com/learner/courseinfo/id:130)
You completed this test on 23/05/2021, 21:22
Out of 20 people that took the test, you rank 3rd
Your score is 80.00%, while the average test score is 72.50%
Well Done!
CORRECT
Which role is responsible for authorizing and monitoring work to be completed and for taking corrective
action within a stage?
Project Manager
Project Support
Project Assurance
Team Manager
CORRECT
Which is one of the six aspects of project performance that needs to be managed?
Accuracy
Reliability
Scope
Ease of use
CORRECT
Role descriptions
Processes
Product Descriptions
CORRECT
CORRECT
Organization
Progress
Business Case
Risk
INCORRECT
Involves people with di erent skills introducing a change that will impact others outside of the team
Has a lifespan that usually covers the delivery of the desired outcomes and the realization of all the expected
bene ts
CORRECT
INCORRECT
It can be tailored for di erent project types or environments with various scales, sizes complexities.
CORRECT
Starting up a Project
Initiating a Project
Directing a Project