Professional Documents
Culture Documents
Presentation Transition From Construction To Commissioning
Presentation Transition From Construction To Commissioning
Practice Procedures in transition
from
Construction to Commissioning
Ridha. Khaldi CSU Supt
(GTP‐ 2018)
What is Pre‐Commissioning and Commissioning?
(1 * ,1 ((5,1 *
%DVLF' HVLJQ$VEXLOW
7HFK6SHFLILFDWLRQV 352 &8 5(0 (1 7
&2 1 75$&76 9HQGRU' RF)$7
3ODQQLQJ62 : 0 LOHVWRQHV 6SDUHSDUWV
+ DQGRYHU&HUWLILFDWHV
Sub‐system:
Is a further sub‐division of a System, which performs a partial operational
function of the System, with little or no interference from the other Sub‐systems.
The Sub‐system is the basic unit for Commissioning
Summary of characteristics for RFC:
Applies to : Sub‐system
Prerequisites : All Pre‐commissioning Activities successfully completed
Consequences : Authorization to begin Commissioning activities :
These dossiers shall contain all the information’s required to demonstrate that
a Sub‐system has reached the "Ready For Commissioning" status (RFC)
Commissioning Activities
Commissioning consists of a series of tests and activities that validate the
construction and prepare a plant for operation.
This is generally considered in two phases:
Phase Activity Milestone
Pre-commissioning Conformity Checks Ready for Commissioning
Static Tests Mechanical Completion
Hydrotests
Flushing & Cleaning
Commissioning Energisation Ready for Start-up
Dynamic Tests
Equipment Running-In
Utilities Start-Up
Pre-Start-Up Activities
Operational Tests
COMMISSIONING
COMMISSIONING STARTUP
START‐UP
COMMISSIONING START‐UP
OPERATION
OPERATION
PRE‐COMMISSIONING DOSSIERS
PROCESS
STARTUP
Operations
UTILITIES PERFORMANCE
STARTUP TESTS
TIME
MECHANICAL COMPLETION
MECHANICAL COMPLETION
MECHANICAL COMPLETION
MECHANICAL COMPLETION
FINAL ACCEPTANCE
PLANT IN OPERATION
COMMISSIONING
1st REQUEST FOR
OF FIRST SYSTEM
PROCESS READY
UTILITIES READY
FOR START‐UP
FOR START‐UP
OF FIRST SYSTEM
OF SITE
OF SITE
Why transition from Construction to
Commissioning is so important?
• Safety environment is complex and difficult to manage
L'environnement de sécurité est complexe et difficile à gérer
Le nombre de participants est assez élevé par rapport aux autres
Phases du projet
Les priorités des parties prenantes entrent parfois en conflit avec
autres
Exigence d’un personnel très qualifié et expérimenté
What is Mechanical Completion ?
• Test Package Set of documentation demonstrating the MC of a system or its
subsystems or sections that can be isolated for test purposes
• Punch List Formal inspection and identification of remaining outstanding works
• Initial Walk down Identification and closure of all category “A” punch items
• Final Walk down Demonstration and acceptance of a pre‐checked system for
hand over & Punch List
• TOD Final dossier including all applicable as‐built engineering documents and
(Turn Over Dossier) construction certificates as per Inspection & Test Plan
attesting the readiness or turn over
What is needed to administer this transition phase
•Standardized preparation for mechanical completion and commissioning
•Controlling tool for the creation and management of all QC and MC forms
Basis of TAG Assignment
• Internal inspection of tanks and vessels.
• Alignment.
• Load testing of lifting equipment
• Flushing.
• Bolt tensioning.
• Dimension control.
• Preservation.
Electrical
• Visual inspection for complete and correct installation.
• Insulation and continuity testing of cables.
• Insulation testing of generator, transformers and motors, panels, distribution
• board etc.
• Earthing checks.
• Static check of switches and control devices.
• Battery preparations.
• Lighting and socket outlet checks.
• Area completion.
• Heat tracing.
• Preservation.
Instrument
Calibration and testing of instruments prior to installation.
Visual inspection for complete and correct installation.
Insulation and continuity testing of cables.
Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing.
Adjustment of control, alarm and shutdown settings.
Loop testing.
Function testing of control systems.
Function testing of field instruments.
Hot oil flushing of instrument tubing.
Area completion.
Preservation.
Piping
• NDE carried out.
• Welding procedures.
• Flushing of pipework.
• Chemical cleaning and testing of pipework.
• Preservation of tested pipework.
• Reinstatement of all items after testing.
• Final inspection of pipework.
• Test ISO's and P&ID's showing the extent of each pressure test.
• Hydraulic tubing.
• Bolt tensioning.
• Pipe supports completed.
• Insulation.
HVAC (applicable for containers)
Visual inspection for complete and correct installation.
Cleaning of ductwork.
Leak testing of ductwork.
Alignment checks.
Mechanical functions checks of equipment.
Preservation.
Flow coding.
Safety
Visual inspection for complete and correct installation.
Preservation.
Area completion.
Structural
Visual inspection for complete and correct installation.
QC documentation.
NDE carried out.
Welding.
Load testing of lifting lugs and monorails.
Surface protection, Insulation and Fire proofing
Visual inspection for complete and correct application.
Thickness checks carried out.
Adhesion checks carried out.
Preservation.
Insulation.
Painting.
Fire proofing.
Architectural (applicable for containers)
Visual inspection for complete and correct installation.
Preservation.
Doors.
THANK YOU