2020‐02‐23

Item # 2

Filling of soil from New materials


& well compacted to
Foundations.

22
Eng. Ahmed Said Refaei

SITE INFORMATION
▪ Soil report recommendations to use A-1-a with A-2-4 soil as
Eng. Ahmed Said Refaei

filling for 1 m depth.


▪ Building net Area = 26000 m2 (180m x 150m).
▪ Excavated area = 32500 m2.
▪ Trucks piling near work location within 100m

23

1
2020‐02‐23

HISTORICAL DATA AND CURRENT INFORMATION
FROM CURRENT PROJECT AND HISTORICAL DATA THE 
PRODUCTION RATES OF FILLING:

Eng. Ahmed Said Refaei
Loader Compactor Bobcat

Rent or O&O Cost 500 Le/day 800 Le/day 100 Le/day

Production Rate 350 m3/day 3200 m2/day 3200 m2/day

24

Supply soil rate = 40 Le/m3 Eng. Ahmed Said Refaei

Labour

INFORMATION Production Rate = 200 m2/day
Rate 108 Le/day

Water soil 150 ltr/m3

25

2
2020‐02‐23

ESTIMATE DETAIL FORM

Eng. Ahmed Said Refaei
26