Professional Documents
Culture Documents
2
Communications generally
Architect’s communications
diverse in terms of
topic
formality
people
3
Communications generally
Things to consider?
recipient (i.e. audience)
client (existing / prospective) / contractor / planning authority /
colleague
subject matter
technical / appointment / contractual
purpose
direction / informative / inquisitorial
4
Communications generally
Things to consider?
style
formal e.g. a notice / personal /technical
terminology
use of capitals
NEC 3 – use of ‘italics’
terms in documents e.g. the contract
means
post / e-mail / facsimile / special or recorded delivery
5
Letters: Structure
Sender’s Address
RPP Limited
Dear Sir
Subject
NEW FACTORY AT XYZ
We acknowledge …
Main Body
6
Letters: Salutation and Signing Off
7
Letters: Example 1
8
Letters: : Example 2
9
Letters: Example 3
Dear Sir
[Insert project name etc]
The following defective work has been noted on the above site:
[Insert list of defective work in sufficient detail to enable the quantity surveyor to
identify it. Include items from previous months until the defects have been corrected]
The above work is to be omitted from your next valuation.
Yours faithfully
Source: STANDARD LETTERS IN ARCHITECTURAL PRACTICE 4th ed D Chappell
10
Letters: Example 4
Dear Sir
[Insert project name etc]
As a matter of urgency, please carry out the making good as indicated on the enclosed
instruction.
The instruction is issued in accordance with clause 2.38.2.
Yours faithfully
Copy: Clerk of works
Source: STANDARD LETTERS IN ARCHITECTURAL PRACTICE 4th ed D Chappell
11
Letters: Example 5
Cantrell and Another v Wright & Fuller Limited [2003] EWHC 1545 (TCC)
“Dear Mr Cantrell
New EMI Unit - Phase 1
I now write to enclose the final certificate as per the contract sum, variations
and omissions. I believe this now discharges our obligations under the
contract.
I would respectfully remind you that you would be advised to check that the
sub-contractors have been paid their due amounts before you make any final
settlement.
Yours sincerely
C R Tanner”
12
Meetings
Examples
design
pre-start
progress meeting
Purpose
outcomes
agenda
Minutes
record
issued
13
Meetings: Agenda
Sports Centre Development
Agenda for Pre Start Meeting
To be held on 2 May 2011 at 11.00am in the site office
Apologies
1. Personnel 13. Contractor’s programme, form and updating
2. Production information 14. Progress reporting
3. Contractor’s copy of contract documents 15. Role of the clerk of works
4. Insurances 16. Samples
5. Bond 17. Covering up work
6. Sub-contractors 18. Setting out
7. Employer’s licensees 19. Services
8. Architect’s instructions 20. Signboard
9. Clerk of works’ directions 21. Consultants and their roles
10. Oral instructions 22. Procedural matters not otherwise covered
11. Queries and information requests 23. Any other business
12. Further meetings and participants 24. Date, time and place of next meeting
Based on an example agenda included in ‘The Architect in Practice’ 9th Edition Chappell & Willis
14
Meetings: Agenda
AGENDA
1. Apologies
2. Approval of Minutes of the Meeting held on xxxx (copy attached).
3. Matters Arising
4. Progress/Programme and Contractor’s Report
5. Design/Information
6. Health and Safety/CDM
7. Any other business
8. Date of next meeting
15
Meetings: Minutes
Structure - introduction:
Project
Location
Title (of meeting)
Date
Time
Present
16
Meetings: Minutes
ITEM DESCRIPTION Action by
Date
1. APOLOGIES
2. APPROVAL OF MINUTES OF THE MEETING HELD ON XXX
2.1 XXX
3. MATTERS ARISING
5. DESIGN / INFORMATION
5.1 xxx
6. HEALTH AND SAFETY / CDM
8. NEXT MEETING
9. DISTRIBUTION
17
Instructions
Instructions
direction / command / order
RIBA standard pro forma – ‘Under the terms of the above-mentioned contract,
I/We issue the following instructions:’
SBC 05 clause 3.10
The Contractor shall forthwith comply will all instructions issued to him by the
Architect/Contract Administrator...
Examples
Variations to the Works
postponement
removal of defective works
18
Instructions
Importance of wording
Simplex Concrete Piles Ltd v The Borough of St Pancras (1958) 14 BLR 80
architect’s letter accepted quotation
no qualification e.g. no adjustment to the Contract Sum
19
Notes & Records
20
Certificates
What is a certificate?
When the architect certifies, he is recording for the parties his professional,
personal and objectively arrived at opinion that the fact (sic) situation
recorded by the certificate is accurate at the time the certificate was issued.
Thus, the certificate must be one which clearly expresses the relevant opinion
of the Architect in a form that shows that the opinion is that of the Architect, is
the one which the contract calls for and which addresses and only addresses
the matters called for.
Cantrell v Wright & Fuller Ltd
21
Certificates
Cantrell and Another v Wright & Fuller Limited [2003] EWHC 1545 (TCC)
“Dear Mr Cantrell
New EMI Unit - Phase 1
I now write to enclose the final certificate as per the contract sum, variations and
omissions. I believe this now discharges our obligations under the contract.
I would respectfully remind you that you would be advised to check that the sub-
contractors have been paid their due amounts before you make any final
settlement.
Yours sincerely
C R Tanner”
22
Certificates
The Employer took issue with the architect’s ‘final account’ and as a consequence
the validity of the architect’s Final Certificate. The matter went first to arbitration
and then to the courts.
The Judge’s comments in Cantrell v Wright & Fuller Ltd on the architect’s
documents were as follows:
the certificate was in a form identical to the immediately preceding interim
certificate .
the sum certified did not state that it was the product of the completed
adjustment process required by clause 30.6.2.
the requirement that the certificate was to be paid within 14 days clearly
indicated, in context, that the certificate was an Interim Certificate.
23
Certificates
24
Certificates
25
Final Thought
In early December 2003 Mr Bullen sent an email to one of his colleagues, in which he
expressed reservations about Mr Mell:
"Have been thinking about Ampleforth … I don't think the replacement PM is up to
the job!!! Have not decided how to play this with Jim Fletcher as yet because I do
not want to prolong my involvement with the project—I'll let you know how it
goes."
In the light of Mr Talabani's evidence on this point, the terms of his email of 26th
August 2004 is surprising: "The only thing holding up executing the contract docs is
Shires appointment. … I suggest we issue a letter of intent for the whole value up to
the end of the job. Then Shires can go fuck themselves."
The Trustees of Ampleforth Abbey Trust v Turner & Townsend Project
Management Limited [2012] EWHC 2137 (TCC)
26
Final Thought
“All of this does, of course, emphasize the vital point that the duty of a
professional man, generally stated, is not to be right, but to be careful.”
Royal Brompton Hospital NHS Trust v Hammond and others (No 7) (2000)
76 ConLR 148
27
Questions
28