TABLE OF CONTENTS
ACKNOWLEDGEMENT ...........................................................................................4
ABSTRACT .............................................................................................................13
CHAPTER 1: INTRODUCTION.................................................................................1
3.5.8 Machine And Equipment Used (Metal Cut-Off Saw Grinder) ...................... 89
REFERENCE ........................................................................................................114
APPENDICES .......................................................................................................115
LIST OF TABLE
Various types of machinery and devices have been used for various uses in many
fields, such as forging, hammering, slicing, etc. However the various problems, such
as low power supply, less workforce and even heavy labour, safety, etc., apply to the
operation which can be carried out either by means of an electric motor or by means
of manual means.
The purpose of this work is to build the smashing, forming and forging process that
are more reliable than manually. This machine executes hammering, shaping and
forging at the required speed, and this machine is Semi-automatic, which is powered
or regulated by the electric motor with the power of the current. This tool is based on
a mechanism that are worth to be made. This power hammer can be used in
manufacturing, domestic activities or small scale activities. It may be used with either
a thin metallic or a sturdy model or body.
CHAPTER 1: INTRODUCTION
1.1_Introduction
The acheivement of the final year task is to provide group of students of the final year
Diploma in Welding with understanding and skills for process planning and research
project execution. It is also to include the information, preparation and expertise
appropriate in the context of the project to identify and explain the steps taken, to show
the ability to coordinate and prepare for project execution and decision-making in
appropriate problem solving.
The aim of this project is to ensure a safe and precious hammering of work, such as
punching, filling, riveting and smiting, i.e. welding, etc. for all planned operating
conditions. The modeling, design and study of automated portable hammering
machines are explained in this article. A crucial aspect of the assembly process
is assumed by the programmed hammering machine (hammering process).
Hammering machine used in some part of the production of material from tool to center
point, automobile frame forming, metal molding and so on. Present innovations
associated with the metal squeezing machine and the shaping machine involved some
outstanding problems in terms of nail push, fitting components, shaping of metal and
breaking of separate issues.
1
effort and human capital involved in the process. But it is now possible to make
it easy to process by inventing automatic hammering. There are very obvious
advantages that the industry finds in the use of automated systems. These advantages
can be very beneficial in the longer term.
1.1.1_Problem Statement
While doing a hammering job, more energy will be needed to finish it. When physical
hammering is used the tasks can be performed, although it may take longer time to
complete. It really is challenging to really do manual hammering task for the production
and operation industry, as they may have various problems such as low power supply,
less workforce and also heavy labour. This automatic hammering will help them
overcome this dilemma. We therefore take this chance to use our knowledge and
experience to produce a power hammer to ensure that the process can be carried out
easily.
1.1.2_Objective
We had a group discussion with the teammates and the superiors. We suggested a
variety of initiatives and discussions. And eventually, we're selecting Power Hammer
as our graduation project. The goals of this project are as follows:
2
1.1.3_Scope of work
Hammering yet is the most widely used im industrial yet required tons of our effort and
time so now we have a propensity to plan an semi automated hammering machine
that allows for semi automatic hammering anytime you need to use. The individual to
literally just need to install the work piece and start. This machine can be used for
semi automatic hammering because the DC motor consists of a pulley fixed to it which
is connected to the cam mechanism which will drive the hammer to forge the part.
The pulley is very efficient to transfer power and act as a medium to increase the
torque. This pulley is mounted on a shaft that act as connecting rod used to produce
lateral motion from the spinning shaft, by connecting the order end of the hammer to
the cam mechanism that has a mid-swing arrangement in order to achieve the
necessary hammer motion with an acceptable torque, we will use the appropriate
die where the work piece is mounted. The power hammer is a tool that can be used
for multipurpose operation either manually or semi automatically, mainly by
hammering a workpiece that can also be used for other purposes, such as punching
forging bending, etc.
3
1.1.5_Advantages of the machine
➢ Rapid Hammering.
➢ Speedy hammering operation.
➢ Very little effort physically.
➢ Multi-Operation.
➢ Maintenance is simplistic.
➢ Comparatively low costs.
➢ Ergonomically friendly.
➢ Effective repetition and impacts
1.1.6_Project Design
4
1.1.7_Project Management
The project management schedule is a written framework that specifies how the
project is to be executed. It describes the scale, priorities, expenditure, timetable and
outcome of the project and is vital to keeping the work on schedule.
➢ Planning
Method of working that traditionaly organize the activities that are needed to
achieve the final goal. This task require development and management of a
plan. This method is a central property and traits for intelligent behaviour. This
process require critical suficient formulation and refinement of an approach
(strategy) to ensure its interact and support with other plans and as a result
incorporates the prediction of activities with the planning and preparation of
situations for how to tackle upcoming problem.
➢ Scheduling
The process, also known as the 'change model,' is a list of staff working in the
offices for a particular day, week or month. A schedule is required for any retail
shop or production facility's everyday operation. The planning process calls for
timetables. A daily optimum scheme combines workers' needs, obligations and
in some cases consumers.
A working day is usually a time schedule, meaning that the first day workers,
followed by the next job, are listed at the top.
Usually a weekly or monthly timetable of staff on the left or on the grid, with
days of a week at the top of the grid, is organized alphabetically. Usually, the
plan employs a repeated shift technique of alternating shifts. It is the chief that
draws the timetable most often. The Human Resources Officer or Scheduling
Specialist may be primarily responsible for the preparation of the strategy in
larger operations.
5
1.1.9_Manufacturing Management
➢ Planning Schedule
Activity/ 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Week
Project
Planning
Design
Sketching
Material
Research
Material
Selection
Approval of
Supervisor
Actual
Measurement
Develop
Engineering
Drawing
Approval of
Material
Measuring &
Marking
Edge Preparation
Cutting
Welding
Installation
Inspection &
Painting
Report Writing
Presentation
7
➢ Production Flow Chart
Designing
Approval of Proposal
Finishing
8
Drawn Conceptual idea are design using
Autodesk Inventor Profesional
Planning The main goals is to ensure that all operations run
constant & smooth without any heavt wastage at
the same time can be finished on time as plan.
9
1.2_Project Flow Chart
START
NO
Report writing
Does the
project is
approve FYP Presentation
YES
Designing
Proposal
Fabricate
10
1.2.1_Management Team
➢ Team Members
11
Name Rusydi Fitri Bin Rudzylan
ID No. 50106118083
ID No. 50106118042
12
1.2.2_Responsible Person
13
1.2.3_Organization Chart
Project Supervisor
Mr. Abdul Aziz bin Dawam
Designer
Tengku Mohd Hafizan bin Tengku
Zahari
Process Planner
Nurul Ainin Sofiya binti Rusdi
Fabricator
Rusydi Fitri bin Rudzylan
Inspection
Wan Muhammad Izzat bin Wan
Mazihan
14
CHAPTER 2: LITERATURE REVIEW
2.1_Introduction
This segment addresses the study created to be used as a primary point for the
revival of existing projects and processes. Various methods may be used to produce
a number of reference as a sources of information for the graduation project. This
study is carried out by on-going industry interventions, identifying emerging
vulnerabilities, challenges that are being addressed, related help hypotheses,
questionnaires and so on to find solutions to the problems raised:-
Hand tools research are long journey that require some timing. Variety of hand tools
are used in blacksmith work. This type of tool work very well when it is done by hand-
forging, but their use only enough only to minor forging. It is to really difficult to realize
that produce force of the strikes, no matter how strong one might attempt to do so by
hand smashing, might not have been sufficient to affect the correct plastic effect in
moderate also intense forging. Usually, more advance machine is used for this reason.
The strength falling die is determined by the summing weight of falling mention
component to the table die.
The hammer of 200 kg is a component that we called falling pieces that are weight at
200000 N. The heavier these components, and the higher the force it smash from
which they fall. The stronger the blast power the hammer is going to deliver. Power
15
hammers are widely found in a number of formsThese hammers are named in part for
their design, in part for their mode of operation. In addition to these, a considerable
number of forging presses and forging machines are used. These hammers and
instruments shall be addressed in more depth in the detail provided.
➢ Trips hammer
➢ Level Spring-Hammer
Level spring hammers are a type of special hammer with a constant lift and a
continuous hammer that are equal with variable power of effect. It is increases
with increasing operation speed contribuite to the increases the number of
strokes per minute. It is powered by single rocking lever that operate on an
elastic rod. Rocking lever contain of a leaf spring such that elastic drive is made.
They suitable for shaping and flattening small forgings to produce a large
numbers of speciment. However their downside is the spring break quite
frequent and this is cause by vibrations during operation. This specific hammers
are produce with weight ram of 30 and 250 kg. Total of strokes produce is from
200 to 40 blows per 60 second.
16
➢ Pneumatic Hammer
The two-cylinder compressor cylinders and a ram cylinder are
mounted in this hammer. The compressor piston compresses air and
takes it to the ram cylinder, where the piston that is integral to the ram
delivers blows to the task. The reciprocation of the compression piston
is obtained from the crank drive, which is controlled by the engine from
the lower gear. The air circulating mechanism between the two
cylinders consists of rotary valves with alternate ports from which air
passes through the ram cylinder below and above the piston. This is
driving the ram up and down.
➢ Hydraulic Hammer
Instead of air oil, he used hammers. In comparison to pneumatic
hammers the hydraulic hammer costs are high. In high strength
applications, hydraulic hammer is used. This is less traffic. Less
noise.
Model:
Blachsmith Air Hammer C41- 55kg
Power Hammer
Price:
RM16518 RM22712
(US $4,000-5,500)
17
Figure 1.2 Indsutrial Hammer
RM 16518-RM 22712
2.1.4_Recent Research of power hammer
The present disclosure addresses a power hammer providing consumers
with a metal forming benefit correlated with powerfull machines at a lesser
price and a lower profile than currently available power hammer systems.
In one aspect, the new power hammer assembly offers controlled forming
capability while remaining efficient in terms of performance, vibration and
compact size and acquisition expense. In some embodiments, the power
hammer assembly of the latest invention includes adjustment functions
that allow for the use of die sets in various configurations, such as the
height of the shank, the length of the shank or in addition, the die sets
produced for use with other machines. In some of the examples, the power
hammer arrangement of the latest invention may compose of a belts
transmission mechanism configured to slip in the case of a die disruption
during installation or service in order to protect the power hammer
assembly. In certain implementations, the power hammer arrangement of
the present invention demands a fine adjustment of the distance between
the upper and lower dies.
18
CHAPTER 3: METHODOLOGY
3.1_Introduction
This section will discuss the specifics of the flow of this project, which will be used to
create a hammer of force from the start to the end of the project. In this project, we
have to develop the product in order to make that it is the right product. We chose this
design because it can quickly help to minimize human energy when it is used. Another
phase, which is the production process, would be the best product. Before that it is
important to make a content collection. This is to choose the necessary material to be
used. The collection of materials is often accompanied by the feature of the
component.
3.1.1_Manufacturing
19
3.1.2_Manufacturing Process
In order to develop a new product concept, certain procedures need to be
carried out without any complications before beginning the project. In addition,
the production process is often known as the method or technique in which
each implementation is performed out. Among the phases that we have
accomplished is:
➢ Costing
➢ Engineering Drawing
➢ Selection Of Materials
➢ Selection of Welding Process
3.1.3_Costing
In order to carry out the project manufacturing process, a selection of items
needs to be taken seriously in order to accelerate the method of delivery of the
material considered for the development of the proposed and completed
project. The following table includes a list of the specification materials needed
to complete this project.
20
S Total
i Price
No I Quantity z Price
t e (RM x
e (Pieces) (RM) Quantity)
m (Thickne
s
ss x
width x
length)
Steel
9 2 11mm RM5.50 RM11.00
Drill Bit Stainless
Steel
10 1 RM7.56 RM7.56
Ellen Key
21
11 4 M10 x RM 1.70 RM6.80
M10 Hex Bolt 16mm~65mm
Hexagon Screw
M10
12 1 7x7x RM 14.66 RM14.66
Machine Key Flat 300mm
13 12 RM 7.40 RM88.80
L Angle Bracket
14 67 M6 RM 0.9 RM60.30
Flanged Hex Nut
15 3 M16 RM3.3 RM9.90
Flanged Hex Nut
16 8 M10 RM 1.00 RM8.00
Flanged Hex Nut
17 8 15mm RM 11.20 RM89.60
Set Screw
18 2 RM 7.50 RM15.00
Self Aligning
Pillow Block
Bearing
19 1 RM12.40 RM12.40
Pillow Set
Screw Block
Bearing
20 1 1kg RM17.90 RM17.90
Poly Putty Hitary
21 2 RM26.78 RM53.56
Aluminium
Pulley Belt
22 2 M6 x 10 RM4.20 RM8.40
Screw
Stainless
Steel
23 1 M5 x 12 RM4.20 RM4.20
Screw
Stainless
Steel
24 1 M4 x 16 RM4.20 RM4.20
Screw
Stainless
Steel
25 2 15mm x 1mL RM 31.20 RM62.40
Rod Stainless
Steel
22
26 2 160mm RM 5.11 RM10.22
Hexagon
Screw
27 6 M6 x 1.0, M6 RM1.10 RM6.60
Hexagon Socket x 40
Head Cap Screw
28 11 M6 x 1.0, M6 RM0.90 RM9.90
Hexagon Socket x 60
Head Cap Screw
29 25 M6 x 1.0,M6 x RM0.90 RM22.50
Hexagon Socket 20
Head Cap Screw
30 44 M6 x 1.0, M6 RM0.90 RM39.60
Hexagon x 25
Socket Head
Cap Screw
31 2 M6 x 1.0, M6 RM0.90 RM1.80
Hexagon x 16
Socket Head
Cap Screw
32 1 2.0mm RM24.10 RM24.10
Stainless Steel
Tension Spring
33 Ring Hook 1 14mm RM23.10 RM23.10
Extension
Coil Spring
34 Ring Hook 1 2.0mm Rm24.10 RM24.10
Extension
Coil Spring
35 17 M6 RM0.60 RM10.20
Flat Washer
36 3 3 ½’’ RM12.00 RM36.00
U Shape Hose
23
39 2 4’’ RM13.80 RM27.60
U Shape Hose
Torx Screw
47 1 RM10.30 RM10.30
Paint
48 1 RM3.30 RM3.30
Paint Brush
49 1 RM7.77 RM7.77
Honda Original
Circlip External
50 1 RM25.00 RM25.00
Pedal Foot Switch
51 RM18.90 RM18.90
Arduino AC-AC
Regulator
52 1 RM103.46 RM103.46
Heavy Duty Drill
TOTAL RM 1090.82
25
26
27
28
29
30
3.1.5_Engineering Drawing (Bom & Exploded Drawing)
31
32
33
34
35
36
3.1.6_Engineering Drawing (Weld Drawing)
37
38
39
40
41
3.1.7_Engineering Drawing (Weld Map & NDT Drawing)
42
43
44
45
46
3.1.8_Engineering Drawing (Shop Drawing)
47
48
49
50
51
52
53
54
55
56
3.1.9_Engineering Drawing (Shop Drawing for Assembly Purpose)
57
58
3.2_Engineering Drawing (Flat Pattern Drawing)
59
3.2.1_Engineering Drawing (Squaring Drawing for Pre Material Removal)
60
3.2.2_Introduction to Quality Improvement
3.2.3_Innovation
61
3.2.4_First Critical Improvement (Shaft Holding Part)
The first critical improvement that we made is to change shaft holding part.
Below is the picture of shaft holding part old design and beside it, is the
picture of new design.
As you can see the previous design use cylindrical hollow and a thin plate as
a holder for the drive shaft that drive the hammer up and down and secondary
shaft that hold the hammer, preventing the hammer from slip while running, it
is welded together by mean of fillet weld and and is place to the wooden frame
by screwing the plate on it. As time past and the machine is used abusively.
The previous design is most likely to fail. This is cause by defect that occur in
weldment that is introduced to stress. Furthermore, the material used is mild
steel so it is prone to rust when expose moist carried out by oxygen. Lack of
suitable coating also contributed to failure. On the new design we use double
pillow block as medium to hold the shaft. This type of pillow block is primarily
made of aluminium and it is produced by casting. There is no defect we
encounter beside manufacture defect. But it is easily replaceable since there
is warranty on it. Further advantage of pillow block is, it included thrust ball
bearing as smoothing agent to constrain the shaft between another pillow
block. So, the driving component can function smooth and seamlessly. Beside
that pillow block come with locking mechanism, this will ensure the shaft in
location and prevent it from sliding as the machine running.
62
3.2.5_Second Critical Improvement (Shaft)
63
3.2.6_Third Critical Improvement (Pulley Locking Mechanism)
64
We analyse the problem with critical thinking and we came up with idea that
we called bush locking mechanism. Basically, it is a rectangular bush that we
drill with 15 mm drill bit in the centre and on every 1 side of the bush we drill 2
set of holes with 5.2 mm drill bit and all hole were threaded by tap drill m6x1.0.
All the hole that are threaded than are fill with set screw. This custom bush act
as stopper for the pulley from sliding outward, because the set crew that we
place in will hold the cylindrical surface of the shaft, with the help of retaining
ring that place in the end of the bush, this will produce more rigid locking
solution.
65
3.2.7_Fourth Critical Improvement (Hammer Holding Part)
66
3.2.8_Fifth Critical Improvement (Frame Material)
67
Figure 1.9 Scanning Tutorial
First step of inventing new fixture is by reverser engineering the physical model
of hammer drill. We separated the hammer drill casing and place the casing
on the printer. Then we scan the casing, after done scanning process we
export the output file to computer aided design software, then we trace the
image_by_using_line_command
After that we place the sketch that we have made and project the primary
sketch to the base of hammer drill. And start placing hole sketch
for clamp, outer diameter of flange nut sketch and sketching suitable location
for jig block
68
Figure 2.1 Clamp Location
After complete designing the base part of the hammer drill, we complete it by
assemble them with jig block and clamp, also weld in place on top of the foot
rail assembly
69
Figure 2.3 Jig Block & Clamp
70
3.3_Seventh Critical Improvement (Cam Assembly & Cam Lock)
The improvement that we made is improve the cam assembly and cam locking
mechanism. Previous design cam mechanism is hold by two cylindrical plate
that are place inside, welded together to the cam housing by mean of butt join.
And they use ball bearing without bearing housing and place inside the cam
housing to smooth the cam. For locking mechanism, the cam housing is
welded on both side below anvil cam bracket. This is not practical because the
area of joint is not flat and to obtain accuracy and make sure the cam housing
Is parallel to the centre of anvil cam bracket is quite challenging.
71
So, on the new design we upgrade the cam housing by combining the base for
locking clamp directly to the cam housing model. Then we place needle
bearing complete with bearing to ensure the seamless of the cam. For the cam
cover we use socket headed screw to seal the cam housing to make sure the
cam mechanism in place. We also make a stabilizer to ensure locking clamp
is hold in position while the machine working. All part that related to cam
assembly is fabricate by mean of computer numerical control. We partner with
GMI to produce the product base on requirement that we set; this is because
this is the key component to ensure the assembly is not failing.
72
3.3.1_Eight Critical Improvement (Dimmer & Paddle Switch)
Our last improvement that we made is installing dimmer and paddle switch
together. This is been done by rewiring three component which is hammer drill,
dimmer and paddle switch. This improvement ensure the machine smoothness
with the ability to control desire speed. With the installation of paddle switch,
this react as emergency stopper beside the dimmer. This will help to save life
if machine gone wrong.
3.3.2_Creativity
Creativity is a broad skill that can be applied to all things. Creativity is a set of
lateral thinking tools that can be applied to any field. Creativity that our group
and our supervisor and co supervisor make the product become reality. That
give a new value for this product
73
3.3.3_Example of Finish Product (Milling,Turning & Laser cut)
ASTM A36 is indeed mild and hot-rolled steel most widely used. It has
excellent welding capabilities and is ideal for grinding, punching, tapping,
drilling and machining. The yield intensity of ASTM A36 is lower than those of
cold roll C1018, allowing ASTM A36 to fold more quickly than that of C1018.
Normally, greater diameters of the ASTM A36 were n’t produced as the hot roll
rounded of the C1018 are being used.
➢ Bar of rectangle
➢ Place bar
➢ Circular bar
➢ Steel forms such as canals, angles, H-beams and I-beams.
75
3.3.7 Application of ASTM A36 Steel
Element Content
Copper, Cu 0.20 %
Iron, Fe 98.0 %
Manganese, Mn 1.03 %
Phosphorous, P 0.040 %
Silicon, Si 0.280 %
Sulfur, S 0.050 %
76
3.3.9 Mechanical Properties of ASTM A36 Steel
77
3.4 _Welding Process Selection
For this power hammer project, we chose Gas Metal Arc Welding (GMAW)
welding processes. We choose these welding processes because of our raw
resources, which are plates and carbon steel which have lower thickness
which is 1.5mm to 4mm.
Gas Metal Arc Welding is generally referred to as Metal Inert Gas (MIG).
(MIG). gIt is a semi-automatic or automated welding process with constantly
fed consumable wire serving as both electrode and filler metal,runing along
with inert or semi-inert shielding gas running through the wire to protect the
welding area from surrounding atmosphere. Constant voltage, direct current
source is most widely seen for GMAW, but constant current alternating current
is often used.
Advantages Disadvantages
In general, the electrode or the filler wire should be selected on the basis of
the following factors:
ER70S-6 is a competent, gentle, solid wire made from steel designed to deliver
higher solder and issues, free of heavy duty, high-speed operation, medium-
speed, slower-speed, short-arc applications. ER70S-6 has been developed for
the application in a variety of gas mixtures, including 100% CO2, 75/25 Ar/CO2
or 98/2 Ar/O2. Except in the most complicated applications, ER70S-6 offers a
smooth, stable arc with limited spreading spreader to produce a welding bead
that suits seamlessly and looks smoothly.
79
3.4.5_Application of ER70S-6 Filler Metal
Carbon(C) 0.06-0.15
Silicon(Si) 0.80—1.15
Iron(Fe) Balance
Manganese(Mn) 1.40-1.85
80
3.4.7_Typical Mechanical Properties of ER70S-6 Filler Metal
Co2
strength(psi)
strength(psi)
area
ft lbs
81
3.4.8_Recommended Welding Parameters
diameter ipm
82
3.5_Fabrication Process (Selection Of Material And Its Form)
We checked and analyzed the materials that need to be included in this project
to satisfy the requirements of our project. In contrast, we have chosen to make
effective use of mild steel to reach the maximum sense of financial quality, as
well as some welding can be carried out. Mild steel is ideal for welding and
general manufacturing applications. It is also easier to mold, drill, weld and cut
than some of the more delicate forms of steel.
83
3.5.2_Fabrication Process (Measuring and Marking)
a) Again after raw materials were selected from the factory, the residual
dirt and rust on the surfaces of the materials are eliminated by polishing
or brushing. Bring the raw materials to the workshop for the labeling of
the materials.
b) Material is mark according to the dimensions as defined in the
engineering drawing that have been accepted with the use of a chalk
stick or permanent marker in order to prevent non-visible
measurements
c) Marking is achieved with the help of measuring tape, ruler and the L-
ruler.
a) The designated materials will be shaped into their dimension with the
use of the milling, lathe, laser cut machine, shearing machine, cutter
and the sawing machine
b) During the operation of the machinery, precautions must be taken to
prevent any injuries that may occur
c) Hollow square frame is place on jig then will be slice by disc cutter
d) Ensure the marked region on the material is opposite to the disk.
e) Run the machine and cut the material perfectly.
f) Off the machine after finish using
g) Removed the by product from the fixture of the disc cutter
84
Figure 2.8 Cutting Process
3.5.4_Fabrication Process (Drilling)
87
3.5.7_Machine and Equipment Used (Shearing Machine)
88
3.5.8_Machine and Equipment Used (Metal Cut-Off Saw Grinder)
a) Identify and make sure that you are familiar with both machine
operations and function
b) Make sure that all guard are installed, safe and usable. Never work if
the guards are absent or defective.
c) Ensure that the saw is correctly mounted to the workbench by
bolts/clamps somewhere around the height of the hip.
d) Verify that the saw is run on an RCD protected circuit
e) Use abrasive cut disks for the right size of the arbor hole.
f) Analyse the cut-off disk for cracks and stones.
g) Make sure work areas and passageways to insure that no slip/trip
hazards are present
89
3.5.9_ Machine and Equipment Used (Grinder)
a) Make sure that both guards and safety shields are in place before
operating the grinder.
b) Make sure that the wheels does not contact the remainder of the job
and the distance between both the wheel and the rest does not exceed
1.5 mm.
c) Confirm that the disks are running perfectly and are not glazed or
loaded.
d) Identify and verify that you are comfortable with the function of the
ON/OFF starter.
e) Defective appliances shall not be used for work. Report directly to
responsible technician for any suspected machine.
90
3.6_ Machine and Equipment Used (GMAW Machine)
a) Make sure that you are familiar with both system processes and
controls.
b) Ensure that work environment is sterile and free of grease, gasoline and
other combustible liquids.
c) Make sure the welding tools, work area and gloves dry to prevent
electrical shocks.
d) Verify that your gloves, your welding pistol and your work leads are in
good order.
e) Make sure that all users are secure from flashes by covering the curtain
to the welding bay or by erecting windows.
f) Begin the smoke extraction device until welding starts.
g) Ensure the job leads do not create a tripping threat.
91
3.6.1_ Machine and Equipment Used (Drilling Machine)
a) Discover and check that you are experienced with both system
processes and functions.
b) Make sure that all guard are mounted, safe and usable. Should not work
if the guards are absent or disabled.
c) Check the workspace and walkways to ensure that there are no slip/trip
risks.
d) Verify that the drill bit is in good order and safely installed.
e) Verify the coolant distribution system to allow adequate coolant flow.
92
3.6.2 Tool and Equipment (Caliper)
93
3.6.5_Tool and Equipment (Ruler)
Measure the distance and keep the dimensions in order for more
metalworking.
94
3.6.8_ Tool and Equipment (Chipping Hammer)
95
3.7.1_Introduction to Safety
Security is the state of safety, the status of defense against physical, societal,
spiritual, environmental, political, mental, occupational, psychological,
educational or other effects of loss, injury, mistake, disaster, harm or some
other occurrence that may be deemed undesirable. Protection may also be
characterized as the management of known hazards in order to achieve an
appropriate degree of danger. This can take the form of protection against
exposure to material that causes health or economic damages. It can require
the safety of individuals or possessions.
Health is the most important factor in any sort of high risk of jobs. Safety at
work is required for the quality of work and when quality is high, efficiency often
improves indirectly by enhancing good work. Safety is the first concern in the
world of engineering when managing a project or other building.
We should maintain that the workspace is free of all dirt and scrap material
that may pose harm and damage to the employee. For eg, gasoline, dirt, metal
dust and garbage.
Make sure that the machines are clean but also that the machine locations are
properly configured according to the 5S definition.
Before the operation, we must ensure that the protection equipment is in good
shape and complete.
96
3.7.5_Introduction to Personal Protective Equipment
97
3.7.8_Personal Protectice Equipment (Safety Goggle)
98
CHAPTER 4: RESULT AND DISCUSSION
4.1_Introduction
As stated, it was found that the project produced requires a specification that
meets the specifications and expectations to produce the best performance.
Sum up, this project has been fruitful in the research process. Consequently, I
hope that this Power Hammer will be improved and innovated from period to
period as an example of making it light but strong so that it is easy to maneuver
around or incorporate artificial intelligence elements.
4.1.1_Process Of Testing
a) VI or Visual Inspection
b) DPI or Dye Penetrant Inspection
99
4.1.3_Factor Affecting Quality Monitoring
Well prepared QC can identify several signs of surface defect as a highlight for
upcoming problem. To preserve quality monitoring and assurance scheme,
the auditor shall check the work piece or specimen and ensure that:
• Welds are made according to the plans and make sure no welds are
incomplete.
100
Figure 5.0 Acceptance Criteria
4.1.5_Visual Inspection Report (Joint 1)
102
Figure 5.2 Joint 2
4.1.7_Visual Inspection Report (Joint 3)
103
Figure 5.3 Joint 3
4.1.8_Visual Inspection Report (Joint 4)
104
Figure 5.4 Joint 4
4.1.9_Introduction To Dye Penetrant Testing
4.2.3_Procedure Qualification
105
4.2.4_Acceptance Criteria
4.2.5_Acceptance Standard
106
4.2.6_Flow Chart Of Dye Penetrant Inspection
107
4.2.7_Dye Penetrant Inspection Report (Joint 5)
109
Figure 5.6 Joint 6
4.2.9_Dye Penetrant Inspecstion Report (Joint 7)
110
Figure 5.7 Joint 7
4.3_Dye Penetrant Inspection Report (Joint 8)
111
Figure 5.8 Joint 8
CHAPTER 5: CONCLUSION
5.1_Final_Coclusion
From overall view of this final year project, the conclusions that can be made
are this project require extensive use of the knowledge obtain from semester
1 until semester 5. Students are encouraged to apply the knowledge that we
learn into the real work project. The subject also trains the student to use
critical thinking to improvise new improvement that are required to enhance
the longevity of the product. Beside that we also learn that proposal making is
real key area to find out the purpose of the project and what kind of product
and design should be produced, by implementing this kind of activity, this help
us to understand working nature. While project planning really helps us to
discipline and stay committed time to time to finish the product. Students also
are exposed with the real environment in planning a project, this help us to
plan maturely, because project planning is one of the keys to successful
product. Next this subject help us to train to be better and practice what we
have learned focus on part that related to welding area. This kind of project
also essentially improve our skills in using several software such as AutoCAD
and Inventor.
The time we built our project, COVID-19 get rage and force our university to
close, this prevent us from finishing our project according to schedule. So, we
prepare animation of the machine as side outcome. There are many obstacles
that face while doing animation. Because this area is not excessively
introduced to us in our study syllabus. This help us be self independent by
doing some research online, book reading by mean to complete this animation.
At last we successfully made our working machine animation.
112
use. At last positive outcome that we can get by exposing to this project is it
taught us to be more punctual in working and the importance of teamwork.
5.1_Suggestion
Based on this project, we have attached some of our suggestion that can be
done at the project for other improvement.
The surface finish of the frame is bare metal, which is prone to rust if expose
to normal environment. With little cleaning the surface finish of the frame can
be smoother and with the help of coating, the frame will have long lasting life
and are more resistant to rust
Most of the fabricated part have sharp edges and burr as a by-product of
cutting. By removing burr and sharp edges it will reduce the risk to fatal
accident, if our body part expose to unconditional circumstances.
113
114
APPENDICES
Welding Procedure 1
115
116
Welding Procedure 2
117
118
Proposal (Project Title)
Proposal (Brief)
119
Proposal (Design Sketch & Drawing)
Proposal (Costing)
120
Proposal (Organization Chart)
121