Professional Documents
Culture Documents
(HVAC System)
Scope of Work
They have several types of works that can deal with the agreement so that can do their responsibilities as a
worker and can perform until such time the plan is complete. For example, the mechanical contractor has a major role in
terms of in charge for cooling system, piping, and/or plumbing of the respective structures and will maintain those
machines/engines everyday. Because of the potential risk regarding the technology, the mechanical contractor can
regulate monitor those things that has a potential malfunctioning before they perform. The main purpose of having a
scope of work is to perform based on their responsibilities under the contract and to follow the schedule based on the
agreement.
People Involved
The following people involved in the respective plans are the mechanical engineering, mechanical contractors,
quantity surveyors, owners or client, project manager, mechanical utilities, architect, civil engineering, master plumbers,
and other professionals involved in the plans including the other roles of mechanical works. Those workers that assigned
their roles including the professionals shall work together as a one team and can perform well especially the mechanical
until the work is done.
Figure 1.3. Supply Air in a Base Cabinet Figure 1.4. Return Air Using Framing Members
Figure 1.5. Radiant Heating Pipe Layout
(a)
(b)
Figure 2.0 (a) and (b) Typical HVAC layout plan
Cost Estimates
Cost estimation for HVAC systems requires expert knowledge because most jobs are designed and laid out
prior to the estimate. The mechanical contractor therefore needs to determine the heating loads and design a system
to fit the required conditions before the estimating process takes place.
On the other hand, larger work requires the heating contractor to develop details for piping, equipment connections,
and controls.
To perform a detailed cost estimate for HVAC systems, the estimator must consider the categories: (1)
materials, (2) equipment, (3) labor, and (4) supplementary costs. The summation of these costs is the final total cost
for HVAC systems.
Sample Problems
Given:
Step 01: Sum the total heating loads and total cooling loads after listing the values in the table.
𝐓𝐨𝐭𝐚𝐥 𝐇𝐞𝐚𝐭𝐢𝐧𝐠 = 𝟓. 𝟔 𝐤𝐖
𝐓𝐨𝐭𝐚𝐥 𝐂𝐨𝐨𝐥𝐢𝐧𝐠 = 𝟕. 𝟗 𝐤𝐖 ← 𝐡𝐢𝐠𝐡𝐞𝐬𝐭 𝐭𝐨𝐭𝐚𝐥 𝐥𝐨𝐚𝐝
Summary:
𝐓𝐨𝐭𝐚𝐥 𝐇𝐞𝐚𝐭𝐢𝐧𝐠 = 𝟓. 𝟔 𝐤𝐖
𝐓𝐨𝐭𝐚𝐥 𝐂𝐨𝐨𝐥𝐢𝐧𝐠 = 𝟕. 𝟗 𝐤𝐖
Write-up:
The figure 01 shows the four respective with different values in terms of heating and cooling loads
including the mechanical room. It is a simple plan wherein the four rooms will compute the total heating
loads and cooling load. It is also a necessary to know in which loads got the highest value so that they can
maintain the loads and to avoid possible malfunctioning of the mechanical utilities
Solution:
Step 01: Solve the number of pipes and 1 ft. serves as the allowance.
9 ft
Number =
1 ft
Number = 9
Note: the number of pipes that is running from north to south should be an even number from the main supply
including the return in order to enter the room at the same point.
Thus 9 + 1
Number = 10 pipes
Step 02: Calculate the total length of pipe with 40 feet much needed to connect to the boiler.
Total Length = 9 ft + 8.25 ft + 9 (7.75ft) + 9 (1.6 ft) + 2(0.8 ft) + 40 ft
Total Length = 143 feet
Summary:
Number of pipes = 10 pipes
Total Length of the Pipe = 143 feet
Write-up:
The figure 02 shows the length of the pipes with diameter including the four directions such as north, west,
east, and south. It is necessary to solve the number of pipes before the total length of the pipe in order to
supply the pipes based on the computations. It consists of return and supply including the length between
two pipes and their measurements.
11